Maplewood Redevelopment Construction Update, 6/2018

15 06 2018

There was an interesting story going around that Maplewood was in serious trouble due to water pressure issues, to the point where its ability to legally house its residents was at risk (no water pressure would have made for a hazardous fire risk). That would have been a huge story had it panned out, but a little bit of checking with the town of Ithaca codes department and the development team turned up no dire situations unfolding, all is going as planned (a welcome change given all the weather and contractor issues that have plagued the project’s tight work schedule so far). There was some worry about water pressure back when the project was first proposed, which is why a new 600,000 gallon water tower is going up on Hungerford Hill Road.

It’s a little sad to see the French Lavender florist and gift shop is closing down after eleven years. It’s not clear if it’s related to construction, or if the timing was coincidental. Coal Yard Cafe was doing a brisk mid-day business at the opposite end of the Maplewood site. With 872 new residents expected by the end of the summer, the site will have appeal to retailers and service providers.

For project background and planning, click here.

For a site plan breakdown, click here.

For a construction timeline, click here.

Webcam link 1 here (updated ~15 minutes).

Webcam link 2 here (updated ~15 minutes).





Cornell Veterinary School Expansion Construction Update, 6/2018

14 06 2018

Looks like we can move this project into the “completed” column. The 12,000 SF, $7 million building is open and occupied – in fact, there appeared to be a couple of folks transferring crates of paperwork into the building as these photos were being taken.

HOLT Architects designed a modest LEED Silver structure with clean, modern lines, and G. M. Crisalli and Associates Inc. did a bring job bringing that design into reality. At this point, the four years of construction at the Cornell University Veterinary School appears to finally be complete. The school will gradually build up to its expanded size (102 to 120 students per class), expand its lab and research capabilities, and through the Community Practice Service building, serve the community in which it resides. The state released its press announcement calling the Vet School Expansion complete last week – and noted that the final price tag for all the phases was $91.5 million.

Before:

Render:

After:





Maplewood Redevelopment Construction Update, 4/2018

30 04 2018

Maplewood has not had the best of luck during the construction. A wet fall, and an unusually wet and cold spring have really dampened efforts to move the project along at a clip that the development team would have liked. Supply issues (framing walls) and concerns from subcontractors about steady, non-weather interrupted work have also made things more complicated. The developer (EdR Trust, with local project representative Scott Whitham of Whitham Consulting) approached the town of Ithaca with a request to extend the working hours again from 7 AM to 10:30 PM for interior work, on top of the four-hour extension (from 9 AM – 5 PM to 7 AM – 7 PM) and the Saturday 8 AM – 4 PM hours previously granted.

It did not go over well. After getting a tongue lashing from members of the board about incompetence, the planning board did offer a partial concession to 9 PM on a 4-3 vote. As a result, barring no further major issues, most of the units are expected to be delivered in July, though some of the later-scheduled townhouse strings will likely not be complete before August. Ostensibly, there’s a fear that the units won’t be ready in time for incoming Cornell graduate and professional students, in which case EdR will incur the substantial cost of putting them up in a hotel, as some of the Collegetown developers had to do a couple of years ago (325 Eddy’s opening was especially rough). The current plan is three phases of move in, on July 1st, July 31st and August 20th.

From what I’ve heard, at least half the units are spoken for in the 441-unit, 872-bed development. Advertisements have been showing up pretty regularly on websites like Craigslist, as well as their own website.

Walking around the site, construction is in just about every stage imaginable, from framing to sheathing to fit-outs to exterior siding and even trim work on the units facing Mitchell Avenue. There have been some changes in the plans, and I’d argue for the better – more color variations in the apartment buildings and the townhouse strings. The southwest corner building on Mitchell was initially supposed to be shaded of blue, but is finished with red fiber cement panels, and the panels on one of the gabled “Ht” strings next to the Belle Sherman Cottages. The apartments also show varying brick and panel ensembles, from navy panels and red brick, light grey panels and maroon brick, dark grey panels with tan brick….it makes for a more colorful and arguably more attractive site.

Quick aside, a second project webcame has been installed. This one looks over the three apartment blocks on the northern (Maple Avenue) end of the site. Link below, along with the southward camera.

For project background and planning, click here.

For a site plan breakdown, click here.

For a construction timeline, click here.

Webcam link 1 here (updated ~15 minutes).

Webcam link 2 here (New! updated ~15 minutes).





News Tidbits 4/7/18: A Day Late and A Dollar Short

7 04 2018

1. It appears the Sleep Inn hotel is moving forward. Building permits for the 37,000 SF, 70 room hotel at 635 Elmira Road were issued by the town of Ithaca on March 23rd. According to the town’s documentation, the project cost is $4.1 million, though it’s not 100% clear if that’s hard costs (materials/labor) and soft costs (legal/engineering/design work), or just hard costs alone.

The Sleep Inn project was first introduced in Spring 2016, and underwent substantial aesthetic revisions to a more detail, rustic appearance. Even then, the project was barely approved by the Planning Board, which had concerns about its height, relatively small lot size and proximity to the Buttermilk Falls Natural Area. The hotel’s developer, Pratik Ahir of Ahir Hotels, co-owns the Rodeway Inn further down Elmira Road. Both the Rodeway and Sleep Inn are Choice Hotels brands, so although the Sleep Inn brand is new to the area (and uncommon in upstate New York), it’s not as unusual as it seems. Given the size, a 12-month buildout seems reasonable. Look for updates as the project gets underway.

2. In a similar vein, the gut renovation and expansion at 1020 Craft Road now has a building loan on file – $1.88 million as of April 3rd, courtesy of Elmira Savings Bank. The existing 10,500 SF industrial building has been gutted down to the support beams, and will be fully rebuilt with an additional 4,400 SF of space. The project is being developed and built by Marchuska Brothers Construction of Binghamton. According to the village of Lansing and the developer, the project will be occupied by multiple medical tenants.

3. The problem with tight publishing deadlines is that if a quote doesn’t arrive in time, you can either put it in afterward as an updated statement, or it gets left out. So on the heels of the report that Visum Development Group is upstate New York’s fastest growing company in terms of revenue (Inc.com’s guidelines were three-year period 2014-16 and at least $100,000 in revenue to start), I wanted to share this for those who might have missed the article update. The statement comes courtesy of Todd Fox, who was asked for comment and responded the following day.

“I would love to acknowledge the Visum team because without them I would never be able to accomplish what I am doing. I’m blessed to have the most passionate and talented people I have ever met. Chris Petrillose is my longest running team member and is the backbone of operations. I also want to acknowledge Patrick Braga, Matt Tallarico, Marissa Vivenzio, and Piotr Nowakowski. They are all rock stars and deserve so much of the credit for our success!

We are currently looking to expand into several new markets, which are as far south as Sarasota Florida and as far west as Boise Idaho. For the Ithaca market, we are essentially hitting the breaks on student housing for Cornell, as we beginning to experience some softening in the market. Our new focus is on for-sale condos and moderate-affordable rentals. We actually have multiple properties under contract and plan to bring about 1,000 to 2,000 new beds online over the next several years.”
Note the last parts. The market for student housing if softening. Visum will focus on for-sale condos and moderate-affordable rentals, things Ithaca could use more of, and 1,000 to 2,000 beds would certainly make a dent in the housing deficit. Of course, proof is in the pudding, so we’ll see what happens over the next several years.

4. The town of Ithaca was less than pleased about Maplewood’s request to extend indoor working hours until 10:30 PM. Labor, weather and building supply (wood frame) issues were cited as reasons for the needed extension. The Ithaca Times’ Matt Butler, who was at the meeting, provided this quote:

https://platform.twitter.com/widgets.js

Yikes. The “happy medium” the board finally gave in to was construction until 9 PM on buildings interior to the project site, away from the main roads. The tradeoff is that EdR and Cornell now expect to not have some of the later structures ready until August 20th, practically move-in day for all of Cornell’s on-campus undergrads.

5. Readers of the Voice and Times will know that the county is pursuing some of the $3.3 billion in federal dollars earmarked but not yet disbursed for opioid crisis treatment. While a temporary addiction facility is being prepared, there are plans in the works to open a detox and stabilization facility in Tompkins County. Unfortunately, it needs much more funding to move forward. The new facility will cost $11 million to build and make operational, and so far about $1 million has been received so far in grants.

For the purpose of this blog, I asked about the design beside Angela Sullivan and Senator Schumer – it is a conceptual design for demonstrative purposes, and a location for a new facility has not yet been fully determined. However, they intend to send a press release once a site has been selected.

By the way, the green logo at lower right is a giveaway on the architect – that would be Ithaca’s HOLT Architects, who are specialists in healthcare facilities.

6. New to the market this week, “Clockworks Plaza” at 402 Third Street in the city of Ithaca’s Northside neighborhood. The 12,821 SF building was one of the few sizable buildings built in Ithaca in the 1990s (1993, to be exact), and is on the market for $2.6 million. The current owner, masked by an LLC, bought the property for $1.5 million in April 2016, the same value for which it is assessed.

That came up on the blog here. The buyer was Steven Wells of suburban Boston, who purchased the property in a buying spree that also included 508 West State Street (former Felicia’s, empty at the time) and 622 Cascadilla Street. 508 West State is now rented by Franco’s Pizzeria. Zaza’s still occupies 622 Cascadilla.

As I wrote at the time of sale:

“They all have different owners, and they’re in varying physical conditions. The only thing that unites these three properties is all that are in areas the city as ripe for redevelopment for urban mixed-use in the Comprehensive Plan. Felicia’s was upzoned in June 2013 to CBD-60, permitting a 60-foot tall building, no parking required. 622 Cascadilla is WEDZ-1a, allowing for five floors and no off-street parking requirement. Lastly, 402-410 Third Street is B-4, 40′ max and 50% lot coverage, but allows virtually any kind of business outside of adult entertainment. Those are some of the city’s more accommodating zoning types, so we’ll see what happens moving forward. At the very least, the public relations game will be starting from behind the proverbial eight ball.”

The reason why the public relations game was ‘behind the eight ball’? He was the guy who sold 602 West State Street and adjacent low-income housing properties to Elmira Savings Bank. There were accusations that the transaction between Wells and the bank was poorly handled, with claims that the lease terms of existing tenants were changed improperly, and tenants not being told their homes were being sold. It’s not clear it that’s accurate, because no one would share their documents to prove their claims. But what is clear is that this created a nightmare situation.

 

7. It looks likely fewer people will be living in City Centre than first intended. The initial 192-unit mix was 61 studios, 78 one-bedrooms and 53 two-bedrooms. The newly-proposed mix is 33 studios, 120 one-bedrooms, and 39 two-bedrooms. It also appears the retail space has been reconfigured from four spaces to three, though the overall square footage appears to be about the same. There are some minor exterior changes proposed as well; paver colors, lighting, the types of metal panel used (Alucoil to Overly Dimension XP and Larson ACM panels), landscaping, and exterior vents. Assuming the PDF is accurate, the panel change is slight, but gives the building a slightly darker grey facade. Some of these changes are in response to code and safety discussions, others are likely value engineering.

8. From the city’s project memo, we see Greenstar’s new store (which is going into the Voice) and a pair of new if small projects.

The first is that it appears Benderson is expanding South Meadow Square again. Along with the pair of endcap additions underway, the Buffalo-based retail giant is looking to add a 3,200 SF addition to the west endcap of one of its smaller retail strings. The addition is on the Chipotle/CoreLife strip, next to Firehouse Subs. The dumpster enclosure currently on-site will be relocated to the Panera strip across the road to make room for the building, which will be flush to the sidewalk with…a blank wall. Seems like a bit of a missed opportunity there. The 35′ x 92′ addition has no announced tenant, though 3,200 SF is reasonable for a smaller restaurant or retail space (Chipotle is 2,400 SF, for instance, and Panera 4,100 SF; the stores in this particular retail strip, which includes a vitamin store, tanning salon and barber shop, are in the range of 1,380-4,089 SF). The total project cost is only $132,000, and no construction period is given in the Site Plan Review document.

The second is a “pocket neighborhood” in Northside. Barken Family Realty of Ithaca is planning to renovate two existing homes at 207 and 209 First Street, and add a new 2,566 SF two-family home behind the properties. They would be set up as a “pocket neighborhood”, consolidated into a single tax parcel with a common area, picnic tables and raised plant beds. The fence would be repaired and the gravel driveways improved. No demolition is planned, but five mature trees would come down to make way for the new home (6-8 new trees will be planted).

Hamel Architects of Aurora designed the new duplex, which is intended to quietly fit into the neighborhood context. Each unit will be two bedrooms. The $265,000 project would be built from October 2018 to March 2019.

9. We’ll finish this week with a potential new build. The above project was first showcased on STREAM Collaborative’s Instagram at an early stage. It is a 3.5 story, 11,526 SF building with 10 units (6 one-bedroom, 4 two-bedroom), and the two one-bedrooms on the first floor are live-work spaces – the front entrances are workspaces for home businesses. It is proposed along West Seneca Street, and only the south side of West Seneca allowed for mixed-uses like live/work spaces. Materials look to be Hardie Board fiber cement lap siding and trim. The design is influenced by other structures along West Seneca, and a bit from STREAM architect Noah Demarest’s time with Union Studio in Providence, Rhode Island, where he worked before setting up his own practice back in Ithaca – there are similarities between here and Union Studio’s Capitol Square mixed-use design in Providence.

The project actually was sent with its name and title, but fingers crossed, it will be part of a bigger article.

 

 

 





News Tidbits 3/31/18: A Bit of a Lull

31 03 2018

1. In Lansing, a local developer seems to have gotten the message when it comes to a small senior housing project. As reported by Dan Veaner at the Lansing Star, the latest version of Eric Goetzmann’s Lansing Meadows calls for 20 2-bedroom units ~1500 SF (square feet) each in ten buildings along a loop road, “Lansing Meadows Drive”. The project uses the entire parcel, with the eastern end set aside for a small (less than 2500 SF) neighborhood retail component.

Goetzmann is less than happy with the latest version, saying that financially it doesn’t work, but he needs to get something built to fulfill the requirements of the BJ’s tax abatement in 2011 – the senior housing component of the project has been delayed so long, the county has prepared legal action to recuperate abated taxes if Goetzmann doesn’t get the senior housing started ASAP. The answer at the last pair of meetings went from “I just want to get this done” to “We’re looking to build 12 units and if we’re successful we’re looking to build some more, which really didn’t bode well for negotiation – at this point, a low or breakeven ROI is a price Goetzmann is willing to pay over paying the county and village millions. The Planning Board is satisfied with the newest design, and a vote to approve a special permit to start construction could be as soon as April 9th. The actual construction docs would take ten weeks and the project has to go out to bid contractors, but Goetzmann is optimistic the units will be built this year.

It’s a quiet month otherwise for the village, with a cell tower and a parking lot expansion the only other things on the latest agenda.

2. Let’s take a quick look at some noteworthy sales from the past month:

The Belleayre Apartments at 702 Stewart Avenue sold for $5,434,500 on the 22nd. The seller was Sebastian Mascaro, who some readers might remember because he previously owned the Chapter House before it burnt down. The buyer was Kimball Real Estate. The 44-unit building, which retains classic Collegiate Gothic details popular when it opened in 1933, is assessed at $3.85 million. Mascaro had paid $4.25 million for the building in November 2011. Don’t expect any big changes here, but it’s evidence of the strength of the local multi-family market.

9 Dart Drive, a 4.56-acre vacant parcel in the village of Lansing, sold for $52,500 to VPA Development on March 22nd. Yes, there is something planned here – the village Board of Trustees is aware. VPA Development’s mailing address is the same as local businessman Nick Bellisario, who is building warehouses on Hall Road in Dryden, and is a partner in the Varna Tiny Timbers (The Cottages at Fall Creek) project. Zoning here is the village’s Medium Density Residentialsingle-family and two-family homes, schools and religious facilities. Zoning is one unit per 20,000 SF for a single-family home, 25,000 SF for a duplex. So in theory, perhaps 8 or 9 home lots if single-family.

3. One of the questions that makes a fairly regular appearance in the inbox – will Maplewood finish on time in July 2018? It’s a good question, one that Cornell and EdR are damn determined to give a yes answer for. To make up for weather delays and other issues, the Maplewood construction team is requesting to do interior work to as late as 10:30 PM Monday-Friday. Keep in mind, this is on top of the Saturday hours and previous workday extension (four hours, two on both sides, to 7 AM – 7 PM). The town of Ithaca, which has to approve these changes, seems amenable to it so long as no generators are operating, doors and windows are closed, and supervisory staff is present – basically, don’t disturb the neighbors.

At last check, unseasonably cold and wet weather over the past several months had led the project to fall behind, and subcontractors to move to steadier jobs elsewhere. The project has fallen as much as 25 days behind schedule. The extensions, if approved, would create an 85.5 hour construction week, manned by different crews.

Side note, the town of Ithaca hasn’t had much else to review lately – the planning board has only had two meetings out of the scheduled six so far this year. The other projects were a single-family home lot subdivision on Trumansburg Road, and renewing the approvals for New Earth Living’s 31-unit Amabel single-family ecohousing development on Five Mile Drive. I have not seen anything underway when I’ve driven by, and the website has not been updated in a while, so it’s nice to know that something is still in the works.

4. For good housekeeping – things are slow in Dryden, so slow they cancelled their monthly planning board meeting. Things are also fairly slow in the town of Lansing, where the big controversy is a plan to relocate the shooting range for Lansing Rod & Gun. The issue is that environmentalists have criticized the gun shot’s proposal for lead shot remediation, as well as saying the range is too close to Salmon Creek. The town is still reviewing documents and has yet to make a decision.

5. Recently, the Collegetown Neighborhood Council floated a Business Improvement District (BID) similar to the Downtown Ithaca Alliance. The reception was lukewarm, according to the Times’ Matt Butler. It’s not that the concept is disliked, although some smaller property owners are a bit nervous about being outvoiced by bigger players. It’s more a concern that a BID would likely be financed by a property tax surcharge, something that the county’s (and arguably, one of upstate’s) most expensive neighborhoods would rather not have to deal with. A DIA-type group may engage in security, local beautification, event planning, or other needs as the business owners as we see fit; as of now, it’s still just a hazy idea, but we’ll see what happens with it.

6. The relative quiet in the project pipeline extends to Ithaca City. At the February planning board meeting, U-Haul corporate had submitted plans for a 5-story building that, in the words of Matt Butler, “they kicked that idea to the curb….just bludgeoned the dude.” Apparently it was too much – too big, too tall, no attractive. Also, the project for 207-209 First Street is not as bad as initially feared. Both existing two-families will be renovated, but not torn down, and a new duplex would be built at the rear of the property lots. The board says it could be similar to the Aurora Street Pocket Neighborhood, and was supportive of the plan overall.

This month was one of the quietest meeting agendas I’ve seen in years – the only project up for formal review and approval was the Stewart Park Inclusive Playground, as well as updates on the Chain Works District zoning, and the City Harbor plans. City Harbor was a late addition. There is plenty in the pipeline, some of which will come forward in the next few months; just seems there’s a bit of a lull at the moment.

7. Just a reminder – meetings for the East Hill Village neighborhood-scale proposal will be held at the The Space @ Greenstar on Monday 4/9 (an update of the past several months, 4/11 (workshops for concept designs), and 4/12 (presentation of preferred concept designs and alternatives). All meetings will be 6-8 PM, and the public is encouraged to attend.

Here’s a copy of the presentation from last May’s meeting – not anything groundbreaking, but it makes it clear that Cornell’s land holding are much more patchwork than folks might realize. I suppose the owner of the East Hill Car Wash stands to make a pretty penny at some point.





Cornell Veterinary School Expansion Construction Update, 3/2018

21 03 2018

The Cornell College of Veterinary Medicine’s new Community Practice Service is set to open in May, and it certainly appears to be in the home stretch. Exterior finishes are underway. Atop the dark blue water-resistive barrier are rigid foam insulating panels, and what appears to be a combination of corrugated steel panels (probably Morin or a similar brand), Alucobond aluminum composite trim panels and simulated wood fiber cement boards. These materials have made or are making appearances on other recent builds as well – HOLT Architects, the designers of the new CPS Building, also incorporated corrugated metal and flat aluminum panels into 210 Hancock’s multi-story apartment block. Meanwhile, wood-like fiber cement shingles will be used as one of the finishes on The Lux apartments at 232-236 Dryden Road.

It seems a little strange that the “clips” on which the wall panels will be fastened are wood instead of steel. Perhaps since the exterior finishes are light, waterproof and will be sealed tight, it’s an acceptable choice. The frame for the rooftop mechanical screen is in place, and the flag strings suggest that the roof membrane is being laid. If you look closely enough through the windows, you can see steel interior stud walls and HVAC ducts. Compared to the renders, there only seem to be a few minor differences in materials and appearance (the corrugated metal panels, and maybe the fenestration over by the entrance).

According to HOLT’s project webpage, the $7 million project is aiming for LEED Silver Certification. Here’s the building description from their webpage (which, kudos to the HOLT website manager, because not many architects include their buildings currently underway):

“The new 11,000sf Community Practice Service Building, is a stand-alone veterinary clinic and teaching facility that will provide a real-world veterinary practice to the surrounding community.

The new building design includes a welcoming waiting area, as well as veterinary surgery, imaging, and exam rooms; procedure induction/recovery, and animal holding areas; lab and pharmacy spaces; staff and faculty offices, conference rooms, lockers, restrooms, and other support spaces.

Once complete, this building will be a beacon for pet health and wellness in the community and on campus – with the architecture exemplifying the quality of learning and client service that will happen within its walls.”





Maplewood Redevelopment Construction Update, 2/2018

19 02 2018

There is so much going on here – it kinda blows my mind because a development of this acreage and number of units is extremely rare in a place like Ithaca, where highly subdivided lands make large acreages difficult to find or assemble, the financial and labor capacity for a large build is limited, and review processes are stringent and rather burdensome. With the exception of a few townhouse strings towards the middle and the community center, it looks like almost everything else has moved into the framing stage. In contrast to the renders, the townhouse strings are showing greater color variation in their brick and fiber cement panels – some are navy blue boards and orange-red brick , while others are jade green boards with maroon brick. Same goes for the apartments, some of which have a navy/orange-red scheme, while others are faced in different shades of grey panels. This helps to create more visual interest and differentiation between otherwise similar structures.

Embedded below are a couple of mock-ups from the on-site display unit inside the leasing trailer. It’s not a bad setup, though on a random note, no one in their right mind would hang a picture frame so close to the top of their bed. The units will come furnished. For those interested, the rental website can be found here. Also included below at the end are a few interior renders, of the community center, a study lounge, the fitness room and a bathroom (not a part of the walk-through mock-up).

For project background and planning, click here.

For a site plan breakdown, click here.

For a construction timeline, click here.

Webcam link here (updated ~15 minutes).