News Tidbits 5/4/19

4 05 2019

1. Generally speaking, when the opposition is opposed to the aesthetics rather than the purpose, then a project is in good shape for IDA approval. That looks to be the case with the Vecino Group’s Arthaus project. The 124-unit all-affordable (50-80% area median income) project at 130 Cherry Street will be seeking IDA approval for an abatement at the May meeting, after hosting its public hearing this month (minutes here). As noted by the Ithaca Times, apart from complaints about it being too big or ugly, there wasn’t much in the way of opposition to the premise of the project, which is what the IDA is more interested in. As far as the IDA is concerned, aesthetics are something to be handled by the Ithaca Planning Board; if it’s okay with the PB, then it’s okay with them. Chances are pretty good that the abatement will be granted. The abatement is worth about $3.73 million towards the $28.8 million project.

2. It may have taken two tries to get the zoning variance approved, but Habitat for Humanity is moving forward with its redevelopment and new builds at 1932 Slaterville Road in the town of Dryden. The existing 19th century farmhouse will be renovated into a four-bedroom home, a first for the local chapter. The land will be subdivided into two additional one-acre parcels for a new three-bedroom home on each lot, about 1,100 SF each. Each home will cost about $70-$75,000 to build, and the goal is to have them ready for occupancy by mid-2020.

Habitat homes are typically sold to families making under 60% of Area Median Income (AMI), or about $36,000/year. The homes would have built with a combination of professional contractors and volunteer labor, including 350+ hours of “sweat equity”, where the future homeowners actively work as members of the construction crew. In a market starved for affordable housing, every little bit helps.

3. We don’t tend to see many big commercial or industrial buildings listed for sale (if in part because there aren’t many), but it looks like the TransAct Technologies building at 20 Bomax Drive in Lansing is now for sale. Now, before anyone gets nervous, the business isn’t going anywhere; they’ve always leased the space since the building opened in 1998 and have a triple-net lease.

A triple-net lease means the tenant pays everything – insurance, maintenance and real estate taxes (formally, net insurance, net maintenance and net real estate taxes on the leased asset – the three nets).  As a result, the rent is substantially lower than it otherwise might be. It may not be all that lucrative, but the property ends up being a fairly safe investment (though with a lot of fine print to determine who pays for things like if a tornado hits or the foundation cracks), generating a modest amount of rent and functioning like an inflation-protected bond, but guaranteed by the lessee rather than the government. All the better when the tenant is stable and signed on for the long-term as TransAct has been.

For just under $6 million, the buyer gets a fairly new industrial building on 7.54 acres with 18,066 SF of office space, 55,759 SF of warehouse and manufacturing space, and the security of a long-term tenant. This will not be an exciting sale, but it’ll be interesting to see who the buyer is. Warren Real Estate is the seller’s agent, and the offering description with financial data is here.

https://platform.twitter.com/widgets.js

https://platform.twitter.com/widgets.js

4. A little bit of soapboxing. I’ve been seeing and getting some messages to this effect lately. First, I’ll note that the first comment is a bit disingenuous. That’s the highest-priced three-bedroom unit. To quote the range of prices from the Ithaca Times:

“Affordable in this case will include rents for people making 50-80 percent of Area Median Income (AMI), which means that rents for studios will be between $737 and $1180 per month, to 1,095 and 1,752 [per month] for a three-bedroom apartment, the highest price.”

Anyway, the comments tend to be to the effect of “this isn’t affordable enough, so I can’t support it”. That’s a textbook case of letting the perfect getting in the way of the good. Here is a project with 124 affordable housing units, with 40 of the units set aside for formerly homeless youth and families with on-site supportive services from TC Action. It would do a lot of good to have this project available to the community.

Honestly, the argument feels like the next evolution of the arguments against affordable housing in general. Now that it’s firmly ingrained that there is a lack of affordable housing in Tompkins County and it does negatively affect the community, the next step is to say, essentially, that nothing is good enough. From a pragmatic stadnpoint, since these projects aren’t something banks and credit unions will fully finance because of the lack of a sizable return on investment, it falls to NYS to award grants. The state will not dispense larger tax credits to make a unit drop from 60% AMI to 30% AMI, that’s up to the developer to make up the bigger financial gap. To do that, either they add in higher-priced units to compensate, or the project doesn’t happen. Which is probably the end goal for many of the complainers anyway. It’s kinda like saying you’re available for a date, but only to those who are millionaire PhDs.

Anyway, weigh each project on its merits. But set reasonable goals.

5. As reported by Dan Veaner at the Lansing Star, developer Eric Goetzmann is seeking changes to the senior housing to be included as part of the Lansing Meadows project. The primary changes are making Lansing Meadows Drive into a one-way street (thus allowing it to be slightly narrower while still able to host on-street parking), and making each duplex into a triplex – three senior housing units per string, for a total of thirty. As a result, the units will be slightly smaller, though still two-bedroom apiece. The two end units in each building will be 1252 SF with a 395 SF garage. The center unit will be 1114 SF with a 251 SF garage. The third change is that Goetzmann and his project team want to amend the approvals to allow the sale of units in the future (the initial plan still calls for market-rate rentals).

This comes with a set of issues that need to be sorted out. The project has to be complete by July 2020 as required by the village in their approval resolution. The village planning board now has to consider the proposed amendments and consider whether they constitute a major change from the approved Planned Development Area (PDA, the village’s DIY zoning). Doing so would either cause the plan to be delayed and violate the resolution, or if declined for further consideration, the resolution would likely trigger a lawsuit between the village, Goetzmann, and the county IDA, who granted an abatement to Lansing Meadows. If they say the changes are minor in the context of the PDA, then construction is expected to start as soon as the amended PDA is granted (May 13th at the earliest).

The plan is to build the northern triplexes first, and then the southern units. The planning board’s not a fan from an aesthetics perspective, but the village’s code officer that the northern half is more elevated, so this reduces stormwater risks. With construction underway and loose soil on the site, if built later the exposed northern half could result in runoff and flash flooding downhill, into the southern half and its new homes. The commercial component on the east side of the property cannot legally be built until all residential units are completed.

It’s been nine years since this project was first pitched, and most stakeholders just want to get this project out of their hair. It’s not clear when that will happen.





News Tidbits 4/27/19

27 04 2019

1. Matt Butler at the Times is providing an in-depth check-up on the mall this week. This was a story the Voice had laid groundwork for as well, so it’s nice that one of the local news orgs was able to make hay of it. The mall, like many middle-class local malls across the country has been struggling in the age of Amazon and the retail meltdown. The overall economy might be humming along, but retail closures continue to spike nationwide, with over 6,100 closures planned this year alone, more than the 5,900 announced in all of 2018. With planned new store openings numbering 2,100, it’s practically two stores closing for every one that opens. Retail mega-landlord Cushman and Wakefield estimates 9,000 stores will close in 2019, and over 12,000 in 2020. In the Ithaca Mall, Gertrude Hawk is gone, American Eagle closed up last year, Ultimate Athletics shut its doors, the Bon-Ton closed as part of the shutdown of the whole chain, and the Sears Hometown store is kaput. The mall’s manager cited a variety of reasons, including chain downsizing, poor performance, and some just stopped paying rent.

This has major economic impacts; the mall’s property value has declined by over 60% since the start of the decade, and the village, the county and the schools have to make up those hundreds of thousands of dollars in property tax revenue somewhere (and the county and schools have). County legislator Deborah Dawson, who represents the mall’s district, suggested doing something similar to the DeWitt Mall downtown, a mix of local businesses, but the mall is a much bigger space to fill (622,500 SF vs. 117,500 SF in the DeWitt Mall), and DeWitt Mall is mixed-use (retail and 45 apartments). Local businesses and experiential outlets can be part of the solution as Running 2 Places is showing with their 18,000 SF theater this spring, but it’s one component of a solution. Residential could be a component, but some legal and logistic issues would need to be sorted out, which owner Namdar Realty has never shown much interest in; the village has also been lukewarm to the idea. About 40 apartment units were floated for a section of the parking lot (west/on the backside of the mall if I remember right), but that idea died during the Great Recession.

There is so silver bullet here. The owner needs to be more proactive then holding a proverbial gun to its’ tenants heads in order to get them to stay. Local governing bodies also have to keep an open mind for redevelopment ideas – if parts of the mall were torn down and replaced with residential, for example. As it is, the only plans on the horizon are an unnamed tenant for the former Bon-Ton space, and the extended stay hotel planned for the parking lot behind (west) of the Ramada Inn. The future of the mall is hazy; like a species faced with a steadily changing habitat, it’s either adapt and evolve, or perish.

2. Courtesy of their Facebook page, here’s a sketch render of what Salt Point Brewing Compant’s new brewery and taproom would look like. It’s a fairly unobtrusive one-story structure with a gable roof and two wings, presumably the taller one for the brewing tanks and the smaller one for service functions. On the outside are wood accents and a two-story deck for outdoor drinking and possibly dining, if the restaurant option is pursued.

The building, as well as associated landscaping and parking improvements, would be located on about three of the five acres sold as Parcel “D” in the Lansing Town Center development. The remaining two acres are wetlands and would be left undisturbed. Salt Point paid $75,000 for the land, and will bring its project forth to the town planning board in the coming months. No word on any job creation figures yet.

3. The NYS DOT county facility plans are moving forward. The state bought its 15 acres from Tompkins County for $840,000 according to a deed filed on April 24th. The building is classified as a sub-residency facility, a step below a primary regional facility (the main office for Region 3 is in Syracuse).

To review, the plans consist of the 30,000 SF sub-residency maintenance building, a 5,000 SF Cold Storage unit, an 8,200 SF salt barn, and a 2,500 square foot hopper building (covered lean-to). The proposed maintenance building will have vehicle storage for 10 trucks, a loader and tow plow, with one additional double depth mechanical bay and single depth, drive-thru truck washing bay. It also includes an office area (three rooms), lunch/break room (30 people), toilet/shower/locker rooms, storage rooms and mechanical/electrical rooms. The site will also contain stockpile areas for pipe, stone and millings, and ancillary site features include parking for 40 vehicles, and stormwater management facilities. A new access drive will be constructed from Warren Road.

The town has been less than pleased with the project, which is not bound to zoning code because it’s a public resource facility owned and operated by a government entity. Rather than voice approval, the planning board voted to acknowledge that they simply had no authority to control the project. Some modifications were made to the plans at the town’s request, such as the fueling station being moved onto airport property across Warren Road, but neighbors are still unhappy that snowplows and heavy-duty maintenance vehicles are about to be their next door neighbors.

The facility is expected to be open by the end of the end of the year. Once all staff and equipment have been moved in, the county may pursue a request for proposals/request for expression of interest for the current DOT property on the shores of the inlet near the Farmer’s Market. A 2015 feasibility analysis found that the site could conceivably host a $40+ million mixed-use project, and the site has became more amenable towards redevelopment with the enhanced density and use provisions made to the city’s waterfront zoning in 2017.

4. The Ithaca city planning board granted a negative declaration of environmental review to the 124-unit Arthaus affordable housing project at 130 Cherry Street. According to my editor Kelsey O’Connor, the latest revisions propose a five-story building that would include a gallery, office and affordable rental space. It would include parking for about 36 vehicles and 7,600 square feet of potential retail or office and amenity space geared toward artists. All of the units would be restricted to renters earning 50 to 80% of the area median income, or about $30,000 to $45,000. The north end of the property will also include a publicly accessible path leading to the inlet.

Speaking in favor of the project were neighborhood business owners and non-profits, and in opposition was councilman George McGonigal, who said both in a letter and in person that it was too big for the site and threatened the industrial character of the neighborhood. They have bigger concerns than housing nearby. Cherry Street is difficult to access with large trucks and commercial vehicles, the Brindley Street and Cecil Malone Drive bridges are small and in poor shape. Secondly, Cherry Street doesn’t provide much room for operations to expand, so that hinders their long-term operational planning. It’s not just lot size, but also the soil – the Emmy’s Organics project fell through because of poor soil not amenable for warehouse and other light industrial functions that rely on a concrete slab. Thirdly, the city’s strict environmental laws, fees and higher property taxes make an urban site less appealing. They can get more land with a lighter tax burden in Lansing, Dryden, or any of the other outlying towns. With these issues in mind, many of the industrial businesses down there now aren’t looking to stick around. Several have already sold or made purchase options with developers as they seek areas with lower taxes, easier access to highways and less strict environmental ordinances.

The unanimous approval by the city planning board allows the project to move forward with consideration for preliminary approval. The goal is to gain approval at next month’s meeting, and once affordable housing funds have been secured, to start construction of the project, likely in December of this year.

5. The Chain Works District presented plans for phase one at the Planning Board meeting. There are four buildings in phase one, of which two are in the city. 43,400 SF Building 21 would be renovated into a commercial office building. The work here is limited to replacing walled-up window openings with new windows, exterior cleaning and painting, and new signage and entrance canopies. Building 24 is a combination of renovation and expansion. The partially built-out basement and first floor would be renovated for commercial office space, the second and third story would be residential, and a new fourth floor would be built for residential uses, for a total of 135,450 SF across 4.5 floors. As with Building 21, new windows would be installed, and the exterior cleaned and painted. New landscaping, sidewalk and parking areas are also planned.

At a glance, the residential in the first phase would host 60 market-rate rental units. Each floor will have one studio unit, nine one-bedroom units, nine two-bedroom units, and one four-bedroom unit. According to the Site Plan Review document, the project would begin renovation in October, and be open by August 2020. The other two building in phase one are renovations of industrial and manufacturing spaces in the town, Buildings 33 and 34. These will retain industrial uses.

This meeting was only for the purpose of sharing and discussing plans, with no voting at this time. According to Edwin Viera at the Times, the board was reluctant to approve any plans without more information about who will be occupying them. That seems a bit odd, because projects are analyzed for their physical impacts, not the tenants, but the Times article says parking and landscaping may change slightly depending on the tenant. According to project representative Jamie Gensel, the USDA is considering renting out some of the office space. The USDA maintains a research facility inside the Holley Center on Cornell’s campus, and there were plans in the late 2000s to build an addition, which were later shelved during the Great Recession. It’s not clear how much space they’re seeking. Not sure what to make of that writeup, honestly, or being told to move the buildings into a different phase (personally, I’d like to be renovations before any new builds happen).

6. 815 South Aurora Street, aka “Overlook”, also continued its review at the planning board meeting. There were some minor design tweaks, seen in the before image (above) and after image (below). Changes in exterior colors, panels, ground-level entrances and fenestration, particularly on the side facing South Aurora Street. The fire trucks are  to indicate that emergency vehicles will be able to safely pull in and out from the road. Overall, project size remains at 49 units and 141 bedrooms.

There’s been some pushback from neighbors regarding size and neighborhood character. There’s an argument that these are dependent on Chain Works, but that argument doesn’t pass the smell test – if Chain Works didn’t happen, fewer units on the South Hill market would make the project even more appealing to Visum Development and Modern Living Rentals. The planning department wants more geotechnical information and bedrock to be removed, details about the new planting and landscaping, and energy systems. Documents submitted indicate the all-residential development will use electric heat pumps. The board has requested a shadow study and flesh out the environmental impacts, which is a common request for larger developments.

7. At least one project is fully approved. Although it seems at least one planning board member asked for affordable housing, the four-unit market-rate Perdita Flats infill at 224 Fair Street was granted preliminary site plan approval. The project is intended to be a sustainable building showcase of eco-friendly features, a net-zero energy showcase of what can be done with environmentally sustainable multifamily housing. The owner/developers, Courtney Royal and Umit Sirt, will be applying for incentives from the NYSERDA Low-Rise Residential New Construction Program and are hoping to attain the Zero Carbon Petal of the Living Building Challenge.





News Tidbits 4/9/19

10 04 2019

1. Something to keep an eye on for potential future retail or hotel development – a pair of properties up for sale along the Elmira Street commercial corridor in the city of Ithaca. 363 Elmira Road is the former Aaron’s rent-to-own (which was a rather dubious enterprise, but I digress). After eleven years, they’ve called it quits and the site’s available for sale or lease from the Lama family of realtors. For $950,000, the buyer gets a 5,892 SF 1960s retail building and a 3,000 SF storage barn on 0.77 acres. The assessment is a more modest $525,000. This is probably too small for a hotel, but food retail or small box retail could make do here.

A little further down the road is the former Cold Stone / Tim Horton’s, which only survived a few years before the Syracuse franchisee threw in the towel on a dozen locations with hardly any notice back in November 2015. The property would later be bought by a suburban chain hotel developer out of Corning, Visions Hotels. The property for sale at 405 Elmira Road is the vacant lot next door, which is owned by the former owners of the Buttermilk Falls Plaza. For some reason, even though the plaza was sold over fifteen years ago, they held onto this 0.74 acre lot, and it was used for extra parking. The price is $465,000. The former Tim Horton’s is arguably too small for a standard chain hotel (60-80 rooms + parking), but if combined with this lot, development becomes much more plausible for Visions. Or, someone else may buy it for food-based or small box retail.

Both 363 Elmira and 405 Elmira are in Ithaca’s SW-2 zoning, which in practice is the city’s catch-all for suburban strip and auto-centric development. Residential would be unusual but legal. Zoning allows 5 floors and 60% lot coverage, though normally the development pattern is towards gobs of surface parking. Should some sales happen down this way, there will be an update.

2. We’ll stick to the real estate sales for the time being – INHS bought a small 0.11 acre vacant lot in Ithaca’s Southside neighborhood last week, and chances are, it’ll be the next standalone for-sale single-family home. The previous owners had used 511 South Plain Street as a double-lot, which came with their home next door when they purchased it in 1986. INHS paid $65,000 for the lot, which is a tidy return for a property assessed at $38,500, and above the asking price of $59,000, which is not uncommon in Ithaca’s rapidly appreciating inner residential neighborhoods. In this case, INHS is likely to do an appropriately-scaled (1100-1400 SF) home for sale to a lower middle-income family making 80-90% of area median income. Seems like a win for the neighborhood, given concerns about gentrification and appropriate development. Expect home plans to come out in the next year or two.

3. So 511 South Plain Street will likely be an example of small infill development, a development of modest scale on what’s currently a vacant lot. Small infill is a way of adding density and addressing some of the area’s housing issues in a way that is less jarring and more accessible to existing homeowners and local landlords. With that in mind, the Tompkins County Department of Planning and Sustainability will be hosting a workshop at the Tompkins County Public Library on Wednesday the 24th at 5 PM on Infill and Small-scale Development. The presentation by the Incremental Development Alliance is for those who are interested to learn about small-scale development and infill, explore ways to design laws to encourage infill with robust and easy-to-understand zoning and design codes, and give education and advice to those who might be interested in being developers of small-scale additions to the community fabric. Think less City Centre and more like 1001 North Aurora or Perdita Flats. It’s a free event, no need to RSVP, and video will be posted online afterward.

4. If you ever wanted to look at the nuts and bolts of a real estate development project, local businessman Gary Sloan has but made practically all of the financial figures available for his stalled 1061 Dryden Road project in the hamlet of Varna. The 36-unit, 84-bedroom project has been for sale for a while now, and has been reduced slightly in sale price, to $1.95 million. Based on these documents, it looks like the CAP rate is 6.25%.

CAP rate, or capitalization rate, is a measure to evaluate the potential return on investment for a real estate developer. It’s basically Net Operating Income divided by Property Asset Value (in 1061 Dryden’s case, the NOI is $824,167, and the PAV for the finished project is $13,190,000). For example, if I make $50,000 a year in net operating income on a $1 million property, my cap rate is 5%. In general terms, higher cap rates mean high potential return, but are generally seen as indices of higher risk projects as well.

However, because different markets have different risks and amounts of risks, what is an acceptable cap rate in one area may not work in another. For office space for example, a cap rate of 3-4% in Los Angeles or New York would be sufficient, but for Phoenix it’s 6%, and Memphis 8%, because the stability and growth of the market isn’t as great. Also, CAP rates for multi-family properties are generally among the lowest in asset classes because they’re often the most stable. So CAP rate is a valuable indicator, but it doesn’t tell the whole story.

The rumor mill says that some local developers have checked the plans out, but no one’s put in any offers to buy. The project comes with a Danter housing report and an analysis of Cornell University enrollment growth, clear nods towards both the potential as general market housing and student housing. But for the time being, the future of this project remains up in the air.

5. As covered previously, the city of Ithaca is looking to do a parking study to figure out how much it needs over the next ten years, and ways to mitigate some of that growth in need. The Ithaca Times’ Edwin Viera has their take, and there are a couple of details worth noting – any work on the Seneca Garage will wait until the Green Street Garage Development is complete, frankly because Downtown Ithaca cannot handle both garages being out of operation at the same time. That would mean a late 2021 or early 2022 reconstruction or redevelopment of the Seneca Street Garage at the earliest.

An RFEI to gauge redevelopment interest among private developers will go out in the next six months, and from there the process would be similar to Green Street – see what comes back after a few months, host meetings for Q&A and public input, score plans and declare a preferred developer (if any) before jumping into negotiations and any potential sales or usage agreements. We’d be well into the 2020 timeframe for any preferred developer decisions, which comes before negotiation and planning board review. There likely won’t be that much time between approvals being granted and construction because the process will take a long time to go through. Some early ideas being floated in a rebuild are a ground-level bus depot, or street-level retail to make for a more active pedestrian experience. This is a long-term project, but the RFEI could be an interesting read when it comes out later this year.

OLD RENDER

NEW RENDER

6. Ithaca Neighborhood Housing Services is considering a tweak to its plans for the Immaculate Conception school property. The biggest change would be that the two family house on the corner of West Buffalo and North Plain Streets would come down and be replaced with three townhomes – this is not set in stone, but intended to show a plausible “maximum density” option. The two single-family units on North Plain are replaced with a string of four townhomes as well. In short, the density plan creates three more affordable units, for a range is 78-83 units total. The range is because the commercial space in the school may either be 6,024 SF and 83 units, or 11,372 SF and 78 units, depending on demand. In either case, there will be 55 parking spaces internally and 37 on the street.

According to the Planned Unit Development Overlay District (PUD-OD) Application, the project would create 1.5 jobs directly in property management/maintenance, and will pursue a Payment in Lieu of Taxes (PILOT) agreement for the property, which is currently tax-exempt. A similar PILOT was used with 210 Hancock. The $25.3 million project would be complete by the end of 2021 – the rest of the filing is the same as the writeup on the Voice here.

7. It might be a bit petty to point this out, but the Common Council’s Planning and Economic Development Committee (PEDC) will be looking at giving their approval to some new murals, and as everything seems to do in Ithaca, two of the three have drawn negative attention. The Dryden Garage aikido mural received complaints that it promoted violence, while the sea life mural for the Seneca garage received complaints that the eel was off-putting, creepy and not appropriate because it wasn’t a native species. For the record, the third was an electrical box with a giraffe pattern, which a couple people called boring, but otherwise no one was upset about it.

Anyway, the PEDC is used to criticism of every flavor, and in the big picture, these are small complaints. Expect them to sign off, send to council for customary approval, and then look forward to the new art later this year.

8. The Common Council is expected to adopt the Findings Statement for the Chain Works District next month, which would be a big step towards approval of the project. A Findings Statement says that the plan is designed with reasonable mitigations acceptable to the city as representatives of public stakeholders, and it isn’t project approval, but it’s essentially an okay to begin applying for approval.

As part of the development process to obtain a PUD, Chain Works will need to submit at least one phase of firm development plans, and UnChained Properties LLC intends to submit Phase 1 of redevelopment to the Planning Board within the next month. Assuming it hasn’t changed, Phase 1 consists of the redevelopment of four existing buildings. Buildings 33 and 34 would be renovated for light industrial uses, Building 21 will be modernized for commercial office space, and Building 24 becomes a mix of office space and 70-80 apartments. Given that it’s been over five years since the project first made news, it feel a bit anti-climatic at this very late stage, but let’s be optimistic that a vacant, contaminated site may be brought back to safe, productive use.

 





News Tidbits 1/21/2019

22 01 2019

1. A quick note regarding the county’s feasibility study of a new county office building on the 400 Block of North Tioga Street on the edge between Downtown and Fall Creek – Ithaca’s HOLT Architects has been tapped to perform the analyses. The idea isn’t totally new to HOLT, who had drawn up rough ideas of a joint city-county office building as part of the Downtown Ithaca Alliance’s 2020 Strategy way back at the start of the decade. This process will quietly continue until the results are ready for review and discussion sometime in March.

In an off-record conversation with a county official, the topic came up of, “why not just move to one of the office buildings in the Cornell business park”, as the county Department of Health has done. This person pointed out that it would much easier to buy a building, renovate it, move in and start operations. Except for one bring problem – the suburban office park is hardly accessible, and so the choice of county occupants would be fairly limited, given the need for the county’s less well-off to be able to access the site. A location on the fringe of Ithaca’s Downtown is much more walkable and readily approachable from buses, bikes and so forth, while a Cornell business park is really only readily accessible to those coming by car or the occasional bus. So the county is willing to walk on coals and risk the ire of nearby residents in order to maintain a more accessible facility.

2. Before it was officially announced, the rumor that INHS was selected for the Immaculate Conception School had been floating around for a few weeks. Most of the city staff and officials I’ve spoken with were actually breathing something of a relief, because most of them know and trust INHS. Or rather, they trust INHS to be one of the less divisive choices out there. They’re local, they plan to have a mix of affordable housing and office space for family services-related non-profits, and they’ll be going through an open house process that will give residents a chance to help shape the project before anything goes up to the city for review.

Two details worth noting – for one, INHS does have timeline in mind for its redevelopment (new construction and renovations) to the site. It would like to have tenant occupancy by December 2021, so they’ve got three years to go from start to finish. Expect meetings this Spring and Summer, and probably a project submission by late summer for a fall planning board review and approval by the end of the year. That will give them time to start applying for and attaining affordable housing grants, and to break ground on the redevelopment sometime in 2020.

For two, the city of Ithaca intends on buying the school gymnasium on the northeast side of the parcel. The gym would be used for indoor recreation by the Greater Ithaca Activities Center (GIAC), which is just next door. They’re looking to pay $290,000 for the parcel. It is not clear if this was planned in conjunction with INHS, if INHS developed two separate purchase plans to accommodate that possibility, or if it simply throws a wrench into things. Generally speaking, gym access and affordable housing were the two signaled prerequisites for any city consideration of a Planned Unit Development (PUD), the DIY Zoning that would give more flexibility with site redevelopment. Regardless of PUD, I suspect renovation of the school and Catholic Charities buildings are one key redevelopment feature, and on the new construction side, the parking lot on the corner of North Plain and West Court Streets isn’t long for this world.

3. Tenant number two has been confirmed for City Centre – Collegetown Bagels will be moving from its 1,500 SF location at 201 North Aurora Street, to a 2,300 SF ground-level retail space inside the 192-unit apartment building. According to Edwin Viera at the Times, “Gregor Brous, owner and operator of Collegetown Bagels, decided to make the move after finding out the current building CTB is located in is being demolished.”

For the record, that’s a couple of years out. Visum Development does have plans for the site, which involve a mixed-use apartment building with approximately 60 units above ground-level retail. A sketch plan review was conducted back in 2015, but the plan has not undergone any formal review, and it has to undergo some redesigns anyway since they had planned to buy Jagat Sharma’s parcel at 312 East Seneca Street, and consolidate it into their project. Sharma instead sold to developer Stavros Stavropoulos, who has his own plans for a six-story building. The rumor has been that any redevelopment of the site is still a year or two away, but it is a likely prospect in the medium-term.

As for CTB, the larger space will allow them to try out some new concepts, expand their drink menu, and from the sound of it, add some alcoholic beverages to their offerings. This is not the first time they’ve looked at the Trebloc site, as they had tentatively agreed to move into State Street Triangle, had the building been approved and built.

4. Just to mention the Planning Board Agenda, for the sake of brevity, here’s the link, but not much is actually being decided on this month. Wegman’s is seeking yet another two-year extension on the 15,700 SF retail building they had approved in December 2014 (long rumored as a Wegmans-owned liquor store or a homegoods store similar to Williams-Sonoma). Amici House is seeking some signage variance approval and approval of site plan changes already made. This is likely to pass since its material color and detail changes, but because this was already done without consent and they’re going back to request consent after the fact, the board may have some harsh words. Amici House attends for its 23 studios to be available for occupancy by young, formerly homeless or otherwise vulnerable individuals by February 1st. Site plan approval is also on the agenda for the Maguire Ford Lincoln renovation and expansion. New proposals are the 200-unit mixed-use Visum affordable housing duo shared on the Voice today, and the Modern Living Rentals proposal for 815 South Aurora, which as touched on the other day, is likely to be pretty sizable.

The supplemental on the Falls Park senior housing project notes that the project is intended to qualify under Ithaca’s Green Building Policy under the “Easy Path” scoring system, and perhaps a bit disappointingly, the smokestack for Ithaca Gun, once intended for incorporation into the public space, will be coming down so that the ground beneath it can be cleaned during the remediation. However, smokestack bricks will be available as mementos for those who want them.

Heading to the ZBA will be a lot subdivision to split a double lot on Homestead Road back into two lots, the Amici House signage, and Agway’s plan to rebuild a 700 SF storage shed destroyed by fire, with a new one-story 1,400 SF structure. Zoning on its waterfront site requires two floors, but the new shed is only one floor and needs a variance.

 





News Tidbits 1/19/2019

20 01 2019

Now, let’s take a look at some notable property sales over the past few weeks. To make this easy, most sales documented in this post will use a standardized format for each entry.

1. What sold and for how much? 8 and 28 Newfield Depot Road, the parcel IDs for the 188-unit Valley Manor Mobile Home Park in Newfield, for $2,300,000 on 12/19/2018.

Who was the seller? Jim Ray Homes, a local manufactured and mobile home dealer, and mobile home park operator.

Who was the buyer? Cook Properties of Rochester, a mobile home management firm with properties across upstate New York.

Anything else? Not especially. The sale was just short of the tax assessed value ($2.3 million vs. $2.369 million), and while it’s a change of ownershipp, it’s also likely a maintenance of the status quo. Still, it’s a high-dollar sale worth noting. The assessment for mobile homes and manufactured homes is a bit funky, and I think the owners only own the lots, which likely contributes to the low price per unit.

2. What sold and for how much? 232 South Geneva Street for $533,000 on 12/20/2018, and 311-13 Farm Street in Fall Creek for $700,000 on 12/20/2018. 232 South Geneva is a 5-unit apartment building in the Henry St. John neighborhood; it sold for $302k in 2013, and $200k in 2008. 311-13 Farm Street is a 3-unit apartment building that sold for $505k in 2009. It includes 15 rentable bedrooms, and a portion that was set aside as an AirBnB by the previous owners, who had it on the market for $750k (assessment $610k). Both are small multi-family examples of the rapid price appreciation Tompkins County has been seeing in walkable urban areas.

Who was the seller? Jeremy Dietz for 232 South Geneva, and S&Y Investments, a California-based LLC (sales docs indicate the owners are John Scarpulla and Allyson Yarbrough) for 311-13 Farm Street.

Who was the buyer? An LLC associated with local landlord and developer Charlie O’Connor, owner of Modern Living Rentals.

Anything else? Don’t expect teardowns here. Generally speaking, that’s not MLR’s approach to Ithaca’s inner neighborhoods. Do expect them to stay rentals, probably with a renovation in the near future (see: 1002 North Cayuga Street and 202-04 East Marshall Street). O’Connor is flush with cash after his multi-million sale of the under-construction 802 Dryden Road to a Pittsburgh-based real estate investor last fall.

3. What sold and for how much? The Sprucewood Apartments in Northeast Ithaca, for $8,640,000 on 12/21/2018.  Sprucewood is a 108-unit apartment complex completed in 1966. All units are three-bedrooms, in eighteen six-unit buildings.

Who was the seller? The Lucente family, who run Lifestyle Properties in Ithaca. They own a host of other housing developments, including the Village Solars under construction in the town of Lansing.

Who was the buyer?  Winston Square LLC, an LLC associated with Stratford Management, a multifamily housing management firm with locations in six states.

Anything else? A case of “under new management”. The Lucentes are a whole lot richer, and Stratford, which mostly owns older apartment complexes across upstate, finally gets a toehold in the stable and lucrative Ithaca market. With it comes a new website and a name change, from Sprucewood to Winston Square. The apartments are primarily located on Winston Court, and the name comes from the late Rocco Sr.’s penchant for naming streets after cigarette brands in the 1950s and 1960s, hence the nickname “Cigarette Alley” for Northeast Ithaca. I don’t imagine that will be a part of the advertising pitch.

4. What sold and for how much? 815 South Aurora Street, for $385,000. The property includes a 2,845 SF industrial building and a 2,537 SF warehouse on 1.85 acres on South Hill. A radio and telecommunication tower is on site.

Who was the seller? Harold Fish. The Fish family has owned the property since at least the 1950s.

Who was the buyer? “IC Overlook LLC”, which appears to be associated with Modern Living Rentals and its owner, Charlie O’Connor.

Anything else? With Todd Fox, O’Connor proposed an 87-unit (all studio units) apartment building for the site in 2015, and in order to move forward, the duo had to make a case for the city to change its rules for building near radio and telecommunication towers. Most communities use the height plus 10 feet; at the time, Ithaca used double the height. This is a 170-foot tower, so that meant a 340 foot radius, instead of 180 feet as seen in most communities. The logic is the height plus a bit for bounce; but planning staff mused that Ithaca was a bit paranoid when the legislation was drawn up in the 1990s. The zoning code was revised, but such that it’s height plus 20% – a 204 foot radius, so the project had to be redesigned a bit. The last that was heard, plans were being for a 125-bedroom project in December 2016, but nothing came to light.

Until now. A sketch plan is scheduled for the planning board meeting next week.

5. What sold and for how much? 327 West Seneca Street, for $235,000 on January 11th.

Who was the seller? The estate of Orson Ledger, a man who was known in his decades of Ithaca for providing affordable housing by running his properties into the ground so that assessments would be low. Folks involved with Ithaca’s rental market in decades past tend to have strong opinions about Ledger, who died in a car accident five years ago.

Who was the buyer? An LLC tied to Visum Development Group.

Anything else? It means Visum’s 12-unit workforce housing proposal approved for 327 West Seneca Street is now one step closer to happening.

6. What sold and for how much? 305 West Green Street, for $560,000 on January 17th. 305 West Green Street is the former Ithaca Plastics. The property hosts a 2,400 SF home and a 5,150 SF industrial building.

Who was the seller? Richard and Sharon Buechel of Dryden, who had owned the property since 1989.

Who was the buyer? Cascade Studios LLC, which is registered to the address of Ithaca musician Brian Thrash.

Anything else? Generally not wise to take guesses on these sort of things, but plans for a music/recording studio, perhaps?

7. Something that catches the eye – local landlord Ed Cope has been actively selling off many of his rental properties. 310 Farm Street was sold for $365,000 on 12/28 to Jonah and Alicia Freedman, as was 312 Farm Street, for $395,000 on the same day. 513 South Aurora Street was also sold on December 28th, to Andrew Schreck for $425,000. Cope sold out of his share of 324 West Seneca Street for $180,200 on January 17th, and sold out of his share of 318-20 West Seneca on the same day for $349,800. That’s in addition to the sale of 115 Linn Street for $540,000 last October. That’s six sales in four months.

Vice-versa, Cope bought 107-09 Hudson Street from the estate of Sophia Tselekis for $540,000 on January 10th. Previously, Cope purchased 115 Hudson for $495,000 in October, and 108-110 Hudson Street for $460,000 in September.

All of this is to suggest that Ed Cope has been a very busy man lately. It would look as if he’s selling off properties to finance purchases of other properties clustered on the 100 Block of Hudson Street, just south of downtown and Six Mile Creek. Cope already owns 105 Hudson Street and 201 South Aurora Street on the corner, 114 Hudson, 117 Hudson and 118-120 Hudson. That leaves three properties in that cluster of eleven that he doesn’t own – 101, 111 and 112 Hudson Street. It’s not clear if something is in the works, but it is curious.

Now onto building loan agreements:

8. Where property received the construction loan? 232-236 Dryden Road, also known as “The Lux”, a 206-bedroom pair of student-oriented apartment buildings completed in 2018.  Visum Development Group completed the project, and plans are in the works for an eight-unit, 16-bedroom third building at 238 Dryden Road.

Who gave them the money? MF1 Capital LLC. The LLC is joint venture between real estate megafirm CBRE, Limekiln Real Estate of New York and Berkshire Group of Boston. According to online reports, it’s a mortgage REIT (Real Estate Investment Trust) focused on providing cash equity to multifamily (about 75% of its business) and seniors housing (the remaining 25%). A bridge loan is a short-term (2-3 year) financial solution, used as a “bridge” when a developer needs quick cash for a prime opportunity and has yet to obtain conventional construction loans. They’re usually easier to obtain because the analysis that goes into determining whether or not to extend the loan is less extensive, usually based on property value (which means a high-value loan in the case of a large Collegetown property). The trade off on these loans is that they often come with a high interest rate; and with that short term period, the loan will have to be paid back within a few years.

What it suggests here is that Visum has put most of its revenue right back into its latest plans in the form of working capital, and that there’s high confidence both in themselves and from the investor that those plans will be successful. That seems to make the most sense given Visum’s explosive growth. On a related note, $1.5 million would be about right for a new eight-unit apartment building on this site.

 

 





News Tidbits 1/18/2019

19 01 2019

It’s been a while. Let’s start with the bad news first; projects that have been cancelled over the past month, or are on the ropes.

1. Heading over to Lansing, the Lansing Senior Cottages is dead. The project, which was developed by Beer Properties in conjunction with Hunt Engineers, had been reduced in size from the initial proposal, from 108 units to 97 units, in 84 buildings (71 single-family, 13 two-family) on about 40 acres. In order to move forward as a pocket-neighborhood housing development (houses closer together than permitted under a medium-density residential zone in the village), it would have needed a Planned Development (PDA) designation from the village of Lansing.

The Planning Board has eight criteria to establish a PDA, and felt that the project didn’t meet four of the criteria (maximum choice in ownership types and occupancy tenure, convenience in location of non-residential facilities, efficient use of land, and desirable change in environment), and was therefore insufficient to merit a PDA. Their vote to deny the PDA also killed the project, since the design isn’t possible in Lansing’s medium-density zone. The density is the legal, albeit at the maximum allowed, which in sewered areas is 20,000 SF (0.46 acres) per single-family, and 25,000 SF (0.57 acres) per two-family. But the law states they have to be on their own, non-clustered lots, with setbacks, minimum road frontage and so forth. In other words, a conventional suburban subdivision.

The site was originally approved for just such a project, the high-end, three-phase, 31-lot Millcroft development, of which only the first phase was ever platted and prepped before the Great Recession kicked in and the market for very large, very expensive homes shrank. The Bush family limited homes to 2,500 SF or greater, and with half-acre lots selling for $80,000, it was clearly geared toward high-end homes, but they lack the combination of acreage or lake views that are the usual prerequisites of Lansing’s $500k+ home sales. Well over a decade later, and the thirteen home lots still have yet to be fully built out, and interest has never been strong. Three of the four recent home sales here sold under assessment, which is a rarity in Tompkins; last year, it was less than ~6% of properties.

Meanwhile, the rest of the Millcroft land went up for sale in 2017. When the Bush family sold a purchase option to the Beers, it was taken about as well as a stick to the eye, and Millcroft Lane residents strongly opposed the 800-1,200 SF senior cottages. In theory, the remaining eighteen lots in the subdivision are still an option, or another layout could be submitted; but a developer is not legally obligated to build houses as big or expensive as the first phase if the Bush family agrees to remove the covenants, which the Beer cottages proposal shows they very are open to.

As for the Beers, it’s a shame the plan won’t move forward, as senior rentals (and senior for-sale, more crucially) are an underserved market in Tompkins County. Potentially, other locations in Lansing or elsewhere might be suitable and more open to cluster-style senior cottages, but after sinking tens of thousands into this proposal, the Beers are unlikely to submit something else in the near future.

2. A little further north in the town of Lansing, a pair of projects are struggling. The 102-unit Cayuga Orchard Apartments project is up for sale from WB Property Group of New York City, as is a 28-lot subdivision, Cayuga Way, which was intended for high-end homes. Cayuga Orchard is asking $3.1 million for the 30.5 acres and plans, though the seller has stated interest in a Joint Venture partnership if a potential buyer is interested and willing to negotiate. The ad briefly states:

“30.5 acres, now approved for 102 units, approved to tap into municipal sewer. Open to JV or to sell outright Located in prestigious town of lansing, best in class schools, 15 min from Cornell University Extremely long approval process for multifamily.”

To be fair, the town of Lansing is one of the easier municipal approval processes in Tompkins County, though an uncertain and red-tape-filled process has been cited as both a barrier to affordable housing and housing development within the county.

The Cayuga Way ad, also from WB Property Group, is for either all 28 lots or by the lot:

“All approved for 28 lot subdivision, roads/improvements are in. Best piece of land remaining in the prestigious Lansing area on “the hill.” All wooded lots. 15 minutes from Cornell University, Downtown Ithaca, and Ithaca and Lansing High Schools.”

Price on request, also called price on application (POA) can be done for several reasons – market fluctuations, a fear of influencing other properties if higher or lower than expected, and more questionably, a chance to size up buyers to see how much they can afford. Presumably, a buyer seeking 1500 SF homes here wouldn’t want to pay as much as someone thinking 3000 SF. Joint ventures are also being considered for this project.

For a town hoping to develop its way out of the continued decrease and likely loss of what was once its largest taxpayer, this isn’t good news. But we’ll see if a partner or buyer comes along.

3. This one was a bit surprising. The Dryden town Zoning Board of Appeals shot down a 3-lot subdivision at 1932 Slaterville Road. The plan was for Habitat for Humanity to buy the property, create two more lots and renovate the existing dilapidated 150 year-old farm house, all three of which would have been sold to qualified low-income families who put in the “sweat equity” to help build and renovate.The variance was needed for a flag lot, because with the land acquisition and renovation costs, the project only penned out financially with two more lots.

On paper, that actually seems like a slam dunk. I thought it would be smooth sailing after Dryden’s Planning Board, which is advisory but tends to be less pro-development than Dryden’s other board, had recommended the variance be approved; in fact, David Weinstein, one of the planning board’s most stringent members, was very supportive, citing the desperate need for affordable housing and feeling its 1-acre per lot density was appropriate for the area. But then the Zoning Board of Appeals runs out with this:

It’s like they’re talking about two totally different proposals. I’d also like to point out that describing affordable owner-occupied housing as “there would be an undesirable change of the neighborhood, which is not in the character of the neighborhood, and could possibly have detriment to the neighborhood” is a really tasteless and poor choice of words.

With the denial of the variance, the project is dead. That’s unfortunate for Habitat, who due to logistical difficulties had to cancel their previous project for four townhomes at 402 South Cayuga Street. As for the $40,000 they were due to receive from the joint Cornell-city-count Community Housing Development Fund, it will go unused.

 

4. Emmy’s Organics is not moving forward with their Cherry Street project. The plan ran into trouble when initial geotechnical studies found that the soils may be in such poor shape on the site that they’re unable to reasonably support the concrete slab for a single-story industrial building, and not even stable enough to support a parking lot. The IURA hired a second geotechnical engineering firm (John P. Stopen Engineering) for $5,000, which found that it would be possible to build, but only if the top three feet of soil were removed, which would raise the project cost. The IURA was willing to consider a larger loan, but Emmy’s decided the project, which was on a tight timeline, was simply no longer feasible. The owners are now looking to build elsewhere, so not only is the $1.4 million project and its 5-10 new jobs are lost, it’s not clear where the firm will move and what’s going to happen with their existing 19 mostly living-wage jobs. It also puts the IURA in a spot because the undeveloped remainder of Cherry Street just became a lot less desirable for smaller light industrial projects like this one.

The project was to use $175,000 in NYS-administered Community Block Development Grant Funds (CDGF) for job creation for low and moderate-income households. These funds have to be allocated by the city by March 31st, or they have to be returned to the state. In a rush to use them before they lose them, the IURA is proposed to shift $49,000 towards lighting improvements in Titus Park, and $126,000 towards $290,000 in acquisition costs to buy the 9,100 SF Immaculate Conception gymnasium from the Catholic Diocese, for use in indoor recreation and presumably as part of the sale of the rest of the property to INHS. The IURA is not totally sure if either use qualifies for the funds, but they’re in a rush to find alternatives before the state takes the money back.





News Tidbits 12/9/18

9 12 2018

1. Let’s start out in Lansing. Milton Meadows if officially underway. The 72-unit apartment complex, the first development to get off the ground at the Lansing Town Center site off Route 34B, will be targeted at the 50% – 80% area median income range (~31k-~48k for a single person household) and give priority to income-qualified veterans.

The plan is to roll out the $17.1 million project in stages as the buildings are completed next year. Nine of the structures will be apartment buildings ranging from 6,600-10,200 square feet (SF), with 8 apartment units apiece. The buildings are designed so that all the units in a structure are the same size range, so all one-bedroom buildings (4), all two-bedroom buildings (3), and all three-bedroom buildings (2). The last building would be a 3,100 SF community center. Also included are 139 parking spaces, a community garden, sidewalks, playground, and stormwater management facilities. The project will be built to LEED Silver energy standards.

Funding comes from a variety of state and local sources, the largest single grant being $5.1 million courtesy of New York State. The first units should be ready by late spring, and the last units will come online next fall.

2. In the next round of county/city/Cornell affordable Housing Development Fund recommendations, breakdown above. Habitat gets some funds towards one of its home builds and to buy two other sites, INHS gets additional funds towards their citywide renovation project, and Visum’s 327 West Seneca Street gets $200,000 (this project was carried over from the last round, because they wanted to make sure Visum knew what it was doing). Perhaps the most interesting component here is the NRP Ithaca Townhomes project on West Hill near Cayuga Medical Center, which has received approval, but with a lack of high-value state funds, it has languished in post-approval funding hell. The original breakdown was 66 units in phase one and 39 in phase two, so the 69 here suggests something was modified a little bit.

Unit sizes will range from $850/month, 745 square-foot 1-bedroom units to $1500/month, 1,344 square-foot 3-bedroom units, with most units being two or three bedrooms. The infrastructure improvements (streets, lighting) will be privately built and maintained by the developer. Seven units (2 1-BR, 3 2-BR, 2 3-BR) will be set aside for the mobility impaired, three units for those with hearing or vision impairment (1 1-BR, 1 2-BR, 1 3-BR), and three units for those with special needs (1 1-BR, 1 2-BR, 1 3-BR), defined in this case as recovering victims of domestic violence situations.

The original plan was to start construction last spring, and frankly, the project probably still needs a sizable state grant before funding can go ahead. But with this funding, it’s another piece of the puzzle. If it has some dedicated funds already, and the state doesn’t have to fork over as much, then the state is more inclined to support the project because on its end, it gets more bang for the buck. So keep your fingers crossed.

3. The rumor mill says that Vecino is falling for Ithaca like a teenage girl for a boy band crush. The multi-state firm specializes in two types of housing – affordable housing (under names like Asteri, Mosaic, Libertad and Intrada) and student housing (Muse), which makes Ithaca a good fit. Rather conveniently, Vecino projects identify segments of their target market in the building name. Asteris, like the one proposed for the Green Street Garage in Ithaca, provide not just affordable housing, but several specialized units for those with developmental disabilities. Intradas, like the 157-unit Intrada going up in Saratoga Springs, provide affordable housing with a handful of units set aside for youth aging out of foster care. So, kinda just a neat little quirk there.

Arthaus, as one might guess, is the artist-focused affordable housing – the only other one I’m aware is in a converted warehouse in Troy (which all my Albany colleagues call ‘hipster central’ or ‘Williamsburg North’, the downtown far removed from its days as ‘Troilet’). The sort of tough part to make clear is that this is not limited to artists. It just has amenities geared towards creative types, like a woodshop and storage space and gallery space run by an outside non-profit. Of course, the Voice commenters hated this with a passion because artists = leftists liberal dirty hippie types = evil incarnate. I’ve learned that the softer reactions tend to be with affordable senior and affordable veterans housing, which I cynically suspect is because the most vocal complainers tend to be more politically conservative in their views, and seniors and vets tend to be more politically conservative than the general population – so rather than engaging in circular fire, some, but definitely not all, will hold their tongue.

But, while the commenters didn’t like it, the city planning board did. It’s 120 units (40 studio, 60 1-bedroom, 20 2-bedroom) of affordable housing (50-80% are median income, just like Milton Meadows in item 1), which is a hefty amount and critically needed. A number of units will be set aside for specialized needs and administered by Tompkins Community Action, which will be offered office space in the building. The project is also seeking to get arts groups involved in the design. The city was looking to start off on the right foot with the upzoned waterfront, and this is exactly the kind of creative, affordable project they were hoping for.

4. My only regret is that because the working title of 116 Catherine was 114 Catherine, readers will be confused for years to come. Jagat Sharma designed a tasteful three-story infill building in Collegetown to the rear of 116 Catherine and the Mission Apartments – these would join the rest of the Lambrou properties that comprise Eddygate Park. Also like 116 Catherine, it’s three units – two six-bedroom units, one five-bedroom unit, about as student-oriented as a project can be. Still, infill is much more preferable to a parking lot in Collegetown. Every bit of housing helps, and it’s a couple million dollars of assessed property to help fill local coffers. If the Lambrous choose to pursue this one, which is smaller than what the CR-4 zoning allows and is tucked away from the street, the planning board is unlikely to give them much trouble.

As for the Sharma-designed building that would potentially built in the foreground of this project, 301B Eddy, the last I heard was that it was not an active pursuit, if not totally off the table.

5. Here we have a do and a don’t. Do: hire a seasoned architect like Jagat Sharma, who knows his way around city staff and boards. Don’t: design anything without checking to see if the rules and regulations changed. In this case, they did, quite a bit.

The problem here with 312 East Seneca Street isn’t the development plan, which calls for ground-floor retail and studios and 2-bedroom apartments on the floors above. That’s all fine and dandy. But the city has really been focused on increasing the quality of building designs submitted for review in Ithaca, and that was codified into the Downtown Ithaca Design Guidelines, which were enacted as law earlier this year. If this were 2013, Sharma and developer Stavros Stavropoulos would probably be okay. As of now, they are not. The only part of this design that’s acceptable is the first three feet facing East Seneca Street. The exposed CMU walls on the sides? Not allowed. And according to the Times’ Matt Butler, the planning director seemed a bit insulted by the design.

Potential design options that would be compatible include additional interior facade visual elements, facade articulation and alternative side materials (brick, stone, metal panel, fiber cement, and for the sides only, synthetic stucco/EIFS) and possibly a step down in height at the rear, since the site is on the edge of its zoning.

Consider for comparison, the new Tompkins Financial building. It’s an interior block site, and while it builds very close to the boundary line and they have (and could have) bigger neighbors, the sides and rear have windows, facade variation and articulation, brick and metal panels, and design elements like sunshades and a small top floor setback. That’s very much in the mindset of what the city is looking for in the design of a downtown project. In any case, if the Stavropoli want to do something here, the sketch plan design will need to be substantially modified before there’s any hope of approval, and some meetings with city staff couldn’t hurt.

6. There have been some potential issues that have sprung up with the Emmy’s Organics project at the end of Cherry Street. The soils may be in such poor shape on the site that they’re unable to reasonably support the concrete slab for a single-story industrial building. If that’s the case, the project may not move forward, which may also result in Emmy’s moving itself and its jobs out of the city. The IURA will vote on Thursday to authorize $5,000 to hire an engineering firm to do an analysis of the geotechnical reports to see what special requirements a foundation would need, and if those requirements make the project infeasible.

7. Quick little note here – Lansing Meadows was delayed this past summer because developer Eric Goetzmann “was not able to secure contractors – too much other construction going on”, according to an email from TCAD’s Heather McDaniel. With TCAD and the village blessing, the construction start has been pushed back to Spring 2019.

8. It’s been a while since 46 South Street (formerly Hamilton Square) has updated their website, but to wrap up this post, here’s some good news for affordable housing advocates – the 73-unit, mixed-income, mixed rental and for-sale proposal by Claudia Brenner and Ithaca Neighborhood Housing Services (INHS) has passed the Trumansburg planning board’s SEQR (State Environmental Quality Review). That means that the environmental impacts are effectively mitigated by the project team. Site plan approval has yet to be issued, and is likely to be hotly debated with neighbors who have been opposed to the project since the proposal was introduced in May 2017. Review began about a year ago, and likely has a few months more yet ahead of it – certainly one of the longer review processes as of late.

On a happier note, color renderings! Nice variation in materials and style. For those so inclined, the 2 hour audio from the planning board can be found on the village website here.





News Tidbits 11/26/18

27 11 2018

Just to get this out in time, he’s a look at what will be a rather long but very interesting city of Ithaca Planning Board meeting tomorrow evening.

1 Agenda Review 6:00

2 Special Order of Business – Planning Report on ILPC recommendation to designate the former Delaware, Lackawanna, & Western Railroad Station at 701 West Seneca Street. 6:05

3 Privilege of the Floor 6:20

4 Approval of Minutes: October 23, 2018 6:35

5 Site Plan Review

A. Project: Chain Works District Redevelopment Plan (FGEIS) 6:40
Location: 620 S. Aurora St.
Applicant: Jamie Gensel for David Lubin of Unchained Properties
Actions: Distribution of FGEIS & Review of Schedule – No Action
Project Description: The proposed Chain Works District seeks to redevelop and rehabilitate the +/-800,000 sf former Morse Chain/Emerson Power Transmission facility, located on a 95-acre parcel traversing the City and Town of Ithaca’s municipal boundary. The applicant has applied for a Planned Unit Development (PUD) for development of a mixed-use district, which includes residential, commercial, office, and manufacturing. The site’s redevelopment would bridge South Hill and Downtown Ithaca, the Town and the City of Ithaca, by providing multiple intermodal access routes including a highly-desired trail connection. The project will be completed in multiple phases over a period of several years with the initial phases involving the redevelopment of the existing structures. Current redevelopment of this property will focus on retrofitting existing buildings and infrastructure for new uses. Using the existing structures, residential, commercial, studio workspaces, and office development are proposed to be predominantly within the City of Ithaca, while manufacturing will be within both the Town and City of Ithaca.

No decisions expected tonight, but the distribution of the FGEIS (Final Generic Environmental Impact Statement) is a major step forward. From here, the Planning Board will review and critique the document, and when satisfied, it will vote for a resolution of completion. A recommendation to adopt the Chainworks PUD zoning and the FGEIS findings will follow, and if successful, the Common Council will also vote to adopt the PUD zoning. That would complete generic review for the site – new builds would still come to the board as necessary, but renovations could potentially begin not long afterward. Timing-wise, the final approvals are still a few months out, but this massive 910+ unit project is slowly closing in on approvals, and potentially, construction.

B. Project: North Campus Residential Expansion (NCRE) 6:55
Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Review of FEAF Part 3
Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). All NCRE materials are available for download at: http://www.cityofithaca.org/DocumentCenter/Index/811

Materials provided indicate that city planning staff are reasonably satisfied that the energy impacts of the massive North Campus housing plan have been mitigated. The only new letter on record this month is a letter of concern from the City Historic Preservation Planner about the project’s visual and aesthetic impacts on the Cornell Heights Historic District to the west.

C. Project: Apartments (12 Units) 7:25
Location: 327 W. Seneca Street
Applicant: Noah Demarest for Visum Development
Actions: Consideration of Preliminary & Final Site Plan Approval
Project Description: The applicant is proposing to construct a three-story apartment building with 12 units. Project development requires the removal of the exiting building and parking area. The project will include exterior bike storage, a trash enclosure, walkways, landscaping, signage, and lighting. The project is in the B2-d Zoning District and has received the required variances for front-, side-, and rear-yard setbacks. A small portion at the rear of the property is in the CDB-60 District. The project has received Design Review. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”), for which the Lead Agency made a Negative Determination of Environmental Significance on September 25, 2018.

Not much to add regarding Visum’s workforce housing (80% area median income) proposal for the State Street Corridor. The project is expected to receive $200,000 from the latest round of the Community Housing Development Fund, the affordable housing fund jointly paid into by the city, county and Cornell. In this case, Cornell will cover $170,000 and the city $30,000. Cornell doesn’t have any hand in this project, but having one entity pay most of the grant for a given project makes it less complex to administer. 

D. Project: Falls Park Apartments (74 Units) 7:35
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Public Hearing, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11).

Note that IFR is a Travis Hyde Properties business entity. The attempt to gain approval for an environmentally compromised project site is likely going to be more heavily scrutinized given the recent controversy regarding proposed demolition procedures for the Old Library site.

E. Project: New Two-Family Dwellings 7:55
Location: 815-817 N Aurora
Applicant: Stavros Stavropoulos
Actions: Declaration of Lead Agency, Review of SEAF Parts 2 & 3
Project Description: The applicant proposes to demolish an existing two-family residential structure and construct two new 1,290 SF two-family dwellings on a 9,590 SF lot. The existing residential building is a legally nonconforming building with a side setback deficiency (2.9 feet instead of the required 5 feet). The proposed redevelopment will include four parking spaces for four three-bedroom apartments. The applicant is requesting the Board’s approval to use the landscaping compliance method for parking arrangement. The project site is located in the R-2b Zoning District and meets all applicable zoning lot and setback requirements. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”).

F. Project: Maguire Lincoln 8:15
Location: 370 Elmira Road
Applicant: John Snyder Architects PLLC
Actions: Declaration of Lead Agency, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to demolish a portion of the existing building and construct two additions with updated exterior materials. The existing building is 18,500 GSF, with 2,265 GSF proposed for demolition. The new building will be 24,110 GSF. Site improvements include incorporation of a new pedestrian walking path, and site connections to Wegmans. Approximately 311 parking spaces are proposed to accommodate customer, service parking, employee, and display parking. Landscape design will improve vegetative cover; however, it will not meet the City of Ithaca’s impervious/pervious requirements (12%). The project site is located in the SW-2 Zone, is subject to the 2000 Southwest Design Guidelines, and will require a zoning variance for a front yard that exceeds the maximum permissible in the SW-2 district (34 feet maximum permitted, 69-feet 3-inch setback proposed). This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”); however, it will be treated as a Type I Action for the purpose of environmental review.

G. Sketch Plan – 312 E Seneca Street, Jagat Sharma 8:35

312 East Seneca is a 4,482 SF three-story mixed-use building on the edge of Downtown Ithaca. The building was long-owned by Ithaca architect Jagat Sharma, who ran his practice from the building (1416 SF), the Alley Cat Cafe (1926 SF), and a four-bedroom apartment (1140 SF) on the upper floors.

A few years ago, the site was floated as part of the potential footprint for Visum Development’s Seneca Flats mixed-use project, though at the time it was made clear that it was not an essential property to the development, and simply a possibility if Sharma chose to sell to Visum. Sharma didn’t – in September, he sold the building to an LLC associated with the Stavropoulos family for $800,000, double the assessed value. That lofty price relative to assessed value was a big clue something was planned here, and it looks like the first glimpse of that will come tomorrow night. The Stavropoli of West Hill have been growing their assets through acquisition or development for the past several years, including the 4-unit North Aurora project in item E. above.

Normally, the Stavropoulos family is low-key about development, preferring lower-profile infill builds in established neighborhoods – the largest project of theirs to date is the 11-unit 107 South Albany project. They often turn to local architect Daniel Hirtler, but this time, Collegetown favorite Jagat Sharma will have a hand in redeveloping the building that housed his office for so many years. This would be Sharma’s first building downtown since the Greenstate Building (127 West State Street) in 1991. For the record, this would be their second Sharma commission, with a duplex planned for 209 Hudson Street being the other (granted, that’s also a modular structure).

Zoning-wise, this is CBD-60. Within that zone, Sharma can design a five-story building up to 60 feet tall, no parking required, with any variety of commercial or residential uses. Any design will have to conform with the recently-adopted Downtown Design Guidelines. The Stavropoli are likely to do all-residential or residential with ground-floor retail. The current building is quite narrow, but it also only occupied the east half of the lot – a new structure could practically touch the neighboring building at 308 East Seneca.

H. Sketch Plan – 114 Catherine Street, Jagat Sharma 8:55

Things are about to get a bit confusing. A few years ago, the Lambrou family, mid-sized Collegetown landlords and developers of Collegetown Park, presented and built an infill project at 114 Catherine Street – while all the working docs used 114 Catherine Street, the address of the existing building set back into the lot, the new 3-unit, 17-bedroom building was christened 116 Catherine Street.

This new building is expected to be a replacement for the existing 114 Catherine Street, the Mission Apartments, and is expected to complement 116 Catherine in appearance (Jagat Sharma designed that as well). Zoning here is CR-4, up to four floors, with a maximum of 50% lot coverage (but not parking required). Expect this to be student housing – probably not too big, a few dozen beds at most, but something to take note of nevertheless.

I. Sketch Plan – 130 Cherry Street, Residential, Vecino Group 9:15

130 Cherry Street is a 4,600 SF auto body shop that’s been for sale for quite a while now. The rumor mill says Vecino CEO Rick Manzardo was walking around the area a couple of weeks ago, and it looks like there was a reason for that. The plan being floated is affordable “artist housing”. This wouldn’t be a new concept to Vecino, who renovated a vacant warehouse in Troy into the 80-unit Hudson Arthaus. What makes the Arthaus unique among affordable housing is that it offers on-site amenities geared to artists, as well as income-based rents for those who make only a modest living while engaged in their creative pursuits.  Those amenities include a wood shop, on-site storage units, gallery spaces managed by a local non-profit, and a computer/digital work suite.

Zoning here is “Cherry Street District” Waterfront Zoning. Since it’s north of Cecil Malone Drive, housing is allowed – but not on the first floor. The first floor is for light industrial and many commercial uses, including restaurants, stores and offices. No ground-level storage permitted, however. In this “artist housing” format, the first floor would likely be the exhibition/gallery.workshop space. The building may be up to five floors with 100% lot coverage once setback requirements are met. Bonus for this site, the Cherry Artspace is a few hundred feet away. With about 179,000 SF in building capacity offered by the site and zoning before setbacks are considered, a potential project could be fairly sizable.

6. Old/New Business 9:35

7. Reports 9:40
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development

8. Adjournment 10:00





Amici House Construction Update, 11/2018

26 11 2018

Apart from some exterior landscaping, finish work and last-minute tidying up, it looks like the residential portion of TCAction’s new Amici House complex is nearly ready for occupancy. It’s not clear if the fiber cement boards are to be painted, and I’m wondering if the interior layout was changed post-approval, since the window arrangement doesn’t match that seen in the renderings, and there appears to be another bump-out (mechanical penthouse, most likely) on the roof that wasn’t present in the renderings either.

With the exception of some information about the Head Start program, there doesn’t appear to be much online regarding the Amici House facility or its housing. The 23 studios for vulnerable / formerly homeless young adults (18-25) are expected to be ready for occupancy by late winter.

General information and development history bout the project can be found here.





News Tidbits 10/20/18

20 10 2018


1. So here’s an intriguing update to the stalled redevelopment at 413-415 West Seneca Street. Ithaca Neighborhood Housing Services was preparing to buy the former Ithaca Glass property and its development plans, which had hit a major snag due to structural issues with the existing building, and continued financial issues with pursuing of a completely new build (bottom). INHS was planning on purchasing the site and going with the original plan, which would have added four units to the existing two apartments and vacant commercial space. But someone outbid them for the site. The buyer, who has not finalized the purchase, may elect to use either of the plans designed by STREAM Collaborative, or pursue a different project at the site.

While that plan may have fallen through, it looks like the INHS Scattered Site 2 rehab/redevelopment plan will be moving forward following approval of amendments to the funding plan by the IURA and Common Council. The revised plan will dedicate funds toward the replacement of fourteen units (four vacant due to structural issues) in three buildings to be replaced with a new thirteen-unit apartment building at 203-208 Elm Street on West Hill, and major rehabiliation of four other structures (sixteen units) in Southside and the State Street Corridor.

2. Speaking of sales, here’s something to keep an eye on – the Lower family, longtime Collegetown landlords, sold a pair of prime parcels on October 4th. 216-224 Dryden Road was sold for $2.8 million, and 301 Bryant Avenue was sold for $1.4 million. Both properties were sold to LLCs whose registration address was a P.O. Box. A couple of local development firms like to use P.O. Boxes, but with nothing concrete, it’s uncertain who’s behind the purchases.

301 Bryant Avenue has some historic significance as the formal home of the Cornell Cosmopolitan Club. Founded in 1904 as a men’s organization to provide camaraderie and support for international students attending the university, the 13,204 SF, 35-bedroom structure was built in 1911 and served as the equivalent of a fraternity’s chapter house, providing a shared roof, shared meals, social events, lectures by students and faculty about other lands and cultures, and professional networking for students arriving from abroad. A women’s club was organized in 1921. As Cornell grew and different international groups founded their own organizations, the club’s purpose was superseded, and shut down in 1958. The building was purchased by the parishioners of St Catherine’s a parish center before the new one was built in the 1960s, and served as a dorm for the Cascadilla School before Bill Lower bought the building in 1973. Lower converted the structure into a six-unit apartment building, with the largest nit being eight bedrooms. With an estimated property assessment of $1.27 million, the sale appears to be for fair value – no issues, and no indications of redevelopment.

216-224 Dryden Road is much more interesting from a development perspective. 11,600 SF in three buildings (county data suggests either 14 units, or 9 units and 20 single occupancy rooms), the earliest buildings in the assemblage date from the early 1900s, but with heavy modifications and additions to accommodate student renter growth. Bill Lower bought the property way back in 1968. The properties are only assessed at $1.87 million, well below the sale price. That suggests that a buyer may be looking at redevelopment of the site. The site is in highly desirable inner Collegetown, and the zoning is certainly amenable; CR-4 zoning allows 50% lot coverage and four floors with no parking required. CR-4 offers a lot of flexibility – 119-125 College Avenue and the Lux are recent CR-4 projects.

3. The other recent set of big purchases also occurred on October 4th. “325 WEST SENECA ASSOCIATES LLC” bought 111 North Plain Street, 325 West Seneca Street, 325.5 West Seneca St (rear building of 325) and 329-31 West Seneca Street for $1.375 million. 325 West Seneca is a three-unit apartment house assessed at $200k, 325.5 West Seneca is a modest bungalow carriage house assessed at $100k, 329-331 West Seneca is a two-family home assessed at $360k, and 111 North Plain Street in a neight-unit apartment building assessed at $475k. Added up, one gets $1.135 million, which suggests the purchase price was reasonable.

Given that 327 West Seneca is currently the subject of a moderate-income redevelopment proposal from Visum, one would expect Visum to likely be behind these purchases, right? But the LLC traces back to the headquarters of a rival real estate development firm, Travis Hyde Properties. The whole thing strikes me as a little odd, but who knows, maybe Frost Travis bought the properties as stable assets rather than development sites.

4. Let’s stick with Travis Hyde Properties for a moment – here are the submissions related to his Falls Park Apartments proposal. Readers might recall this is the plan for 74 high-end senior apartments on the former Ithaca Gun site. Drawings here, 138-page submission package courtesy of TWMLA’s Kim Michaels here. Trowbridge Wolf Michaels Landscape Architecture will handle the landscape design, and newcomers WDG Architecture of Washington D.C. are designing the building.

No cost estimate has been released for the project, but buildout is expected to take 20 months. 150 construction jobs will be created during buildout, and the finished building will create four permanent jobs. The project will utilize New York State Brownfield Cleanup Program (NYS BCP) tax credits. In the case of this project, the credits would be a smaller credit to help cover the costs of site remediation insurance, and a larger credit awarded by the state that would cover 10-20% of the project’s property value, depending on whether it meets certain thresholds. It is still not clear at this point if a CIITAP tax abatement will be pursued.

The 74 units break down as follows: 33 two-bedroom units (1245 SF), 9 one-bedroom units with dens (1090 SF), and 32 one-bedroom units (908 SF). All units include full-size kitchens, wood and/or natural stone finishes, and about half will have balconies. Also included in the 133,000 SF building is 7,440 of amenity space, and there will be 85 parking spaces, 20 surface and 65 in the ground-level garage.

A number of green features are included in the project, such as LED lighting, low-water plumbing fixtures, and a sophisticated Daikin AURORA VRV high-efficency HVAC system, which uses air-source heat pumps. It look like there is some natural gas involved, however, for heating the rooftop ventilation units, and in the amenity space’s fireplace.

Due to soil contamination issues, the plan is essentially to dig up the soil and cart it off to the landfill in Seneca County. The soil runs up to 11.5 feet deep, and the building foundation will be 15 feet below current surface level (about 85% of the foundation will be a shallow slab, with deeper piles near the northeast corner). As a result, some of the bedrock will be removed and disposed of as well. What soil does remain on-site will be sealed in a NYSDEC-approved cap. Concerns about VOCs in the groundwater are somewhat mitigated by the geology of the site (horizontal fractures carry the VOCs downhill), but the ground level is a ventilated garage in part to prevent sustained exposure to vapor intrusion. The project will be presented at this month’s Planning Board meeting, where the board is expected to declare itself lead agency for environmental and site plan review of the proposal.

https://platform.twitter.com/widgets.js

5. So, one of the reasons why the Voice writeup on the Carpenter Park site didn’t include building renders was because in a follow-up phone call for hashing out the emailing of PDF images, Scott Whitham of Whitham Planning was adamant they not be used, describing them as highly conceptual. He didn’t even want to pass them along out of fear they’d mislead the general public. For the merely curious, here are images taken by Second Ward Councilman Ducson Nguyen.

The architecture firm that’s involved with the project is a newcomer to the Ithaca area – Barton Partners, which has a lot of rather high-end, traditional-looking design work scattered throughout the Northeast, as well as a new more modern designs similar to the placeholders. Can’t make any hard conclusions at this point, but a look through their portfolio gives an idea of what one might expect to see with the Carpenter Park redevelopment.

6. The former Wharton movie studio at Stewart Park is slated to become a gallery and visitor’s center, thanks to a $450,000 state grant. The building, which was the studio’s main office from 1914 to 1920, and is currently used by the city Board of Public Works, will be renovated into the Wharton Museum, with exhibit space, a public meeting room, and a terrace / seating area overlooking the lake. The project will be a joint effort by the Wharton Studio Museum and Friends of Stewart Park, with assistance from the City of Ithaca. Todd Zwigard Architects of Skaneateles (Skinny-atlas) will be in charge of designing the new museum space. It will be fairly modest in size, about 1,000 square feet, with the rest remaining for BPW use; the public works division will compensate the loss of space with an addition onto its annex nearby.

The project should dovetail nicely with a couple of other local nonprofit projects underway – the revitalization and expansion of the Stewart Park playground will give younger visitors something to do while their parents or grandparents check out the museum, and there’s potential to work with The Tompkins Center for History and Culture on joint projects that encourage visitors to pay a visit to both Downtown and the lakefront.

7. The Old Library redevelopment is once again the subject of controversy. Due to structural issues with the roof and concerns about it collapsing onto workers during asbestos abatement, the city condemned the building, which changed Travis Hyde Properties plans from sealing the building in a bubble and removing the asbestos before demolition, to tearing it down without removing asbestos from the interior first. Much of the asbestos from its late 1960s construction was removed as part of renovations in 1984, with more in the 1990s, but in areas that weren’t easily accessible, it was left in place.

The new removal plan has led to significant pushback, led by local environmental activist Walter Hang. A petition floating around demands that the city un-condemn the building and then forces Travis Hyde to renovate the building enough to stabilize the roof to remove the asbestos.

While the concern about the asbestos is merited, there are a couple of problems with this plan. It boils down to the fact that New York State code, rather than the city, defines what a developer can and can’t do with asbestos abatement. The two options here are stabilization and removal before demolition of the above-ground structure, or tearing it down piece by piece and using procedures like misting to keep the asbestos from getting airborne, with monitors in place to ensure no fibers are entering the air. The city can’t force a developer to choose one approach over another, if a building is condemned, and the city can’t force Travis Hyde to renovate the building to a state where it wouldn’t be condemned. That would be the NYS Department of Labor’s role. But if the city rescinded its condemnation, a roof renovation would involve removing the existing roof – a procedure that involves misting the on-site asbestos to keep it from getting airborne. With workers going in an out of the building to stabilize the structure and being put at risk by the unstable roof as well as the asbestos, the Department of Labor isn’t going to sign off on anything putting crewmen at risk of a roof collapse.

There is some consternation with this, and that’s fair. The development project did take several months longer to move forward than first anticipated, though had it started on time it’s not clear if the city and THP wouldn’t have been in this position anyway if work had started sooner. Demolition is expected to start within thirty days of the permit being issued (and it has, so in effect, any day now), and take six to eight weeks to complete.

8. Unfortunately, I had to miss this year’s architects’ gallery night, which is a shame because the local firms like to sneak in yet-unannounced plans. Case in point, this photo from Whitham Planning and Design’s facebook page clearly shows something is planned at the site of the Grayhaven Motel at 657 Elmira Road. The Grayhaven has four on-site structures, and the two westernmost buildings look as they do now…but the footprints of the two eastern buildings, where one first pulls in, do not match their current configuration. Intriguing, but also frustrating. The boards on the floor are related to the Visum Green Street proposal, and the other wall board is a North Campus proposal that didn’t make the cut, previously discussed on the blog here.

9. Out in the towns, there’s not a whole lot being reviewed as of late. The town of Lansing will have a look next week at marina renovations, a one lot subdivision, and a 4,250 SF (50’x85′) expansion of a manufacturer, MPL Inc., a circuit board assembler at 41 Dutch Mill Road. The expansion of their 14,250 SF building will create five jobs or less, per site plan review documents.

In Dryden town, the town board continued to review the proposed veterinary office in the former Phoneix Books barn at 1610 Dryden Road, and they’ll had a look at a cell phone tower planned near TC3. Danby’s Planning Board looked at an accessory dwelling application and a two-lot subdivision last week. Ulysses had a look at a proposal for a 6,400 SF pre-school and nursery building planned for 1966 Trumansburg Road, a bit north of Jacksonville hamlet.

The village of Cayuga Heights Planning Board has a single-family home proposal to look at 1012 Triphammer Road, and in the village of Lansing, the Planning Board and Board of Trustees will review and weigh consideration of a PDA that would allow the Beer family’s proposal for multiple pocket neighborhoods of senior cottages to move forward on 40 acres between Millcroft Way and Craft Road. Trumansburg is still looking at the 46 South Street proposal from INHS and Claudia Brenner.

10. Last but not least, the city of Ithaca Planning Board’s agenda for next week. Apart from the long-brewing Carpenter project, there’s nothing else that’s new, continuing the relative lull in new projects. Cornell’s North Campus Expansion continues its public hearing, and the new warehouse and HQ for Emmy’s Organics looks ready to obtain final site plan approval.

1 Agenda Review 6:00
2 Privilege of the Floor 6:05
3 Approval of Minutes: September 25, 2018 6:15
4 Subdivision Review

A. Project: Minor Subdivision 6:20
Location: 111 Clinton St Tax Parcel # 80.-11-11
Applicant: Lynn Truame for Ithaca Neighborhood Housing Services
Actions: Consideration of Preliminary & Final Subdivision Approval

Project Description: The applicant is proposing to subdivide the 1.71 acre property onto two parcels: Parcel A measuring 1.6 acres (69,848 SF) with 299 feet of frontage on S Geneva St and 173 feet on W Clinton St and containing two existing buildings, parking and other site features; and Parcel B measuring .1 acres (4,480 SF) with and 75 feet of frontage on W Clinton St and containing one multi-family building. The property is in the P-1 Zoning District which has the following minimum requirements: 3,000 SF lot size, 30 feet of street frontage, 25-foor front yard, and 10-foot side yards. The project requires an area variance of the existing deficient front yard on the proposed Parcel B. The project is in the Henry St John Historic District. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”), and is subject to environmental review.

The story behind this is that for legal purposes, INHS needs to split an existing house from its multi-building lot before it can proceed with renovating it as part of the Scatter Site Housing renovation project. No new construction is planned.

B. Project: Major Subdivision (4 Lots) 6:30
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Nels Bohn for the Ithaca Urban Renewal Agency (IURA)
Actions: Consideration of Preliminary Subdivision Approval

Project Description: The IURA is proposing to subdivide the 6-acre parcel into four lots. Lot 1 will measure 1.012 acres, Lot 2 will measure 1.023 acres, Lot 3 will measure 2.601 acres, and Lot 4 will measure .619 acres. Lot 3 will be sold to Emmy’s Organics (see below), Lot 4 will be left undeveloped for future trail use, and Lots 1 & 2 will be marketed and sold for future development. This subdivision is part of a larger development project that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

The Emmy’s Organics project is really two components – one, the new building in the city-owned Cherry Industrial Park, and two, the city’s (IURA’s) construction of a street extension that would service Emmy’s and two smaller lots which could then be sold to a buyer committed to economic growth for presently low and moderate-income households.

5 Site Plan Review
A. Project: Construction of a Public Road 6:45
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Nels Bohn for the Ithaca Urban Renewal Agency (IURA)
Actions: Consideration of Preliminary & Final Approval

Project Description: The IURA is proposing to extend Cherry Street by 400 feet. The road will be built to City standards with a 65-foot ROW, 5-foot sidewalks and tree lawn, and will be turned over to the City upon completion. The road extension is part of a larger development project that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

B. Project: Construction of a 14-24,000 SF Production Facility (Emmy’s Organics) 7:00
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Ian Gaffney for Emmy’s Organics
Actions: Consideration of Preliminary &Final Approval

Project Description: Emmy’s Organics is proposing to construct a production facility of up to 24,000 SF, with a loading dock, parking for 22 cars, landscaping, lighting, and signage. The project will be in two phases: Phase one, which will include a 14,000 SF building and all site improvements; and Phase two, (expected in the next 5 years) which will include an addition of between 14,000 and 20,000 SF. As the project site is undeveloped, site development will include the removal of 2 acres of vegetation including 55 trees of various sizes. The facility is part of a larger project that includes subdivision of land a 40-foot road extension by the Ithaca IURA extension that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

C. Project: North Campus Residential Expansion (NCRE) 7:20 Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Public Hearing (continued)

Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). All NCRE materials are available for download at: http://www.cityofithaca.org/DocumentCenter/Index/811

D. Project: Falls Park Apartments (74 Units) 7:50 (Notes above)
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Project Overview Presentation, Declaration of Lead Agency
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11).

E. Sketch Plan – Mixed-Use Proposal – Carpenter Business Park 8:10

6 Zoning Appeals 8:30
# 3108, Area Variance, 327 W Seneca Street
# 3109, Area Variance, 210 Park Place (construction of a carport)
# 3110, Area Variance, 121 W Buffalo Street (installing a deck and wheelchair lift)
# 3111, Use Variance, 2 Fountain Place (the proposed B&B in the old Ithaca College President’s Mansion)
# 3112, use Variance, 2 Willets Place

7 Old/New Business 8:40
Special Meeting October 30, 2018: City Sexual Harassment Policy, Special Permits (Some of the BZA’s Special Permits Review duties are set to be transferred to the Planning Board).

8 Reports 9:00
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development

9 Adjournment 9:25