NYS DOT Sub-Residency Facility Construction Update, 3/2020

23 03 2020

The NYS DOT county facility plans are moving forward. The state bought its 15 acres from Tompkins County for $840,000 according to a deed filed on April 2019, and on its second try, the state secured a competitive bid from Streeter Associates of Elmira. The building is classified as a sub-residency facility, a step below a primary regional facility (the main office for Region 3 is in Syracuse).

The project has been in the works in some form since at least the mid 2000s. The existing waterfront property built in 1958 is cramped, local traffic impinges on operations, and it poses environmental risks (the salt barn is too close to the inlet). The joint planning efforts between the NYSDOT and Tompkins County identified a 10.8-acre site in the Village of Dryden, at the intersection of Ellis Drive and Enterprise Drive, for a new maintenance facility. That property was acquired by NYSDOT in 2006, but it was never built out because internal analyses raised concerns about how quickly trucks would be able to get to state-maintained highways on the west side of Cayuga Lake. DOT still owns that property.

With the waterfront study completed by Fisher Associates in 2015, it became clear that an ideal location would be closer to Ithaca. By the fall of 2016, it became clear that the site near the airport suggested in the previous study, was the location that the county and the state wanted to go with. The county has seen the DOT site as a major component of a proposed airport business park, but lack of demand as noted in the 2016 Camoin Associates study put the kibosh on that plan, and so the NYS DOT will be there by itself for at least the next few years.

To review, the plans consist of the 30,000 square-foot sub-residency maintenance building, a 5,000 square-foot Cold Storage unit, an 8,200 square-foot salt barn, and a 2,500 square-foot hopper building (covered lean-to). The proposed maintenance building will have vehicle storage for 10 trucks, a loader and tow plow, with one additional double depth mechanical bay and single depth, drive-thru truck washing bay. It also includes an office area (three rooms), lunch/break room (30 people), toilet/shower/locker rooms, storage rooms and mechanical/electrical rooms. The site will also contain stockpile areas for pipe, stone and millings, and ancillary site features include parking for 40 vehicles, and stormwater management facilities. A new access drive will be constructed from Warren Road (more specifically, the address will be 960 Warren Road).

The town has been less than pleased with the project, which is not bound to zoning code because it’s a public resource facility owned and operated by a government entity. Rather than voice approval, the planning board voted to acknowledge that they simply had no authority to control the project (in fact, the Federal Aviation Administration [FAA] was the lead agency for environmental review, since the site is in the flight path of the airport’s runway). Some modifications were made to the plans at the town’s request, such as the fueling station being moved onto airport property across Warren Road, but neighbors are still unhappy that snowplows and heavy-duty maintenance vehicles are about to be their next-door neighbors.

The facility is expected to be open by the end of the year. Once all staff and equipment have been moved in, the county may pursue a request for proposals/requests for expression of interest for the current DOT property on the shores of the inlet near the Farmer’s Market. A 2015 feasibility analysis found that the site could conceivably host a $40+ million mixed-use project, and the site has become more amenable towards redevelopment with the enhanced density and use provisions made to the city’s waterfront zoning in 2017.

Presently, the site is being cleared, graded and underground utility connections are being laid. It would appear this will be likely be a “T-shaped” slab foundation – excavate the perimeter for the footers, build forms for the footers and foundation walls, lay down gravel and rebar grids for the slab, pour the concrete for the footers, let cure, pour for the foundation walls and let cure, and then after they’re checked for any flaws after curing, the slab can be poured. The earthwork has been subcontracted out to Binghamton’s Gorick Construction, who also did the demolition and foundation work for Library Place in the city of Ithaca.

Image from the Lansing Star.





Village Solars Construction Update, 3/2020

22 03 2020

This mostly reuses the Voice gallery writeup, but it’s a chance to publish all the unused photos as well.

***

At the Village Solars site off of Warren Road in Lansing, phase five of apartment construction is underway. 24-unit 36 Village Circle North (3 three-bedrooms, 6 two-bedrooms, 3 one-bedrooms and 12 studios), which replaces an older 12,000 square-foot 10-unit structure, is fully framed, sheathed with ZIP Panels, shingled and fitted with doors and windows. The installation of exterior fiber cement trim boards has yet to happen, perhaps because the Lucente family’s in-house construction team was waiting for warmer weather.

Building M is a new build on previously vacant land. It is an 18-unit building with 12 studios and 6 two-bedroom units. It too is now fully framed, sheathed, and roofed. The sets of wires dangling from below the eaves are utility lines for the air-source electric heat pumps, as construction continues they’ll be bundled together and boxed up into the exterior siding (the heat pumps themselves will be boxed in with a decorative screen in a bump-out). The 50 year-old blue apartment building in the photos below will be torn down later this spring to make way for a larger apartment building.

As previously reported in late February, Rocco Lucente Jr. gave the following timeline for buildout: “We are on time, on budget, the project is going very well. We should have our current two (#36 & #119) completed by June and July. The next two (community center and #117) will come the next summer, and the final two (#2 & 22) will be the summer after that! So by Summer 2022 the current project will be completed.”





3105 North Triphammer Construction Update, 3/2020

22 03 2020

This mostly reuses the Voice gallery writeup, but it’s a chance to publish all the unused photos as well.

***

S.E.E. Associates/Andy Sciarabba’s new 9,600 square-foot office building at 3095 North Triphammer Road is coming along. The cast stone veneer has been attached, the doors and windows have been fitted, and interior steel stud walls are being built for its tenants (units can be merged if desired). At last check just after the holidays, Sciarabba passed along a note to give an update on the business end.

“We have signed one office tenant already, 1300 square feet and have a verbal commitment from another tenant, primary and acute care physician. We can accommodate up to seven tenants and we are using air source (electric) heat pumps. The shell should be ready for tenant fit up in January with the first occupancy about March. Our goal is to bring services to this part of Lansing which currently do not exist.”

The $500,000 project is expected to be completed by next summer. Local architect George Breuhaus is the creator of the design.

Additional project info can be found here.





Lansing Meadows Construction Update, 3/2020

22 03 2020

This mostly reuses the Voice gallery writeup, but it’s a chance to publish all the unused photos as well.

***

There’s been a little bit of controversy lately with developer Eric Goetzmann’s senior housing project on Oakcrest Drive in the village of Lansing. Goetzmann has approached the village and the Tompkins County Industrial Development Agency for permission to convert the rental project to for-sale senior housing. Physically, the changes would be very limited, as it’s mostly the creation of interior lot lines. In terms of concept, though, it’s a more substantial change. The IDA went into private Executive Session to discuss the matter because it involved Goetzmann’s finances and topics of potential future legal action, and the result was that they objected to making them for-sale. The village is willing to consider lot subdivision if Goetzmann and the IDA can work out their differences. Not to delve into speculation behind the Executive Session, but as proposed, it sounds like a 55+ person could buy the unit and let their college kids occupy it, and hope a future Homeowner’s Association handles it. That doesn’t sound like the senior housing the county had in mind.

As approved, the residential components consist of two phases. Four one-story triplexes (12 units total) will be ready for occupancy by the end of July 2020. Two more triplexes (6 units) will be built in a second phase to be ready for occupancy in December 2020. One of the triplexes has been roofed and fitted with windows, a second is fully framed, the third was being framed out, and the fourth was just a concrete pad with sub-slab utility hook-ups poking out. Project planning, design, and construction services are being provided by an all-in-one firm, McFarland Johnson of Binghamton.

A history of the project and an overall description can be found here.