Maguire Ford-Lincoln Construction Update, 1/2020

18 01 2020

The new exterior cladding is going up on the renovated and expanded Maguire Ford-Lincoln at 504 South Meadow Street. Generally speaking, the materials consist of Alcoa ribbed aluminum panels on the back and sides, Alpolic aluminum panels on the front, and painted panels on the old service wing being retained and incorporated into the renovation. For automakers, aluminum panels are often the desired finish of choice because it projects a clean, modern image, and automotive sales are all about pushing the latest and greatest technologically-advanced four-wheeled machines out onto the roads. You can see on the rear wall how rails are attached to the exterior wall, and the panels are attached to the rails above the sheathing. (The reason why the facade wasn’t finished out in that section is because they’ll be installing an awning atop the ribbed panels.)

Many of the windows have yet to be fitted, and the old service wing is still sheathed in Tyvek housewrap while it waits for its exterior panels given the way it was flapping in the breeze, the contractor might want to use more fasteners). The curved “airfoil” feature with the Ford blue oval has yet to be installed at the front entrance, but there are spaces on either side of the entrance that suggest where it will be attached to the main structure. The Lincoln logo will go above 2×3 black aluminum swatch on the northeast corner next to the entrance, as requested by Ford corporate design guidelines. Initially, the plan was to have an exposed concrete masonry base, but late in the review process they upgraded to stone veneer, which lends a more upscale and aesthetically pleasing appearance to the structure. It does look like some windows were changed or deleted when compared to the last set of drawings from review, but minor fenestration alterations are typically a minor enough change that re-review isn’t warranted.

According to a filing with the Tompkins County clerk on January 13th, CFCU Community Credit Union is lending the Maguire Family of Dealerships $5,362,500 to fund the renovation and expansion. This is unusually high; the Site Plan Review estimated the cost of the project at $1.5 million. The loan notes that fees and other expenses mostly related to the mortgage total $1.788 million, which still lends a very substantial $3.574 million towards the construction project itself, to be paid out in six payments, and all except about $12,000 of that going to the general contractor, G.M. Crisalli & Associates of Syracuse. The terms of the agreement stipulate a completion no later than July 1st.

Background information and project details can be found here.





Maguire Ford-Lincoln Construction Update, 10/2019

8 11 2019

Over at 504 South Meadow Street, the concrete foundation pad is in, and the exterior masonry block wall and steel frame appear to be built out. Fireproof gypsum sheathing board are being attached to the structural steel at the back – interestingly enough, the building doesn’t appear to have exterior stud walls, so it’s not 100% clear if the west windows as depicted in the renders will make it into final product. Lighter gauge steel at the front denotes future architectural details like the curved foil vestibule and the modern, clean image Ford wants its franchisees to project. That part’s not really negotiable. Maguire is required to follow a preset design language and the architect (John Snyder Architects) has to keep the design within those bounds. Some interior steel stud walls can be seen in the building’s interior, though it doesn’t appear much progress has been made on the utilities rough-ins (mechanical, electrical, plumbing).

To give an idea of that corporate design language, the recently renovated Maguire’s Ford Lincoln in Palmyra Pennsylvania also has the curved foil vestibule, large glassy facade facing out into the public lot, and muted light and dark greys with aluminum (Alpolic) metal composite panels. The architects can decide where those features go and how they fit together, so long as they fit together in a way Ford approves (and Ford does weigh in – they rejected some of the Planning Board’s ideas, so Maguire had to sort of meet the two stakeholders halfway with details like the rear/west wing masonry. It’s not Ford’s particular desire, and it’s less than what the Planning Board wanted, but they accepted the compromise).

It’s always struck me as a little odd to put in curbing while heavy duty vehicles are still coming in and out of the construction site given the possibility of crushing the newly-laid curbing, but it’s not all that unusual. The new curbing (laid by machine, kinda mesmerizing to watch) gives an idea of where the new greenspaces will be on site. The planning board was very adamant about having a certain percentage of green space on the dealership lot when reviewing the project, which will be filled in with a number of trees and ornamental shrubs much later, when construction is nearly complete.

The last I checked, although approvals have been granted, the Maguire Nissan on Cinema Drive in Lansing village did not yet appear to be underway. The Nissan brand will move to that new 25,200 square-foot location when it is complete.

I’d expect this $1.5 million, 24,110 SF project to be ready sometime next spring. Background writeup and project description here.





Maguire Ford-Lincoln Construction Update, 8/2019

14 08 2019

The north wing of the Maguire Ford-Lincoln dealership is about as gutted as it can get, with nothing left but the foundation footers, the concrete slab, and the structural steel.

New rebar is being kept on site for the foundation slab of the new additions, with a steel mesh likely intended for the concrete pour. The mesh will be laid into the excavated footprint and used to strengthen the concrete as the slab hardens. It’s a little hard to tell from a distance (the fencing perimeter is quite large, given that some of the site is still actively in use for car sales), but it looks like wood forms have been assembled for pouring and curing of the foundation walls and footers for the northwest addition – the northeast addition is not so clear, because the large soil mound blocks it from view. The trailer on site belongs to Breton Construction of Attica, perhaps for subcontracted excavation or foundation work. G. M. Crisalli & Associates is the general contractor.

The last I checked (drive-by a few weeks ago), work had yet to start on the new Maguire Nissan in the village of Lansing. Nissan will relocate from this site to their new showroom across town when it is ready in about a year. (It’s a strange combination of automakers. Ford and Nissan shared design and mechanical work on the Nissan Quest/Mercury Villager minivan back in the ’90s, but I can’t think of any other overlap between the brands.)

Project information and a detailed history and description of the Maguire Ford-Lincoln reconstruction can be found here.

Final site plan.





Maguire Ford-Lincoln Construction Update, 5/2019

2 06 2019

When the Maguire Carpenter Park proposal was shot down in November 2016, that wasn’t the end of the company’s expansion plans. Maguire is by far the largest auto sales firm in the county, and is the 11th-largest employer with about 440 employees as of 2018. Auto makers expect constant refreshing of facilities to keep up with their designs; a failure to maintain the preferred aesthetics and desired features in a sales facility could result in the loss of privileges to sell the latest models rolling off the assembly line.

There’s also another factor that goes into vehicle sales, that being vehicle service, which is a large share of Maguire’s business (something like 40%). People don’t like to travel far to get their vehicles inspected and repaired. This limits Maguire’s ability to move to just the urban and inner suburban parts of the county; the town of Lansing might have offered them land at the Town Center, sure, but the Town Center site is too far away from most of the county’s population for the Maguires to maintain a viable business operation.

While the Chrysler-Fiat dealership was refreshed and modestly expanded a few years ago, the next phase of projects is more substantial. Maguire Ford-Lincoln-Nissan will be the first of those projects. Located at 504 South Meadow Street on the southwest side of the city, it is a two-story auto dealership on 3.11 acres, originally built in 1983 and expanded in 1999. Maguire will be demolishing some of the older portions and building new additions – the southern half of the building, used more for service, will remain largely intact from the outside, though the interior will be renovated. The northern half is where the bulk of the work will take place. The existing building is 18,500 SF, with 2,265 SF proposed for demolition and 7,865 SF of additions. The new building will be 24,110 SF.

The goals of the project are to meet Ford’s revised corporate standards and customer experience requirements, and improve interior circulation while expanding the Ford/Lincoln sales area (quick note for those unaware, Lincoln is the luxury sister brand to Ford; Mercury was the upscale in-between brand, before it was shut down a decade ago). The Nissan dealership will move to a brand new 25,300 SF location to be built off of Cinema Drive in the village of Lansing.

The western addition includes a service drive through addition to the rear (west side) of the building, including the expansion of the existing second floor for additional offices displaced from the first floor. This addition replaces an existing canopy (open air) structure currently used for car parking. The first floor will be renovated to include a new service waiting area for customers.

The northeastern addition includes expansion of the showroom end of the building (north and east side), aligning the building with the existing service bay portion of the building currently located on the south side of the building. Also included in this addition is a new entrance to the showroom meeting Ford corporate branding requirements. On the outside, Ford corporate requirements dictate new metal exterior panels that will encompass all sides of the building. The showroom (north side) will be differentiated from the service side of the building with differing types of metal panels. The showroom addition also includes the new Ford “foil” curved form vestibule. The interior will also feature new plumbing, electrical, mechanical and HVAC. To quote the application, “(t)his will transform the exterior appearance of the building making the exterior of this “utilitarian” car dealership into a modern, contemporary car showroom and service center.”

On the outside, new striping, LED lighting and landscaping will be deployed. During the review process, the planning board had issues with the lack of green space, so the lot attempts to use as much as possible within the limited size of the lot and Ford’s corporate requirement for parking spaces on-site (brands dictate a lot of the programming). The site will host 311 spaces, the vast majority (207) for new car display, and a smaller number for staff, customers and on-site service parking, but it also meets the 12% green space requirement for the SW-2 zone.

It’s a pretty tight timeline for construction, and Ford was pressuring Maguire quite a bit on the lengthy approvals process (the BZA wasn’t planning meetings in December 2018 or January 2019 due to lack of quorum, so the project team was practically begging the planning board to approve the front yard variance at the same time as preliminary approval). The project is expected to be completed by the end of the fall at the latest (this says September, but I dunno when the permits were issued in March as planned). During review, the project added more windows as requested, but did not employ masonry as suggested by the board because Ford rejected it.

John Snyder Architects of Ithaca is the project architect, and local firm Elwyn and Palmer is the structural engineer for the project. Saratoga Associates (of Saratoga Springs, fittingly) is the site and civil engineer. According to a tipster, G. M. Crisalli of Syracuse is the general contractor – and it’s not their first Ithaca rodeo, as they were GC for the Dryden Eddy Apartments and the Top of the Hill Apartments in Collegetown. The project cost is estimated to be $1.5 million, according to the Site Plan Review filing.

At this time, demolition is underway, and it looks like Bellisario Excavation and Drainage is the demo/site prep subcontractor. Some of the exterior facade has been stripped in the areas to be refaced and/or built out, while the northern wing is largely exposed thanks to the selective tear-downs. Props to the car salesmen who were working while all of this was going on.

 

Gosh, have trucks gotten expensive…

Early site plan.

Final site plan.

 





News Tidbits 11/26/18

27 11 2018

Just to get this out in time, he’s a look at what will be a rather long but very interesting city of Ithaca Planning Board meeting tomorrow evening.

1 Agenda Review 6:00

2 Special Order of Business – Planning Report on ILPC recommendation to designate the former Delaware, Lackawanna, & Western Railroad Station at 701 West Seneca Street. 6:05

3 Privilege of the Floor 6:20

4 Approval of Minutes: October 23, 2018 6:35

5 Site Plan Review

A. Project: Chain Works District Redevelopment Plan (FGEIS) 6:40
Location: 620 S. Aurora St.
Applicant: Jamie Gensel for David Lubin of Unchained Properties
Actions: Distribution of FGEIS & Review of Schedule – No Action
Project Description: The proposed Chain Works District seeks to redevelop and rehabilitate the +/-800,000 sf former Morse Chain/Emerson Power Transmission facility, located on a 95-acre parcel traversing the City and Town of Ithaca’s municipal boundary. The applicant has applied for a Planned Unit Development (PUD) for development of a mixed-use district, which includes residential, commercial, office, and manufacturing. The site’s redevelopment would bridge South Hill and Downtown Ithaca, the Town and the City of Ithaca, by providing multiple intermodal access routes including a highly-desired trail connection. The project will be completed in multiple phases over a period of several years with the initial phases involving the redevelopment of the existing structures. Current redevelopment of this property will focus on retrofitting existing buildings and infrastructure for new uses. Using the existing structures, residential, commercial, studio workspaces, and office development are proposed to be predominantly within the City of Ithaca, while manufacturing will be within both the Town and City of Ithaca.

No decisions expected tonight, but the distribution of the FGEIS (Final Generic Environmental Impact Statement) is a major step forward. From here, the Planning Board will review and critique the document, and when satisfied, it will vote for a resolution of completion. A recommendation to adopt the Chainworks PUD zoning and the FGEIS findings will follow, and if successful, the Common Council will also vote to adopt the PUD zoning. That would complete generic review for the site – new builds would still come to the board as necessary, but renovations could potentially begin not long afterward. Timing-wise, the final approvals are still a few months out, but this massive 910+ unit project is slowly closing in on approvals, and potentially, construction.

B. Project: North Campus Residential Expansion (NCRE) 6:55
Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Review of FEAF Part 3
Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). All NCRE materials are available for download at: http://www.cityofithaca.org/DocumentCenter/Index/811

Materials provided indicate that city planning staff are reasonably satisfied that the energy impacts of the massive North Campus housing plan have been mitigated. The only new letter on record this month is a letter of concern from the City Historic Preservation Planner about the project’s visual and aesthetic impacts on the Cornell Heights Historic District to the west.

C. Project: Apartments (12 Units) 7:25
Location: 327 W. Seneca Street
Applicant: Noah Demarest for Visum Development
Actions: Consideration of Preliminary & Final Site Plan Approval
Project Description: The applicant is proposing to construct a three-story apartment building with 12 units. Project development requires the removal of the exiting building and parking area. The project will include exterior bike storage, a trash enclosure, walkways, landscaping, signage, and lighting. The project is in the B2-d Zoning District and has received the required variances for front-, side-, and rear-yard setbacks. A small portion at the rear of the property is in the CDB-60 District. The project has received Design Review. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”), for which the Lead Agency made a Negative Determination of Environmental Significance on September 25, 2018.

Not much to add regarding Visum’s workforce housing (80% area median income) proposal for the State Street Corridor. The project is expected to receive $200,000 from the latest round of the Community Housing Development Fund, the affordable housing fund jointly paid into by the city, county and Cornell. In this case, Cornell will cover $170,000 and the city $30,000. Cornell doesn’t have any hand in this project, but having one entity pay most of the grant for a given project makes it less complex to administer. 

D. Project: Falls Park Apartments (74 Units) 7:35
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Public Hearing, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11).

Note that IFR is a Travis Hyde Properties business entity. The attempt to gain approval for an environmentally compromised project site is likely going to be more heavily scrutinized given the recent controversy regarding proposed demolition procedures for the Old Library site.

E. Project: New Two-Family Dwellings 7:55
Location: 815-817 N Aurora
Applicant: Stavros Stavropoulos
Actions: Declaration of Lead Agency, Review of SEAF Parts 2 & 3
Project Description: The applicant proposes to demolish an existing two-family residential structure and construct two new 1,290 SF two-family dwellings on a 9,590 SF lot. The existing residential building is a legally nonconforming building with a side setback deficiency (2.9 feet instead of the required 5 feet). The proposed redevelopment will include four parking spaces for four three-bedroom apartments. The applicant is requesting the Board’s approval to use the landscaping compliance method for parking arrangement. The project site is located in the R-2b Zoning District and meets all applicable zoning lot and setback requirements. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”).

F. Project: Maguire Lincoln 8:15
Location: 370 Elmira Road
Applicant: John Snyder Architects PLLC
Actions: Declaration of Lead Agency, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to demolish a portion of the existing building and construct two additions with updated exterior materials. The existing building is 18,500 GSF, with 2,265 GSF proposed for demolition. The new building will be 24,110 GSF. Site improvements include incorporation of a new pedestrian walking path, and site connections to Wegmans. Approximately 311 parking spaces are proposed to accommodate customer, service parking, employee, and display parking. Landscape design will improve vegetative cover; however, it will not meet the City of Ithaca’s impervious/pervious requirements (12%). The project site is located in the SW-2 Zone, is subject to the 2000 Southwest Design Guidelines, and will require a zoning variance for a front yard that exceeds the maximum permissible in the SW-2 district (34 feet maximum permitted, 69-feet 3-inch setback proposed). This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”); however, it will be treated as a Type I Action for the purpose of environmental review.

G. Sketch Plan – 312 E Seneca Street, Jagat Sharma 8:35

312 East Seneca is a 4,482 SF three-story mixed-use building on the edge of Downtown Ithaca. The building was long-owned by Ithaca architect Jagat Sharma, who ran his practice from the building (1416 SF), the Alley Cat Cafe (1926 SF), and a four-bedroom apartment (1140 SF) on the upper floors.

A few years ago, the site was floated as part of the potential footprint for Visum Development’s Seneca Flats mixed-use project, though at the time it was made clear that it was not an essential property to the development, and simply a possibility if Sharma chose to sell to Visum. Sharma didn’t – in September, he sold the building to an LLC associated with the Stavropoulos family for $800,000, double the assessed value. That lofty price relative to assessed value was a big clue something was planned here, and it looks like the first glimpse of that will come tomorrow night. The Stavropoli of West Hill have been growing their assets through acquisition or development for the past several years, including the 4-unit North Aurora project in item E. above.

Normally, the Stavropoulos family is low-key about development, preferring lower-profile infill builds in established neighborhoods – the largest project of theirs to date is the 11-unit 107 South Albany project. They often turn to local architect Daniel Hirtler, but this time, Collegetown favorite Jagat Sharma will have a hand in redeveloping the building that housed his office for so many years. This would be Sharma’s first building downtown since the Greenstate Building (127 West State Street) in 1991. For the record, this would be their second Sharma commission, with a duplex planned for 209 Hudson Street being the other (granted, that’s also a modular structure).

Zoning-wise, this is CBD-60. Within that zone, Sharma can design a five-story building up to 60 feet tall, no parking required, with any variety of commercial or residential uses. Any design will have to conform with the recently-adopted Downtown Design Guidelines. The Stavropoli are likely to do all-residential or residential with ground-floor retail. The current building is quite narrow, but it also only occupied the east half of the lot – a new structure could practically touch the neighboring building at 308 East Seneca.

H. Sketch Plan – 114 Catherine Street, Jagat Sharma 8:55

Things are about to get a bit confusing. A few years ago, the Lambrou family, mid-sized Collegetown landlords and developers of Collegetown Park, presented and built an infill project at 114 Catherine Street – while all the working docs used 114 Catherine Street, the address of the existing building set back into the lot, the new 3-unit, 17-bedroom building was christened 116 Catherine Street.

This new building is expected to be a replacement for the existing 114 Catherine Street, the Mission Apartments, and is expected to complement 116 Catherine in appearance (Jagat Sharma designed that as well). Zoning here is CR-4, up to four floors, with a maximum of 50% lot coverage (but not parking required). Expect this to be student housing – probably not too big, a few dozen beds at most, but something to take note of nevertheless.

I. Sketch Plan – 130 Cherry Street, Residential, Vecino Group 9:15

130 Cherry Street is a 4,600 SF auto body shop that’s been for sale for quite a while now. The rumor mill says Vecino CEO Rick Manzardo was walking around the area a couple of weeks ago, and it looks like there was a reason for that. The plan being floated is affordable “artist housing”. This wouldn’t be a new concept to Vecino, who renovated a vacant warehouse in Troy into the 80-unit Hudson Arthaus. What makes the Arthaus unique among affordable housing is that it offers on-site amenities geared to artists, as well as income-based rents for those who make only a modest living while engaged in their creative pursuits.  Those amenities include a wood shop, on-site storage units, gallery spaces managed by a local non-profit, and a computer/digital work suite.

Zoning here is “Cherry Street District” Waterfront Zoning. Since it’s north of Cecil Malone Drive, housing is allowed – but not on the first floor. The first floor is for light industrial and many commercial uses, including restaurants, stores and offices. No ground-level storage permitted, however. In this “artist housing” format, the first floor would likely be the exhibition/gallery.workshop space. The building may be up to five floors with 100% lot coverage once setback requirements are met. Bonus for this site, the Cherry Artspace is a few hundred feet away. With about 179,000 SF in building capacity offered by the site and zoning before setbacks are considered, a potential project could be fairly sizable.

6. Old/New Business 9:35

7. Reports 9:40
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development

8. Adjournment 10:00