Library Place Construction Update, 1/2020

17 01 2020

Library Place is making progress over at 105 West Court Street (the new mailing address; guess we should stop saying 314 North Cayuga Street now). The concrete masonry unit (CMU) northeast elevator/stair tower has topped off, and it looks like part of the northwest tower is being assembled now. The square holes above the lower levels of the tower are most likely slots for structural steel. If I’m reading the floor plans right, a third stair tower will be constructed along the south wall of the building. The concrete foundation footers have been poured, and a CMU foundation wall is being assembled; the pink materials along the outside of the wall are lightweight polystyrene insulation boards, Owens Corning Foamular from the looks of it. I see a work truck on site for subcontractor Gorick Construction of Binghamton, but rather surprisingly there’s no signage around for general contractor LeChase Construction.

Signs along the perimeter fence advertise a Spring 2021 opening for the four-story, 86,700 SF building. Prices for the 66 senior housing units are not yet available. Amenities will include a restaurant, à la carte home health services from an on-site agency, community room, courtyard gardens, workout facilities, warming pool, and underground parking. Senior services non-profit Lifelong will provide on-site activities and programs.

More information about the history of the project and its stats can be found here. The project website is here.





Library Place (Old Library Redevelopment) Construction Update, 3/2019

27 03 2019

Not a whole lot to say at the moment – everything above surface level on the site has been cleared as of the end of February, and grading/leveling is taking place. Part of the existing 1960s foundation will be reused for underground parking, and part of it will be taken out. According to the project team, an examination of the existing foundation column footers vs. the blueprints found that eight of the column footers were not where indicated on the as-built drawings. That created a conflict with portions of the new structure, ans so these column footers are being removed (probably by the demolition subcontractor, Gorick Construction of Binghamton; LeChase is the general contractor overseeing the whole project).

It might seem weird, but this isn’t the first time something like this has happened. Half the footers were missing outright at Ed Cope’s Ithaca Glass site, which led to a total overhaul of the project plans (now held by Visum, although I haven’t heard anything about the plan since the transfer was announced in November).

It’s a bit unusual since the project is already underway (or at least, the site prep is), but Library Place has yet to receive approval for a tax abatement. The Tompkins County Industrial Development Authority (IDA) will be receiving the tax abatement application in early April and the board will get their first glance at it on April 10th. A public hearing on the abatement will be held sometime before the May 8th IDA meeting. Assuming the application is approved at the May 8th meeting, pile driving would start within a few days of approval.