News Tidbits 5/11/19

12 05 2019

1. The proposed revision (downzoning) along West State / MLK Jr. Street is moving forward with circulation (review by city departments and associated stakeholders), with a couple of major revisions. The zoning would not be CBD-60. It would be CBD-52 for structures with less than 20% affordable housing, and CBD-62 for structures with 20% or more affordable housing. The quirk in the height is due to mandatory floor heights, which will be 12 feet for the first floor, and 10 feet for each floor above – in other words, five floors for projects with a lack of affordable units (=< 80% area median income), six otherwise.

For 510 West State Street, in which all 76 or 77 units are affordable (my unit count is 76, but they typed 77 in a couple sport of the Site Plan Review), the project would remain largely intact. The new setback requirement would push the fifth and maybe a very small portion of the sixth floor back from West State/MLK Jr. Street for the mandatory fifteen feet, so a little square footage would be lost there. The city had initially sought thirty foot setbacks, but the Ithaca Fire Department said that it would not be reachable by their trucks if the fifth floor was that far away from the street face.

Now, some more astute readers might be wondering is this affects Visum’s other West End project at 109 North Corn Street. The answer is no. The setback rule only affects buildings fronting West State / MLK Jr. Street. The downzoning is intended to protect an aesthetically pleasing segment of West State more than anything else. The setback does technically apply to West Seneca Street, but the building height there is 40 feet anyway, which is the same as the setback.

The affected blocks now also include the 300 and 400 Blocks of West State Street. The only publicly known project that would be impacted is INHS’s Salvation Army redevelopment, which was only aiming for five floors on the West State Street side anyway, but could potentially be impacted by the setback rule – the project design is still in the concept stages with no public images.

A speaker during public comment asked to extend the zoning further to Downtown, and some councilors have discussed further downzoning because “the developers can just pursue a PUD”. That thought process ignores the drawbacks. The more areas impacted and the more stringent zoning becomes, the more labor and time intensive it becomes for city staff because it would likely trigger more PUDs, even while resulting in less development in general because a PUD adds months to a project timeline, uncertainty that lenders don’t like, and forces the Common Council to take on the role of a second Planning Board (which some councilors might be fine with, but some definitely would not and raised this as a complaint during the vote on whether to create the PUD overlay to begin with). Also, if the downzoning were to be applied to a property against the owner’s wishes, say the County Annex property for example, it would likely trigger a costly lawsuit. TL;DR, it looks tempting for additional “community benefits”, but could have significant negative impacts and should be used sparingly.

2. Staying in the realm of laws for a moment, there’s an ordinance that should be made aware to residents of Northside and Fall Creek. A proposal from 1st Ward councilor Cynthia Brock would require every rental agreement and every home sales transaction within 1200 feet of the Ithaca Area Wastewater Treatment Facility’s boundaries to provide documentation of the potential issues and hazards of living near the plant – “you should be prepared to accept such inconveniences and discomfort as a normal and necessary aspect of living and operating in proximity to a waste water treatment facility,” as the document states.

The document isn’t ill-intentioned, but this does impact over a hundred existing Northside and Fall Creek homes and apartments, and quite reasonably would have a negative financial impact on them, whether they plan to sell or if they rent out space. There is nothing on record that these residents have been notified of this proposal. City staff don’t even seem comfortable with the proposal as-is, they don’t think Fall Creek residents are substantially impacted and suggested a cutoff at Route 13, but the 1200 square foot radius seems to be the version being considered right now, paying a trip to city attorneys to see if it’s legal to apply it to all rentals, a detail added at the meeting. Honestly, this doesn’t seem well thought out at this time, and poses a burden to existing homeowners who have not been made aware because of the lack of sufficient outreach.

3. Arthaus and Library Place have had their tax abatement requests approved, on 7-0 and 6-1 votes. The former will bring 124 affordable housing units including special needs housing and artist-centric amenities to the city of Ithaca at 130 Cherry Street. The latter will provide 66 senior housing units on the former Library property on the 300 Block of North Cayuga Street. Arthaus is expected to start construction at the end of the year, while Library Place will resume this month, with completions in 2021 and 2020 respectively.

County legislator Leslyn McBean-Clairborne voted against the Library Place proposal, citing some of the concerns raise over the lack of affordable housing (three units will now be 80% area median income) and general discontent with the site. In my intro post to the project, I mentioned if vaguely that there was a legislator who thought the affordable housing, condominiums, and Travis Hyde projects were all terrible – that was McBean-Clairborne, who has generally favored county offices on the site instead of housing. The county did a study to consider renovating the old library for offices back in 2011, a couple years before the RFP, but the study found it was financially prohibitive because of the building’s unusual interior layout (that soaring 1960s atrium wasn’t a good use of space, and wouldn’t have been cheap to replace).

4. Carpenter Park is also moving forward, in this case with the pursuit of its special PUD zoning. The project is seeking the PUD because of some quirks in yard setbacks, and soil tests showing that they couldn’t place some of the parking underground as initially planned (so now it’s in an above ground garage between the ground-floor retail and the apartments in Buildings B and C). The project would bring about 411,600 SF of new space, including 208 apartments (42 affordable) and an expansion of Cayuga Medical Center’s medical offices, resulting in the creation of 150 jobs. The vote was 4-1, with councilor Brock opposed. The full council will vote on the PUD next month, and then the project can go to the planning board for design review. Keep in mind that the above designs might change somewhat, though the general scale and program mix should stay the same.

5. The Tompkins County Airport has received a $9,999,990 grant, as announced by U.S. Senator Chuck Schumer at a press conference earlier this week. The county was strongly hoping these funds would come through. With the state grant, it means the county is only paying about $260,000 of the $24.5 million bill. Click the link here to learn more about the airport expansion project.

6. The Gun Hill Residences appear to be in the process of selling. A real estate trade magazine notes Southeastern U.S. regional bank SunTrust is giving the buyer a $13.3 million acquisition loan for DMG Investments LLC. DMG Investments is an American subsidiary of a Chinese development firm, DoThink Group of Hangzhou. The company has been active in upstate recently. DMG co-owns a new 322-bed student housing apartment in Albany and has projects scattered across the country. The full sales price has not been discolosed, as the deed has yet to be filed. It was noted that the ca. 1989, 94-unit, 273-bed Gun Hill Residences on Lake Street was nearly completely full at the time of closing (late spring, which is reasonable given a couple of kids might have washed out of Cornell or otherwise moved out). The property was previously owned by Rochester’s Morgan Communities, which was raided by the FBI last year. Morgan purchased the property in February 2011 for $6.15 million, and the current county assessment for Gun Hill is $12.65 million.

OLD render

NEW render

7. Some modest revisions to the Immaculate Conception School plans. Old render first, new render second. The design of the renovated school building has changed substantially, though the overall size has remained consistent. The changes could be due to any number of reasons, from cost concerns to utilities placements necessitating design changes. The single-family homes have been replaced with a four-string of townhomes, and the yellow string has been earmarked for for-sale units.

If I may – make one of the olive green townhome strings red or orange like the houses that have been removed. Keeps it from being so “matchy-matchy”, to borrow a JoAnn Cornish term. More renders can be found on INHS’s sparkling new website here.

On that note, on Monday May 13th the City of Ithaca will hold a Public Information Session for the proposed PUD (Planned Unit Development) for the Immaculate Conception School redevelopment. The Public Information Session will begin at 4:00 PM, in the Common Council Chambers in City Hall. In accordance with the requirements of the PUD, the developer and project team will present information about the project and answer questions from the public.

8. Looking at agendas:

The city Project Review Meeting (the run up to Planning Board meetings) will look at signage changes for the new Hilton Canopy on Seneca Way, a Presentation and potential Declaration of Lead Agency for 510 West State Street (now 50-70% area median income, initially it was 80-90% AMI), The 141-bed, 49 unit Overlook student housing at 815 South Aurora (updated, and review of Full Environmental Assessment Forms Part 2 and 3), final site plan approval for Arthaus and consideration of preliminary site plan approval for the Chain Works District (the focus right now is the renovations for phase one, office space, industrial space and 60 apartments). Apparently, the “Ezra” restaurant at the Hilton is now being called “The Strand Cafe”, after the theater that once stood on the site. More information can be found in the May project memo here.

The town of Ithaca will continue its review of Chain Works as well. Their portion of phase one involves the renovation of two manufacturing spaces into industrial and warehouse space (i.e. minimal work, just a sprucing up of the digs). Also your casual reminder that, unlike Dryden, Lansing or really any other sizable community in Tompkins County, the town permitted the construction of not a single new housing unit – again – last month. It looks the next stage of Artist Alley ($150,000 buildout) and Cayuga Med’s radiation vault ($2 million cost) were permitted.

It appears that the Beer family is heading back for another visit to the village of Lansing Planning Board regarding their until-now cancelled senior cottages project. The only thing known at the moment about this latest iteration is that it would fit the village’s cluster zoning, which means 97 units or less, but not in the same configuration as before (the pocket neighborhood-style homes were too close for code). We’ll see what happens.

Nothing much to note in Lansing town. Review of the Osmica event venue and B&B will continue, as will consideration of the Lake Forest Circle subdivision renewal and the 12,000 SF commercial building proposed for North Triphammer Road just north of Franklyn Drive.

– Courtesy of the village of Trumansburg, we have a new working title for 46 South Street, formerly Hamilton Square – now it’s “Crescent Way”. PApar krief, including revised EAFs, supplements and BZA findings here. The final version has some site plan changes on the location of some townhouse string types, but the overall unit count remains the same at 73 units (17 market rate for-sale, 10 affordable for-sale, 46 affordable rentals). Approval is on the horizon, a little more than two years to the date of when the project was first introduced. The project will be built in phases, with completion not expected until 2023.

 


Actions

Information

5 responses

13 05 2019
CornellPhD

Great update; had totally forgotten about the Corn Street project admittedly.

Was there housing proposed in Ithaca town for it to reject?

13 05 2019
B. C.

They’ve taken over five years to attempt a zoning overhaul to a form-based code. Few want to propose anything until they know what the new code looks like. (OTOH, the rental registry, which depressed rental units through additional costs, rules and paperwork, was quickly hashed out and practically sailed through the town board.)

17 05 2019
Karl Madeo

I’m wondering about the proposed city ordinance concerning the area around the waste water treatment plant. What kind of “Inconveniences and discomfort” do you think is being referenced?

28 05 2019
News Tidbits 5/27/19 | Ithacating in Cornell Heights

[…] Looks like the number of units has settled on 77. The question here remains what to do with the State Street elevation, given the likely zoning change will force a 15′ setback from the 5th floor instead of the sixt…. […]

23 06 2019
News Tidbits 6/23/19 | Ithacating in Cornell Heights

[…] with bad faith for the moment – the IAWWTF proposal creates some uncomfortable questions. The first proposal was everything within a 1200 foot radius of the plant. The new one is everything west of Route 13 within that 1200 foot […]

Leave a comment