Cornell Veterinary School Expansion Construction Update, 3/2017

26 03 2017

There’s been quite a bit of progress over at the Vet School. It looks like the exterior glass and aluminum are going on the new library and administrative wing. Windows and sheathing have been installed on the north face as well, with a water-resistive barrier applied over the sheathing. The new atrium is being framed out.

According to the Vet School’s construction update page, interior framing and utilities installations are underway in the new wing, and the new cafeteria is under construction – both are aiming for August completions. The new atrium and lecture hall will be closed off shortly, with interior work to launch in earnest once that occurs.

Thanks to Maria Livingston over at HOLT Architects, readers now know what the new Community Practice Service building will look like. Syracuse’s G. M. Crisalli and Associates Inc. has been selected as general contractor, and construction for the $7 million, 12,000 SF wood-frame structure is expected from March 2017- March 2018.





Tompkins Financial Corporation HQ Construction Update, 3/2017

25 03 2017

Apparently I forgot to to an update on the Tompkins Financial project last month? It must have slipped off the radar after the Voice received its spark notes version. Funny how it was about 60 F when the February photos were taken, and about 30 F when the March photos were snapped.

Anyway, structural steel framing is underway, giving an idea of the bulk of Tompkins Financial Corporation’s new 110,000 headquarters at 118 East Seneca Street. Framing has started for the first five floors of the seven story building, and mor beams will be built upward and outward – note the indents in the elevator core on the side facing Seneca Place, intended for future steel beams. The lowest floors have also received corrugated steel decking. There are still a couple of floors to go, as evidenced by the wood forms on the elevator shaft. The concrete will extend another two floors before it’s topped out. The building’s ground to rooftop height will be exactly 100 feet.

A May or early June topping out seems plausible. Occupancy is intended by March 2018. JPW Erectors, a division of the JPW Companies of Syracuse, is in charge of the framing, while LeChase Construction is the general contractor.

February 2017





Cayuga Meadows Construction Update, 3/2017

23 03 2017

Another project is on the final stretch towards completion. Conifer LLC’s Cayuga Meadows affordable senior housing project is largely finished from the outside, with only some minor trim and landscaping left. Most of the work has transitioned to the interior, fitting out the units and finishing them out in time for their late summer occupancy. Leasing is underway. Here’s a copy of the rental ad:

Located in the heart of Ithaca, Conifer Village at Cayuga Meadows is a brand new senior apartment community offering energy efficient one and two bedroom apartments homes for individuals 55 and older. Cayuga Meadows has set aside nine units for those with disabilities and an additional three units for hearing and visually impaired. The community will offer many amenities along with breathtaking views of Cornell University and the hills of Ithaca. Occupancy by Summer 2017. 

Qualified Hurricane Irene or Tropical Storm Lee impacted residents will be given priority for the first 90 days of rent up.

That last part might seem a little odd, but it was a stipulation of their state grant funding, which was source from the Storm Recovery Act (not so much Ithaca, but the Southern Tier did receive substantial damage from the remnants of Tropical Storm Lee back in 2011).

Advertised features and amenities include:

Fully equipped kitchens with Energy Star rated appliances & fixtures
Dishwasher
Elevator
Great room with kitchenette
Laundry center
Fully equipped fitness room
Computer lab
Controlled building access
Professional on-site management
24 hour emergency maintenance
GREEN building (don’t think LEED certified though)
Accessible for people with disabilities (7 for mobility impaired, 3 for visually impaired)
Ample on-site parking (72 spaces offhand)
Community vegetable garden
Easy access to public transportation

Rents will go for $779 for a 1 bedroom, 1 bath (59 units available, 654-689 SF), and $929 for a 2 bedroom, 1-2 bath unit (9 units, 905 SF). Applicants must be 55+ and be income eligible, which at 60% of area median incomes means seniors making ~$30,840/year or less for a single person, or ~$35,280/year or less for a couple. If any readers here are on the cusp and unsure, it never hurts to ask – the general inquiry email is cayugameadows@coniferllc.com.





Collegetown Terrace Construction Update, 3/2017

22 03 2017

From the outside, Collegetown Terrace’s third and final phase is nearly complete. Some cement panels and clapboards are still being attached at the ends and the south face, and the entry areas need to be finished out, but otherwise it looks like the exterior is mostly finished.

Peering through the windows as the lights clicked on, it looks like drywall has been hung in most of the units, and closet doors and cabinetry are or are being installed, meaning they’re pretty far along and that finishing work is all that’s left for some units (there are 344 units, so it could take a while to do them all). All in all, things look on track for the expected summer completion. Kudos to Welliver for keeping such a massive building on schedule.

\





602 West State Street Construction Update, 3/2017

21 03 2017

The new addition has risen out of the ground at Elmira Savings Bank’s new $1.7 million branch office at 602 West State Street. The cinder block shaft will host the elevator shaft/stairwell, and the steel framing is underway for the new 1600 SF north extension. The non-historic blue paint is being stripped from the bricks of the existing structure, and from the plastic on the roof, it looks like a new roof is being laid, probably EPDM (synthetic rubber) or something similar. The building’s insulation is being updated, and the plan is to have an all-electric HVAC system (heat pumps).

Although the initial press release called for March opening, June or July seems more likely. Elmira Savings Bank will occupy 3,300 SF on the first floor. The second floor, also about 3300 SF, will host for-rent office space. HOLT Architects is in charge of design, and Edger Enterprises is in charge of the buildout. Based off the signage, it looks like John Mills Electric (IBEW Union, Local 241) is doing the subcontracted electrical work.





Ithaka Terraces Construction Update, 3/2017

20 03 2017

Over at the Ithaka Terraces located at 215-221 West Spencer Street, Building “A” is fully framed, sheathed, nearly all Low-E windows have been fitted and the roof has been shingled. Buildings “B” and “C” are still in the process of framing and sheathing. Building “D” might be excavated at this point, but all the snow made it impossible to tell.

Note that the condos use double-stud walls, meaning their are two sets of wood stud walls used in the exterior frame, parallel to each other but spaced apart by about 5 inches. That space is then filled with R39 densely-packed cellulose insulation. The result has its pros and cons. The cons are that it’s more expensive to build, and it reduces the interior space a little bit. The pro is that it’s very energy efficient, which comes in handy for a project trying to achieve net-zero energy use. Along with the low energy consumption and green features, the project will be powered by a solar array owned by the developer out in Caroline.

Since these buildings will have a stucco finish, and stucco tends to absorb moisture but ZIP sheathing does not, most building codes require a water-resistant barrier between the ZIP sheathing and the exterior stucco. This allows the wall to repel and drain off moisture without risking the integrity of the facade. In the photos below, the WRB is the would be the thin white coating going over the sheathing.

Formal marketing for the 12 units is expected to launch in a couple of months. 10 2-bedrooms and 2 3-bedroom units will be available, with prices ranging from $265,000-$390,000.





201 College Avenue Construction Update, 2/2017

2 03 2017

201 College Avenue is reaching for the sky – when these photos were taken about a week and half ago, the structural steel was as high as the third floor, so there’s still two more floors to be boxed out by the H-beams. Although only five floors, the mezzanine-approach to maximizing square footage means that the units on the third through fifth floors are quite tall, 16 feet from sub-floor to sub-floor, 70 feet for the whole building.

The basement level, which only occupies the west half of the building (the east half is slab-on-grade) has been fleshed out with reinforced concrete walls – the windows on the street corner will look into a gym and game room, while the two pocket windows on the northwest corner will look into the mechanical room. The blue boards on the concrete are rigid styrofoam panels used for insulation and moisture protection.

It looks like some wall framing is underway on the first floor for the three-bedroom units – those CMU walls face the stairwell, and the exterior walls of the building itself. The interior unit walls will likely be a more typical lightweight steel frame.

There’s been some documentation floating around that suggests an early working name for 201 College Avenue was “The Heustis Lofts”, Heustis (sometimes Huestis) Street being the original name of College Avenue. However, it doesn’t seem the moniker was officially adopted.
20170218_115452 20170218_115504 20170218_115509 20170218_115538 20170218_115559 20170218_115623 20170218_115712 20170218_115735 20170218_115747 20170218_115756 20170218_115802

201_college_v5_1