107 South Albany Street Construction Update, 7/2018

18 07 2018

107 South Albany is a curious mix of sheathing. The front and part of the sides consists of standard Huber ZIP System plywood panels, while the sides use GP DensElement fiberglass mat sheets with maroon liquid flashing. Atop that, wood furring is being attached, and trimboards and fiber cement lap siding (or panels, for the wall next to the central staircase) are added to finish out the exterior. The front entry will have a brick veneer, but only on the first floor, so that doesn’t explain the difference in sheathing. The windows are fitted, but the front entry is not.

These apartments should be open for occupancy in time for the new academic semester. Advertisements say August 1st, but that might be a stretch. Still, these are coming in at a more modest cost than other new market additions ($1,100/month), and adds some density to the State Street Corridor.

Background information on the project and its specifications can be found here. Renting Ithaca (Nick Stavropoulos) is the developer, and Flatfield Designs (Daniel Hirtler) is the architect.





Harold’s Square Construction Update, 7/2018

17 07 2018

Harold’s Square is starting to take shape. The white sheets on top of the basement level are Sika Corporation UltraCure NCF curing blankets. When the steel was laid, corrugated decking was laid on top to create the base of the floor. A rebar wire mesh was then laid and tied into place, and the concrete was poured into the floor cavity, with wood forms to keep the pour in place. The rebar strengthens the concrete and ensures structural integrity. In this mid-June Facebook photo from the Harold’s Square page, you can see the decking going over the structural steel. A week and a half later, you can see the rebar grid over the completed decking. The concrete was poured in early July, the slab was covered in the cellulose fiber blankets to promote an even and structurally sound cure, and after seven days they tested the concrete and the results came back all-clear, meaning they can start to put weight on the concrete and work their way up.

Meanwhile, structural steel erection will be taking a short break as masonry work begins on the Commons-facing side of the project, followed by masonry work on the Sage Building. The steelwork will resume in late July. Subcontractor Paolangeli will be doing backfilling (earthwork to cover up the foundation) on the Green Street (south) side of the project now that the shell of the basement has been built.

The WordPress for the project can be found here, and the Ithacating project description here.





118 College Avenue Construction Update, 7/2018

16 07 2018

The last of Visum’s trio of Collegetown projects underway is the 5-unit, 28-bedroom building at 118 College Avenue. Officially, one other Visum project has city approvals and is permitted to start construction, a close fraternal twin to 118 College just a few houses up at 126 College Avenue. However, the existing house is rented out for the academic year, so any build-out there (and Visum seems to have deep enough pockets to eventually do it, all things considered) will not begin until June 2019 at the earliest.

As with 210 Linden, Romig General Contractors is in charge of the buildout, and Taitem Engineering is doing the structural engineering – as with Visum’s other projects designed by STREAM Collaborative, the building is built to be net-zero energy capable. Using electric heating and appliances, energy efficient fixtures, low-E windows, double-stud exterior walls and high grade insulation creates a very high degree of energy efficiency that they hope to tie into an off-site solar array, offsetting the carbon footprint of the building and its use.

118 College still has another floor to go before it’s topped out, and the mechanicals will be hidden inside the historically-inspired “Italianate cupola” penthouse. Water and sewer service was installed this past week. I’m uncertain this one will be ready in time for returning Cornell students late next month, though it’s not impossible given that it’s a relatively small wood-frame structure. So far, with the rough window openings I’m seeing one substantial difference from the renders – the windows on the wings of the front facade are smaller than originally planned.





City Centre Construction Update, 7/2018

16 07 2018

Not too much to add here regarding City Centre. The modular exterior panel system continues to rise. These photos were taken last weekend when the building was up to its sixth floor, and it’s not up to the seventh of its eight floors. For those needing a more regular fix, the webcam on the top of Seneca Way updates every fifteen minutes or so, and can be seen here. Looks like it missed me by three minutes.

Here’s an interesting little aside. A few folks have complained, in the way that many of us like to do, that the name “City Centre” is rather pretentious, particularly the faux-British English ‘Centre’. Newman Development Group has actually reused the name on another project they’re doing, in Lincoln Nebraska. That project is significantly larger than Ithaca’s, an $85 million downtown redevelopment of the former Lincoln Journal-Star newspaper office and printing press into a ten-story mixed-use with first-floor retail, two floors of offices, and 239 apartments on the upper floors. Like Ithaca’s project, it’s one of the largest urban projects in the city (rather impressive given Lincoln is ten times Ithaca’s size), and received a local tax abatement on the order of $15 million. Lincoln was selected by Newman specifically because its downtown area is close to a major university, in this case the University of Nebraska. Perhaps their Ithaca project is a new market pioneer for them – they see potential success in a mix of urban professionals and college students, and are looking for other opportunities in similar communities.

Looking at the apartment rental prices is enough to give most folks pause. Studios, which make up 33 of the 193 units, range from $1,795-$1,875/month. the 120 1-bedroom units go from $1,995-$3,015/month, and the 39 two-bedrooms range from $2,560-$3,415/month. With those prices, a prospective tenant could rent an entire house for themselves in Fall Creek or Northside; maybe it’s for the best that their attentions are drawn here instead. For the sake of comparison, City Centre Lincoln is $900-$1,200/month.

More information about Ithaca’s City Centre can be found here.





Hilton Canopy Hotel Construction Update, 7/2018

15 07 2018

As previously mentioned on the Voice, the new 131-room Canopy by Hilton is one floor short of topping out. Interestingly, the ground level/lobby uses Georgia-Pacific DensGlass fiberglass mat sheathing, while the upper level use National Gypsum eXP boards. I’m not sure why the change – both are fire-rated, mold and water resistant. It probably doesn’t have to do with the exterior finishes (brick veneer is used at both ground level and on some of the wall projections above), but it’s possible it has to do with the construction material. The ground level is composed of poured concrete, while the upper floors are structural steel and accompanying steel stud walls. Regardless of the reason, both are being covered with the same water-resistive barrier. You can see the interior stud walls through the rough window openings, but interior work hasn’t progressed much farther than that on the more recently erected upper floors. The lower floors appear to be undergoing utility rough-ins.

It still isn’t clear what the replacement panel color will be for the yellowish “Applesauce Cake” – not sure if Whitham Planning and the rest of the project team persuaded the city “Dark Ash” grey was okay, or if another color was chosen. If someone knows, feel free to chime in the comments.

Further information on the Canopy hotel can be found here.





Chapter House / 406 Stewart Avenue Construction Update, 7/2018

15 07 2018

With 400-404 Stewart Avenue complete, developer Jim Goldman is focusing on the completion of the other half of his reconstruction, 406 Stewart Avenue. This is the property that Goldman originally owned and was destroyed in the spread of the fire that erupted at the Chapter House building. Architect Jason K. Demarest’s 3.5 story design is completely framed and sheathed in ZIP Panels; the panels are then covered in HydroGap, a premium grade housewrap to remove excess moisture while keeping new moisture from penetrating into the plywood sheathing. This is then layered over with (what I suspect are fiber cement) shakes, in contrast to the first floor’s lap siding.

My first inclination was that they needed to be painted, but looking at the design render, it appears as if the project team decided to reverse the brown and red siding bands, so now the first floor is red like the original building, but the upper floors are brown. This is not the first major change to the design, which was approved by the ILPC, but any revisions may have been done out of committee view at the staff level. The fenestration on the third floor is different, and the dormer on the gable roof was deleted. Note the partially glazed-in access stair for the third floor apartments, and the quarried bluestone stair columns and base.

There’s still a fair amount of work to do on the exterior with facade installation, trim and finish pieces and the installation of a steel grate to access the enclosed stair column. The one inside shot shows drywall hung with doors and some trim in place, but some pieces are still missing, the wall needs to be painted and the floors have to be finished. However, it’s not an especially large building (four units and eleven bedrooms as-approved), so chances are pretty good this will be ready to go by mid-August.

As for the Chapter House, a few shots through the window glass show the carpeted staircase leading up to the eight apartment units, and an unfinished 3,000 SF commercial space still looking for a tenant.





210 Linden Avenue Construction Update 7/2018

13 07 2018

Time to take a look at Visum’s smaller Collegetown projects. 210 Linden is the largest and furthest along; the city allowed them to hook up to water and sewer service this week.

Note there are some clear differences between what was originally approved, and what’s being built. The fenestration is a different layout – the top floor windows originally did not line up with the window arrangement of the other floors. Secondly, the floor-to-ceiling multi-pane treatment on the top floor’s front (east) facade has been eliminated, given a similar if slightly glassier treatment as the other three floors, which had a balcony window reduced in size. The most likely guess is value engineering – save cost, save time, especially the latter since the building needs to be open by mid-August.

The overall shape remains the same, but with these changes it’s a bit of a question mark as to the appearance of the final materials – it’s probably the same as approved, since the vertical wood rails over the sheathing indicate the LP SmartSide fiber cement lap siding is coming at some point. The sheathing is a mix of Huber plywood zip panels with its specialized tape system, and TYPAR housewrap over plywood panels courtesy of North Main Lumber, a regional lumber sales chain. Romig General Contractor is doing the build-out, and their work with Visum is arguably the first multi-family project they’ve tackled in the Ithaca area.

Although 210 Linden is too small to host much in the way of amenities (it has a garbage collection room and bike room in the basement), its 37 residents will have full access to the amenities offered in The Lux just up the street. Connecting the dots, those were probably quartz countertops in the Lux update; seems plausible the same high-end fixtures, cabinetry and appliances would be used in both.

The background info/intro to 210 Linden can be found here.