Village Solars Construction Update, 11/2018

21 11 2018

The Village Solars complex is a development project that never truly stops. Lifestyle Properties (the Lucente family) only builds two or three new apartment buildings each year, but after four years of construction, it has resulted in quite a large development. A visit to the site shows the next buildings are just getting underway – based off the latest site plan, it appears to be Building “L” and Building “K”, which is a little out-of-order in that these two were supposed to built in 2020-2021, after another phase that so far remains unbuilt. Building L’s foundation has been formed and poured, with all the utilities poking out of the concrete, to be routed into the framing as the building goes up; Building “K” looks like it’s still in the excavation stage. The crushed stone helps with drainage, site leveling and preventing cracks in the concrete due to settling. That water will be pumped out before the footers are poured.

Each of the two buildings, which have slightly different designs, is designed to host 24 units – 3 three-bedroom, 6 two-bedroom, 3 one-bedroom, and 12 of the one-bedroom “micro-units”, which are 400-500 square feet. Expect a mid-2019 opening for the pair. Next year’s phase likely involves one more apartment building in Phase “4”, as well as the construction on their mixed-use community center building (Building “F”), which will go in that empty space in the last photo. The town of Lansing’s Village Solars amended PDA law (#6 of 2016, to be technical) says the developers are only allowed one more building to be built before the community center must be constructed, and that the center must be built by the end of 2020.





Village Solars Construction Update, 6/2018

16 06 2018

It looks like there’s a lull in the construction at the moment. Both 102 Village Place and 116 Village Circle appear to be complete, though a quick guess would be that 102 Village Place is already occupied, and 116 Village Circle will be ready for its first tenants at the end of the month. The two have a total of 42 units, 24 in the former and 18 in the latter. TCAT is in discussions to add or modify a bus route to service the growing apartment complex, which has already added a couple hundred residents to the area since 2013, with plans for hundreds more over the next several years.

According to the phasing plan, the next phase is to replace 2 Village Circle and 22 Village Circle with a pair of 18-unit buildings. Those would be twelve studios and six two-bedrooms each, replacing two ten one-bedroom unit buildings (net gain of 28 residents, for those keeping in track). Demolition has not yet started on the existing structure, but the most likely plan is to start a little later in the early summer, and have the new pair of buildings ready for a spring 2019 occupancy.





Village Solars Construction Update, 3/2018

24 03 2018

It looks like 102 Village Place is just about complete from the outside, with only some minor finishing work like trim boards remaining on the to-do list. Its peer, 116 Village Circle, is a little further behind, with rough-ins, insulation and drywall in place inside, and exterior facade work underway. The air-source heat pumps have been installed, but not fully hooked up yet. The 42 units in these two (24 and 18 respectively) should be ready for occupancy by the end of the spring.

I never caught it before, but the project docs say the developer, Lifestyles Properties (the Lucente family), will plant over 500 cherry trees on the property as phases concludes and the land is no longer disturbed. Perhaps a few of the saplings below are included in that figure.

According to the phasing plan, the next phase is to replace 2 Village Circle and 22 Village Circle with a pair of 18-unit buildings. Those would be twelve studios and six two-bedrooms each, replacing two ten one-bedroom unit buildings (net gain of 28 residents, for those keeping in track). These would likely start later this year for a 2019 completion.

After that time, Phase 3b, a 20-unit, 20-bedroom mixed-use community building (building “F”, all-new), would also start construction, with the start of phase 4, the 24-unit replacement of 36 Village Circle, to follow in the 2019-2020 timeframe. 3b has to start before Phase 4 if even just one day sooner, as that was added as a stipulation by the town planning board before any new phases commence (presumably, it would also have to be completed in reasonable time). Lifestyle Properties says the two buildings per year phase-in works well for Tompkins Trust Company as lender (its market segment and location can comfortably absorb another 42 or so units every year), and for the in-house construction team and preferred subcontractors. Spring 2022 is the practical conclusion, but there are plans for additional buildings east of the current site, which could add a few hundred more units throughout the 2020s.

Just as a subjective observation, there has definitely been a change in Lansing’s development pattern. It’s still fairly suburban, but the numerous 3,000 SF Cardamone homes that seemed to be ever-underway on cul-de-sacs in the mid 2000s have now been reduced to a trickle – I never see more than 2 or 3 underway at any one time these days, and driving through Cayuga Way, Woodland Park and Whispering Pines is often a waste of gas. However, multi-family is taking off in areas with sewer access, like here at the Village Solars, and with the English Village / Cayuga Orchard properties between East Shore Drive and Triphammer Road. Likewise, the village is getting plenty of infill on its vacant parcels, from large projects like the Bomax Drive Apartments and Cayuga View Senior Living, to smaller ones like Triphammer Row.

There’s some evidence to back that up – according to the federal HUD Building Permits Database, from 2003-2006, Lansing town and village approved 187 single-family homes and not a single multi-family unit. From 2013-2016 (the latest available), the two approved 92 single-family homes and 148 multi-family units.





Village Solars Construction Update, 1/2018

24 01 2018

Work continues at the Village Solars apartment project in Lansing, though it’s mostly been interior construction these past couple months. 102 Village Place has had some of its composite wood siding applied (LP SmartSide treated and engineered wood siding), and the electrical wiring and air-source heat pump units are in place, though not fully connected just yet.

102 VP was already framed, roofed and fitted by the November visit, so chances are, they’ve already done utilities rough-ins and insulation, and they’ve moved on to drywall, baseboards and interior trim boards, priming and painting, and maybe some plumbing fixture and cabinetry installs. The three-story apartment building, which replaces a ten-unit 1970s structure, will have 24 units – 12 studios, three 1-bedroom, six 2-bedroom, and three 3-bedroom. If one wants to look at this from a population perspective, each of the ten units was a 1-bedroom, so the back of the envelope says there will be a net gain of 26 residents (one per bedroom, 36 – 10). And presumably, a couple million dollars in assessed value.

116 Village Place, the younger of the pair, is not as far along but has been fully framed, wrapped and shingled since November, and some siding has been attached. It looks like not all the windows have been fitted, given the wrapped rough opening on the third floor in the first photo below. Based off the open door in that same photo, it looks like framing, insulation and utilities rough-ins (plumbing, electrical, HVAC) are ongoing. 116 is the smaller building of the two, with 18 units, 12 studios and six 2-bedrooms. Like 102, it also replaces an older apartment building, an eight-unit structure of one-bedroom units (and 14 more residents on-site, using the same math as before).

Lifestyle Properties is the developer, with their in-house contractor in charge of construction. It doesn’t look like the new units are being marketed yet, but existing 2-bedrooms are going for $1,325/month, and 3-bedrooms for $1,375-$1,720/month. Anecdotally, Lifestyle has had an easier time filling the smaller units than the larger 3-bedroom units.





News Tidbits 12/9/17: Not Enough Time in the World

9 12 2017

1. The good news is, Maplewood is progressing. The bad news is, it is not progressing fast enough. A combination of bad weather (rain-outs), and staffing issues. The weather delays had been so bad (with rain 2.5x monthly normals in October) that some subcontractors walked away to take other jobs – while the ~200 Maplewood construction jobs are quality union labor, it’s been difficult to get a full week’s work in. It’s a Monday-Friday job; with a rain-out, they lose a day in the week. That means they also lose out on a day’s pay. Over the past year, 37 days have been partially or fully rained out. A provision in the subcontractors’ contracts allows them to leave for other jobs id the issue becomes too severe, so some have done just that. Not hard feelings, just a tough situation for everyone.

Now about 25 days behind a very tight schedule, EdR and LeChase are asking to be allowed to regularly work 8 AM – 4 PM Saturdays. The town is open to this, but wants more documentation before signing off. So, expect a six-day workweek during the winter and spring. The goal is still to deliver the $80 million, 872-bed project by July.

2. The Seneca Street Garage is “showing its age”. As the garage is now about 45 years old and is designed to last about 50 years, some components are starting to deteriorate. The city has constructed some shoring posts to keep the concrete pillars relatively stable. They are not at risk of collapse, but the tension cables, which are used in combination with rebar to provide for a heavy-duty concrete structure with fewer columns, are starting to wear out. Decades of salt, water and corrosion will do that.

The city will lose about 20 parking spaces from the life-extension measures. The Times is reporting that the city hopes to get another ten to fifteen years out of the garage, and hope to have a plan for replacement parking in place within ten years. That could be a demo and rebuild of the garage, or it could be something more substantial, like the Green Street Garage project. It’s something to mull over now, but there are no big decisions planned anytime soon. Perhaps a Seneca Street rebuild with mixed uses ends up being one of the big urban developments of the late 2020s.

3. A development site on West Hill has exchanged hands. As covered previously, Bella Vista was a planned 44-unit condominium project on Cliff Street that was approved in 2007, and never came to fruition. The site it was proposed for, an 11.71 acre property at 901-999 Cliff Street, was put up for sale in December 2015 for $395,000. Finally, it has been sold.

The developer, Mauro Marinelli as Primary Developers Inc., sold the land to American Blue Sky Holdings LLC for $330,000 on the 5th. The LLC is owned by local businessman Greg Mezey, who previously bought the 12,000 SF medical office building next door at 821 Cliff Street for $945,000 in February 2015. Since then, he and realtor Ryan Mitchell have undertaken some modest building and site improvements. As Red Door Rentals, they own and manage a few apartment houses with a total of about 25 bedrooms.

So what does that portend here? Good question. Watch and wait, for now. The Bella Vista project could still be built, but it must be re-approved by the city of Ithaca, since project approval is only good for two years. Zoning is R-3a, primarily residential uses with up to 4 floors and 35% lot coverage. Parkin is one space per unit or three bedrooms (whichever produces more), and small-scale commercial is allowed with a special permit. The site’s topography is a challenge, but the size of it and its proximity to downtown and the West End make it an interesting opportunity.

4. It looks like the first phase of Dryden’s Maple Ridge subdivision has just about filled out. For owner/developer Paul Simonet, it’s been a long time coming – the development launched right before the recession in 2008, and development didn’t really take off until the economy recovered. In 2013, there were three houses. By November 2014, only four houses had been built, with a duplex underway. Now, there are ten homes, and just about all one of the home lots have been sold. Some of the lots in phase one were combined by buyers.

Interesting, many of the homes built in Maple Ridge are modulars – I half-jokingly suggest that Carina Construction take prospective buyers through here to show them the variety of options one can pursue with modulars. It looks like this latest build on Applewood Lane will also be a modular – the foundation is built (note the dark Bituthene membrane for moisture protection), and the pieces will be trucked over and craned and assembled shortly, if they haven’t been already.

Ultimately, Maple Ridge is supposed to be three phases and 50 lots, and phase two will have about 29 lots, and since these are larger, they’re less likely to consolidated as phase one’s were. Given the need for a new road and infrastructure, sales seem unlikely until well into next year. The village minutes (the few they upload) does show that Simonet is actively pursuing the second phase.

It also answers a question from last week – the Elm Street office/warehouse complex will be the new home of the Ithaca Ice company, after some modest renovations.

5. The Lakeview affordable housing plan for the 700 Block of West Court Street, now called “West End Heights” was selected to receive a $100,000 grant from the inter-municipal and Cornell affordable housing fund (CHDF), but the funds will be delayed a little bit because they need to be moved into the 2018 budget, as the check will be going out in 2018.

6. The latest phase of the Village Solars (the reconstruction of 102 and 116 Village Circle) is being built with a $6 million construction loan from Tompkins Trust Company. The agreement was uploaded to the county’s records on the 7th. The contractor is “Actual Contractors LLC” with an address at Stephen Lucente’s home on the lake – it’s their in-house construction crew. Albanese Plumbing will be rigging sprinklers, heating and water pipes, T.U. Electric will be doing electrical and fan installations, and Bomak Contractors of Pennsylvania is the subcontractor for excavation, bedding and foundation work. Apparently Larry Fabbroni, the consulting architect, charges $90/hour for design work, while engineering/surveying is $107.50/hour.

102 and 116 comprise 42 units (24 and 18 units respectively), but if you’ve been reading the construction updates for the project, then you already knew that. The loan says both buildings have to be completed by August 15th, 2018.

7. Not a whole lot going on at the moment. Lansing town will be hosting a Planning Board to look at a telecommunications tower, and three new 1-acre home lots to be carved from a larger lot off East Shore Circle. The city’s project review meeting is so slim, they didn’t need to attach any files – just the old business with the Sophia House addition on the Knoll, and that’s it. The city Board of Public Works will be looking at plans for a new inclusive playground at Stewart Park.





Village Solars Construction Update, 11/2017

25 11 2017

Another redeveloped building is underway at the Village Solars property along the 1000 Block of Warren Road in Lansing. The original 8-unit, 8-bedroom 116 Village Circle is no longer of this world; the early 1970s structure was torn down to make way for a new three-story building with 6 2-bedroom units and 12 microunits (400-600 SF). Along with the framed and sheathed 102 Village Place, that means that Lifestyle Properties does in fact have two buildings underway at the site; perhaps the last visit in September just happened to catch the project during a brief lull.

102 Village Place has been fully framed, sheathed, roofed, windows and doors have been fitted, and the fiber cement siding is just beginning to be installed (possibly by T&J Contractors of Auburn; most construction work by Lifestyle Property/the Lucente family is handled by an in-house crew). On the inside, expect electrical, plumbing, and HVAC to be underway; with no open doors or windows, it was not clear if they’re hanging drywall yet. In comparison to the “older” new apartment buildings, these new ones have different fenestration and even have stone veneer at the bases, though the overall building designs are generally similar. It’s not completely certain what the purpose of all the eaves (eavelets?) are on the walls of 102, though given the utility lines, it may have something to do with weather/ice protection for the air source heat pumps, which are shielded by small eaves and wood lattice on the latest completed apartment buildings.

The replacement structure for 116 Village Circle is just starting the framework for the second floor. As previously noted, it’s not uncommon to just housewrap over the rough openings, and cut out the holes later. The excess will be trimmed off and the edges will be fastened back to the inside wall, allowing for a tight and complete wrapping of the rough opening. Taking a guess, 102 will probably be done by the end of March, and 116 the end of June perhaps.

Side note, I’ve never noticed the Village Solars construction crew put a flag up on topped-out structures before.





Village Solars Construction Update, 9/2017

1 10 2017

It looks like the Village Solars are moving along, albeit at the slowest pace in years. Since 102 Village Place was torn down back in June, the site was cleared, the foundation and underground utilities reconfigured, and framing has begun on its replacement. The wood frame was up to the top floor by the time of this late September site visit, and erection of the roof trusses was due to take place in just a few days. The housewrap is already in place, and as the interior receives its frames, pipes, wiring and rough-ins, work will being on window and door fittings. Probably looking at an early spring finish here.

Note that it’s not uncommon to just housewrap over the rough openings, and cut out the holes later. The excess will be trimmed off and the edges will be fastened back to the inside wall, allowing for a tight and complete wrapping of the rough opening.

Interestingly, none of the other tear-downs or new building sites have started, meaning that only one building is currently under construction. That’s rather unusual for Lifestyle Properties, whose in-house construction crew typically works on 2 or 3 buildings at a time. There was a dirt pile near one of the future building sites, but it’s been that way for a while, so it’s likely being used as a staging area. The limited construction suggests that the Lucentes may be falling behind their anticipated construction timeline, which generally calls for two or three buildings a year in order to stay on track.