Cornell Law School Renovation Update, 3/2017

28 03 2017

Finally starting to see a little bit of progressing on the renovations to Hughes Hall. The rest of the old masonry wall on the lower floors has been stripped out, and is covered with plastic and plywood for the time being. Eventually, the space will be opened as the new glass enclosure is built for the new west staircase. For the record. the stairwell is completely new; it replaces one that was slightly further to the east, on the inside corner of the building. This gut renovation is down to the studs, and then some. No work on enclosing the loggia just yet.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver is the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete, meaning November 2017 if all goes to plan.

 





Gannett Health Center Construction Update, 3/2017

27 03 2017

The new northeast wing of the Gannett Health Center has been framed, sheathed, and windows have been fitted. From the outside, work is also complete on the new concrete skin for the late 1970s northwest wing, which unlike the original building, it was finished out with concrete instead of stone. Meanwhile, the remaining portion of the original 1950s structure is still undergoing interior work and the new canopy has yet to be erected, so it’ll be a couple of months before the new curtain walls are fully installed. A new roof membrane is also on the to-do list.

Looking closely at the sheathing on the new building, you can see the clips that will be used to attach the new limestone veneer (Cornell has the time and the money for the real deal; most developers opt for less expensive but similar-looking precast concrete). Based off the roofline, it looks like fireproof fiberglass mat gypsum sheathing (in this case, GP DensGlass), followed by a silver moisture protection barrier, and then metal panels or limestone depending on the location.

October 2017 is the given completion date on the Cornell Facilities webpage, but the new building should be open by August; the new landscaping is what will extend into the fall. The Pike Company of Syracuse is the general contractor (they’re also doing Upson Hall nearby), and Downtown Ithaca’s Chiang O’Brien are the designers-of-record.

I did not get as close to the site as I would have liked, because the snow was still quite deep in some spots, and some of my usual vantage points were blocked off.





Cornell Veterinary School Expansion Construction Update, 3/2017

26 03 2017

There’s been quite a bit of progress over at the Vet School. It looks like the exterior glass and aluminum are going on the new library and administrative wing. Windows and sheathing have been installed on the north face as well, with a water-resistive barrier applied over the sheathing. The new atrium is being framed out.

According to the Vet School’s construction update page, interior framing and utilities installations are underway in the new wing, and the new cafeteria is under construction – both are aiming for August completions. The new atrium and lecture hall will be closed off shortly, with interior work to launch in earnest once that occurs.

Thanks to Maria Livingston over at HOLT Architects, readers now know what the new Community Practice Service building will look like. Syracuse’s G. M. Crisalli and Associates Inc. has been selected as general contractor, and construction for the $7 million, 12,000 SF wood-frame structure is expected from March 2017- March 2018.





The Cherry Artspace Construction Update, 3/2017

26 03 2017

The corrugated metal exterior has been attached, the roof is complete, and the doors and windows are being fitted. Once the steel framing was completed, the exterior work was expected to move quickly, as all the components had already been assembled and were just waiting in storage. McPherson Builders is making quick work of the 1,900 SF project.

The Cherry Artspace crew do a great job providing updates on their website, on a much quicker timeframe than this blog. They also have some interior shots, which show the mezzanine area, and the insulation that has yet to be installed. The first show inside the new venue is scheduled for April 20th (for those interested, tickets here).

I did an in-depth interview for the Voice about the Cherry Arts and the Artspace with Director Samuel Buggeln and Associate Director Jennifer Herzog, which I very much enjoyed. A copy of that can be found here.





Tompkins Financial Corporation HQ Construction Update, 3/2017

25 03 2017

Apparently I forgot to to an update on the Tompkins Financial project last month? It must have slipped off the radar after the Voice received its spark notes version. Funny how it was about 60 F when the February photos were taken, and about 30 F when the March photos were snapped.

Anyway, structural steel framing is underway, giving an idea of the bulk of Tompkins Financial Corporation’s new 110,000 headquarters at 118 East Seneca Street. Framing has started for the first five floors of the seven story building, and mor beams will be built upward and outward – note the indents in the elevator core on the side facing Seneca Place, intended for future steel beams. The lowest floors have also received corrugated steel decking. There are still a couple of floors to go, as evidenced by the wood forms on the elevator shaft. The concrete will extend another two floors before it’s topped out. The building’s ground to rooftop height will be exactly 100 feet.

A May or early June topping out seems plausible. Occupancy is intended by March 2018. JPW Erectors, a division of the JPW Companies of Syracuse, is in charge of the framing, while LeChase Construction is the general contractor.

February 2017





Collegetown Terrace Construction Update, 3/2017

22 03 2017

From the outside, Collegetown Terrace’s third and final phase is nearly complete. Some cement panels and clapboards are still being attached at the ends and the south face, and the entry areas need to be finished out, but otherwise it looks like the exterior is mostly finished.

Peering through the windows as the lights clicked on, it looks like drywall has been hung in most of the units, and closet doors and cabinetry are or are being installed, meaning they’re pretty far along and that finishing work is all that’s left for some units (there are 344 units, so it could take a while to do them all). All in all, things look on track for the expected summer completion. Kudos to Welliver for keeping such a massive building on schedule.

\





602 West State Street Construction Update, 3/2017

21 03 2017

The new addition has risen out of the ground at Elmira Savings Bank’s new $1.7 million branch office at 602 West State Street. The cinder block shaft will host the elevator shaft/stairwell, and the steel framing is underway for the new 1600 SF north extension. The non-historic blue paint is being stripped from the bricks of the existing structure, and from the plastic on the roof, it looks like a new roof is being laid, probably EPDM (synthetic rubber) or something similar. The building’s insulation is being updated, and the plan is to have an all-electric HVAC system (heat pumps).

Although the initial press release called for March opening, June or July seems more likely. Elmira Savings Bank will occupy 3,300 SF on the first floor. The second floor, also about 3300 SF, will host for-rent office space. HOLT Architects is in charge of design, and Edger Enterprises is in charge of the buildout. Based off the signage, it looks like John Mills Electric (IBEW Union, Local 241) is doing the subcontracted electrical work.