NYS DOT Sub-Residency Facility Construction Update, 3/2020

23 03 2020

The NYS DOT county facility plans are moving forward. The state bought its 15 acres from Tompkins County for $840,000 according to a deed filed on April 2019, and on its second try, the state secured a competitive bid from Streeter Associates of Elmira. The building is classified as a sub-residency facility, a step below a primary regional facility (the main office for Region 3 is in Syracuse).

The project has been in the works in some form since at least the mid 2000s. The existing waterfront property built in 1958 is cramped, local traffic impinges on operations, and it poses environmental risks (the salt barn is too close to the inlet). The joint planning efforts between the NYSDOT and Tompkins County identified a 10.8-acre site in the Village of Dryden, at the intersection of Ellis Drive and Enterprise Drive, for a new maintenance facility. That property was acquired by NYSDOT in 2006, but it was never built out because internal analyses raised concerns about how quickly trucks would be able to get to state-maintained highways on the west side of Cayuga Lake. DOT still owns that property.

With the waterfront study completed by Fisher Associates in 2015, it became clear that an ideal location would be closer to Ithaca. By the fall of 2016, it became clear that the site near the airport suggested in the previous study, was the location that the county and the state wanted to go with. The county has seen the DOT site as a major component of a proposed airport business park, but lack of demand as noted in the 2016 Camoin Associates study put the kibosh on that plan, and so the NYS DOT will be there by itself for at least the next few years.

To review, the plans consist of the 30,000 square-foot sub-residency maintenance building, a 5,000 square-foot Cold Storage unit, an 8,200 square-foot salt barn, and a 2,500 square-foot hopper building (covered lean-to). The proposed maintenance building will have vehicle storage for 10 trucks, a loader and tow plow, with one additional double depth mechanical bay and single depth, drive-thru truck washing bay. It also includes an office area (three rooms), lunch/break room (30 people), toilet/shower/locker rooms, storage rooms and mechanical/electrical rooms. The site will also contain stockpile areas for pipe, stone and millings, and ancillary site features include parking for 40 vehicles, and stormwater management facilities. A new access drive will be constructed from Warren Road (more specifically, the address will be 960 Warren Road).

The town has been less than pleased with the project, which is not bound to zoning code because it’s a public resource facility owned and operated by a government entity. Rather than voice approval, the planning board voted to acknowledge that they simply had no authority to control the project (in fact, the Federal Aviation Administration [FAA] was the lead agency for environmental review, since the site is in the flight path of the airport’s runway). Some modifications were made to the plans at the town’s request, such as the fueling station being moved onto airport property across Warren Road, but neighbors are still unhappy that snowplows and heavy-duty maintenance vehicles are about to be their next-door neighbors.

The facility is expected to be open by the end of the year. Once all staff and equipment have been moved in, the county may pursue a request for proposals/requests for expression of interest for the current DOT property on the shores of the inlet near the Farmer’s Market. A 2015 feasibility analysis found that the site could conceivably host a $40+ million mixed-use project, and the site has become more amenable towards redevelopment with the enhanced density and use provisions made to the city’s waterfront zoning in 2017.

Presently, the site is being cleared, graded and underground utility connections are being laid. It would appear this will be likely be a “T-shaped” slab foundation – excavate the perimeter for the footers, build forms for the footers and foundation walls, lay down gravel and rebar grids for the slab, pour the concrete for the footers, let cure, pour for the foundation walls and let cure, and then after they’re checked for any flaws after curing, the slab can be poured. The earthwork has been subcontracted out to Binghamton’s Gorick Construction, who also did the demolition and foundation work for Library Place in the city of Ithaca.

Image from the Lansing Star.





Ithaca Tompkins Regional Airport Construction Update, 2/2019

3 03 2019

The spark notes: A multi-component expansion and reconfiguration of a regional airport, the $24.7 million Ithaca-Tompkins Airport expansion will result in six new gates, three new boarding bridges and 15,600 SF of new space, allowing the airport to take on additional flights, larger planes and serve an international clientele. The expansion, which will create at least sixteen new jobs serving the airports growing operation, will be finished by the end of 2019.

Now for the long version. I did a long-form history of airports in Tompkins County back in 2011 here. Ithaca had an aiport down around Taber Street in the 1910s, and a few years later it relocated to where Cass Park is today. The Flood of 1935 quashed hopes for the lakeshore airport, and so Cornell took it upon itself to buy the land in 1944 for an airport from some farmers in Lansing, open said airport in 1948, and operate it as its own airport until transferring ownership to Tompkins County in 1956, finally closing the municipal airport down by the lake. It was just as important for Cornell to get out of its airport as well, as it was a financial drain and managerial headache. The old airport merged into Cass Park in the 1960s and Hangar Theatre came along in 1975. Meanwhile, the regional airport in Lansing was completely rebuilt in 1994.

Although Tompkins County isn’t especially large, it has a couple of things going for it that its regional peers in Binghamton and Elmira don’t. For one, Ithaca-Tompkins is more affluent and enjoys a growing economy. For two, Ithaca’s economy is much more cosmopolitan; Cornell and Ithaca College have students, staff and faculty flying in and out regularly, often with connections to more lucrative international flights. Ithaca’s growth in hospitality and tech have contributed to this as well, as its a comparatively popular choice for visitors from the big East Coast cities. It also helps that major highways don’t actually make it to Ithaca, making driving an even bigger pain for visitors.

In a 2011 NYS Dept. of Transportation study of state airports, it was noted that although Ithaca-Tompkins services an area half the size of Binghamton, it’s economic impact is 25% greater ($66 million vs $52 million), and the airport generates 23% greater revenue ($28.6 million vs. $23.2 million). It also supports/generates 510 jobs (ITH had 204 FTE employees in 2009), vs. 483 for BGM. The study noted that the airport hosted 110,000 passengers in 2009, and generated $5.33 million in state and local tax revenue annually. Since that time, airport teaffic has generally bounced around between 95,000 and 110,000 enplanements (passengers boarding at ITH), with 101,000 enplanements in 2018, and a 9% increase in cargo flights. With arrivals, the number of passengers served exceeds 200k.

My personal recollection of the airport announcement was that it was nearly out of the blue. The Voice, Times and other outlets were given less than a day’s notice by the state’s economic development unit, and talking through the usual back channels (Slack and Twitter), everyone quickly suspected it was airport-related because of the location of the big economic announcement. Sure enough, that’s what it was, with the governor breaking the news. Since then, the pace has been remarkably rapid. As a government-owned public resource, the airport does not have to go through the regular environmental review process, where the village of Lansing declares itself lead agency for review and takes several months or more to make decisions. Here, Tompkins County is the lead agency. Government authorities (state and county) basically tell the village what they were planning to do, and invite their comments for consideration as with any member of the public. In some cases, like with the new DOT building on Warren Road, they’ll also hold public open houses (note that will be a separate construction update series, after it gets underway). The airport project started construction in October (with another visit from the governor), and the intent is for the expanded facility to be open by the end of this year.

C&S Companies is the all-in-one engineer and architect for the project. C&S is a large, multi-disciplinary firm headquartered in Syracuse with offices in nine states and Washington D.C., and has previously provided design and engineering services for ITH. Streeter Associates of Elmira is the Phase I general contractor, having won the bidding process for Phase I ($7.638 million of work) in September. The Ithaca Tompkins airport expansion project is being financed through $14.2 million of funding by the New York State Government, as part of the Upstate Airport Economic Development and Revitalization Competition. The airport is pursuing federal grants worth $10.2 million to fund Phase II of construction later this year, and if awarded, Tompkins County is expected to provide the remaining $260,000. It looks like the county is prepared to issue municipal bonds to cover the $10 million if they have to.

The expansion comes with encouragement from the airlines; United’s Newark flights, which had struggled with on-time departure rates, were replaced with flights to Washington D.C. late last year, and American Airlines added flights to Charlotte were added late last year. Delta Airlines provides an Ithaca to Detroit route, and American also provides an Ithaca to Philadelphia routeThe airport is currently aiming to regain service to the New York City area, a possible Toronto or Montreal route via Air Canada, and obtain a flight route to Chicago. Ithaca-Tompkins will rebrand itself to “Ithaca Tompkins International Airport” with the addition of the customs facility. The airport won’t host regular international flights yet, but it will now be capable of accepting chartered flights from Canada, and increasingly, wealthy Asian visitors have been pushing for direct service.

There has been some pushback from the community, regarding carbon emissions, catering to the wealthy, and the potential presence of ICE, the acronym for the highly controversial Immigration and Customs Enforcement agency. The county legislature has refuted the accusations and claims, saying they would prohibit the facility if ICE were to move in, that the carbon emissions would be even worse if flying into Philadelphia or New York and driving up, and that while they would love more federal money for buses or homeless housing, that’s not how federal earmarks work.  Offhand, the TIGER transportation grant applications for buses and better mass transit get shot down every time (they’re extremely competitive, having only a 10% acceptance rate) – there have been eight attempts by Ithaca and Tompkins County over the past decade, as well as one transit application as part of a regional economic development grant to the state, which also failed. Homeless housing grants through HUD or NYS HCR are also very competitive.

Running down the components of the expansion can be a little disorienting. The May announcement had the following details:

  • Major security enhancements, including updating TSA baggage screening to be compliant with post-9/11 security requirements and adding another line for passenger security screening to alleviate wait times.
  • Reconfiguration of the security checkpoint and relocation of TSA office space as part of a 7,500-square-foot expansion of the passenger hold room.
  • Reconfiguration of airline office space and expansion of baggage screening space as part of a 2,500-square-foot addition on the east side.
  • Baggage security and check-in improvements to streamline the process and improve efficiency.
  • Three new passenger boarding bridges to accommodate jet aircraft and additional service.
  • Six new passenger boarding and departure gates, bringing the total number of gates at the airport to twelve.
  • Addition of 1,700-square-feet of space at the main entrance and an expanded ticket counter to improve passenger circulation and provide more room for ticket lines.
  • Construction of a new 5,000-square-foot Federal Customs Facility.
  • Technology upgrades to include high-speed WiFi, Bluetooth connectivity and additional charging ports and outlets.
  • Food service enhancements, such as expanding a pre-security café and adding 4,000 square feet of space for post-security food concessions.
  • Installation of a separate bus lane and a wind-resistant waiting area for buses, taxis and hotel shuttles.
  • Installation of new plumbing, HVAC, fire protection, mechanical and electrical systems.
  • Installation of a new geothermal water-source heat pump system to reduce natural gas usage for the terminal.

 

Those details were revised and a little more fleshed out in the SEQR forms shared with the county in July 2018:

– The Passenger Terminal Expansion will consist of three additions totaling 15,600 SF. 8.500 SF is an addition to the passenger holding area (which makes flying sound about as comfortable as it feels), 5,400 SF for additional bagging screening space and office space for the TSA and for airlines, and 1,700 SF by the main entrance for expanded passenger circulation and ticket counter space.

– Apron reconstruction, 40,000 SF. The apron is the area where planes park, refuel, and where some passenger loading/unloading takes place.

– Utilities replacement, interior “building enhancements”, one new passenger boarding bridge, and refurbishment of the existing boarding bridge.

– Installation of a geothermal heating and cooling system using 40 underground wells, 350-400 feet deep, and a closed-loop piping system. The operation is similar to a heat pump system, using the earth’s latent heat as a reservoir. The ground disturbance area to install the wells will be about 15,000 SF (~0.35 acres).

– Installation of overhead canopies with solar panels in the airport parking lot.

-Construction of a new 5,000 SF customs facility. The facility will be a one-story masonry structure with steel framing. The facility will accommodate no more than twenty passengers, and is exclusively tailored towards international business visitors – it’s been previously stated that business executives and Asian visitors, who often come in via Canada, have expressed a strong interest in private jet accommodations.

– Approximately ten new employees as a result of the terminal expansion, and six more from the construction of the new customs facility, for a total of sixteen new full-time jobs.

– Cayuga Solar (the new solar extension of the Cayuga Power Plant) will provide electricity to power ground source heat pumps, and solar panels will be erected above the parking lots which will have the secondary advantage of keeping a lot of the snow off of parked cars. It is expected that at least 80% of gas consumption will be eliminated, replaced by the solar power and electric heat pumps. That will save $50,000 annually on utility costs, even with a terminal that is 1/3 larger.

Separately, the state just announced an additional $1.5 million grant for a shared vehicle and aircraft fueling and storage facility. A vehicle fueling facility was originally planned for the NYS DOT site nearby, but had received pushback from neighbors, so the state decided to consolidate it with the aircraft fuel facility and build it on airport land across Warren Road from Borg Warner.

The photos below only show the 1,700 SF addition by the airport’s main entrance; the security situation makes taking photos more complicated than in most places (and my goal is to write news, not make it). At some point, a formal photo tour might be possible, but for now, the photo set is limited.





News Tidbits 1/6/18: Extra Ketchup/Catch-Up

6 01 2018

1. It looks like plans for a new historically-inspired group housing facility are moving along. The Ithaca Landmarks Preservation Commission (ILPC) will review the plans for a new “converted barn” at 310 West State Street at their meeting next week. The project is still in the “Early Design Review” stage, meaning it has a few meetings yet ahead of it.

The developers, David Halpert and Teresa Halpert Deschanes, plan to restore the existing ca. 1880 house, and build the second house as a matter of historic correctness and financial feasibility (the money generated by the new carriage house/barn helps to pay for the expensive renovations needed to the existing home, which is in a poor condition due to previous ownership). The new build’s design won’t be as architecturally unique as they one that was condemned and torn down several years ago, but will reuse a couple of design elements. The previous had an irregular shape, brick finish and mansard roof; the replacement will have a rectangular footprint with Hardie Board (fiber cement) siding and a gable roof, similar to barns from the late 1800s time period it is taking its cues from. The project also comes with new landscaping, fencing and 36 solar panels on the new build’s roof.

The plan is that each house will be its own co-op; a unique attribute for this area. I can imagine some Voice commenters would deride it as an “adult dorm”, but there is a niche market for these adult co-ops as seen with companies like WeLive in New York and San Francisco. The Ithaca Urban Renewal Agency (IURA), which is helping the project paply for state grants, has separately noted that the ILPC has already given indications that the plans would likely be accepted.

2. As part of the RFP for the Green Street Garage development, a few developers took part in a tour of the property conducted by the IURA. According to Josh Brokaw at Truthsayers, Visum Development, Ithaca Neighborhood Housing Services (INHS), Purcell Construction of Watertown/Virginia and Missouri-based Vecino Group were on the tour. Visum has previously commented on site interest, but complained that the RFP parameters were of insufficient length to put an application together – the RFP was modified later in December from 60 to 90 days, short of the six months Visum suggested. INHS may have been there on Rimland/Peak’s behalf, as they’ve been in talk to manage the affordable housing component of that project. Purcell Construction is the firm building City Centre on behalf of Newman Development Group, and Vecino Group (Spanish for “neighbor”, by the way) is a national developer with interests in affordable, supportive and student housing.

It’ll be spring before we find out who submitted what, but it looks like there will likely be a few contenders with Rimland/Peak, even if they have a clear advantage.

3. According to a press release sent to the Times (dunno if anyone at the Voice received it), New Roots Charter School is planning to expand its service by adding 6th, 7th and 8th grade classes to its grades 9-12 program. The move would lead to the enrollment of another sixty students into the school.

It is not clear whether the school plans to stay in the Clinton House downtown or move to another location in the city; should they move, there is a potential opportunity a few blocks away at the former Immaculate Conception School, if the Catholic diocese is willing to entertain the idea.

4. Marketing has officially launches for Tiny Timbers’ Varna project, “The Cottages at Fall Creek Crossing”. The layout of the houses is the same from the initial rendering, but the selected models changed quite a bit. That means something here because, like the Belle Sherman Cottages, this is a case where you buy the lot and house and Tiny Timbers builds that specific house, it’s not a “bring your own plan” setup. The website appears to be down for maintenance at the moment (linking anyway), but realtor Brent Katzmann via Zillow is showing homes ranging from an 812 SF 2 bd/1 ba for $192,900, to a 2,175 SF 3 bd/2 ba for $272,900. The prices are in a sweet spot right in the middle of Tompkins County’s housing market, and lower than most new builds thanks to the pre-fabricated approach Tiny Timbers utilizes. All the home designs were penned up by STREAM Collaborative.

5. Probably worth a quick mention for those who like trying new restaurants – Bol is open at the former Titus Gallery at 222 East State Street on the Commons. Created by the same guys behind Simeon’s, the 1,200 SF restaurant recently opened and is serving up ramens, salads, curries and broths. As you can guess, the theme is bowl-based dishes. Yelp reviews appear to be mixed, but don’t let stop you from giving it a try.

6. In Mayor Myrick’s state of the city speech, a couple of things to watch for in the coming months – movement on a public facilities master plan, and Waterfront development. I and Mike Smith covered this somewhat at the Voice, as has Nick Reynolds at the Times, but the potential to move and consolidate police, fire and city hall could very substantially reshape Downtown Ithaca, as could consolidation of water/sewer and streets in Southwest Ithaca.

Meanwhile, the West End and Waterfront are seen as the potential major development opportunities even with their physical and environmental obstacles, if simply because the number of choice parcels in Downtown and Collegetown is running low, and most other neighborhoods would put up enormous resistance with concerns of quality-of-life impacts. Waterfront development would involve a push to relocate the DEC and DOT facilities, something that the county is also keen on. Residents can also expect some movement on the Green Street Garage redevelopment, while the city does a parking study to determine how much parking is needed with future growth. This is all happening in a good economic but challenging political environment, so 2018 should be an interesting year. Of course, the phrase “may you live in interesting times” is often a damning one.

https://platform.twitter.com/widgets.js

7. Click the link above for a video of Cornell/EdR’s Maplewood advertising itself. The most interesting thing to my eyes is the apparent redesign of the community center, from an edgier modern design to a more traditional style with a gable roof. It looks like it will contain a lounge, exercise room, and perhaps small group meeting rooms (though that might actually just be apartment building study space). The EIS likely does not require any re-review since it looks to be mostly aesthetic changes, with little to any change to program space.

8. Someone’s lovin’ it – the new McDonald’s is open at 372 Elmira Road. Pardon me while I move that one into the “complete” column on the project map. I had in my notes that the store was renovated in 1972, and 14850.com has a photo of the truly original McDonald’s that stood on the site in the 1960s – check out those golden arches.

9. Eye candy for the week – here is the first published render for the Tompkins Center for History and Culture, aka the Heritage Center. As part of the state’s Regional Economic Development Council awards, the project received $1.365 million in grant funds – one, a $1.06 million arts and culture grant, the other a $305,000 economic development grant (the project is intended as a tourism generator and tourist information center). The plan is to have the $1.8 million project open in early 2019.

10. West End Heights (709 West Court Street) is now more likely to move forward this year thanks to $250,000 in Community Housing Development Fund grants from the county and city of Ithaca. The county is giving $100,000, and the city $150,000. The project will bring 60 units of affordable housing, with 30 units reserved for vulnerable individuals getting mental health support, and six for formerly homeless individuals who may have HIV/AIDS. The goal is to start construction this year, with a late 2019 or early 2020 completion.

At its January meeting, the city of Ithaca Common Council also awarded $100,000 to Amici House for its expansion and 23 units of housing for formerly homeless or vulnerable young adults.