Tompkins Financial Corporation HQ Construction Update, 2/2018

23 02 2018

About the only major exterior facade work left on Tompkins Financial’s new headquarters is the stone veneer on the front face. I don’t have information on file on what kind of stone it is apart from a generic “stone veneer” description. It may be cast stone, a concrete masonry product mixed and molded to resemble natural-cut stone.

Over the blue and black air/vapor barriers, Dow TUFF-R polyiso rigid foam insulating boards are being laid between rails. Atop those, a second set of steel rails, called continuous anchors, are attached to the building. When the polyiso is attached and the rails are screwed on, the stone panels are slid into place, and then they’re mortared or caulked with silicone. There will be a gap between the polyiso and the stone that serves as a drainage cavity for water that gets absorbed and needs to be eliminated. The whole process is about keeping moisture from seeping inward and damaging the more sensitive building materials like the gypsum boards, while allowing any latent moisture in the materials (having been exposed to the elements during construction) to escape outward.

The entrance canopy is up, and steel clasps for the sunshade installs on the front are ready for when the facade is nearing completion. The lights are on, and one can presume that with three months left in the schedule, most of the big interior tasks (utilities, drywall, fixtures) have been completed. Parts of the granite base appear to be in place, but most of the ground floor and its parking area remain a work in progress.





Harold’s Square Construction Update, 2/2018

22 02 2018

Not all cranes come on wheels. Many larger cranes are assembled and disassembled on site. A concrete crane pad is formed and poured to provide a base for the crane, with the pieces assembled upward from the base. That’s what you can see in the photos below. The size can vary depending on the size of the crane required, whether it’s free-standing or tied-in, whether there are rock anchors that can be used, and the soil upon which it and the pad will rest. Here, the crane pad will rest on a thick, firm mud layer beneath, and the concrete will be reinforced with a tied-in (meaning the grid bars are tied together) steel rebar grid. According to the Harold’s Square website, the crane pad itself will rest on a 4’6″ deep concrete, 38′ x 38′. Keep in mind, there will actually be two cranes on-site. The one mounted here will be the heavy-duty 300-ton crane, but they construction team will use a mobile 55-ton crane as well. The elevator pits are also being boxed and formed.

All the piles have been driven in at this point, and the sides of the site have been shored up as necessary with lagging and steel H-beams. The low-rise Commons-facing portion of the building will utilize an 18″ rebar-reinforced mat slab foundation, while the tower portion will have a 30″ rebar-reinforced mat slab. These pours should happen by mid-March. The structure will be anchored into the foundation, which will evenly distribute the weight and support the floors above. After the foundation is in, the only way to go is up.





107 South Albany Street Construction Update, 2/2018

20 02 2018

The wood frame for the eleven-unit 107 South Albany Street project is now up to the second floor. ZIP panel sheathing has started to be attached and interior stud walls have been erected. It does not appear utilities rough-ins have started on the ground floor yet.

The project recently underwent a last-second but substantial design change. It doesn’t affect the interior square footage (something that would have sent it back to the Planning Board), but the aesthetic have changed up quite a bit.  The tall mid-building stair column and flat roof with cornice have been ditched in favor of a less prominent stairwell with a small gable, and a large hipped roof. The fenestration and ground floor details remain largely the same. Before and after renders are at the bottom of this post.

Marketing for the eleven one-bedroom units has started, with units starting at $1,395/month – pricey, but not Collegetown pricey. The advertisement for a “luxury unit” reads as such:

“Brand new luxury 1 bedroom apartment in Ithaca’s newest development available August 1, 2018. One block from the Ithaca Commons and a bus stop with multiple routes at your door.

The Unit:
– Is beautifully furnished
– Boasts high end finishes throughout including: custom cabinetry, quartz counter-tops, stainless appliances and a beautiful tiled bath.
– Has laundry in building
– Includes indoor bike storage
– Water, high speed internet, common area maintenance and snow removal included in this professionally managed 11-unit building

The exterior, with cornice and orthodox windows are additional architecturally designed items that add to the beauty of the building. No detail has been overlooked. A must see as downtown Ithaca continues to grow. Photos are from other recent projects and are for illustrative purposes. They represent the types of finishes you will find within apartment.”

It’s a bit of a risk, since the real estate waters are generally untested west of Ithaca’s downtown, although a couple other small projects are planned along the State Street Corridor. Long-time residents also worry about gentrification encroaching on the edge of the Southside neighborhood. However, city planners are pushing development westward from the downtown core, and the possibility of a government center on the Central Fire Station site a block away means that there may soon be a large employer practically at its doorstep. The Facebook ads are pitched with an eye to students, but that seems a stretch; even with the buses, this is a bit too far out for many Cornell or Ithaca College kids to consider, and it’s double the per bedroom price of shared South Hill, Fall Creek or outer Collegetown units.

The developers, the Stavropoulos family, don’t seem especially inclined towards any one neighborhood. Previous projects include a pair of duplexes in Fall Creek, a new home on Linn Street, and home additions on South Hill. The Stavropoulos family’s next project after this would potentially be the duplex pair at 209 Hudson Street on South Hill, if approvals are granted. Arguably, South Hill is a safer bet financially thanks to Ithaca College, though becoming less amenable due to the concerns from permanent residents regarding quality-of-life manners, which has led to a new zoning overlay to rein in infill in that neighborhood.





Maplewood Redevelopment Construction Update, 2/2018

19 02 2018

There is so much going on here – it kinda blows my mind because a development of this acreage and number of units is extremely rare in a place like Ithaca, where highly subdivided lands make large acreages difficult to find or assemble, the financial and labor capacity for a large build is limited, and review processes are stringent and rather burdensome. With the exception of a few townhouse strings towards the middle and the community center, it looks like almost everything else has moved into the framing stage. In contrast to the renders, the townhouse strings are showing greater color variation in their brick and fiber cement panels – some are navy blue boards and orange-red brick , while others are jade green boards with maroon brick. Same goes for the apartments, some of which have a navy/orange-red scheme, while others are faced in different shades of grey panels. This helps to create more visual interest and differentiation between otherwise similar structures.

Embedded below are a couple of mock-ups from the on-site display unit inside the leasing trailer. It’s not a bad setup, though on a random note, no one in their right mind would hang a picture frame so close to the top of their bed. The units will come furnished. For those interested, the rental website can be found here. Also included below at the end are a few interior renders, of the community center, a study lounge, the fitness room and a bathroom (not a part of the walk-through mock-up).

For project background and planning, click here.

For a site plan breakdown, click here.

For a construction timeline, click here.

Webcam link here (updated ~15 minutes).





The Lux (232-236 Dryden Road) Construction Update, 2/2018

19 02 2018

Things continue to move at a good clip over at “The Lux” at 232-236 Dryden Road. It looks like the insulated concrete forms (ICFs) have acquiesced to standard wood framing and ZIP panels on the upper floors. The building facing Dryden Road, 232/The Lux South, has commenced with framing of four of its five floors, and the elevator core/stairwell stands at full height (zoning only allows four floors/45 feet, but its a sloped site, so technically that bottom floor is a partially exposed basement level). 236/The Lux North has begun work on its basement level with the construction of ICFs covered with a vapor and water-resistant barrier (Resisto), and it appears that the first blocks for an elevator core/stair column are being assembled.

There might have been some internal reconfiguration. Site plan review documents noted that 232 Dryden will have 20 units and 53 bedrooms, and 236 Dryden will host 40 units and 138 bedrooms. But, a recent post on Visum’s facebook page suggests the project will have 207 bedrooms, not 191 as originally conceived. Everything appears to be on track for an August 2018 occupancy.

Even with the expected Cornell dorm additions in the next three years, the Lux’s location in inner Collegetown gives it an advantage over more remote housing options – students/parents with deep pockets will often pay more to be next to campus, while the amenities and worry-free living help seal the deal (worry-free in the sense that there’s no “deferred maintenance” to be concerned with when the units are brand new). Rents here are going for $1,200-$1,300 per bedroom, though they have a promotional running right now for 10% off rent for the first month.

It appears there was an unusual but interesting contest held by Visum that invited students to compose interior designs for the three common rooms in the complex. Registered applicants (individual or group) received floor plans and interior documents to aid in their designs, and had about eight weeks to submit their final plans (December 2nd – January 21st). The winning team gets $2,500 and a building lounge will be named in their honor. Snagged from the website and included below are some mockups of the gym, a study room and a commons space.





400-404 & 406 Stewart Avenue Construction Update, 2/2018

18 02 2018

This pair appears to be coming along quite nicely. 400-404 Stewart Avenue is looking good. GAF asphalt roof shingles are being laid over the Raptor brand underlayment. The trim has been attached, with some of the ornamental board starting to go up aside the brackets. The cornice and bracket trim is to be painted grey and black, as are the gables on the dormers (I guess they do technically count as gable dormers on a mansard roof, even with the pitch as steep as it is). It has a vaguely Georgian colonial feel to it; the design is a heavy nod to the original building design from a century ago.

Most if not all of the Redland Heritage SWB brick is attached, and the overhangs have been framed and sheathed, with some underlayment applied – these will actually be finished with more expensive but historically appropriate (simulated) slate shingles. The transom windows and picture windows of the first floor retail/bar/restaurant space have been fitted, but the trim has yet to be attached. The bluestone veneer at the base is largely complete. The doors have yet to be fitted, as do the heavy brackets and ornate detailing of the first floor exterior.

Advertisements for the upstairs apartments has yet to make an appearance, but there are ads going around for the retail space (3,000 SF, $35/SF).

As for the new 406 Stewart Avenue, the mismatched rough window openings on the front facade appears to have been fixed. The recessed front porch is framed, and if I’m seeing it right, the stonework is already in place at the base. The construction crew is starting to cut out the openings from the Huber ZIP panels on the third floor. It is definitely a different interior layout than they had in mind when the renderings were presenting – there are substantial differences in the fenestration of the building’s north face.  The gable roof and dormer has yet to be framed, but if they’re aiming for a Q2 and Q3 opening, they look to be on track from a glance.





210 Linden Construction Update, 2/2018

18 02 2018

So here’s some good news – 210 Linden Avenue is moving forward once again. The city’s Board of Public Works (BPW) held a special meeting on the 30th that would create a loading zone in front of 210 Linden Avenue. This is important because the new state fire code restrictions say no construction can occur along Linden since the street is no longer considered wide enough. By eliminating the parking space in front of 210 Linden and replacing it with a loading zone, it created a “wider” street since a fire crew would no longer have to worry about parked cars along the street frontage. This made it easier for the project to obtain a fire code variance from the state.

BPW is ostensibly not a fan of the arrangement, but given that the developer (Visum) was notified by the city of the change after the existing building had been torn down, they were willing to grant the loading zone given the unique circumstances.

Well, mostly unique. One other project was subject to the the same issue under very similar circumstances – Novarr-Mackesey’s 238 Linden Avenue. That project team is also asking for a loading zone during this month’s BPW meeting, and hopes to be granted a state fire code variance as well (and 210 Linden gives them reason to be optimistic). While every future project planned for Linden is now in limbo, it appears likely these two will be able to move forward.

Also in the good news category, a state fire code variance was granted for another Visum project, 118 College Avenue, under the expectation that the city and NYSEG will follow through with their plans to bury the power lines on College Avenue in the next two years. With the lines to be buried relatively soon, the state felt comfortable granting the variance for a building taller than 30 feet (118 College is just under 45 feet).

The buildings are aiming for an August 2018 completion. They are wood-framed structures, which in comparable economic circumstances, can move along faster than a concrete or steel. Even then, it’s still going to be a tight deadline for William H. Lane Inc.

A glance at Zillow shows that the basement 1-bedroom unit appears to be spoken for (the basement unit was a modification to the original plan, perhaps because many amenities will be shared with its siblings 201 College and “The Lux” at 232-236 Dryden Road), but the nine 4-bedrooms/2-bath units (1,365-1,440 SF) have not. Zillow says there are ten 4-bedroom units – that doesn’t seem correct. They are going for $4,400 apiece, or $1,100 a bedroom. That’s actually a sizable price drop from the $5,000/month they were being offered for before the fire code debacle.

 





News Tidbits 2/10/18: It’s In The Minutes

10 02 2018

1. It’s round four of the senior housing proposed as part of the Lansing Meadows PDA. This time, developer Eric Goetzmann is proposing two six-unit strings, two stories, all units two-bedrooms with enclosed garages. The Lansing Star notes that the site plan is very unusual in that all the housing is clustered at one end of the property, leaving a big vacant space that could in theory be sold off. Apparently it also caught the Lansing village planning board’s attention.

“It just looks too obvious,” said Planning Board Chair Mario Tomei. “There’s got to be some other thought going through your head about what that green area is going to be. Are you willing to share it?”

Goetzmann replied, “I don’t have anything, Mario. I need to get these 12 built. To get these things done, and then I’m going to be done with this. I don’t have any other plans for the future. I’ve listened to what you’ve said. I’ve never pushed anything. The last plan I brought here was 100% within the code. If I wanted to come back and fight it I could have done that. You had a reaction to it, and I understand. I do commercial development, not residential. But I agreed to it as part of (the overall plan to build BJ’s). I made a commitment to get these things done, and I want to get them done.”

That much is correct. The county IDA granted Goetzmann a tax abatement on the construction of BJ’s in 2011, on the provision of the wetlands and senior housing being built. After several extensions, the IDA had told him no more, the housing either starts this year, or they’ll consider him to have breached their contract. So if Goetzmann doesn’t start work on the senior housing soon, they’ll consider legal action, possibly a “clawback” on the abated taxes. As a result, this has a whiff of desperation, although the vacant land is still a question mark to just about everyone. The planning board will continue to review the plans later this month.

2. So here are a few other interesting little tidbits out of the village of Lansing:

– At the Crystal’s Salon and Spa site at 2416 North Triphammer Road, there is an early concept plan being considered for redevelopment into mixed uses with about sixty housing units. There are wetlands on the property, which the developers (as yet unknown) have said will be avoided. Zoning for the property is Commercial Low Traffic (CLT), which allows multi-family housing with a special permit. CLT is otherwise limited to office space and low-traffic operations, non-retail and non-food service. The spa might be permitted as a “clinic” health facility, the code’s a little vague at points. Crystal’s is 3.42 acres, which seems a little small for a Lansing project, though not impossible, and it’s certainly more plausible if it includes the vacant 5.61 acres next to it. Maximum height is 3 floors/35 feet., no limit on lot coverage so long as it meets setbacks and parking requirements.

1020 Craft Road, a former manufacturing facility, is being renovated by Marchuska Brothers Construction for a medical office tenant. Pyramid Brokerage has a site plan concept sketch up on their website.

The 140-unit Bomax Road apartments plan had a litigation hearing on February 2nd. It appears the developer of the proposed complex has won? If so, the plan could legally move forward.

Cayuga View might be a summer or even an early fall opening, rather than Spring 2018.

3. Over in Dryden, not a whole lot going on at the moment. The town will be reviewing the plans for Nick Bellisario’s second warehouse at 57 Hall Road. The 10,800 SF structure is a 60′ x 180′ x 20′ pole barn with a corrugated metal finish, garage bays, four parking spaces and some modest landscaping. It’s designed to complement the 12,000 SF warehouse next door, which is used by Tiny Timbers for manufacturing the components of their modular home kits. However, it’s not clear if there is a tenant in mind here.

4. It appears that there’s been some movement on the Cornell North Campus dorms. From the Student Assembly’s Campus Planning Committee fall notes:

Aspiration – 2000 new beds, 275 new freshman/year for 4 years

Process

  • Housing Master Plan will be shared with CPC in two weeks
  • Early site review: North Campus the area of focus – existing freshman and number of sophomores, and area with developable sites
  • RFP Process: 24 developers, 9 responses,  interviewed 4
  • Cornell funding decision: this will be owned and operated by Cornell
  • Fee developer to construct
  • Board of Trustees approved this early portion of the process over summer

Paul Stemkowski, serving as the North Campus Housing Expansion project manager reported:

  • We have a developer
  • Site analysis has commenced, reviewing municipal zoning and boundaries in the site areas, natural features, and a noted historic district   
  • Phase 1: proposed as 800 beds on CC Lot (1200 beds initial studies) 4 and 5 story buildings and new dining element
  • Sophomore and freshman villages
  • Appel Fields: housing proposed here for 3 to 4 stories

Timeline: August 2020 goal for phase 1 phase 2: 2021

Phase I will open spaces for deferred maintenance work- Balch Hall needs lots of restoration, rehabilitation

So, we’re looking at 4-5 floors and at least 800 beds in multiple structures on what is CC lot (the leftmost blue patch in the map), and 3-4 stories in multiple structures on the Appel Fields (rightmost blue patch). It will be Cornell owned and operated, but that makes the RFP part a bit confusing – tapping someone to build and sell Cornell the final product, or what exactly? If August 2020 is the goal, then summer 2019 is probably the hard deadline for a construction start, so expect formal site plan review to begin this fall at the latest (sooner if an in-depth Environmental Impact Statement (EIS) is expected by city planning staff). The only commercial component appears to be new dining facilities, though they are considering additional carryout food service options. No new parking will be added, and work on the Helen Newman Hall athletic facility is not a part of the expansion plans.

The October minutes cover plans for the College of engineering, with a gut renovation of Hollister and demolition of Carpenter Hall and Ward Labs. However, these appear to already be outdated, given Cornell’s state-funded plans to renovate Ward into the CEPSI+ business incubator.

5. Lansing is finally getting that sewer line, though it won’t be along North Triphammer Road. According to the Lansing Star, the new sewer will go along East Shore Drive and Cayuga Heights Road because it appeared more feasible, and gave the village of Lansing an opportunity to reconfigure a difficult intersection. The current treatment facilities are not far from maximum capacity, and as a result, the village is expanding the lot size needed for a single-family home with a sewer connection, from 30,000 SF to 45,000 SF (just over an acre). An unsewered lot requires 60,000 SF. for the record.

Relevant to this blog, the line will terminate at a trio of lots under development or redevelopment in the town – the RINK, which is adding a climbing wall, as well as the 117-unit and 102-unit English Village and Cayuga Orchard housing developments. The village mayor, Donald Hartill, says the sewer project is in good financial shape, and that a revised land survey will allow final engineering to commence, ultimately leading to construction later this year.

 

6. City Harbor updated its website with additional info. Most of it has been shared previously, but the developers note that the project would create 120 new jobsGreenstar would be responsible for about 60 of those positions, while Guthrie, the waterfront restaurant and a few management/maintenance roles would compose the rest.

7. Not a whole lot going on at the moment. The city of Ithaca Landmarks Preservation Commission (ILPC) will host its monthly meeting next Tuesday evening to continue consider of historic designation of the Nine, and provide design guidance to a smaller proposal for the adult co-op planned at 314 West State Street. The original nine-bedroom proposal was considered too big to adequately defer to this existing historic building, so the structure was reduced to a similarly-designed six-bedroom building.

Meanwhile, the city planning board will host its Project Review meeting next week as well, but only two projects are on the agenda – Novarr’s revised College Townhouses project at 119-125 College Avenue (on the Voice here) and the Stewart Park inclusive playground.





Cayuga View Senior Living Construction Update, 1/2018

3 02 2018

Somehow, these sat in my drafts folder for a week after they slipped off the radar. Anyway, Cayuga View Senior Living is topped out, most of the windows and entryways have been fitted, and much of the exterior has been wrapped. Exterior finishes include concrete masonry unit (CMU), face brick and fiber cement panels.

Worth a quick note, the property management here will be from Cornerstone Group of Rochester, the same firm developing the 72-unit Milton Meadows affordable housing at the Lansing town center. Some properties they own and manage, others like Cayuga View are managed on behalf of a client (the Thalers, in this case).

Touted amenities include “Hot Water, Basic/Standard Cable, Designer Kitchens, Energy Efficient New Construction, Trash Removal, Rooftop Garden Access, 24/7 Maintenance, Community Room, Fitness Center, Library/Computer Room, Secure Intercom, Wi-Fi Campus, [and] 24/7 Site Monitoring”, under the marketing moniker “Discover New Freedom”. One of the senior sub-markets the Thalers hope to target are snowbirds (like themselves), for whom they expect to rent the units year-round but only spend the warmer months and holidays up in Lansing. For $1,500-$2,775/month, that’s a lot of money to give up for a place to not live in all-year round. But that’s just one millennial’s shallow-pocketed perspective.

Taylor the Builders plans to deliver the 87,359 SF, 60-unit building sometime this spring – probably later in the season, perhaps May or June. No details are publicly available on the percent of units pre-leased, or for occupants of the twin 1,340 SF commercial spaces on the first floor. Background info on the project can be found here.





News Tidbits 1/27/18: The Shutterbug

28 01 2018

1. Let’s do some houses of the week. Above, the four new homes Tiny Timber has constructed at 1624 Ellis Hollow Road in Dryden. Each home lot is a little over an acre. The subdivision was approved last spring for the wooded parcel a couple miles east of Ithaca, and since then, Tiny Timbers has been busy selling units and lots to buyers. Two were sold in August, one in September, and the last in December. Therefore, this is 100% built out, since the last lot is a conservation lot at the rear (north) end of the property, designed to protect Cascadilla Creek. The units utilize a shared driveway, with spurs for each home. If you want to look at the homes more closely, click to enlarge the photos.

A similar plan is underway just up the road at 1540 Ellis Hollow Road, where Tiny Timbers will take a long, narrow undeveloped property and subdivide the land into five home lots and a rear (north) lot protected by a conservation easement. These homes will also be served by a common driveway. This proposal is still going through the review process, and when approved, the time frame for build-out will probably be similar. The home designs are the work of local architecture firm STREAM Collaborative.

2. Over in the village of Lansing, work has started on the next six-unit (hexplex?) at the Heights of Lansing property off of Bomax Drive. It appears that the foundation slab and footers have been formed, poured and insulated with foam boards. This is the first new townhouse string to be built in the development in six years.

Several reasons have been given for the long pause. The developers have said that the natural gas moratorium disrupted and delayed build-out plans. Secondly, the patriarch of Forest City Realty/IJ Construction, Ivar Jonson, passed away in 2014. More recently, the Jonson family (his wife Janet and daughter Lisa Bonniwell) were embroiled in a lawsuit to prevent a zoning change that would allow a market-rate apartment complex to be built down the road. Bonniwell was incensed enough to run for mayor in 2017 in an effort to stop the proposal, but did not win the election. The zoning change has been approved and the apartments were approved in October, but the Park Grove project has yet to move forward.

The townhouses were approved along with the last single-family home permit; there were some rather testy exchanges regarding sewer line easements and the installation of street lighting in conjunction with those permits. The lighting has to be in by March 2019.

Assuming these are like the other townhouses, expect them to be 3-bedroom units, low 2000s SF with garages, and to go for $350-$450k when they’re finished several months from now.

3. Dryden’s new Rite Aid is coming along. Fully framed, and the plastic in the window openings is likely intended to allow construction crews to work indoors without exposure to the fierce winter elements. The curbing and paving is complete in the parking lot, and it looks like they install metal bollards all around the lot’s perimeter to keep the less-than-attentive from driving into the wall (something that happened to the Nice N’ Easy in my hometown no less than three times before they finally put some in). It is still planned to open in March.

4. Over in Fall Creek, it appears a small apartment building is in line for some major renovations. 1002 North Aurora, a four-unit building built in 1898, had been on the market for $395,000. The seller had owned the property for 24 years, and the price was only slightly above the assessed value of $375,000.

On Friday, the property sold for $400,000 to an LLC associated with local developer Modern Living Rentals (Charlie O’Connor et al.). The same day, a building loan agreement was filed from Tioga State Bank to the LLC for $712,000. A lot of that was going towards the land acquisition, and once soft costs are deducted as well, the loan is $287,000.

MLR tends to be very transparent about their plans, and a glance at their recently updated website shows the purchase and a ‘information on this project coming soon’. However, they already uploaded the interior renovation plans from STREAM Collaborative. It’s a very thorough interior renovation, and it appears to complete change interior floor plans, with new bedrooms (net gain of one?) as well as new kitchens, bathrooms, and fire rated ceilings. Exterior changes appear to include a renovated fire escape staircase, a couple new windows on the third (top) floor), and a new skylight. While old, this apartment building is a hodge-podge of additions from decades past, so let’s see what a renovation can do to clean things up. It’s plausible the renovations would be complete by August, so they can appeal to students as well as the general market.

Quick aside, MLR has a few other “future developments” posted, though none that readers here aren’t already aware of – the 42 townhouse units at 802 Dryden, the proposed 201 North Aurora / Seneca Flats that isn’t moving forward for a while yet, and 217 Columbia, the duplex that unintentionally set South Hill into an uproar. 217 Columbia should be completed this year, and 802 Dryden in summer 2019.

5. It looks like Amici House is finally moving forward. The project, located at 661-701 Spencer Road, received a $3,732,469 loan from the New York State Homeless Housing and Assistance Corporation. The money was announced back in April, and appears to be getting disbursed now.

The five-story, 20,710 SF (square-foot) project, approved by the city of Ithaca last January, calls for 23 studio housing units for homeless or vulnerable young individuals in the 18-25 age range. Along with the units and office/function space for local social services non-profit TCAction, the plan also calls for a 7,010 SF early heard start facility, called the “Harriet Gianellis Childcare Center”, that will house five classrooms, kitchen and restrooms, and an outdoor play area. The childcare facility will serve 48 low-to-moderate income families and create up to 21 jobs.

Recently, the HGCC applied for a low-interest loan from the IURA, $90,690 to help cover unanticipated moving expenses associated with the project. TCAction thought they could stay on-site during construction, but the contractor said otherwise, so they’ll be 609 W. Clinton while the new Amici House is built. The loan says it will generate three jobs, but that’s more a technical stipulation than an actual figure associated with the project. The funding for the childcare appears to be separate, $1,325,000 already approved by the state, $603,000 from M&T Bank, and $84,200 from a standing IURA loan. It is fully funded, although it is not completely clear if it will be built concurrently with the housing (the likely answer is yes).