The Maplewood Redevelopment, Part III: Site Photos

5 09 2017

The rough construction timeline for the Maplewood structures looks something like this: Apartment buildings B and C started construction first in the spring, and the first townhouses were scheduled to begin in May. All of the major apartment buildings are expected to start construction by the end of August, while the last of the townhouse strings will not begin build-out until January 2018. Roughly speaking, the ends of the project site have earlier starts than structures in the middle of the site, and the more traditional-looking townhouse units start construction before the more modern strings.

The timeline is likely slightly behind schedule. During the mid-August site visit, a worker said that five of the foundations had been completed, but it seems at least six should have been finished by that point. The reason given for the relatively slow progress has been the wet summer, which has interfered with certain parts of the construction. For example, concrete pouring and curing for the foundations becomes a lot more complicated with the presence of frequent downpours. Rainwater can damage the foundation during certain stages of the process by causing the new pour to become soft again, reducing its structural integrity. Depending on timing, extra precautions have to be taken, or even worse, if it’s a real washout of a day the pour simply can’t take place at all. Several construction days have been lost, and to pick up the slack, the project asked for and received approval to increase the workday from 8 AM – 6 PM, to 7 AM – 7 PM, with the town’s stipulation that the extra two hours keep work noise below 85 decibels.

The photos below come from three separate time periods – February, which was mostly just site prep and excavation for underground utilities, the continuation of utilities excavation and installation in April, and the readying of connections to those new utilities in August. The circular concrete structures seen in April and August are for underground electric utility junctions. Similar structures may be used for wastewater pipes and drainage pipes. The teal pipes are PVC sewer pipes, and the rectangular precast concrete sections are protective covers. New curbing is being installed along Mitchell. I don’t know what the ridged crescent-shaped orange structures are, but if a reader knows, feel free to chime in in the comments.

Above-ground, it looks like the masonry stairwells for apartment buildings B and C have been built as of August. The slots in the sides suggests structural steel frames. A trailer on-site belongs to Peppard & Sons Masonry of Lockwood, so they may be the pertinent sub-contractor. Foundation slabs can be seen, and wood forms have been prepared for future pours.

 

Pre-development site photos:

February 2017:

June 2017:

August 2017:


Actions

Information

6 responses

6 09 2017
Ex-Ithacan

Great series Brian, I look forward to updates on the progress. Thanks!!!!

17 10 2017
Maplewood Redevelopment Construction Update, 10/2017 | Ithacating in Cornell Heights

[…] For a construction timeline, click here. […]

19 02 2018
Maplewood Redevelopment Construction Update, 2/2018 | Ithacating in Cornell Heights

[…] For a construction timeline, click here. […]

30 04 2018
Maplewood Redevelopment Construction Update, 4/2018 | Ithacating in Cornell Heights

[…] For a construction timeline, click here. […]

15 06 2018
Maplewood Redevelopment Construction Update, 6/2018 | Ithacating in Cornell Heights

[…] For a construction timeline, click here. […]

27 09 2018
Maplewood Construction Update, 9/2018 | Ithacating in Cornell Heights

[…] For a construction timeline, click here. […]

Leave a comment