312-314 Spencer Road Construction Update, 1/2017

10 01 2017

The new duplexes on Old Elmira Road seem to be moving right along. The east building has three shades of siding, one for each floor, and a third at gable-level. The exterior is accented by white trim boards. The variety in colors is an easy to way visual interest to an otherwise simple design. We’ll have to wait and see what colors they break out for the west building, which also benefits from a window bay projection facing towards the open space. It looks like plans to use shake siding on the bay projection have been dropped. Both building appear to be fully roofed and shingled. Signage at the edge of the road suggests precast concrete Superior Walls were used in the foundation work.

The 4 3-bedroom units are expected to hit the market in February. In the November update, I noted that Craigslist had these at $1700; the Modern Living Rentals website, which is the rental company for developer Charlie O’Connor, has them listed at $2100. Consider these a preview of the 4 two-family homes to be built at 607 South Aurora this spring and summer, which are also an O’Connor project.

20170107_113210 20170107_113347 20170107_113417 20170107_113438 20170107_113506 20170107_113530 20170107_113545 20170107_113554





210 Hancock Construction Update, 1/2017

9 01 2017

So much to see over at the 210 Hancock site. First, the prefabricated wood wall panels of section “A”, the south wing of the apartment building, are up to the top (fourth) floor, and one gets a pretty good idea of the vertical scale of the building. For the record, roof height will be 46 feet, not counting mechanicals. The second section to the north of it, “B”, was designed by HOLT Architects to be a little closer to the street, so it looks less like one continuous wall, and helps create the impression of separate structures. The first floor of these two subsections, which is framed by metal and wood rather than wood alone, will house the daycare, rental offices and commercial space. Sections “C” and “D” will consist of apartments over the indoor garage, which is currently wrapped in plastic sheeting, and separated from the other two section by a CMU stairwell.

The rental townhouses are fully framed (210 Hancock’s website says window install is expected to start soon), and it appears that Lecesse has start construction on the seven for-sale townhouses – the foundation walls have been excavated and poured. These units have a slab (shallow) foundation, and not having to worry about excavation allows the townhouses to move along at a faster clip. The apartments and rental townhouses should be ready by August, the for-sale townhouses by November. Ithaca Neighborhood Housing Services (INHS) has a website up for rental applications here and qualified home-owners here.

20170106_155902 20170106_155925 20170106_160000 20170106_160020 20170106_160043 20170106_160130 20170106_160153 20170106_160227 20170106_160247 20170106_160309 20170106_160331 20170106_160347 20170106_160457 20170106_160508 20170106_160531 20170106_160540 20170106_160610 20170106_160626 20170106_160639 20170106_160700 20170106_160711 20170106_160720 20170106_160736 20170106_160744 20170106_160821 20170106_160855
inhs_pride_design_v6_1

inhs_pride_design_v5_3 inhs_pride_design_v5_2

202_hancock_1 202_hancock_2

202_hancock_3





Collegetown Terrace Construction Update, 1/2017

8 01 2017

And to think that a year ago about this time, Collegetown Terrace’s Building 7 was just an excavated trench.

On the outside, facade installation continues. It looks like that, along with the fish scales and aluminum panels, there might be a dark blue fiber cement siding not unlike that seen on the smaller buildings lining East State Street. The east cinder block stairwell seen in November’s photos has been wrapped in waterproofing and is now receiving its exterior finishes. Most of the windows have been fitted at this point. The AC units have yet to be installed, and from what could be seen through the windows and openings, the inside has had drywall hung in some locations, but is still down to the stud walls in other sections. There are a couple of architectural quirks that give the building a little bit of visual interest – for instance, the reverse-pitch on the roof where Valentine Place terminates, probably indicating a stairwell or landing area, breaks up the monotony of the wall. I really like the curtain-wall glass used for the amenities/common area at the southwest corner of the structure.

A pine tree on the roof is a traditional way to celebrate the “topping out” of the building.

By the way, I have been wrong – the fish scales are in fact metal, their finish coat just makes them feel like vinyl. According to a trade industry website, they are “0.032-aluminum (0.032” thickness), diamond-shaped, flat metal CastleTop Shingles from ATAS International Inc. of Allentown, Pennsylvania. ikon.5 architects selected three standard colors-Hartford Green, Patina Green and Hemlock Green-and four designer colors-Adobe Dust, Metallic Gold, Acorn Yellow and Louisburg Green.” It looks like the shingles are more commonly advertised for roofing, although their interlocking tabs allow them to be used for walls as well. The three shades of green on Building 7 are the three standard colors, logic being that designer color shingles likely cost more and were used more sparingly. The other four show up on Building 3 where it approaches East State Street.

 

20170106_163724 20170106_163805 20170106_163817 20170106_163912 20170106_163931 20170106_163951 20170106_164021 20170106_164026 20170106_164102 20170106_164206 20170106_164212 20170106_164249 20170106_164309 20170106_164636 20170106_164719 20170106_164730  20170106_164800 20170106_165233





News Tidbits 1/7/17: Storage and Storefronts

7 01 2017

1. Like a phoenix, it looks like Wings Over Ithaca is coming back. The franchise, whose Ithaca location was shut down after the owner was charged with 26 counts of tax evasion, will be operated under a new ownership consisting of four young Cornell alumni from the New York City area. However, while the ownership is changing, the management team for the eatery will be largely the same. The new incarnation will also be in a new location – Wings, which called East Hill Plaza its home for fifteen years, will now be located in a 1,743 SF retail storefront at 119-121 Dryden Road in Inner Collegetown. The property, owned by Ithaca Renting, previously held a Greek restaurant and then a tobacco shop, but it’s been more often vacant than occupied over the past ten years. A new kitchen is being installed in the retail space to accommodate. Expect an early Spring opening.

distributed_sun

2. This sounds promising, but I’m not comfortable with the precision of the details. According to Cassie Negley over at the Times, Washington D.C.-based Distributed Sun LLC, a rapidly-expanding solar energy company, wants to build two large-scale solar installations in the town of Dryden. One would be on Cornell land south of Route 366 on Turkey Hill Road, the other near the Willow Glen Cemetery on non-Cornell private land. The company is familiar with the area, as they are Cornell’s partner on the large-scale array recently installed near the county airport. The company also has plans for seven arrays on four parcels in Spencer in Tioga County, and they’re working with Cornell on solar installations for the tech school down on NYC’s Roosevelt Island.

The topic of discussion is whether or not a PILOT (Payment In Lieu Of Taxes) could be reached for the installation – solar installations are already exempt from NYS taxes, but school districts and towns can levy their own. Since the Cornell property doesn’t pay taxes, a lump PILOT that covers both could actually pay more than taxing the non-exempt proposal at full value. The construction timeframe at present is April-October 2017; and, here’s the imprecise part, the arrays would create 200-250 local jobs and another 100 jobs nationwide – and, from the town minutes, that doesn’t appear to be a typo. Presumably, most of that is construction, and a few in maintenance. I’d like to see the numbers for permanent local jobs, because along with the renewable energy growth and reduced electricity costs for nearby residents, the permanent jobs would be one of the big economic selling points. Given the Mettler Toledo news a few months ago, new jobs in Dryden would be welcome.

100_13701

3. Time for some sad news – 722 University Avenue is gone. The university demolished the 5,738 SF, 116 year-old house it earlier this week. The property has a storied history as the home to several fraternities and sororities; it’s kind of a shame it wasn’t renovated to provide student housing. The university has no long-term plans to redevelop the lot.

20170101_152251 20170101_152310 20170101_152348 20170101_152359

4. Dryden, the storage capital of Tompkins County. Across the street from the 79,000 SF Storage Squad self-storage facility under construction, 4 Season Storage is busy putting up their own addition. According to a loan filing on the 3rd, 4 Season’s new building is 12,000 SF, and the hard construction costs come in at $481,172. CFCU is the lender. The structure is already framed and is being roofed, the cross trusses already separate the exterior units (not sure if those will be climate-controlled like the interior ones). Storage Squad is further behind, a graded site and a couple of reinforced concrete walls at the moment.

20161119_145216

5. In case you were wondering, here are some of county administrator Joe Mareane’s planning and development goals for 2017 –

– Negotiate the purchase of the Tompkins Trust Building for use by the History Center and Heritage Education Center. Also, develop a “governance”, or operations, plan for how the facility will be managed and maintained; how space will be allocated; how rent will be determined, etc.
– Work with NYS DOT and local agencies (Planning and ITCTC) to secure funding for a Route 13 traffic study.
– Facilitate the development of a realistic business strategy that allows the Airport to continue to
serve the community and be financially self-sufficient.
– With TCAction, put plans in place for a new residential project aimed at providing a meaningful
amount of housing for the chronically homeless.
– Bring alternative plans to re-use the rear portion of the Human Services Annex to the Legislature; implement its recommendation.

There’s a possibility, based on the 2016 notes that follow, that the 24-unit Re-Use project and the housing for the chronically homeless may be two different projects – the Re-Use housing project is described as transitional re-entry housing, while the housing for the chronically homeless is said to be in the property acquisition phase – i.e. still scouting out sites, with the goal of construction within two years. They might be the same, they might not, it’s not 100% clear from the notes. As for the Human Services Annex, there have been talks for additional space for Cayuga Medical Center’s services, or space for courthouse functions, and a decision is expected in Q1 2017.





News tidbits 12/24/16: Looking to the Future

24 12 2016

20161211_132440

20161211_132501

20161211_132542

1. Going to take advantage of this light week to go through some of the photo stash. I thought of doing a Poet’s Landing update, but because LeChase is mostly working on site clearing/prep and excavation at this point, and given the snow on the ground, it didn’t seem like there was a whole lot to be gained from making a unique update. But, rest assured, it’s still underway, there’s just not a whole lot to see at the moment. Once the snow melts off, the slab foundations work should be visible, and there might even be some framing going up by mid-winter. The six new apartment buildings and their 48 units should be ready by the fall of 2017.

20161209_121337

2. 107 South Albany in the city is another one that doesn’t merit its own post just yet, but work should be taking place at some point soon. The building permits have been filed with the city for the 6-unit, 9-bedroom renovation and addition to the rear of the existing building, and from peering inside the existing windows, there’s the impression that interior demolition work could be underway – could explain the broken window on the second floor at least. There was no excavation work yet in the backyard, where the new wing will go. The Site Plan Review document says July 2016 to August 2017. Maybe there will be something to talk about by the next round of downtown updates.

3. Some folks might remember Phoenix Books, the hard-to-miss barn bookstore off of 366 as one approached Ithaca from Dryden. The store closed last year after 30 years of business, and the barn itself is about a century old. Now the property at 1608 Dryden Road is for sale. The barn, a small outbuilding, and 29.3 acres for $229,900. According to the Zillow posting, a sale is already pending.

4. From sales to sold. An industrial property in the Inlet Corridor of Ithaca town has exchanged hands. The property is at 142 Ithaca Beer Drive, next door to the growing brewery and restaurant. According to the listing with Pyramid Brokerage, the property consists of “Two commercial buildings totaling 6,812SF on 2.79 acres at south end and just off of Ithaca’s Elmira Road (NYS Route 13) commercial corridor. Ideal for combo of office (812SF) and industrial/warehouse (6,000SF) with lots of room to expand. All municipal services. Warehouse building has high ceilings, concrete floors, 2 overhead doors and more. Great opportunity for light industrial/manufacturing with array of flex space.”

The Iacovellis used it to house their construction equipment, and had it on the market for $409,000. It sold for just under that, a reasonable $400,000, to Greentree Garden Supply, which has operations a stone’s throw away from the property. Greentree makes their own soil products (potting soils, soil formula), so that may be a potential future use of the warehouse they just picked up. Good for them; they seem to be thriving as well as their garden plants.

58505e689f6ef-image

5. Here’s a cool idea – the Lansing School District is planning to build an outdoor classroom as part of $4.95 million in renovations. Cassandra Negley has the full story at the Times. The renovations were approved by a landslide 240-32 vote, which was helped by the fact that the project will be funded with grants and money from the school district’s reserve (rainy day) fund – no additional cost will be assumed by the taxpayers. In advocating for the project, school district staff noted that it would provide for “multi-sensory experiences”, a useful asset during the instruction of natural and environmental science topics, and cited studies that showed students performed better academically when given the opportunity to have classes in outdoor spaces. The space would be used as covered play space during recesses.

maplewood_v7_5

6. Going off into hand-waving territory here. Enter at your own risk.

You might have heard in the news this week that New York State, even though it added 104,500 jobs over the past year, is estimated to have recorded a population loss of about 1,800 people. That’s not a good thing for a number of reasons, but it’s a more acute issue upstate. New York City issued building permits for 101,705 residential units from 2013-2015, with another 13,000-14,000 estimated this year, and the city, just the boroughs and not even counting the suburbs, makes up nearly all the population growth (375,272 through July 2015, vs. 367,179 as the total gain for the state from 2010- July 2016). Upstate continues to hemorrhage people to other states. Not a surprise to anyone who’s travelled outside of Ithaca, Saratoga or the few other bright spots. What can we expect for Ithaca in a bad piece of news for Upstate?

Here are some off-the-cuff tallies for population growth. Ithaca’s estimated to be 30,788 as of July 2015, up 774 since 2010. The estimates due out early next year cover July 1, 2015 to July 1, 2016.  What opened in that time frame?

By my count, Stone Quarry (82 beds), the Lofts at Six Mile Creek (66 beds), 804 East State (18 beds), 707 East Seneca (18 beds), 206 Taughannock (10 beds), the Lehigh Valley House condos (6 units, will assume county average 1.7 occupants per unit, for 10 residents), 116 Catherine Street (17 beds), and the 140 College Avenue (12 bed addition). Allow another half dozen or so units with a dozen beds total, for accessory apartments or new single-family homes. Only one of these projects replaced existing housing units – a one-bedroom bungalow came down for 804 East State. The gross gain is about 244 people, if we assume the standard of one person per bedroom or studio unit.

Now let’s do some subtractions. Hughes Hall closed on Cornell’s campus. -47 off the bat, for 197. Now, the math can’t easily accommodate those who had a household member move in/be born, or move out/pass on. But trends suggest a 2% decrease per decade, so we’ll treat it as negligible. So, my baseline prediction for the 2016 estimate is 30,981.

Just thinking offhand of the projects that have opened since July 1, 2016, expect at least 210 more for the July 1, 2017 estimate, and 670 in 2018, because that’s when Collegetown Terrace phase III (344 bedrooms), Novarr’s townhouses (net gain ~60 bedrooms), 210 Hancock (90 bedrooms) and Todd Fox’s latest trio (net gain ~110 bedrooms) are included in the figures. These drive-by numbers are based just on what’s underway, or approved and financed. The 2017, or more particularly the 2018 numbers could go up. So roughly, 30,981 in 2016, 31,191 in 2017, and 31,861 by July 1, 2018, assuming no major catastrophes and that the local economy’s growth and residential vacancy rate is consistent.

For the record, the purely mental figure I use for a 2020 census is 32,500. That would consider Harold’s Square (146 bedrooms), City Centre (250 bedrooms), the first phase of Chain Works (80+ bedrooms), as well as other proposals that may arise in the next year or two and open before April 1, 2020, the official census date. I do not factor in any new Cornell North Campus dorms in the estimate, since the new dorms will initially function as temporary replacements for existing space that will be concurrently closed and renovated.

Now, when thinking about the town of Ithaca, things get really weird because of Maplewood – a loss of 370-380 beds. The town doesn’t have any large multifamily underway – my partially-imputed count from permit reports gives about five newly-occupied duplex units and 20 or so homes for the July 2015 – June 2016 period, and the 10 Belle Sherman townhouses. That’s probably 100-120 beds total. The town of Ithaca will likely show a decrease in population in the 2016 census estimate because of the Maplewood closure, and it will be bad optics because there’s all this talk of affordable housing issues, and seeing a decline in population in the news will inspire a negative kneejerk reaction – either “if it’s going down do we really need housing”, or “hey, it’s going down, then why are the rents so damned high”. Have that talking point ready, Ithaca town board.

For the 2017 count/2018 release, the partially-educated guess is an increase of 150 given Brookdale, but the 872 new Maplewood residents won’t come into count until the 2018-19 estimation period, at which point we’re pretty much at the next census. I’m thinking around 21,500 for 2020 (from 19,930 in 2010), if the current trends continue and major housing projects are completed.





201 College Avenue Construction Update, 12/2016

18 12 2016

The Collegetown construction boom continues. In 2017, the city can expect at least five projects to open in the neighborhood, with a net gain of about 118 beds and $16 million in assessed tax value** – a two-family house at 123 Eddy Street; Cornell’s, 6-story, 76,000 SF Breazzano Center for its Executive MBA Program; the 5-unit, 28-bed 126 College Avenue;  the 9-unit, 36-bed 210 Linden Avenue; and lastly, the 5-story, 74 bed 201 College Avenue. Which has also been by far the most contentious one.

The project was first proposed in March – and from beginning to end, the only substantial change was a mild revision to its upper floors to create a setback as a modern deference to the Grandview House further up the block. That resulted in a loss of two bedrooms, dropping the plan from 76 to 74 beds.

For Todd Fox, who proposed the building through his company Visum Development Group, there wasn’t much room for revisions. He was going to, and paid, a premium on the property – $2.65 million, formally deeded in June by its previous owner, a small-scale local landlord who owned it for about seven years prior. The site held an early 1900s apartment house with three large spruce trees at the front, which became another source of contention during the debate.

To make the project financially feasible, he needed to build to the maximum 5 floors and 70 feet allowed by the site’s MU-1 zoning (the project would have been outright impossible before the 2014 CAFD zoning overhaul, due to the parking requirement), and building micro-units with mezzanines would make the project pencil out – the profit value of the vertical space was effectively maximized. Working with architect Noah Demarest of STREAM Collaborative, he proposed a fairly modern building with fiber-cement panels, woven bamboo boards and cedar accents.

However, one thing that did not factor in to the calculations was the neighbor of 201, 203 College’s Neil Golder. Neil is a 44-year resident of Collegetown, having moved in in 1972, and buying his house in the early 1990s. As the kitchen manager for Loaves and Fishes and a former Common Councilor for the 4th Ward, he’s well known among the Ithaca community and is well connected to its grassroots organizations, as well as the political movers and shakers. By any account, Neil and his late partner Kathy Yoselson are beloved stalwarts of Ithaca’s progressive scene. However, Neil has generally not been a fan of development, particularly Collegetown’s (with one notable exception – 307 College).

What 201’s debate boils down to is a clash of two strong personalities. Todd Fox, who is probably the most gung-ho and financially adept developer one will find in the city of gorges; and Neil Golder, who was determined as hell to stop the project planned for the house next door, which wasn’t just a development, it was a project that he deeply felt would be a major detriment to his quality of life. Hence, Neil launched the group “Save the Soul of Collegetown“, under the auspices of protecting all of Collegetown, but mostly as a personal vehicle to drum up support to battle Fox and his apartment building.

The point of this summary isn’t to summarize every detail. You can read the 580+ page summary from the city, or all the Voice articles here. But there are a few key plot points.

After review and a negative declaration of environmental significance (meaning, effectively mitigated), he project received preliminary approval in June, and the city and the planning board were promptly slapped with a lawsuit by Golder. The stated case was that the environmental assessment was inadequate and that the project needed an EIS. Although it was quite a stretch given past precedent, it did make the planning board quite uncomfortable. John Schroeder, a longtime board member who served with Neil on the council, did a very deep analysis of the 2014 zoning code and determined that the building may be illegal on technicality.

That technicality was about building facade length, and whether Bool Street was a primary facade – if it was, it would legally have been required to be two separate buildings for having too long of a continuous face to the street. The zoning code, however, illustrated that an approach with indents such as 201’s were acceptable, and the city planning department, in their pre-site plan review assessment and meetings with Fox, had signed off on the plan as legal and acceptable. And they maintained that it was acceptable. So there ended up being a battle between the planning board, which is appointed though knowledgeable community members, and the planning department, which consists of vetted city staff. These kinds of battles are extremely rare, and it is likely that 201 was the first in decades.

While this debate raged, the building far exceeded its intended start date of July 2016. As a result, the site went on the market, and the plans were cast into jeopardy.

Although Fox and his team wanted to avoid a trip to the Board of Zoning Appeals, it was determined by the board to be the only legitimate course of action. The BZA had to decide whether or not the project was legal. And, in a 3-1 decision in October, they decided it was legal, due to ambiguity in the code, and a lack of timeliness on the part of the planning board, as the legality was not considered until after months of review, after preliminary approval was granted. After the BZA ruling, work on the building began the next day.

No one walked away from this one looking good; One reader emailed in and compared it to a Clinton vs. Trump vote. The debate sent a chill down the development community, and created additional bitterness for some of the old-timers who felt Ithaca was selling out to developers and student interests. The planning department and board were also left with some resentment towards the other; now that the code has been clarified, one can hope further battles like this can be avoided.

Anyway, the building itself. Here are the floorplans. The mechanical room, a trash room, interior bike storage, gym and storage space occupy the basement. Four three-bedroom and four four-bedoom units (28 beds), with about 1,000 SF each, occupy the first and second floors. The third and fourth floors have micro-units, 16 of which will be about 392 SF studios, 8 of which will be 670 SF with two bedrooms, give or take a few feet for each (32 beds). The top floor has nearly the same layout as three and fourth, with eight micro-units of about 392 SF and 2 two-bedrooms of about 670 SF. However, the westernmost two units are studios, which have balconies and are about 400 SF each. So, 14 beds on the top floor, for a total of 74. The smaller units make use of mezzanine spaces and netting to increase usable space.

Fox’s rental company, Modern Living Rentals, is handling the leases. The units are currently listed from $1,670/month to $4,170/month, depending on size and location.

In the photos below, note that the excavated portion is only half of the building footprint – the basement only occupies the western half of the structure. The eastern half is slab-on-grade (Collegetown has more stable soils than most of the valley locations, so multi-story slab foundation buildings are feasible). The elevator core will be in the middle bridge of the “H”-shaped structure. Foundation forms are up and the concrete is being poured – through the fence, you can see one of the concrete footers already in place.

William H. Lane Inc. of Binghamton, who just finished up the Marriott downtown, is the general contractor for the approximately $6 million project, which is paying a premium to meet the opening date of August 2017.

**If you add in Phase III of Collegetown Terrace, which is on the fringe of what’s normally considered Collegetown, raise those numbers to 462 beds and $71 million.

20161209_153319

20161209_153332

20161209_153341

20161209_153350

20161209_153402

20161209_153706

201_college_site 201_college_v5_1





Tompkins Financial Corporation HQ Construction Update, 12/2016

18 12 2016

The future headquarters of Tompkins Financial Corporation is starting to rise from the ground at 118 East Seneca Street. The elevator core and south stairwell are being poured section by section. Forms are being put into place to build the next level of the core. It looks like structural steel surrounded by concrete fortified with steel rods (rebar). The small holes within the elevator core are where the structual steel of the superstructure will tie in. The basement appears to be fully excavated with all the wood lagging in place. The four H-shaped steel bars next to the elevator core are piles, which will carry the building load. More on those in a minute.

The basement for the TFC HQ is a bit of an unusual setup. The excavated portion (12-13 feet deep) only encompasses the floor plate for the basement and ground floor. The second to seventh floors will have larger floor plates. The elevator core actually sits at the northeast corner of the ground floor’s floor plate – the area between it and the Hilton Garden Inn will be the driveway, and behind it, the customer parking lot. Stairwells to the upper levels will also rise on the northeastern boundary of the property, and the northwest corner of the first floor, close to the parcel’s lot line with the DeWitt Mall. The upper floors will have the support of additional load-bearing columns along the perimeter of the property (they will tie into the end-bearing steel foundation piles seen here in August, which seem to be capped and at ground level now).

Along with the perimeter piles and the piles within the ground floor plate, four support columns will rise from through the parking area to the floors above. Those appear to be pile caps for two of those support columns in the second to last photo. The four H-shaped steel bars are capped with a thick block of concrete from which the support columns will tie into, and use as their base. The weight of the building will be transferred through the steel structure, through the pile cap and evenly distribute the weight into those piles, which will transfer the load down into very firm soil 65-70 feet below ground level. This is what will give the building its stability.

Anyway, seems like I forgot to take photos of the drive-thru bank branch under construction across the street – which is probably close to completion at this point, if not already. The $31.3 million office building will open in March 2018. LeChase Construction is the general contractor, and HOLT Architects is responsible for the design.

20161209_125159 20161209_125207 20161209_125228 20161209_125243 20161209_125309 20161209_125322 20161209_125401 20161209_125416

tfc_hq_first_floor_plan

tfc_hq_profile





Hotel Ithaca Construction Update, 12/2016

15 12 2016

The Hotel Ithaca addition at 222 South Cayuga is topped off and has taken the shape of the final product. Most of the new windows have been fitted into the exterior walls. Air conditioning units will be installed in the smaller openings. Peering inside, it looks like the interior framing is all set, and utilities rough-ins are underway.

In most places, the DensGlass fiberglass mat sheathing is being sealed up with R-Guard FastFlash liquid flashing, to close up the seams, joints and fasteners. Some of the newer sections, like the south wall, have yet to be sealed – in fact, workers were cutring and installing the DensGlass boards on the balconies while these photos were being taken. Since the balconies aren’t meant for full-time occupancy, the fiberglass mats are going directly onto the steel studs, without the R-Max polyiso. Taking a guess here, the gray coat on the front (east) wall might be a primer material for the exterior facade.

Along with general contractor and frequent Hart Hotels partner Krog Corp, it looks like Henderson Johnson Inc. of Syracuse was tapped for some subcontracting, and IBEW-sponsored John Mills Electric of Ithaca is handling the electrical rough-ins for the new wing.

The new $13.77 million addition should open in May 2017, just in time for the big graduation weekends. More background info on the Hotel Ithaca project can be found here.
20161209_122235 20161209_122240 20161209_122252 20161209_122341 20161209_122350 20161209_122356 20161209_122509 20161209_122807 20161209_122819 20161209_122840

hotel_ithaca_final_1





209-215 Dryden Road Construction Update, 12/2016

14 12 2016

Cornell’s Breazzano Family Center at 209-215 Dryden Road is closed up for the winter. Literally, with white plastic sheeting, as a protective measure against the elements while interior work moves along. The plywood holes on the front and back sides are removable so that a lift can deliver materials to different floors of the 6-story building. One can make out the dramatic entry foyer above the steel stretching out the sheeting above the ground floor. Note that the height of the building, 80 feet, is the maximum permitted under Collegetown’s form zoning (MU-2, up to 6 floors or up to 80 feet).

The plan is to have the new 76,300 SF building open by Summer 2017. Hayner Hoyt Corporation of Syracuse is the general contractor.

After the last Breazzano update a couple months ago, I had contacted Cornell to do a piece about the expanding Executive MBA program, what’s driving the growth, why Collegetown, and so on…but after being led around or misled by several emails over a few weeks, I gave up on the piece. For what it’s worth, Poets and Quants did a thoughtful article and interview here with the Johnson School Dean, Soumitra Dutta, talking about the future of the MBA program and the business school merger with the Dyson/AEM program and the Hotel School. Maybe I’d have had better luck if I just sidestepped Cornell’s PR unit.

20161209_155004 20161209_155019 20161209_155104 20161209_155204 20161209_155215 20161209_155234 20161209_155258

209-215_2





St. Catherine of Siena Parish Center Construction Update, 12/2016

12 12 2016

Over at St. Catherine of Siena’s new parish center, it looks like the GlasRoc sheathing towards the roof has been sprayed with the dark blue waterproofing, some “continuous anchors” (metal rails) have been attached, and the exterior panels are being attached. The renders show a different color and possibly material, so it’s not 100% clear on whether this is the final appearance.

Below that, the stone veneer is progressing, and most of the gypsum sheathing has been waterproofed. Only a few of the smaller windows have been installed, the rest still have yet to be fitted. In the second to last photo, the new enclosed walkway from the parish center to the church is coming along, framed but not yet outfitted with its expansive glass walls.

20161209_162951 20161209_163002 20161209_163043 20161209_163048 20161209_163128 20161209_163150 20161209_163302