Masonic Temple Renovation Update, 4/2018

13 05 2018

The Masonic Temple renovation is low-key but worth an explainer. Here we go:

The 17,466 SF Masonic Temple at 115-117 North Cayuga Street is a bit of an unusual building. It was one of the last designs by prolific local architects Arthur Gibb and Ornan Waltz, and completed in 1926. The style is Egyptian Revival, which was also used for the Sphinx Head Tomb at 900 Stewart Avenue, and to a lesser extent in the Carey Building, which was built around the same time. Egyptian Revival architecture uses what are or are perceived to be Egyptian motifs (stark facades, strong symmetrical elements, Egyptian-themed ornamentation), and experienced a resurgence in the 1920s following the opening of King Tut’s tomb – the early 20th century designs are sometimes grouped in as a subcategory of Art Deco.

Keep in mind that Freemasonry is a loose affiliation of fraternal groups, with some degree of secrecy (that they like to play up, for better or worse). Although diminished in this age, they played a role in community social life much as Greek Life does on college campuses. The Ithaca Freemasons wanted something exotic with just a hint of foreboding, so the architects went with minimal ornamentation, strong symmetry, simple, slit-like windows, and a bare, impassive facade, here a thin limestone veneer over a steel frame (a modern idea for the time). To quote William D. Moore’s Masonic Temples: Freemasonry, Ritual Architecture, and Masculine Archetypes, “a critic claimed that Ithaca’s Masonic Temple could help visitors to imagine themselves ‘transported to the civilizations of the Pharaohs…There is no mistaking this structure for an abode of commerce’.”

By the 1990s, the Masonic Temple had fallen into disuse, and local developer and major landlord Jason Fane picked it up in 1993. Fane had made his intent clear that he preferred to demolish the building and build new on the site, a stone’s throw from the hear of Downtown. In response and concern to that idea, the building was landmarked in 1994. You could probably see some parallels to the Nines situation here, only the Nines owners aren’t already multi-millionaires and don’t have a negative public image.

It’s a difficult building to reuse. Not only does one contend with the extra hurdles and costs of working with a landmarked historic structure, but the rooms are cavernous and the building has been described as functionally obsolete – its outdated mechanical systems and lack of handicap accessibility have made it a difficult sell to prospective commercial tenants. The last tenant was the Odyssey nightclub, which moved out over a decade ago. Older folks tend to remember a restaurant prior to that, Europa.

Fane himself was never a big fan of what was considered his “white elephant” property; out of concerns he was letting it decay to the point of an emergency demolition, the CIITAP tax abatement rules were modified in 2014 to say that applicants had to be code compliant on all their other existing properties, and was targeted at Fane, who was seeking an abatement at the time for an apartment proposal at 130 East Clinton Street (it was denied and the project was never built).

The best way to describe the Masonic Temple problem is that it’s not the location, and it’s not out of a lack of interest – it was simply the cost of making it code-compliant and more accessible for tenants. Early plans considered putting The History Center here, while an earlier plan from 2012 considered buying the property from Fane and making it into a community center. The 2012 plan never made much headway – Fane was not keen on selling, and he still harbored hopes of demolishing it. The History Center plan was also seen as more expensive than a specialized space for The History Center.

The city has long hoped that they and Fane would see eye-to-eye, and finally it appears that dream is coming true. In July 2015, the city Common Council voted to support an application from Fane to the New York State Main Street Program, a state-sponsored grant program that encourages revitalization efforts at historic sites in downtown urban centers. In December of that year, the state awarded Fane a $500,000 grant towards the rehabilitation of the building (which cost a little over $1 million total). The initial plans were to get the ball rolling on construction in summer 2016, but it does appear that much-lauded renovation plan is finally moving forward now.

The renovation, designed by architectural preservation specialists Johnson-Schmidt & Associates of Corning, calls for the creation of three commercial spaces, the installation of a ramp at the rear of the auditorium, and a new elevator on the southwest side of the building. With the interior kitchen still intact, it is likely that at least one of the commercial spaces would be geared towards a restaurant tenant.

A new roof membrane will be applied, the exterior limestone and stucco will be cleaned and repaired, the street windows repaired and repainted, and the auditorium windows, which had been boarded up by previous tenants, will be replaced with similar-looking new windows. The front entrance’s stone steps would be redone, and the front doors and lamp posts would be restored. The Ithaca Landamrks Preservation Commission signed off on the work in January 2017. The plans can be seen in the application here.

At the moment, it looks like asbestos abatement is underway, and the ground-level light wells are having their deteriorated concrete removed and replaced. Kascon Environmental Services is performing the asbestos removal, and McPherson Builders Inc. of Ithaca is the contractor-of-record. I asked Fane via email if the plans had changed at all since January 2017, or if there were any tenants on board, but as is often the case with him and his lawyer/representative Nate Lyman, there is no response.

3/30/2018

4/28/2018





City Centre Construction Update, 4/2018

12 05 2018

Mostly just clearing out my stash at this point; as the webcam shows, exterior framing is up to the third floor.

A number of changes have been made to the City Centre project, inside and out. Whitham Planning and Design shepherded the alterations through the planning board, which was generally okay with them. Among the revisions:

-Landscaping Changes. Among them, street tree species and layout, and tree grates are being replaced with FlexiPave porous paved covers. The number of shrubs was decreased, perennial flowers increased. Bike racks were relocated, street lights, curbing and curb ramps were adjusted, concrete planters were added by the parking drop-off area, a pergola with string lights was added, bollards were added, the sidewalk width along East Green Street was reduced from 6′ to 5′, and pavers were changed to a slightly darker shade of grey.

-On the first floor, the lobby layout was reconfigured, and some exterior doors were relocated for ease of access. The number of retail spaces was reduced from four to three, but the total square footage for the retail is about the same (11,000 SF). A storm water vault and fire pump room were added in the underground garage, and the parking spaces were reconfigured slightly to accommodate (still about 71 spaces).

-The unit mix has changed from 61 studios, 78 one-bedrooms, and 53 two-bedrooms, to 33 studios, 120 one-bedrooms, and 39 two-bedrooms. Still 192 units total, but with fewer studios and two-bedrooms and more one-bedrooms, basically. This might have to do with what’s easiest to rent to the target market (young professionals, a few downsizers, deep-pocketed students). Perhaps studios aren’t seen as having enough space for the upmarket market segment.

-The exterior facing materials have been changed from Nichiha aluminum panels to Overly Dimension XP Metal Systems, and Alucoil Larson ACM aluminum panels. The color palette is generally the same, perhaps slightly greyer with the revised paneling. Air intake vents were added to the building facade. Fenestration (window size/arrangement) was also changed up.

The floor buildout is a rather interesting process, because they’re practically building from the inside-out as each floor is added. The interior steel stud walls and structural steel supports go up first, then roof decking overhead, and then what appear to be prefabricated modular exterior wall panels with Marvin Windows already fitted. The dark panel is Dow Thermax Xarmor, which apart from sounding like a Star Wars extra, is a heavy-duty fire-rated fiberglass insulation board covered with a dark exterior facer that serves as a water barrier. These panels can be set into place very quickly, saving time and labor costs. The ground-level is more typical fireproof gypsum sheathing. The steel rails on the upper floors are likely for the aluminum exterior panels, so they may clipped into place.





Harold’s Square Construction Update, 4/2018

10 05 2018

Ithaca weather is not accommodating. Originally, the pour for the concrete slab was supposed to take place on April 3rd. It’s tricky, because this is a large footprint and the building is very heavy, necessitating a thick slab – 30 inches thick. That has to all be poured at once, without any potential interruptions like rain or snow, which can weaken the concrete as it cures (upsets the mix and water balance). That was rescheduled the first time due to winter weather, and was expected to take place on the 11th, which was rained out. 4/16 was also cancelled due to winter weather. Finally the concrete was able to be poured on the 23rd.

In the photos below, you can see some wood forms are still in place for smaller sections (entryway, lower right of site). The vertical concrete column bases are being poured (note the squares of vertical rebar in the sections yet to be encased), with steel plates atop the finished column to tie into the steel beams. The hole in the lower right (southeast) corner is for one of the elevator cores. Taylor the Builders will have this heading skyward in short order.





Tompkins Financial Corporation HQ Construction Update, 4/2018

7 05 2018

It appears that TFC’s new headquarters is just about done – from the outside, paving, landscaping and signage is about all that’s left. The signage plan, a fairly conservative “halo” style courtesy of Ithaca Sign Works, can be seen on the city’s website here.

As these photos were taken, a moving crew was busy carting office materials from TFC’s office space across the street. Corporation staff should be moved into the new building by the end of May. Tompkins Trust Company Division CEO Greg Hartz has said that 119 and 121 East Seneca would be held onto and rented out, with the bank retaking space in those buildings as it needs. Meanwhile, the historic 2 and 3-story buildings on Bank Alley just south of the M&T Building have been sold to the county for use as the new Tompkins Center for History and Culture, which will open in 2019.

On the whole, a project like this is a big net positive for the city. As opposed to the tried-and-true suburban office park route, TFC’s commitment to the city, and the work of city personnel as well as TCAD to keep them in downtown results in a major addition to the city’s tax base ($3,782,311 in new tax revenue over 10 years), the retaining of hundreds of workers downtown who by proximity would be more likely to shop, dine or live nearby, and the prospect of dozens of well-paying jobs being created at the new headquarters over the next several years. It looks like that the company added 22 employees system-wide in 2017, for a total of 1,041. A little over 300 of those will work in the new headquarters, the vast majority moving from the other offices in downtown Ithaca, with another 18 or so from the Lansing office.

Design-wise, it has a solid if conservative appearance, befitting of a stable, button-up corporation. HOLT Architects added a modern touch with the windows, and created visual interest by contrasting the dark grey brick with the tan brick, beige face stone and grey aluminum panels. The building height and dimension occupy an intermediate size between the DeWitt Mall and Seneca Place, which allows it to be imposing without being overbearing.

Other firms involved in the bringing this project from vision to reality include the engineers and surveyors at Elwyn & Palmer, Trowbridge Wolf Michaels Landscape Architects, and Rochester’s LeChase Construction. Credit also goes to JPW Erectors for the steel framework, the Carpenters’ Union Local 277 and the IBEW (International Brotherhood of Electrical Workers) Local 241.

 





Hilton Canopy Hotel Construction Update, 4/2018

5 05 2018

Construction continues on the Canopy, but the plans are in a state of modest flux. The fiber cement panels were changed to a different manufacturer, which uses a different paint supplier. The original Cem5 fiber cement panels use Swiss Pearl paints, while the revision proposes Nichiha panels using PPG paints. The replacement colors are very similar.

However, the dull yellow “Applesauce Cake” accent panels (itself a replacement for Cem5 “Carat Topaz”), was rejected by Canopy. The replacement color, a charcoal grey “Dark Ash”, was disliked by the board, so the project team is still trying to determine a suitable color replacement with enough to get the order filed with the manufacturer without delaying the construction timeline. I wonder if, given the orange Canopy logo and branding, if a soft “rustic” orange shade might be available? The thought being that it would tell visitors quickly that this building is a Hilton Canopy, and a warm, subtle shade would brighten the facade without being obnoxious. From what I see, one can custom order panels, which is no doubt more expensive, but I’m not seeing a list of standard colors anywhere.

While excavating, the project team did find some small fragments of the Strand Theater, which stood on the site until its demolition in 1993. The “most decorative” pieces are going to be used in a display inside the hotel lobby, and further consideration is being made for an exterior mural.

The landscaping is being tweaked to extend a sidewalk through the property to Seneca Way, as well as a curb-cut and smaller planters to fit within the property line. A pair of ginkgo trees planned for the property are being replaced with some dense shrubs and perennial instead. This is the eleventh version of the project I now have on file. Background info and specifications can be found here.

The hotel has completed foundation work and is up to the second floor. The steel skeleton and elevator cores/stairwells continue to rise, with thinner exterior steel stud walls on the ground floor and fireproof gypsum panels on the second floor. The finished product should be coming onto the market in about a year.

 





107 South Albany Street Construction Update, 4/2018

4 05 2018

The new 11-unit apartment building at 107 South Albany Street is fully framed and roofed. It looks like the roof underlayment is down and the shingles are starting to go on -the photos below show plumbing and electrical boxes already installed on the first floor. Most of the sheathing is in place, and given the plastic, utilities roughs-ins are likely ongoing inside the new structure. From the listing on Zillow:

“Brand new luxury 1 bedroom apartment in Ithaca’s newest development available August 1, 2018. One block from the Ithaca Commons and a bus stop with multiple routes at your door.
The Unit:
– Is beautifully furnished
– Boasts high end finishes throughout including: custom cabinetry, quartz counter-tops, stainless appliances and a beautiful tiled bath.
– Has laundry in building
– Includes indoor bike storage
– Water, high speed internet, common area maintenance and snow removal included in this professionally managed 11-unit building
The exterior, with cornice and orthodox windows are additional architecturally designed items that add to the beauty of the building. No detail has been overlooked. A must see as downtown Ithaca continues to grow. Photos are from other recent projects and are for illustrative purposes. They represent the types of finishes you will find within apartment.”
 

I have never heard the phrase “orthodox windows” unless the topic was a church.

An August 1st opening means this building’s going to have to move at a fairly quick pace over the next few months. I don’t see any current information on rent, but the last I had seen was $1,100/month for a 1-bedroom, which isn’t Collegetown extreme, but it’s premium-priced for the State Street Corridor, and not unusual for new construction. Apartments.com seems to suggests that all the units are spoken for.

Background information on the project and its specifications can be found here. Renting Ithaca (Nick Stavropoulos) is the developer, and Flatfield Designs (Daniel Hirtler) is the architect.





The Lux (232-236 Dryden Road) Construction Update, 4/2018

3 05 2018

At the site of The Lux at 232-236 Dryden Road, framing continues on the new apartment buildings. I’m under the impression that, like the Ithaka Terraces project also designed by STREAM, these are thick double-stud exterior walls. Double-stud walls are built using two sets of wood stud walls used in the exterior frame, parallel to each other but spaced apart by about 5 inches. That space is then filled (if like STREAM’s other projects) with R39 densely-packed cellulose insulation. The result has its pros and cons. The cons are that it’s more expensive to build, and it reduces the interior space a little bit. The pro is that it’s very energy efficient, which comes in handy for a project trying to achieve net-zero energy use.

On top of that appears to be wood furring strips for the cladding. I think the white panels on the north side might be boards with some kind of waterproofing? The roof on 232 Dryden appears to have had underlayment applied, but no EPDM (synthetic rubber) or similar finish yet.

The Amvic ICF will be faced with grey stucco and a black brick veneer, while the upper levels will use LP SmartSide white and marigold yellow fiber cement lap siding. The reflective material is likely insulation that’s also intended to keep out the moisture from the exterior brick.

The top floor will be finished with fiber cement panels with LP SmartTrim laid out patterned to give some visual interest to the top of the structures. The windows are Anderson 100 series units with black frames, and what will be white casings. Still rough openings in some of the walls, and the balconies are just starting to get built on the west face. 236 Dryden has yet to be fully framed, but the roof trusses are underway.

In its March email blast, the developer, local firm Visum Development group, announced that the contest to design lounge, gym and study rooms was won by two graduate architecture students from Cornell – for that, they win $2500 and will have a lounge named after them. The winning designs are here. As of February, about half of the 207 bedrooms were leased.

The project did pay a quick visit to the planning board recently to ask if they would could have permission to not screen some of the rooftop utilities – though less attractive and meant as a cost efficiency, these are less visible parts of the roof per the diagrams provided to the city. I didn’t hear any issues with it, so I assume it was deemed acceptable by the board.





210 Linden Avenue Construction Update 4/2018

1 05 2018

Looks like the first stud walls are going up on the third floor of the four-story 210 Linden apartment project (note the basement is partially exposed). Quite a bit of progress from the excavated hole and foundation pad back in February. This is a wood-frame structure with Huber ZIP System plywood panel sheathing and, presumably if like the other Visum projects, Amvic insulated concrete forms at the basement level. ICFs are thermally insulated plastic blocks filled with concrete – they tend to be a more expensive approach, but they also tend to have a higher grade of insulation (higher R-value), making for a more energy-efficient structure, and Visum and its project architect (STREAM Collaborative) have an eye towards net-zero energy capability, meaning all energy consumed by this building comes from renewable sources. ZIP panels are an increasingly popular to the traditional plywood and housewrap method (and since the integrated water-resistive barrier on the ZIP panels is a vivid green, they’re hard to miss). The choice of ZIP panels vs. housewrap really boils down to a matter of preference by the project team; ZIP panels tend to be easier to install (lower labor cost), but more expensive as a product.

Although my October notes show that William H. Lane Inc. was the general contractor on file, it appears that Romig General Contractor is the firm on-site. Romig of Horseheads is not known locally for involvement with multi-family projects, but as partners in Jepsen Romig Development (now Jepsen Holdings Inc.), they’ve been involved with several luxury homes built around the county (Southwoods, South Pointe, etc.) and they state on their website that they’ve provided commercial services to the ScienCenter and the Cayuga Ridge supervised care facility.

Also notable is that it appears the asking price for rent on the four-bedroom units has come down a fair amount since their first advertisements in the fall, from $1250/bedroom to $950/bedroom. This may be anecdotal evidence of some slack in the Collegetown market, as Maplewood’s 872 beds enter and steadily get absorbed into the rental market mix.

Background information on the project and more renders can be found here.





Chapter House / 406 Stewart Avenue Construction Update, 4/2018

30 04 2018

It’s hard to believe it’s been over three years now since the fire that decimated the Chapter House and the neighboring apartment house at 406 Stewart Avenue. According to a recent write-up by Mark Anbinder at 14850.com, the new build at 400-404 Stewart Avenue will host one eight units –  studio apartment, three 1-bedroom apartments, one 2-bedroom apartment, and three 3-bedroom apartments. The units are aiming for a summer occupancy, and CSP Management (Jerry Dietz and his team) are in charge of the rentals on behalf of developer/owner Jim Goldman.

From the outside, the building is practically complete, except for landscaping/paving, trim pieces, and facade installation of the ground-level bluestone veneer. The 4-unit, 11-bedroom apartment building next door is not as far along, with roof trusses only just being installed, and sheathing (ZIP panels) and window fittings underway on the lower floors. It’s a reasonable bet to say these will be available for their first tenants in time for the start of the new academic year in late August.

As fair as anyone’s aware, the ground-floor space restaurant/bar is still available for lease, at $35/SF (at 3,000 AF, that means $105,000 annually). Chapter House owner John Hoey has said in the comments here that the price is too high for his business. The possibility of a “Chapter II”, as some have dubbed it, seems increasingly remote. Any other potential lessees can contact David Huckle or August Monkemeyer at the Ithaca branch of Pyramid Brokerage.





Maplewood Redevelopment Construction Update, 4/2018

30 04 2018

Maplewood has not had the best of luck during the construction. A wet fall, and an unusually wet and cold spring have really dampened efforts to move the project along at a clip that the development team would have liked. Supply issues (framing walls) and concerns from subcontractors about steady, non-weather interrupted work have also made things more complicated. The developer (EdR Trust, with local project representative Scott Whitham of Whitham Consulting) approached the town of Ithaca with a request to extend the working hours again from 7 AM to 10:30 PM for interior work, on top of the four-hour extension (from 9 AM – 5 PM to 7 AM – 7 PM) and the Saturday 8 AM – 4 PM hours previously granted.

It did not go over well. After getting a tongue lashing from members of the board about incompetence, the planning board did offer a partial concession to 9 PM on a 4-3 vote. As a result, barring no further major issues, most of the units are expected to be delivered in July, though some of the later-scheduled townhouse strings will likely not be complete before August. Ostensibly, there’s a fear that the units won’t be ready in time for incoming Cornell graduate and professional students, in which case EdR will incur the substantial cost of putting them up in a hotel, as some of the Collegetown developers had to do a couple of years ago (325 Eddy’s opening was especially rough). The current plan is three phases of move in, on July 1st, July 31st and August 20th.

From what I’ve heard, at least half the units are spoken for in the 441-unit, 872-bed development. Advertisements have been showing up pretty regularly on websites like Craigslist, as well as their own website.

Walking around the site, construction is in just about every stage imaginable, from framing to sheathing to fit-outs to exterior siding and even trim work on the units facing Mitchell Avenue. There have been some changes in the plans, and I’d argue for the better – more color variations in the apartment buildings and the townhouse strings. The southwest corner building on Mitchell was initially supposed to be shaded of blue, but is finished with red fiber cement panels, and the panels on one of the gabled “Ht” strings next to the Belle Sherman Cottages. The apartments also show varying brick and panel ensembles, from navy panels and red brick, light grey panels and maroon brick, dark grey panels with tan brick….it makes for a more colorful and arguably more attractive site.

Quick aside, a second project webcame has been installed. This one looks over the three apartment blocks on the northern (Maple Avenue) end of the site. Link below, along with the southward camera.

For project background and planning, click here.

For a site plan breakdown, click here.

For a construction timeline, click here.

Webcam link 1 here (updated ~15 minutes).

Webcam link 2 here (New! updated ~15 minutes).