Cornell Law School Renovation Update, 5/2017

24 05 2017

Externally, not much has changed since March, although it looks like work is starting on enclosing the north loggia. The Fork and Gavel Cafe is closed for renovations through September, but a carry-out offshoot will serve in its place. Most of the work on this $10.2 million project is internal, converting former dorms into academic office and support space. With any luck, the next visit will be from the inside.





Cornell Veterinary School Expansion Construction Update, 5/2017

24 05 2017

So many projects in the final stretch up on East Hill. The Vet School expansion’s multipurpose atrium is in the process of being closed up with its curtain wall glazing. An interior shot from the start of May shows interior stud walls are up and utilities rough-ins taking place, but drywall, interior trim and fixtures had not been undertaken.The concrete for the “grand staircase” had just been poured.

The atrium will be called “Takoda’s Run“, in honor of a greyhound adopted by alumna Janet Swanson (for whom Cornell’s wildlife rehabilitation center is named). The Swanson family are major university benefactors – Janet, Class of 1963, has given millions of dollars to the Vet School since the mid-2000s. Husband John (BS 1961, B.M.E. 1962, M.M.E. 1963), an engineer and tech executive, has given tens of millions to the university. The atrium in Duffield Hall and a lab suite in Weill are named for him, as well as several endowed professorships, fellowships and scholarships. Not just leaving it to Cornell, the couple has buildings named after them at Washington and Jefferson College in Pennsylvania, and a $41 million donation to the University of Pittsburgh led to the Swanson School of Engineering. My former editor at the Voice is definitely not a fan of this practice, but for those with a lot of money to burn, naming opportunities can be found or scoffed at here.

From the outside, the new administrative and library wing haven’t changed much since March, but at this point all Welliver has left is some window installs, exterior panels and finishes. Since I’m on a kick at the moment, the Flower-Sprecher library is named for former governor Roswell Flower (1892-94) for allocating funding, and in the early 1990s, Dr. Isidor Sprecker ’39 (Americanized from Sprecher) donated a substantial sum for renovation. It looks like some underground utilities work is going on out by the curb, possibly in preparation for the new landscaping and lighting fixtures.

The new Community Practice Service Building is underway, although I don’t have photos – the Poultry Virus Building has been demolished and the site was being cleared and readied for new construction. The timeline for the new 12,000 SF HOLT Architects-designed building is May 2017-May 2018, a couple months later than originally programmed.

The project seems to be a little bit behind schedule. The project team was initially aiming for a June completion, which was a little optimistic. The new schedule calls for an August opening.

 





Upson Hall Construction Update, 5/2017

22 05 2017

Home stretch for Upson Hall’s $74 million makeover. Nearly all of the turquoise water-resistive barrier (WRB) has been covered up with terracotta panels and aluminum inserts at this point. The utilities shaft and mechanical penthouse have been faced with a water resistant base layer and aluminum clips, and will be faced with grey metal panels. Note that those thin yellow aluminum plates on the exterior are a finished design featurethey’re intended to be a nod to the original canary yellow aluminum curtain bands that once lined Upson Hall’s facade. At this point, the upper three floors are occupied, the lower two floors and basement are being finished out, the exterior is nearly complete and interim landscaping features will be installed by The Pike Company before the building opens for full occupancy in August.

Over the next ten years, Cornell would like to utilize LTL Architects and Perkins + Will to redo the rest of the Engineering Quad with designs similar to Upson Hall. The $300 million plan also calls for the demolition of Carpenter Hall and a new multi-story building on the corner of Campus Road and College Avenue. Whether or not those things happen remains to be seen. The earliest renders of the Upson Hall plan are included at the end of this entry, and while the general design has remained the same, some of the design features, such as the shape of the bump-outs, the fenestration, and the emphasis on the south terrace were revised before the final plan was drafted.





Tompkins Financial Corporation HQ Construction Update, 4/2017

25 04 2017

I could see the clouds to the north and west, I knew the rain was coming. I even glanced at a radar still on my phone and assumed that, as most fronts tend to do, it was moving west to east in a diagonal SW-NE band – by that logic, I had about fifteen minutes to take photos, run to my car and get my umbrella. As it turns out, the front was pushing north to south. So I did not have fifteen minutes. I had five. Oops.

Anyway, TFC’s new HQ is topped out and decked with corrugated steel (a bit sooner than anticipated), though it’s not built out – the rear (north) flank and the east flank are missing. Those are the portions that will be built over the surface parking. You can make out a couple of the support piles in the pics below, and those will tie into the structural columns in the garage area, and into the structural steel of the upper levels. As noted with 201 College, it’s a bit unexpected that the structure would top out before even a single floor is built out, but it is what it is. The building’s height is there, but in terms of breadth, it’s less than half of the final product. The elevator core is at full height, and the steel stud wall and gypsum sheathing on the back separate the future ground-floor bank branch from the rear parking, which will be reserved for customers and clients. Pipe scaffolding has been erected as workers begin work on the interior (sprinkler system, utilities rough-ins).

Occupancy is intended by March 2018. JPW Erectors, a division of the JPW Companies of Syracuse, is in charge of the framing, while LeChase Construction is the general contractor. HOLT Architects penned the 110,000 SF building’s design.





201 College Avenue Construction Update, 4/2017

19 04 2017

Dropping by Visum Development Group‘s 201 College Avenue project, I was a little surprised that one half of the building is so much further along than the other half.

201 College is a “H” or dumbbell-shaped structure – the bridge between the two halves hosts the elevator shaft and part of the circulation (hallway). The west wing has completed structural framing, the exterior stud walls are being installed, and even some of the sheathing (fire-rated GP DensGlass fiberglass mat gypsum) is up on the ground level. Peering inside, it looks like some of the interior stud walls have already been set.

In contrast, the east wing isn’t that much further along than it was two months ago – the ground level masonry has been built-out, but the structural steel has not advanced since the February update. It’s not a sign of any difficulties, and other structures have taken or are taking similar approaches – Tompkins Trust’s new HQ has topped out, for example, but the north and east wings have yet to be built out beyond the elevator core. Still, it will take several weeks for the east wing to catch up when William H. Lane Inc. moves ahead with that side of the structure.

According to the construction loan docs filed with the county, the 33,398 SF project is being funded with a $7,870,673 loan from Pennsylvania-based S&T Bank, separate from the $2,640,000 from Visum and its backers that went towards purchase of the property. Hard costs, which are the construction materials and labor, comprise $6,841,038 of the loan, while soft costs comprise $506,984 (permits, legal, marketing, architect and engineering fee, liability insurance, financing costs such as loan fees/taxes/recording costs). An additional $300,000 serves as contingency (your “cover your butt” cash in case of unexpected expenses or poor occupancy rates), and $226,158 is set aside as interest reserve (a special savings account that pays the lender interest on the construction loan while the building is under construction – the objective is to get the building done and occupied before the reserve runs out).

The timeframe is quite tight on 201 College, with a planned August 2017 opening. The rest of the building should move along quickly over the next few months.





Village Solars Construction Update, 4/2017

19 04 2017

At the never-ending Village Solars apartment complex in Lansing, Building “I” is nearly complete from the outside. It sports a few details that make it stand apart from earlier phases – the balconies railings are a different design, a dark-colored fiber cement board is being used for some of the balcony alcoves, and the heat pumps have been hidden away under a wood lattice screen. Given how clean the immediate project site is, it would not be a surprise if this building is aiming for a May 1 occupancy.

Meanwhile, Building “J” is a little further behind – the windows and doors have been fitted and the roofing is complete, but the exterior wood grain and fiber cement panels are still a work in progress, as is the building trim. The doors on the upper levels will likely lead to small juliette balconies like those seen here. Inside, it’s stud walls and rough-ins, and there did not appear to be any drywall hung yet.You can see the unscreened Daikin heat pumps in the fourth photo below. It looks like the roofing was done by T and J Associated Contractors out of Auburn.

It doesn’t look like work has started on Phase 4 yet, which should consist of the last three buildings in the first stage of build-out (“K”, “L”, and “M”). If it’s anything like the previous phases, the construction team will start with the Phase 4 site clearing this summer. The later stages of development call for multiple phases to the east, and possible replacement of some of the older 1970s apartment buildings with newer structures [3/22 Town Board Minutes]. Potentially, the complete build-out would be around 423 units, from 400 SF studio micro-units to 1,185 SF three-bedroom two-bath apartments. Keep in mind, that would be several years out, well into the next decade. Along with those units come community space, retail components, expanded trail and outdoor components and a bus stop.

Rents look to be in the middle of the market – the micro-unit studios start at $865/month, going all the way up to top-of-the-line three-bedroom units at $1680/month. One-bedrooms and two-bedrooms start at $950/month and $1260/month respectively.

While looking around, an older gentlemen walking his dog went in and out; dunno if it was a relative of the Lucente family (the owner/developers, d/b/a Lifestyle Properties), or a curious onlooker.

 





Cornell Law School Renovation Update, 3/2017

28 03 2017

Finally starting to see a little bit of progressing on the renovations to Hughes Hall. The rest of the old masonry wall on the lower floors has been stripped out, and is covered with plastic and plywood for the time being. Eventually, the space will be opened as the new glass enclosure is built for the new west staircase. For the record. the stairwell is completely new; it replaces one that was slightly further to the east, on the inside corner of the building. This gut renovation is down to the studs, and then some. No work on enclosing the loggia just yet.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver is the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete, meaning November 2017 if all goes to plan.