Lansing Meadows Construction Update, 3/2020

22 03 2020

This mostly reuses the Voice gallery writeup, but it’s a chance to publish all the unused photos as well.

***

There’s been a little bit of controversy lately with developer Eric Goetzmann’s senior housing project on Oakcrest Drive in the village of Lansing. Goetzmann has approached the village and the Tompkins County Industrial Development Agency for permission to convert the rental project to for-sale senior housing. Physically, the changes would be very limited, as it’s mostly the creation of interior lot lines. In terms of concept, though, it’s a more substantial change. The IDA went into private Executive Session to discuss the matter because it involved Goetzmann’s finances and topics of potential future legal action, and the result was that they objected to making them for-sale. The village is willing to consider lot subdivision if Goetzmann and the IDA can work out their differences. Not to delve into speculation behind the Executive Session, but as proposed, it sounds like a 55+ person could buy the unit and let their college kids occupy it, and hope a future Homeowner’s Association handles it. That doesn’t sound like the senior housing the county had in mind.

As approved, the residential components consist of two phases. Four one-story triplexes (12 units total) will be ready for occupancy by the end of July 2020. Two more triplexes (6 units) will be built in a second phase to be ready for occupancy in December 2020. One of the triplexes has been roofed and fitted with windows, a second is fully framed, the third was being framed out, and the fourth was just a concrete pad with sub-slab utility hook-ups poking out. Project planning, design, and construction services are being provided by an all-in-one firm, McFarland Johnson of Binghamton.

A history of the project and an overall description can be found here.





Library Place Construction Update, 1/2020

17 01 2020

Library Place is making progress over at 105 West Court Street (the new mailing address; guess we should stop saying 314 North Cayuga Street now). The concrete masonry unit (CMU) northeast elevator/stair tower has topped off, and it looks like part of the northwest tower is being assembled now. The square holes above the lower levels of the tower are most likely slots for structural steel. If I’m reading the floor plans right, a third stair tower will be constructed along the south wall of the building. The concrete foundation footers have been poured, and a CMU foundation wall is being assembled; the pink materials along the outside of the wall are lightweight polystyrene insulation boards, Owens Corning Foamular from the looks of it. I see a work truck on site for subcontractor Gorick Construction of Binghamton, but rather surprisingly there’s no signage around for general contractor LeChase Construction.

Signs along the perimeter fence advertise a Spring 2021 opening for the four-story, 86,700 SF building. Prices for the 66 senior housing units are not yet available. Amenities will include a restaurant, à la carte home health services from an on-site agency, community room, courtyard gardens, workout facilities, warming pool, and underground parking. Senior services non-profit Lifelong will provide on-site activities and programs.

More information about the history of the project and its stats can be found here. The project website is here.





Lansing Meadows Construction Update, 12/2019

21 12 2019

In the interest of brevity, I’m going to hold off on writing most of the backstory – as Dan Veaner at the Lansing Star noted, the project had at least nine major changes over nine years, and was a discussion topic at no less than 58 meetings. Several articles can also be found on the Voice here.

Lansing Meadows is a $14 million mixed-use project consisting of the BJ’s Wholesale Club that opened in 2012, wetland creation (done outside the area in the Cayuga County town of Montezuma), and a residential component on Oakcrest Road that was a stipulation of the village of Lansing as part of the creation of the Planned Development Area. The senior housing on Oakcrest is being built on wetlands created by an overflowing culvert in the 1970s, when the mall was built. The rest of the site was a vacant, unofficial dumping ground for materials. Whether they’re new or old, by law wetlands removed by development have to be replaced.

The project also has a payment in lieu of taxes (PILOT) with the Tompkins County IDA, which was controversial when granted (PILOTS and abatements for retail projects are generally discouraged), and as the years went on and the sentiment was that the developer, Eric Goetzmann of Triax Management Group d/b/a Arrowhead Ventures LLC, was dragging his feet on the residential and the county had started to take legal steps to “claw back” the $2.32 million in benefits before Goetzmann finally put something forth. Even then, the residential portion had to go through a few iterations in order to come to a mutually-acceptable plan with the village. The final set of plans were approved in June 2019.

As approved, the residential components consists of two phases. Four one-story triplexes (12 units total) will be ready for occupancy by the end of July 2020. Two more triplexes (6 units) will be built in a second phase to be ready for occupancy in December 2020. All units are senior rental housing, set aside for those aged 55+.

The two end units in each building will be 1252 square feet with a 395 square foot garage. The center unit will be 1114 square feet with a 251 square foot garage. Although not explicitly stated, the square footage appears to be in the ballpark for new two-bedroom or two-bedroom plus den apartments. The units all face a one-way private loop road, called “Lansing Meadows Drive”. Being a one-way allows it to be narrower, yet still meet the village’s specifications and allowing on-street parking. Project planning/design/construction services are being provided by an all-in-one firm, McFarland Johnson of Binghamton.

Framing and sheathing has been completed for one of the 1.5 story triplexes, with framing underway on a second and foundation work ongoing with the next two. The framing is standard wood frame on a concrete slab foundation with underground utility hook-ups, and the sheathing is the ever-popular Huber ZIP plywood panels. Windows and doors have been fitted into the most complete unit, and the roof has been shingled. Rather interestingly, it looks like vinyl trim boards are already in place on the eaves of the structure, something that usually doesn’t come along until much later in the construction process. On the inside, it appears that mechanical, electrical and plumbing rough-ins are ongoing.

The space on the easternmost end of the parcel is intended to be developed at a later date for a small-scale (~2,000 SF) commercial retail component, possibly a small restaurant or coffee shop.

 

 

 

 





Library Place Construction Update, 10/2019

10 11 2019

Quoting the roundup at the Voice:

“With the foundation piles in place, wood forms have been erected for the pouring of the concrete footers and exterior foundation walls for the four-story building. Part of the old library’s foundation is being reused in the project, but the two buildings have somewhat different footprints, so some new foundation walls are necessary. The rebar extended from the steel piles is encased in concrete and capped, and the steel bolts rising out of the cap will tie into the structural skeleton of the building above. Underground water pipes are being connected from the building to the city’s water system this week.

You might notice some similarities with the Cornell project with the forming and pouring walls, but also note some big differences as well – some of the building sites in Cornell (the sophomore village buildings) don’t require deep foundations. The soil on the hills is in better shape than it is in the more low-lying areas, and can generally handle a heavier load. This gives Cornell the benefit of being able to do quicker, less expensive foundation work in those areas where a shallow foundation is feasible.

The $17 million mixed-use building, which will contain commercial space, space administered by Lifelong and 66 senior apartments, is anticipating opening at the tail end of 2020 or early 2021.”

One thing that’s not readily apparent quite yet is that there’s a partially underground parking garage below the primary structure. That garage does not extend all the way to the street except for the entrance, which is where the fence gates are (and where these photos start from). You can eyeball the perimeter walls from the three concrete wells partitioned off in various boxes – the northern one, seen in the fourth photo, will house an elevator, mechanical room and stairwell, the middle one next to the excavator will house the trash room, and the southern one, next to the huge stack of masonry blocks, will house a maintenance room and southern stairwell.





105 Dearborn Place Construction Update, 8/2019

7 08 2019

The 12-bedroom, 16-person luxury senior home under construction at 105 Dearborn Place is substantially complete. The stone veneer is being attached to the base, and Schickel Construction is building up the porte cochere, with decks and patios soon to follow. Landscaping and paving will come at the end of construction. Also, note the heat pump on the exterior in the lower right of the third photo. The exterior finishes appear to be durable, detailed and of high quality, befitting for a high-end independent living facility. According to developer, Bridges Cornell owner Elizabeth Classen Ambrose, the new building will have a “grand opening” event later this year. Some lavish renders from the project website follow at the end of the post (I have no idea what the small structure is next to the house – a playhouse for visiting children?). Quick aside, while this blog refers to the project by its street address, Bridges staff prefer it be called “The Craftsman”.

An interesting side note, Classen Ambrose picked up the relative new (2005) single-family home at 116 Dearborn Place for $900,000 on June 6th. However, no redevelopment is planned. Apparently, some fraternities had been looking at the property, and to prevent some raucous neighbors from moving next door, she bought the property and intends to rent it out as she sees fit. It’s not uncommon to hear in the Voice comments, “if you don’t want [xyz] happening next door, buy it,” and in Classen Ambrose’s case, she did. Classen Ambrose has also joined the City Harbor development team as a project investor, and by the time this piece runs, there will be a related piece of news on the Voice’s website.

More background info about the project can be found here and here.

 





Library Place (Old Library Redevelopment) Construction Update, 8/2019

7 08 2019

With tax abatement approvals in hand, construction on the 67-unit Library Place project is set to move forward. According to the project website, at the moment 20 steel test piles are being driven into the ground to verify the correct depth to the subsurface layer that will support the weight of the structure (the library’s foundation is being reused, but the new 4-story building is heavier and has additional load bearing needs). If all goes well, the remaining 60 piles will be delivered and driven into the ground, with pile driving work to wrap up around Labor Day. This is somewhat later in the year than first anticipated.

It looks like the pile driver in the photos below came from Ferraro Pile and Shoring Inc. of Buffalo. Some grading and surveying equipment is also scattered about the site. LeChase Construction is the general contractor for the project, and Travis Hyde Properties is the developer for the senior housing project.

Quick aside – I can generally tell how familiar readers are with Ithaca when they email asking questions about “Mr. Travis Hyde”. Quick refresher, Travis Hyde is led by company president Frost Travis of the locally prominent Travis family of developers, and his brother-in-law, company vice-president Chris Hyde.

The 50 year-old time capsule from the Old Library was recovered and opened in a public ceremony; coverage of that and the contents can be found courtesy of my Voice colleagues here. The full history of the project and a description of the plans can be found here.





105 Dearborn Place Construction Update, 5/2019

24 05 2019

We’ll change up the format a bit for this post. Below is a recent email from Ithaca resident Joan Jacobs Brumberg:

I had an opportunity to talk yesterday with Elizabeth Classen Ambrose who is the organizational power behind a growing Bridges community. I wanted to find out more about Library Place interiors but we ended up spending a fascinating hour talking about The Craftsman, a new kind of Ithaca residence for the elderly resembling the group homes in Holland and Denmark.

Four things about this project — to be completed in November 2019– strike me as important for the public to know:
1. This is a new form of independent living for 16 older folks who do not want home or apartment to care for. Each individual room is lovely with private bath and fireplace, small refrigerator. I believe you bring your own furnishings, ie.,  the things you care about most.
2. No upfront payment and no lease.
3. Residents have access to special Car Share vehicles and also Bridges shuttle service if they do not drive.
4. Many amenities for the elderly: warming pool, gym, a trainer, maybe podiatrist and physical therapy. And a special add on: garden space.

I told some people my age about this facility and everyone asked “How did you learn about it?” Even if they are candidates for Library Place, my friends have older parents, relatives, and friends who are burdened with private homes or apartments that are increasingly hard to care for.

***

It came as part of an article pitch for the Voice, but since I did an article about Bridges for the Voice two years ago, I declined. The website for the new house is online, with plenty of rather sumptuous interior renders (a few embeds are below many more are on the website). The twelve bedrooms (eight single-occupancy, four double-occupancy for couples) will feature heated floors, fireplaces in some units, large-screen televisions, optional dry bar with refrigerator and hot beverage maker, and private deck or patio areas. Other planned features include an on-site fitness center, storage room, car share, spa and salon services, on-site concierge, and lush landscaping befitting a high-end independent living facility. Residents are expected to be able to go about their daily activities with little to no assistance, but cooking, cleaning and laundry are taken care of by staff. Pending “interviews” by staff for compatibility, residents may even be allowed to have their pets join them.

Schickel Construction has the house largely finished from the outside. Painting of the cedar shingles continues, and architectural detailing/trim (balconies, porch columns) is ongoing. The stone veneer has yet to be attached to the built-out cinder block basement level, but all of the windows and most of the doors have been fitted. No photos of the back side, because there was a kitchen staffer on break who was clearly uncomfortable with this shutterbug.

More background info about the project can be found here.

 





News Tidbits 5/4/19

4 05 2019

1. Generally speaking, when the opposition is opposed to the aesthetics rather than the purpose, then a project is in good shape for IDA approval. That looks to be the case with the Vecino Group’s Arthaus project. The 124-unit all-affordable (50-80% area median income) project at 130 Cherry Street will be seeking IDA approval for an abatement at the May meeting, after hosting its public hearing this month (minutes here). As noted by the Ithaca Times, apart from complaints about it being too big or ugly, there wasn’t much in the way of opposition to the premise of the project, which is what the IDA is more interested in. As far as the IDA is concerned, aesthetics are something to be handled by the Ithaca Planning Board; if it’s okay with the PB, then it’s okay with them. Chances are pretty good that the abatement will be granted. The abatement is worth about $3.73 million towards the $28.8 million project.

2. It may have taken two tries to get the zoning variance approved, but Habitat for Humanity is moving forward with its redevelopment and new builds at 1932 Slaterville Road in the town of Dryden. The existing 19th century farmhouse will be renovated into a four-bedroom home, a first for the local chapter. The land will be subdivided into two additional one-acre parcels for a new three-bedroom home on each lot, about 1,100 SF each. Each home will cost about $70-$75,000 to build, and the goal is to have them ready for occupancy by mid-2020.

Habitat homes are typically sold to families making under 60% of Area Median Income (AMI), or about $36,000/year. The homes would have built with a combination of professional contractors and volunteer labor, including 350+ hours of “sweat equity”, where the future homeowners actively work as members of the construction crew. In a market starved for affordable housing, every little bit helps.

3. We don’t tend to see many big commercial or industrial buildings listed for sale (if in part because there aren’t many), but it looks like the TransAct Technologies building at 20 Bomax Drive in Lansing is now for sale. Now, before anyone gets nervous, the business isn’t going anywhere; they’ve always leased the space since the building opened in 1998 and have a triple-net lease.

A triple-net lease means the tenant pays everything – insurance, maintenance and real estate taxes (formally, net insurance, net maintenance and net real estate taxes on the leased asset – the three nets).  As a result, the rent is substantially lower than it otherwise might be. It may not be all that lucrative, but the property ends up being a fairly safe investment (though with a lot of fine print to determine who pays for things like if a tornado hits or the foundation cracks), generating a modest amount of rent and functioning like an inflation-protected bond, but guaranteed by the lessee rather than the government. All the better when the tenant is stable and signed on for the long-term as TransAct has been.

For just under $6 million, the buyer gets a fairly new industrial building on 7.54 acres with 18,066 SF of office space, 55,759 SF of warehouse and manufacturing space, and the security of a long-term tenant. This will not be an exciting sale, but it’ll be interesting to see who the buyer is. Warren Real Estate is the seller’s agent, and the offering description with financial data is here.

https://platform.twitter.com/widgets.js

https://platform.twitter.com/widgets.js

4. A little bit of soapboxing. I’ve been seeing and getting some messages to this effect lately. First, I’ll note that the first comment is a bit disingenuous. That’s the highest-priced three-bedroom unit. To quote the range of prices from the Ithaca Times:

“Affordable in this case will include rents for people making 50-80 percent of Area Median Income (AMI), which means that rents for studios will be between $737 and $1180 per month, to 1,095 and 1,752 [per month] for a three-bedroom apartment, the highest price.”

Anyway, the comments tend to be to the effect of “this isn’t affordable enough, so I can’t support it”. That’s a textbook case of letting the perfect getting in the way of the good. Here is a project with 124 affordable housing units, with 40 of the units set aside for formerly homeless youth and families with on-site supportive services from TC Action. It would do a lot of good to have this project available to the community.

Honestly, the argument feels like the next evolution of the arguments against affordable housing in general. Now that it’s firmly ingrained that there is a lack of affordable housing in Tompkins County and it does negatively affect the community, the next step is to say, essentially, that nothing is good enough. From a pragmatic stadnpoint, since these projects aren’t something banks and credit unions will fully finance because of the lack of a sizable return on investment, it falls to NYS to award grants. The state will not dispense larger tax credits to make a unit drop from 60% AMI to 30% AMI, that’s up to the developer to make up the bigger financial gap. To do that, either they add in higher-priced units to compensate, or the project doesn’t happen. Which is probably the end goal for many of the complainers anyway. It’s kinda like saying you’re available for a date, but only to those who are millionaire PhDs.

Anyway, weigh each project on its merits. But set reasonable goals.

5. As reported by Dan Veaner at the Lansing Star, developer Eric Goetzmann is seeking changes to the senior housing to be included as part of the Lansing Meadows project. The primary changes are making Lansing Meadows Drive into a one-way street (thus allowing it to be slightly narrower while still able to host on-street parking), and making each duplex into a triplex – three senior housing units per string, for a total of thirty. As a result, the units will be slightly smaller, though still two-bedroom apiece. The two end units in each building will be 1252 SF with a 395 SF garage. The center unit will be 1114 SF with a 251 SF garage. The third change is that Goetzmann and his project team want to amend the approvals to allow the sale of units in the future (the initial plan still calls for market-rate rentals).

This comes with a set of issues that need to be sorted out. The project has to be complete by July 2020 as required by the village in their approval resolution. The village planning board now has to consider the proposed amendments and consider whether they constitute a major change from the approved Planned Development Area (PDA, the village’s DIY zoning). Doing so would either cause the plan to be delayed and violate the resolution, or if declined for further consideration, the resolution would likely trigger a lawsuit between the village, Goetzmann, and the county IDA, who granted an abatement to Lansing Meadows. If they say the changes are minor in the context of the PDA, then construction is expected to start as soon as the amended PDA is granted (May 13th at the earliest).

The plan is to build the northern triplexes first, and then the southern units. The planning board’s not a fan from an aesthetics perspective, but the village’s code officer that the northern half is more elevated, so this reduces stormwater risks. With construction underway and loose soil on the site, if built later the exposed northern half could result in runoff and flash flooding downhill, into the southern half and its new homes. The commercial component on the east side of the property cannot legally be built until all residential units are completed.

It’s been nine years since this project was first pitched, and most stakeholders just want to get this project out of their hair. It’s not clear when that will happen.





News Tidbits 4/24/19

25 04 2019

1. Here’s a real estate sale worth noting. A vacant 25-acre parcel of land between 1758 and 1786 Trumansburg Road (just south of Jacksonville) sold for $140,000, according to a deed filed with the county today. What makes this sale interesting is that the buyer is an LLC associated with the operating address of Classen Home Health, the senior healthcare firm run by local businesswoman Patty Classen. The Classen family has not been shy about investing in development projects, though her sister Elizabeth is the more active one at present. Elizabeth owns the Bridges Cornell Heights skilled care facility, and  is also involved as a partner in Travis Hyde Properties’ 66-unit Library Place Development. Taking a semi-educated guess, there’s a good chance this property will be developed out into senior housing at a later date, so it’s worth keeping an eye on.

2. Meanwhile, over in the village of Lansing, the former Autodesk Building has exchanged hands. The 19,470 SF office building on 2.37 acres sold for $4.14 million, from the Colbert family of commercial landlords (Greenstate Properties) to an LLC led by local businessman and developer Bryan Warren of Warren Real Estate. The Colberts developed the property and opened the building in 2002. The price was substantially more then  the assessment of $3.15 million, but that’s probably not because of a planned redevelopment. It likely has more to do with having a tenant lined up for the building, the Alcohol and Drug Council of Tompkins County, who will build out and operate a 40-bed detox facility at the site. A stable, long-term tenant is a strong asset to have when selling a property. The village of Lansing has not been a fan of the project (the argument being, those in treatment “don’t belong [here]” and pose a safety threat), but since it’s just an interior renovation and medical uses are permitted in its zoning, there’s not much the village can do as long as everything remains in compliance with code. The sale may be finished, but the facility won’t host overnight stays until at least the summer, and the renovations won’t be finished until late 2020.

3. How often do I report things out in Enfield? Practically never. But the town planning board is reviewing a pair of small apartment projects this month. Patrick Head, owner of Head’s Excavating, plans to build a pair of four-unit apartment buildings, each on a different site in the town. The first would be at 1795 Mecklenburg Road, and the other on the southwest corner of Enfield Center Road and Van Dorn Road. All of the units would be rentals, two bedrooms each, and according to the Environmental Assessment Forms, it looks like each unit will be about 1200 SF, with either two floors or one floor with a finished basement. Both properties are currently vacant; the former used to host a farmhouse but was destroyed by fire in September 2015, and the later is a vacant 5-acre lot that was created through the subdivision of a larger property.

4. Sticking with the rural towns for now – out in Danby, plans are underway for a new mixed-use project at 1839-1849 Danby Road. The development calls for a small commercial retail plaza and a space for a cafe or restaurant, as well as additional residential rental space. 1839 Danby Road is a two-family house with six bedrooms, and 1849 Danby Road is a four-unit apartment house with six bedrooms, along with a couple of garages and sheds.The historic portions of the homes would be saved and incorporated into the development, which is designed to incorporate sustainable building practices (green roofs, alternative energy sources), and create a “town center” like sense of place in the hamlet of Danby. That includes a small B&B, a seasonal food market, and the small market/cafe. Ultimately, if successful the project would expand out to fifteen housing units and two more commercial spaces. It’s not big by most standards, but it’s notable for a 3,500-person town. Property owner Olivia Vent is the developer, and the plans are being designed by Ben Rosenblum Studio.

5. According to the town of Dryden’s planning department, the medical project at 2141 Dryden Road will be fairly modest in size – two floors, 3600 SF. The 908-acre Mill Creek subdivision on Caswell Road is listed as 40 lots, up one from the previous 39, though it could just be something like a stormwater parcel. Also of note, the Route 13 development study from Warren Road to the western boundary of the village of Dryden. With several large development floated for the corridor, the county has an RFP out to do a study for “strategic guidance” so as to allow development while minimizing potential negative impacts (traffic, environmental degradation from in-commuters, etc.) The RFP for that closed on the 22nd.

6. Will the Lansing Meadows senior housing ever happen? Developer Eric Goetzmann of Arrowhead Ventures is trying to change the senior housing in the Lansing Meadows project again. Given that the village and the county have had it up to their proverbial necks with his shenenigans, this has the potential to be very poorly received. The approved plan as it stands is for twenty two-bedroom units. It was supposed to start construction last year, but was delayed a year due to construction bids coming in higher than anticipated. Either the bids have come in too high again and he’s trying to value engineer the project, or some other issue has arisen. We’ll see how this one goes next Monday.





News Tidbits 4/11/19

12 04 2019

1. Chances are very good that the county legislature will approve the purchase of the former orthodontics office on the 400 Block of North Tioga at their meeting next week. At least two subcommittees are recommending it, the feasibility study came back with reasonably positive results, and there appear to be no significant hurdles to moving forward. Representatives of the neighborhood sent in a letter with 25 or so signatories requesting the county build or deed away some land to build affordable housing on the Sears Street (rear) frontage of the lot, which is something the county is actively exploring but has yet to make a firm commitment to. It could range from townhouses, to three single-family homes, to two duplexes and a single-family home, to nothing, so 0-5 units, but the city and neighbors would appreciate at least a few homes to maintain neighborhood character. It’s doubtful the county would build the housing, but could deed lots to INHS or another affordable developer for the purpose of building out.

In terms of the project dimensions, there’s still a lot to be sorted out. The new office building could range from 32,000 SF to 46,000 SF, 3-4 floors, and 25-42 parking spaces. The historic building at 408 North Tioga may be renovated and repurposed for county offices, or sold off as-is. Concept site plans can be seen on the county website here. The vote on the evening of the 16th will only be for the county to purchase the property, and not to choose which development scenario is preferable. To be specific, there are actually three votes planned, one after another – the vote saying the environmental impacts are mitigated, the vote saying that the project is a public resource project exempt from zoning, and the vote to purchase.

The timeline on this project is very quick as local projects go. The county plans to break ground on the office building by this July, and have it occupied by the end of 2020 (this probably means HOLT Architects has concept drawings ready to go right now). The renovation or sale of the historic neighbor would also occur by December 2020. The housing, if any, would be a third phase after the other two components are completed.

The county estimates the total cost of a possible eventual project (designed to LEED Silver standards) to be $18.55-$19.55 million.  That estimate includes new building development ($12.8 to 14.5 million), land acquisition, and related renovation to 408 North Tioga, for which they would allocate $1 million for the 3,800 SF building. The initial acquisition costs would be covered by general county funds re-allocated in an amended Capital Program, and although it’s not clear in this agenda, it seems likely a municipal bond issue would be used to cover the construction costs.

Quick aside, it turns out the county did conduct a feasibility study back in 2011 to see if they could repurposed the Old Library into a county office building. That study, also conducted by HOLT, found that because of the library’s open atrium and unusual layout, the renovation costs made the project infeasible. It’s actually cheaper to build new than it would have been to rebuild the old library’s interior.

2. The Carpenter Business Park development held another community meeting in its quest for a PUD, and the Times’ Edwin Viera described it as “a firm shakedown”. The project has garnered some controversy as it had to shift to above ground parking (the result of soil tests indicating that the soils were in poor condition as they are along much of Ithaca’s West End) and no longer conformed to the site zoning. First ward council member Cynthia Brock made several swings at it for height, density, and the placement of affordable housing on the northern end of the site, for which she has made clear she will not support the PUD request. This is not a surprise, as Brock has not been circumspect with expressing her dislike of any proposed residential uses for the site. Her ward colleague George McGonigal likewise expressed concerns, and the fifth ward’s Laura Lewis noted concerns about traffic – there would be three access points to the 411,600 square-foot project.

Quick refresher – PUD stands for “Planned Unit District”, or as I often call it on the Voice and here on the blog, “Do-It-Yourself (DIY) zoning”. A project need not follow zoning code if it offers certain community benefits. The city recently expanded it for certain non-industrial properties, with Common Council now getting to vote on projects alongside the planning board to determine if community benefits are worth the variance from the legal zoning for a site.

3. It’s been almost two years since it was first proposed, but the mixed-income 46 South (formerly Hamilton Square) project is inching forward in Trumansburg. The Tburg Planning Board is down to the nitty-gritty at this point, exterior finishes, plantings, parking and fencing. The zoning variances have been approved, though the number of parking spaces per unit was bumped up from 1.2 to 1.4 spaces per unit to satisfy zoning board concerns (there will be 144 parking spaces on-site). According to the Times’ Jaime Cone, there was spirited debate over the use of wood trim vs. a lumber composite material (Trex), which is wood fiber mixed with plastic, the plastic cousin of fiber cement. There are still some lingering concerns from the board, but it’s possible that preliminary approval for the project could be granted in May.

The basic project specs have stayed the same in recent revisions – a mix of 17 market rate for-sale homes, 10 affordable for-sale townhomes, six affordable rental townhomes and 40 affordable rental apartments, plus a nursery school. The school, designed by HOLT Architects,has been redesigned to invoke a “barn” aesthetic.

While this may very well come to fruition, this contentious and drawn-out process was effective at repelling other potential developers in the village, so in a way those opposed still got some of what they ultimately wanted. The mixed-income housing may be approved, but it seems very unlikely anyone else will be taking interest in building much in Trumansburg for a while.

4. Normally the Times’ Edwin Viera does a good job as their go-to guy for real estate reporting, but the headline on this piece is a little misleading: “Old Library, Arthaus projects will have to try again for tax abatements”. They weren’t rejected. The IDA was only supposed to review applications this month, the vote is scheduled for next month.

That noted, there is still useful information in his article. We now have some potential rent figures for Arthaus: $737/month for a studio at the 50% area median income (AMI) price point, to $1,752 for a three-bedroom at the 80% AMI price point. At 124 units, the project would be the largest single addition to Ithaca’s affordable housing scene in over 40 years.

As expected, the 66-unit Library Place project garnered the lion’s share of attention and public criticism. Most were opposed, but a few members of the public spoke in favor. I had heard a rumor that Frost Travis offered to set aside three units for 80% AMI, but have yet to confirm. Ithaca mayor Svante Myrick did expressed some reservations with the project for its lack of affordable housing – the CIITAP mandatory affordable housing policy became law shortly after the CIITAP application was filed, so it fell into a legal grey area that the city didn’t want to fight a legal battle over. Travis Hyde also plans to pursue an abatement for Falls Park in due course, and that would have to have an affordable housing component.

5. Quick note – the College Townhouses project at 119-125 College Avenue has a construction loan on file with the county. $18.3 million, courtesy of NBT Bank of Norwich. That’s a heck of a lot than the $10 million estimate first reported when the project first went public. The project unit count is revised upward slightly, from 67 units to 72 units, still a mix of studios, one-bedrooms and two-bedrooms. The unit breakdown is not listed in the loan document, but previously the full occupancy would have been about 90 residents if one per bedroom or studio. Co-developer Phil Projansky signed the loan, which notes that he, John Novarr and any other investors involved have put up $4.47 million towards development of the project.

NBT Bank is a regional bank with a limited Ithaca presence but a major player in other upstate markets. This is their second major project they’ve financed in Tompkins County, the first being a $33.8 million loan for Harold’s Square.

6. The Maguires have reason to be optimistic in Lansing. While the review process has taken longer than anticipated due to concerns over lighting and signage, the village planning board looks likely to sign off on their new 25,235 SF Nissan dealership at 35 Cinema Drive.

7. Dear diary – the Common Council was “excited” and “praised” a project, according to my Voice colleague Devon Magliozzi. One hopes that bodes well for INHS’s Immaculate Conception School PUD application. As previously noted, the project hosts a number of community benefits, including 78-83 units of affordable housing (at least four owner-occupied),  the sale of the former school’s gym to the city for use as a community gym by the Greater Ithaca Activities Center, office space for family and children’s social services group, special needs housing and the renovation and preservation of the Catholic Charities building, which would continue to be used by the organization. The board also praised the outreach by INHS in designing the site, reducing the school addition from five floors to four at neighbors’ request (INHS was able to compensate the loss of housing elsewhere on the site).

This is a good sign, but the city has never issued a major PUD. The only two recent PUDs were the Temporary Mandatory PUDs (TMPUDs) on the West End and Waterfront, which were used in effect to stop the Maguire Waterfront dealership, and the Cherry Artspace, which was incidentally roped into it. Those were 2-8 and 8-2 votes respectively, a denial and a approval. The fact that a rather pedestrian 1,900 SF building in an industrial area got two “nay” votes leads me to be cautious until the ICS documents are signed and filed.

8. On that note, the CDBG and HOME fund disbursals are posted. INHS would get $200k of the $350k requested for the ICS project. The other economic development and housing-related submissions were also mostly or fully funded. Most of the public service ones were not.