Library Place Construction Update, 1/2020

17 01 2020

Library Place is making progress over at 105 West Court Street (the new mailing address; guess we should stop saying 314 North Cayuga Street now). The concrete masonry unit (CMU) northeast elevator/stair tower has topped off, and it looks like part of the northwest tower is being assembled now. The square holes above the lower levels of the tower are most likely slots for structural steel. If I’m reading the floor plans right, a third stair tower will be constructed along the south wall of the building. The concrete foundation footers have been poured, and a CMU foundation wall is being assembled; the pink materials along the outside of the wall are lightweight polystyrene insulation boards, Owens Corning Foamular from the looks of it. I see a work truck on site for subcontractor Gorick Construction of Binghamton, but rather surprisingly there’s no signage around for general contractor LeChase Construction.

Signs along the perimeter fence advertise a Spring 2021 opening for the four-story, 86,700 SF building. Prices for the 66 senior housing units are not yet available. Amenities will include a restaurant, à la carte home health services from an on-site agency, community room, courtyard gardens, workout facilities, warming pool, and underground parking. Senior services non-profit Lifelong will provide on-site activities and programs.

More information about the history of the project and its stats can be found here. The project website is here.





Library Place (Old Library Redevelopment) Construction Update, 8/2019

7 08 2019

With tax abatement approvals in hand, construction on the 67-unit Library Place project is set to move forward. According to the project website, at the moment 20 steel test piles are being driven into the ground to verify the correct depth to the subsurface layer that will support the weight of the structure (the library’s foundation is being reused, but the new 4-story building is heavier and has additional load bearing needs). If all goes well, the remaining 60 piles will be delivered and driven into the ground, with pile driving work to wrap up around Labor Day. This is somewhat later in the year than first anticipated.

It looks like the pile driver in the photos below came from Ferraro Pile and Shoring Inc. of Buffalo. Some grading and surveying equipment is also scattered about the site. LeChase Construction is the general contractor for the project, and Travis Hyde Properties is the developer for the senior housing project.

Quick aside – I can generally tell how familiar readers are with Ithaca when they email asking questions about “Mr. Travis Hyde”. Quick refresher, Travis Hyde is led by company president Frost Travis of the locally prominent Travis family of developers, and his brother-in-law, company vice-president Chris Hyde.

The 50 year-old time capsule from the Old Library was recovered and opened in a public ceremony; coverage of that and the contents can be found courtesy of my Voice colleagues here. The full history of the project and a description of the plans can be found here.





News Tidbits 5/11/19

12 05 2019

1. The proposed revision (downzoning) along West State / MLK Jr. Street is moving forward with circulation (review by city departments and associated stakeholders), with a couple of major revisions. The zoning would not be CBD-60. It would be CBD-52 for structures with less than 20% affordable housing, and CBD-62 for structures with 20% or more affordable housing. The quirk in the height is due to mandatory floor heights, which will be 12 feet for the first floor, and 10 feet for each floor above – in other words, five floors for projects with a lack of affordable units (=< 80% area median income), six otherwise.

For 510 West State Street, in which all 76 or 77 units are affordable (my unit count is 76, but they typed 77 in a couple sport of the Site Plan Review), the project would remain largely intact. The new setback requirement would push the fifth and maybe a very small portion of the sixth floor back from West State/MLK Jr. Street for the mandatory fifteen feet, so a little square footage would be lost there. The city had initially sought thirty foot setbacks, but the Ithaca Fire Department said that it would not be reachable by their trucks if the fifth floor was that far away from the street face.

Now, some more astute readers might be wondering is this affects Visum’s other West End project at 109 North Corn Street. The answer is no. The setback rule only affects buildings fronting West State / MLK Jr. Street. The downzoning is intended to protect an aesthetically pleasing segment of West State more than anything else. The setback does technically apply to West Seneca Street, but the building height there is 40 feet anyway, which is the same as the setback.

The affected blocks now also include the 300 and 400 Blocks of West State Street. The only publicly known project that would be impacted is INHS’s Salvation Army redevelopment, which was only aiming for five floors on the West State Street side anyway, but could potentially be impacted by the setback rule – the project design is still in the concept stages with no public images.

A speaker during public comment asked to extend the zoning further to Downtown, and some councilors have discussed further downzoning because “the developers can just pursue a PUD”. That thought process ignores the drawbacks. The more areas impacted and the more stringent zoning becomes, the more labor and time intensive it becomes for city staff because it would likely trigger more PUDs, even while resulting in less development in general because a PUD adds months to a project timeline, uncertainty that lenders don’t like, and forces the Common Council to take on the role of a second Planning Board (which some councilors might be fine with, but some definitely would not and raised this as a complaint during the vote on whether to create the PUD overlay to begin with). Also, if the downzoning were to be applied to a property against the owner’s wishes, say the County Annex property for example, it would likely trigger a costly lawsuit. TL;DR, it looks tempting for additional “community benefits”, but could have significant negative impacts and should be used sparingly.

2. Staying in the realm of laws for a moment, there’s an ordinance that should be made aware to residents of Northside and Fall Creek. A proposal from 1st Ward councilor Cynthia Brock would require every rental agreement and every home sales transaction within 1200 feet of the Ithaca Area Wastewater Treatment Facility’s boundaries to provide documentation of the potential issues and hazards of living near the plant – “you should be prepared to accept such inconveniences and discomfort as a normal and necessary aspect of living and operating in proximity to a waste water treatment facility,” as the document states.

The document isn’t ill-intentioned, but this does impact over a hundred existing Northside and Fall Creek homes and apartments, and quite reasonably would have a negative financial impact on them, whether they plan to sell or if they rent out space. There is nothing on record that these residents have been notified of this proposal. City staff don’t even seem comfortable with the proposal as-is, they don’t think Fall Creek residents are substantially impacted and suggested a cutoff at Route 13, but the 1200 square foot radius seems to be the version being considered right now, paying a trip to city attorneys to see if it’s legal to apply it to all rentals, a detail added at the meeting. Honestly, this doesn’t seem well thought out at this time, and poses a burden to existing homeowners who have not been made aware because of the lack of sufficient outreach.

3. Arthaus and Library Place have had their tax abatement requests approved, on 7-0 and 6-1 votes. The former will bring 124 affordable housing units including special needs housing and artist-centric amenities to the city of Ithaca at 130 Cherry Street. The latter will provide 66 senior housing units on the former Library property on the 300 Block of North Cayuga Street. Arthaus is expected to start construction at the end of the year, while Library Place will resume this month, with completions in 2021 and 2020 respectively.

County legislator Leslyn McBean-Clairborne voted against the Library Place proposal, citing some of the concerns raise over the lack of affordable housing (three units will now be 80% area median income) and general discontent with the site. In my intro post to the project, I mentioned if vaguely that there was a legislator who thought the affordable housing, condominiums, and Travis Hyde projects were all terrible – that was McBean-Clairborne, who has generally favored county offices on the site instead of housing. The county did a study to consider renovating the old library for offices back in 2011, a couple years before the RFP, but the study found it was financially prohibitive because of the building’s unusual interior layout (that soaring 1960s atrium wasn’t a good use of space, and wouldn’t have been cheap to replace).

4. Carpenter Park is also moving forward, in this case with the pursuit of its special PUD zoning. The project is seeking the PUD because of some quirks in yard setbacks, and soil tests showing that they couldn’t place some of the parking underground as initially planned (so now it’s in an above ground garage between the ground-floor retail and the apartments in Buildings B and C). The project would bring about 411,600 SF of new space, including 208 apartments (42 affordable) and an expansion of Cayuga Medical Center’s medical offices, resulting in the creation of 150 jobs. The vote was 4-1, with councilor Brock opposed. The full council will vote on the PUD next month, and then the project can go to the planning board for design review. Keep in mind that the above designs might change somewhat, though the general scale and program mix should stay the same.

5. The Tompkins County Airport has received a $9,999,990 grant, as announced by U.S. Senator Chuck Schumer at a press conference earlier this week. The county was strongly hoping these funds would come through. With the state grant, it means the county is only paying about $260,000 of the $24.5 million bill. Click the link here to learn more about the airport expansion project.

6. The Gun Hill Residences appear to be in the process of selling. A real estate trade magazine notes Southeastern U.S. regional bank SunTrust is giving the buyer a $13.3 million acquisition loan for DMG Investments LLC. DMG Investments is an American subsidiary of a Chinese development firm, DoThink Group of Hangzhou. The company has been active in upstate recently. DMG co-owns a new 322-bed student housing apartment in Albany and has projects scattered across the country. The full sales price has not been discolosed, as the deed has yet to be filed. It was noted that the ca. 1989, 94-unit, 273-bed Gun Hill Residences on Lake Street was nearly completely full at the time of closing (late spring, which is reasonable given a couple of kids might have washed out of Cornell or otherwise moved out). The property was previously owned by Rochester’s Morgan Communities, which was raided by the FBI last year. Morgan purchased the property in February 2011 for $6.15 million, and the current county assessment for Gun Hill is $12.65 million.

OLD render

NEW render

7. Some modest revisions to the Immaculate Conception School plans. Old render first, new render second. The design of the renovated school building has changed substantially, though the overall size has remained consistent. The changes could be due to any number of reasons, from cost concerns to utilities placements necessitating design changes. The single-family homes have been replaced with a four-string of townhomes, and the yellow string has been earmarked for for-sale units.

If I may – make one of the olive green townhome strings red or orange like the houses that have been removed. Keeps it from being so “matchy-matchy”, to borrow a JoAnn Cornish term. More renders can be found on INHS’s sparkling new website here.

On that note, on Monday May 13th the City of Ithaca will hold a Public Information Session for the proposed PUD (Planned Unit Development) for the Immaculate Conception School redevelopment. The Public Information Session will begin at 4:00 PM, in the Common Council Chambers in City Hall. In accordance with the requirements of the PUD, the developer and project team will present information about the project and answer questions from the public.

8. Looking at agendas:

The city Project Review Meeting (the run up to Planning Board meetings) will look at signage changes for the new Hilton Canopy on Seneca Way, a Presentation and potential Declaration of Lead Agency for 510 West State Street (now 50-70% area median income, initially it was 80-90% AMI), The 141-bed, 49 unit Overlook student housing at 815 South Aurora (updated, and review of Full Environmental Assessment Forms Part 2 and 3), final site plan approval for Arthaus and consideration of preliminary site plan approval for the Chain Works District (the focus right now is the renovations for phase one, office space, industrial space and 60 apartments). Apparently, the “Ezra” restaurant at the Hilton is now being called “The Strand Cafe”, after the theater that once stood on the site. More information can be found in the May project memo here.

The town of Ithaca will continue its review of Chain Works as well. Their portion of phase one involves the renovation of two manufacturing spaces into industrial and warehouse space (i.e. minimal work, just a sprucing up of the digs). Also your casual reminder that, unlike Dryden, Lansing or really any other sizable community in Tompkins County, the town permitted the construction of not a single new housing unit – again – last month. It looks the next stage of Artist Alley ($150,000 buildout) and Cayuga Med’s radiation vault ($2 million cost) were permitted.

It appears that the Beer family is heading back for another visit to the village of Lansing Planning Board regarding their until-now cancelled senior cottages project. The only thing known at the moment about this latest iteration is that it would fit the village’s cluster zoning, which means 97 units or less, but not in the same configuration as before (the pocket neighborhood-style homes were too close for code). We’ll see what happens.

Nothing much to note in Lansing town. Review of the Osmica event venue and B&B will continue, as will consideration of the Lake Forest Circle subdivision renewal and the 12,000 SF commercial building proposed for North Triphammer Road just north of Franklyn Drive.

– Courtesy of the village of Trumansburg, we have a new working title for 46 South Street, formerly Hamilton Square – now it’s “Crescent Way”. PApar krief, including revised EAFs, supplements and BZA findings here. The final version has some site plan changes on the location of some townhouse string types, but the overall unit count remains the same at 73 units (17 market rate for-sale, 10 affordable for-sale, 46 affordable rentals). Approval is on the horizon, a little more than two years to the date of when the project was first introduced. The project will be built in phases, with completion not expected until 2023.

 





News Tidbits 4/11/19

12 04 2019

1. Chances are very good that the county legislature will approve the purchase of the former orthodontics office on the 400 Block of North Tioga at their meeting next week. At least two subcommittees are recommending it, the feasibility study came back with reasonably positive results, and there appear to be no significant hurdles to moving forward. Representatives of the neighborhood sent in a letter with 25 or so signatories requesting the county build or deed away some land to build affordable housing on the Sears Street (rear) frontage of the lot, which is something the county is actively exploring but has yet to make a firm commitment to. It could range from townhouses, to three single-family homes, to two duplexes and a single-family home, to nothing, so 0-5 units, but the city and neighbors would appreciate at least a few homes to maintain neighborhood character. It’s doubtful the county would build the housing, but could deed lots to INHS or another affordable developer for the purpose of building out.

In terms of the project dimensions, there’s still a lot to be sorted out. The new office building could range from 32,000 SF to 46,000 SF, 3-4 floors, and 25-42 parking spaces. The historic building at 408 North Tioga may be renovated and repurposed for county offices, or sold off as-is. Concept site plans can be seen on the county website here. The vote on the evening of the 16th will only be for the county to purchase the property, and not to choose which development scenario is preferable. To be specific, there are actually three votes planned, one after another – the vote saying the environmental impacts are mitigated, the vote saying that the project is a public resource project exempt from zoning, and the vote to purchase.

The timeline on this project is very quick as local projects go. The county plans to break ground on the office building by this July, and have it occupied by the end of 2020 (this probably means HOLT Architects has concept drawings ready to go right now). The renovation or sale of the historic neighbor would also occur by December 2020. The housing, if any, would be a third phase after the other two components are completed.

The county estimates the total cost of a possible eventual project (designed to LEED Silver standards) to be $18.55-$19.55 million.  That estimate includes new building development ($12.8 to 14.5 million), land acquisition, and related renovation to 408 North Tioga, for which they would allocate $1 million for the 3,800 SF building. The initial acquisition costs would be covered by general county funds re-allocated in an amended Capital Program, and although it’s not clear in this agenda, it seems likely a municipal bond issue would be used to cover the construction costs.

Quick aside, it turns out the county did conduct a feasibility study back in 2011 to see if they could repurposed the Old Library into a county office building. That study, also conducted by HOLT, found that because of the library’s open atrium and unusual layout, the renovation costs made the project infeasible. It’s actually cheaper to build new than it would have been to rebuild the old library’s interior.

2. The Carpenter Business Park development held another community meeting in its quest for a PUD, and the Times’ Edwin Viera described it as “a firm shakedown”. The project has garnered some controversy as it had to shift to above ground parking (the result of soil tests indicating that the soils were in poor condition as they are along much of Ithaca’s West End) and no longer conformed to the site zoning. First ward council member Cynthia Brock made several swings at it for height, density, and the placement of affordable housing on the northern end of the site, for which she has made clear she will not support the PUD request. This is not a surprise, as Brock has not been circumspect with expressing her dislike of any proposed residential uses for the site. Her ward colleague George McGonigal likewise expressed concerns, and the fifth ward’s Laura Lewis noted concerns about traffic – there would be three access points to the 411,600 square-foot project.

Quick refresher – PUD stands for “Planned Unit District”, or as I often call it on the Voice and here on the blog, “Do-It-Yourself (DIY) zoning”. A project need not follow zoning code if it offers certain community benefits. The city recently expanded it for certain non-industrial properties, with Common Council now getting to vote on projects alongside the planning board to determine if community benefits are worth the variance from the legal zoning for a site.

3. It’s been almost two years since it was first proposed, but the mixed-income 46 South (formerly Hamilton Square) project is inching forward in Trumansburg. The Tburg Planning Board is down to the nitty-gritty at this point, exterior finishes, plantings, parking and fencing. The zoning variances have been approved, though the number of parking spaces per unit was bumped up from 1.2 to 1.4 spaces per unit to satisfy zoning board concerns (there will be 144 parking spaces on-site). According to the Times’ Jaime Cone, there was spirited debate over the use of wood trim vs. a lumber composite material (Trex), which is wood fiber mixed with plastic, the plastic cousin of fiber cement. There are still some lingering concerns from the board, but it’s possible that preliminary approval for the project could be granted in May.

The basic project specs have stayed the same in recent revisions – a mix of 17 market rate for-sale homes, 10 affordable for-sale townhomes, six affordable rental townhomes and 40 affordable rental apartments, plus a nursery school. The school, designed by HOLT Architects,has been redesigned to invoke a “barn” aesthetic.

While this may very well come to fruition, this contentious and drawn-out process was effective at repelling other potential developers in the village, so in a way those opposed still got some of what they ultimately wanted. The mixed-income housing may be approved, but it seems very unlikely anyone else will be taking interest in building much in Trumansburg for a while.

4. Normally the Times’ Edwin Viera does a good job as their go-to guy for real estate reporting, but the headline on this piece is a little misleading: “Old Library, Arthaus projects will have to try again for tax abatements”. They weren’t rejected. The IDA was only supposed to review applications this month, the vote is scheduled for next month.

That noted, there is still useful information in his article. We now have some potential rent figures for Arthaus: $737/month for a studio at the 50% area median income (AMI) price point, to $1,752 for a three-bedroom at the 80% AMI price point. At 124 units, the project would be the largest single addition to Ithaca’s affordable housing scene in over 40 years.

As expected, the 66-unit Library Place project garnered the lion’s share of attention and public criticism. Most were opposed, but a few members of the public spoke in favor. I had heard a rumor that Frost Travis offered to set aside three units for 80% AMI, but have yet to confirm. Ithaca mayor Svante Myrick did expressed some reservations with the project for its lack of affordable housing – the CIITAP mandatory affordable housing policy became law shortly after the CIITAP application was filed, so it fell into a legal grey area that the city didn’t want to fight a legal battle over. Travis Hyde also plans to pursue an abatement for Falls Park in due course, and that would have to have an affordable housing component.

5. Quick note – the College Townhouses project at 119-125 College Avenue has a construction loan on file with the county. $18.3 million, courtesy of NBT Bank of Norwich. That’s a heck of a lot than the $10 million estimate first reported when the project first went public. The project unit count is revised upward slightly, from 67 units to 72 units, still a mix of studios, one-bedrooms and two-bedrooms. The unit breakdown is not listed in the loan document, but previously the full occupancy would have been about 90 residents if one per bedroom or studio. Co-developer Phil Projansky signed the loan, which notes that he, John Novarr and any other investors involved have put up $4.47 million towards development of the project.

NBT Bank is a regional bank with a limited Ithaca presence but a major player in other upstate markets. This is their second major project they’ve financed in Tompkins County, the first being a $33.8 million loan for Harold’s Square.

6. The Maguires have reason to be optimistic in Lansing. While the review process has taken longer than anticipated due to concerns over lighting and signage, the village planning board looks likely to sign off on their new 25,235 SF Nissan dealership at 35 Cinema Drive.

7. Dear diary – the Common Council was “excited” and “praised” a project, according to my Voice colleague Devon Magliozzi. One hopes that bodes well for INHS’s Immaculate Conception School PUD application. As previously noted, the project hosts a number of community benefits, including 78-83 units of affordable housing (at least four owner-occupied),  the sale of the former school’s gym to the city for use as a community gym by the Greater Ithaca Activities Center, office space for family and children’s social services group, special needs housing and the renovation and preservation of the Catholic Charities building, which would continue to be used by the organization. The board also praised the outreach by INHS in designing the site, reducing the school addition from five floors to four at neighbors’ request (INHS was able to compensate the loss of housing elsewhere on the site).

This is a good sign, but the city has never issued a major PUD. The only two recent PUDs were the Temporary Mandatory PUDs (TMPUDs) on the West End and Waterfront, which were used in effect to stop the Maguire Waterfront dealership, and the Cherry Artspace, which was incidentally roped into it. Those were 2-8 and 8-2 votes respectively, a denial and a approval. The fact that a rather pedestrian 1,900 SF building in an industrial area got two “nay” votes leads me to be cautious until the ICS documents are signed and filed.

8. On that note, the CDBG and HOME fund disbursals are posted. INHS would get $200k of the $350k requested for the ICS project. The other economic development and housing-related submissions were also mostly or fully funded. Most of the public service ones were not.





Library Place (Old Library Redevelopment) Construction Update, 3/2019

27 03 2019

Not a whole lot to say at the moment – everything above surface level on the site has been cleared as of the end of February, and grading/leveling is taking place. Part of the existing 1960s foundation will be reused for underground parking, and part of it will be taken out. According to the project team, an examination of the existing foundation column footers vs. the blueprints found that eight of the column footers were not where indicated on the as-built drawings. That created a conflict with portions of the new structure, ans so these column footers are being removed (probably by the demolition subcontractor, Gorick Construction of Binghamton; LeChase is the general contractor overseeing the whole project).

It might seem weird, but this isn’t the first time something like this has happened. Half the footers were missing outright at Ed Cope’s Ithaca Glass site, which led to a total overhaul of the project plans (now held by Visum, although I haven’t heard anything about the plan since the transfer was announced in November).

It’s a bit unusual since the project is already underway (or at least, the site prep is), but Library Place has yet to receive approval for a tax abatement. The Tompkins County Industrial Development Authority (IDA) will be receiving the tax abatement application in early April and the board will get their first glance at it on April 10th. A public hearing on the abatement will be held sometime before the May 8th IDA meeting. Assuming the application is approved at the May 8th meeting, pile driving would start within a few days of approval.





Library Place (Old Library Redevelopment) Construction Update, 2/2019

17 02 2019

I’ll admit I’ve actively avoided writing this one up because it has more twists and turns than a soap opera, and it ends up being extremely hard to follow as a result. There are over forty articles from local outlets regarding the site, and Travis Hyde Properties compiled about two dozen of the pieces it liked onto their website. The Voice has eighteen Old Library articles on file, but because of a tag mix-ups, it’s more like thirty. Here’s an attempt to distill everything into one post.

The Old Library site refers to the former Tompkins County Library, located at 310-14 North Cayuga Street. From 1967 to 2000, the library was housed there. However, once the library moved downtown in 2000, the building was used for day reporting for low-level criminal offenders, and for records storage. These were eventually relocated to other properties, and the 38,630 SF would be vacant by early 2015. However, the county didn’t like the idea of hanging onto it. Its unusual interior design (a large atrium) was difficult to adapt to other uses, inefficient from an energy standpoint, and the building’s utilities systems were running short on useful life, and would be expensive to replace. As a result, the building was declared surplus.

The idea of a Request for Expressions for Interest (RFEI), was hatched in late 2013. An RFEI is basically a prerequisite to a Request for Proposals (RFP), feeling out interest by asking for less paperwork – an RFP to RFPs in a sense. While the building was no longer useful for the county’s needs, it sits on a site close to downtown Ithaca, next to historic DeWitt Park (and in the DeWitt Park Historic District). It’s walkable, and the city’s 2013 rezoning allows up to four floors and 50 feet. The RFEI stressed mixed uses with an emphasis on senior housing, and compatibility, energy efficiency, and growth of the tax base. The hope was that someone would use the site to help the county meet its goals, though the county was unsure how it would go – an earlier RFP in 2000 garnered no interest in the property.

As luck would have it, there were six responses to the RFEI, which can be found here. Two, INHS and IAD, dropped out before an RFP went out – INHS had acquired the 210 Hancock site and decided to focus on that. The DPI condo proposal declined to respond to the county’s RFP, citing frustrations with the county’s frequent delays, and that had one of the favored proposals in the feedback I received. The other two “reader’s choices” were Cornerstone’s affordable housing plan, and Franklin Properties collaboration with STREAM Collaborative, which called for reusing the structure of the building.

By the time the RFP has been issued and responded to in April 2015, three projects were up for review – Cornerstone’s 73,600 SF 54-unit affordable housing plan (<80% AMI), Travis Hyde’s 72,500 SF, 60-unit market-rate senior apartments plan, and Franklin/STREAM’s 58,000 SF building, with 22 higher-end condominiums and medical office space. All would pay the county $925,000 for the site.

The next few months were not enjoyable. The Cornerstone project asked for a PILOT tax agreement and lost county support. That left Franklin and Travis Hyde and Franklin Properties. The Franklin project had strong public support. But in June 2015, the county Old Library Committee of legislators recommended the Travis Hyde project 3-2. Two legislators genuinely favored Travis Hyde, one voted in favor just to move it out of committee, one liked the Franklin proposal though expressed some unhappiness with all of them, and one thought all three proposals were outright terrible.

A week later came the full county legislature’s vote – 6-6, a hung vote with two absent. Neither proposal had the eight votes of support needed to move forward. That’s when things started to get ugly. The city’s Common Council and Planning Board submitted letters recommending the Franklin proposal, which ruffled some feathers in the legislature. One legislator was accused of an ethics violation because the Travis family donated to her congressional campaign two years earlier, and recused herself from future votes. The Old Library plan was sent back to committee, where the committee was unable to come up with an endorsement. There was a very good chance neither plan would get the required eight votes, and the county would be unable to make a decision on how to sell off a property they didn’t want. More failed votes ensued.

Finally, in early August, the Travis Hyde proposal got the nod in an 8-5 vote. There was definitely some bitterness afterwards, and an air of unscrupulous behavior. A legislator who switched his support to Travis Hyde would lose re-election to a strong advocate for the Franklin project later that year. He moved districts and into Fall Creek just as the other deciding vote retired from the Fall Creek district; there have been accusations it was orchestrated, but nothing was ever proven, and believe me, my then-editor, Jeff Stein who’s now at the Washington Post, had worked hard to find something.

For the record, this is why I have a strong aversion to RFPs. It works well when there’s one clear choice. But here, the disconnect between suburban and rural legislators, and passionate city residents, as well as all of the fighting and accusations that went with it, really created an unpleasant and rancorous experience. I dread the RFP for the NYS DOT site, which will come up in a year or two.

The project wouldn’t begin to move through municipal review until early 2016. The Ithaca Landmarks Preservation Commission (ILPC), who had stated a strong preference for the Franklin proposal, was first up – there was no point in going to the planning board if the ILPC isn’t on board (and the Planning Board is generally the more accommodating of the two). The project they were first presented had 51 units, 6,500 SF of space for senior services Lifelong, community space (2,000 SF), and a modest amount of street-level commercial space (4,000 SF).

There were eight different designs that the development team submitted in an effort to satisfy the ILPC. Here’s the major ones – One. Two. Three. Four. Five. Six. Seven. Eight, the final design. If you want to be picky, there are some minor revisions too, for things like facade materials tweaks. As review continued, it was decided that it would be more efficient to hold the ILPC and Planning Board meetings on the project at the same time in one group, so that one panel wouldn’t contradict the other.

After several months and several major redesigns, it wasn’t looking good. The ILPC felt that every design was simply too big and one called it “an impossible building”. County staff and officials were getting angry because they felt that the city was trying to spite them, and one planning board member’s comment was effectively “you should do what we tell you to do,” so once again, the project site was in an uncertain and acrimonious situation.

By October 2016, the plans had been modified to be 17 percent smaller, 73,400 SF with 57 units. This included a 950 SF ground-floor commercial space and a 1,900 SF community room to be administered by Lifelong, which had made the decision to stay in its building next door and not move into the new building. Some of the indoor parking was moved to an outdoor rear lot to shrink the structure further, and the fourth floor was set back from the rest of the building. This too was turned down, but there was just enough of a window for possible approval that Travis Hyde decided to give it one more shot.

Frankly, this project was hanging by a thread. Travis had informed the county that he was “bruised and battered”, but would make one last attempt. The last shot was February 2017’s meeting. The foundation of the old library would be reused in the latest design, and the third floor was pulled back from the street. It passed, 4-3. One vote essentially made all the difference. That allowed the project to move forward with environmental review SEQR) from the planning board.

This reviewed version called for 54 senior apartment units, 32 parking spaces, a 2,000 SF community room, 1,160 SF of retail, and 86,700 SF of total space, as the interior parking was now underground as part of the reused old foundation. The sale of the site was approved by the county after the project was greenlighted, in September 2017. The 3 no’s in the 11-3 vote were two Franklin proposal advocates and the legislator who said all the projects were terrible two years earlier, so points for consistency.

The actual interior layout at this point, is something of a question mark. In May 2018, it was announced that the project would be partnering with luxury senior services provider Bridges Cornell Heights on the project. As part of that, the design was updated to 67 units, though there was no change in total square footage. According to the press release, “(o)n site, there will be a restaurant, a la carte home health services from an on-site agency, a community room, courtyard gardens, workout facilities, pool and parking. The partners will also work with Lifelong to provide on-site activities and programs.” Units will be a mix of 1-3 bedrooms, market rate and available to renters 55 and older. The name of the project also changed, from “DeWitt House” to “Library Place”.

Continuing the theme of controversy with the project, by the time financing was secured for the now $17 million plan (up from $14 million in 2014), the building’s roof had become structurally unstable. The fear was that construction workers could be inside if it suddenly collapsed. An engineering report filed by Ryan Biggs/Clark Davis Engineering and Surveying in August led the city’s director of code enforcement to condemn the building. The initial demolition plan was to seal the building up and cart out the asbestos in sealed containers, a “contained” demolition. The new plan was to demolish on site with spraying to prevent airborne contaminants, a “controlled” demolition. This led to community protests, and the mayor threatened to torpedo the project unless a second engineering report was carried out by a third party engineer of the city’s choosing, with no affiliation to Travis Hyde. The second report, from Dende Engineering, confirmed the first report’s findings, so the city okayed, if somewhat begrudgingly, the new demolition plan. In response to the demolition, a neighboring couple wrapped their nearby home and rental buildings in plastic as a dramatic show of concern, which caught the attention of broadcast media.

The project is seeking a tax abatement, but the Tompkins County Industrial Development Authority (TCIDA) has yet to schedule a meeting to review the application and take a vote.

Demolition and site prep is expected to last through the winter, and construction will begin during the spring. A fall 2020 opening is anticipated. Alongside Travis Hyde Properties and Bridges Cornell Heights, the project team includes HOLT Architects for the building design (all eight of them), TWMLA for the landscape architecture, LeChase Construction as general contractor, and Hayes Strategy for marketing. Gorick Construction of Binghamton is handling the demolition, with Delta Engineers, Architects and Surveyors doing the air quality monitoring. The project website is here, as are the air quality reports.

December 9th:

January 19th: