210 Hancock Construction Update, 2/2017

20 02 2017

Normally construction sites get updates every two months. But at the INHS Hancock project site, things are getting really interesting in a short time.

First, the main apartment building. In just the past month, section “A”, the southernmost wing, has been wrapped in Blueskin, roofed, and the windows have been fitted. Answering a question from a few months back, it looks like the Blueskin’s purpose is to be the water/vapor membrane under the brick. The section of “A” under the weatherproof plastic tenting is being bricked – a few loose bricks can be seen in the last photos through holes in the plastic. Not only do the workers appreciate some protection from the elements, brickwork requires temperatures to be kept above freezing so that the water in the mortar doesn’t freeze out, so not only is there plastic wrap, Lecesse has also deployed portable heaters. Section “B” will follow with the Blueskin sheathing, roofing and window-fitting, and then “C” and “D”, which host the indoor garage (hence the CMUs) and are still being framed out.

The five rental townhouses have a typical wood-frame build-out – first comes wood framing and roofing, then tar papered and shingling, housewrapping and window fitting. Interestingly, the seven for-sale townhouses (collectively referred to as “202 Hancock”) are using Huber ZIP sheathing panels, which the rentals did not. The Hancock street trio of homes have been framed but not roofed, while the Lake Avenue quartet are still being framed out, awaiting the rest of their roof trusses. The insides of the for-sale homes are still just bare stud walls at this point, while the rentals are probably far enough along that most utility rough ins have been completed, and sheetrock is being hung in the units. All in all, Lecesse Construction and their subcontractors have been moving at a very good clip over the past month or so.

A construction loan filing on January 23rd states Tompkins Trust lent INHS $1,581,796 to finance the 202 Hancock units. The total cost (hard and soft) of the seven for-sale units is estimated at $2.36 million. The five two bedroom units (1,147 SF) will be sold for about $114,000, and two three-bedroom units (1,364 SF) for $136,000, to qualified applicants making 60-80% of local AMI, or $37,000-$49,000/year.

For the sake of comparison, the apartment building and for-sale units are partially financed with a $7,790,511 loan from a Citibank fund – through an LLC, Citibank bought the low-income housing tax credits (LIHTCs) awarded to the project by New York State. The apartment building’s total cost comes to $13.8 million, with the rest financed through INHS’s money, federal tax credits, housing grants and a low-interest loan from the state’s housing division (NYSHCR).

Renters or homeowners interested in obtaining a unit can fill out an inquiry form here. The rentals will be ready for occupancy by August 1st, 2017, and the for-sale units are looking at a November 2017 completion.

20170218_132608 20170218_132630 20170218_132650 20170218_132705 20170218_132720 20170218_132737 20170218_132806 20170218_132824 20170218_132828 20170218_132850 20170218_132905 20170218_132928 20170218_133033 20170218_133051 20170218_133132 20170218_133217 20170218_133245 20170218_133259 20170218_133312 20170218_133355 20170218_133420

inhs_pride_design_v5_3

blueskin-vp100-brick inhs_pride_design_v6_1202_hancock_2 202_hancock_1 202_hancock_3

inhs_pride_design_v6_1





The Cherry Artspace Construction Update, 1/2017

20 01 2017

The Cherry Artspace was saved for last because originally, these photos were going to be used in an Ithaca Voice article. But, with the State Theatre piece running this week, it didn’t seem like a good idea to run two pieces about performing arts spaces in a short span, so the Cherry Arts will be profiled in a piece next month. That would make these photos too old by then, so here they are.

The Styrofoam block “floaters” are mostly in place and a steel rebar mesh has been laid on top in anticipation of pouring the concrete slab – the mesh will provide increased strength to the concrete as it cures. Water, sewer and utility hookups are piped beneath and up through the foundation. Looking at the sawhorses, it looks like McPherson of Ithaca is the general contractor. The 1,900 SF building should be ready for its first performances sometime this Spring.

20170107_115618 20170107_115631 20170107_115645 20170107_115703 20170107_115707 20170107_115729

cherry_2





Upson Hall Construction Update, 1/2017

18 01 2017

It’s become a little more difficult to shoot photos from certain angles, now that one of the previously-open sidewalks has been closed off. But, it’s not a surprise, they’ve been working on Upson’s new face. The exterior stud framing has been underway on the lowest floors of the west face. Sheathing is being attached, and the rough openings indicate future windows. The lowest floors of the east side, a little further along, have already been coated in turquoise waterproofing material, and are being fitted with windows. On the upper floors, there’s been considerable progress with the terra-cotta and the aluminum surrounds. It doesn’t look like there’s been much progress with attaching new mineral wool and clips, the current work is either finishing up what was well-underway (the upper floors), or getting started with the new exterior (the lower floors), not a whole lot of work going for the in-between stages at the moment.

Inside, you can see the new interior framing being built inside the fully-gutted and renovated interior. According to Cornell’s last update in December, interior demolitions are complete, mechanical rough-ins are ongoing in the basement, and electrical and plumbing are underway on the first and second floors.

Like Gannett, The Pike Company is the general contractor in charge. LTL Architects and Perkins+Will are in charge of design.

20170107_103946 20170107_104030 20170107_104052 20170107_104055 20170107_104104 20170107_104120 20170107_104139 20170107_104430 20170107_104456 20170107_104540 20170107_104555 20170107_104906 20170107_104910 20170107_104921 20170107_104955





Cornell Veterinary School Expansion Construction Update, 1/2017

17 01 2017

Starting to see more progress on the structural frame of the $74.1 million Vet School additions. The reinforced concrete frame of the new library and administrative offices now extends all the way back to the rest of the Vet School complex; the new section is draped over with plastic sheets. Also, as the new wing gets fleshed out, the rough openings of the windows are taking shape. It doesn’t look like there’s been too much exterior progress on the new atrium.

According to the project webpage (last updated two weeks ago), interior framing (metal stud walls probably) is underway, rough-ins are underway, and the new cafeteria is under construction. Welliver will have the new atrium and lecture hall fully closed up by the end of January. Most of the Vet Research Tower work has been completed, but new office layouts are still in the works for the sixth and seventh floors, and that work won’t get underway until this Spring.

The new $7 million ($4.9 million hard cost) Community Practice Service Building is out for bid, with a march demo planned for the Poultry Virus Building currently on site, and a March 2018 opening, about seven months after the bulk of the new Vet School structures. It is a wood-frame 12,000 SF building designed by HOLT Architects, and I still have yet to find an image of the design.

20170107_102456 20170107_102508 20170107_102521 20170107_102540 20170107_102615 20170107_102640 20170107_102646 20170107_102708 20170107_102740 20170107_102838 20170107_102846

cad048742a281097e5667382eced42333f5656954f5a3ef1021519c03b4abe9f

20160522_131445 20160522_131417 20160522_131344

20160522_131403





Gannett Health Center Construction Update, 1/2017

15 01 2017

Okay, for as much as I miss the old banded concrete and glass, the large window panes, clear glazing and thin aluminum frames designed by Ithaca’s Chiang O’Brien Architects do have a certain modern chic going. However, this armchair critic still has yet to decide if he likes the offset between the outer and interior frames of the curtain wall. The windows have made their way north along the old east wing. Peering through, you can make out some of the new metal stud walls, so utilities rough-ins for the gutted 1950s structure are underway.

The new entry canopy has yet to be built out. Pike, the contractor, could soon insert the northernmost panes where the old east wing’s interior is exposed, but the curtain wall glazing won’t be finished until the canopy has been constructed.

The new three-story 18,000 SF northeast wing, which replaces the former Ho Plaza entry, rose pretty quick – like the Breazzano Center, it’s wrapped up in plastic to limit workers’ exposure to the cold. The outside of the new wing will be faced in a couple types of limestone, with a bluestone transition panel and bluestone veneer at its base – the 1979 west wing is being updated so that the two will look similar, although the 1979 wing will retain its concrete exterior, giving the two wings some visual contrast.

According to Cornell’s revamped project website, the Gannett project is 70% complete. Whether that included the new addition that opened last year is not clear. The entire project should be finished by this fall.

20170107_105817 20170107_105841 20170107_105904 20170107_105908 20170107_105926 20170107_105950 20170107_110000 20170107_110007 20170107_110038 20170107_110100 20170107_110108

gannett_northeast_persp gannett_north_final gannett_eat_persp gannett_east_final gannett4





Ithaka Terraces (215-221 West Spencer Street) Construction Update, 1/2017

14 01 2017

The first building of the Ithaka Terraces, Building “A”, is fully framed and in the process of being roofed. The project uses double stud exterior walls in tandem with Insulated Concrete Forms (ICFs), which is thermally insulated plastic filled with concrete. The zip sheathing goes on over the surface. The purpose of the thick, more premium approach is for more efficient insulation, since the condo units are designed to be net-zero compatible (the high energy efficiency reduces the need for off-site renewable energy sources, and net-zero becomes more feasible as a result).

Further up the sloping site, smaller Building “B” has completed the ICF erection ground floor and is starting work on the upper floors. Note the reinforced concrete wall facing South Cayuga (east). That will eventually be back-filled and hidden from view. As seen in some of the early concept designs below, only the top floor of the three floors of Building “B” and “D” will have windows facing outward; the South Cayuga side of the property is where the parking lot will be laid.

The other large building in the four-building cluster, Building “C”, a mirrored floorplan of “A”, is just getting started; the site was being prepped and graded when these photos were taken last week. Building “D”, a mirrored floorplan of “B”, will start construction at a later date, as the other three get further along. In the last photo, one can see the winding temporary staircase workers use to get to the building themselves. AquaZephyr, an Ithaca firm specializing in eco-friendly construction, is the general contractor in charge of the buildout.

The 12-unit condo project will begin formal marketing later this Spring. There will be 10 two-bedroom units and 2 three-bedroom units, in the $265k-$390k range. A late 2017 opening is planned. Interested readers can submit queries here.

20170107_112320 20170107_112356 20170107_112359 20170107_112419 20170107_112433 20170107_112437 20170107_112656 20170107_112710 20170107_112727 20170107_112735

215-221_spencer_v1_2 215-221_spencer_v3_1

ith_terr_intro





602 West State Street Construction Update, 1/2017

13 01 2017

With the sidewalk along Meadow St closed off, getting up close to the Elmira Savings Bank project just became much more difficult. From the front, there hasn’t been much exterior work yet – judging from the dumpster, Edger Enterprises has been more focused on gutting the interior of the hundred year-old building. It does look like that, since November, some of the historically inaccurate blue paint has been stripped from the east facade. It doesn’t look like there’s been much progress on the new wing on the north side, the foundation looks about the same at it did two months ago. Dunno if they’ll be hitting that March 2017 completion date.

More info about the project can be found here.

20170107_114207 20170107_114322 20170107_114328 20170107_114404 20170107_114448 20170107_114515 20170107_114552 20170107_114603 20170107_114747 20170107_114801 20170107_114856





312-314 Spencer Road Construction Update, 1/2017

10 01 2017

The new duplexes on Old Elmira Road seem to be moving right along. The east building has three shades of siding, one for each floor, and a third at gable-level. The exterior is accented by white trim boards. The variety in colors is an easy to way visual interest to an otherwise simple design. We’ll have to wait and see what colors they break out for the west building, which also benefits from a window bay projection facing towards the open space. It looks like plans to use shake siding on the bay projection have been dropped. Both building appear to be fully roofed and shingled. Signage at the edge of the road suggests precast concrete Superior Walls were used in the foundation work.

The 4 3-bedroom units are expected to hit the market in February. In the November update, I noted that Craigslist had these at $1700; the Modern Living Rentals website, which is the rental company for developer Charlie O’Connor, has them listed at $2100. Consider these a preview of the 4 two-family homes to be built at 607 South Aurora this spring and summer, which are also an O’Connor project.

20170107_113210 20170107_113347 20170107_113417 20170107_113438 20170107_113506 20170107_113530 20170107_113545 20170107_113554





210 Hancock Construction Update, 1/2017

9 01 2017

So much to see over at the 210 Hancock site. First, the prefabricated wood wall panels of section “A”, the south wing of the apartment building, are up to the top (fourth) floor, and one gets a pretty good idea of the vertical scale of the building. For the record, roof height will be 46 feet, not counting mechanicals. The second section to the north of it, “B”, was designed by HOLT Architects to be a little closer to the street, so it looks less like one continuous wall, and helps create the impression of separate structures. The first floor of these two subsections, which is framed by metal and wood rather than wood alone, will house the daycare, rental offices and commercial space. Sections “C” and “D” will consist of apartments over the indoor garage, which is currently wrapped in plastic sheeting, and separated from the other two section by a CMU stairwell.

The rental townhouses are fully framed (210 Hancock’s website says window install is expected to start soon), and it appears that Lecesse has start construction on the seven for-sale townhouses – the foundation walls have been excavated and poured. These units have a slab (shallow) foundation, and not having to worry about excavation allows the townhouses to move along at a faster clip. The apartments and rental townhouses should be ready by August, the for-sale townhouses by November. Ithaca Neighborhood Housing Services (INHS) has a website up for rental applications here and qualified home-owners here.

20170106_155902 20170106_155925 20170106_160000 20170106_160020 20170106_160043 20170106_160130 20170106_160153 20170106_160227 20170106_160247 20170106_160309 20170106_160331 20170106_160347 20170106_160457 20170106_160508 20170106_160531 20170106_160540 20170106_160610 20170106_160626 20170106_160639 20170106_160700 20170106_160711 20170106_160720 20170106_160736 20170106_160744 20170106_160821 20170106_160855
inhs_pride_design_v6_1

inhs_pride_design_v5_3 inhs_pride_design_v5_2

202_hancock_1 202_hancock_2

202_hancock_3





Collegetown Terrace Construction Update, 1/2017

8 01 2017

And to think that a year ago about this time, Collegetown Terrace’s Building 7 was just an excavated trench.

On the outside, facade installation continues. It looks like that, along with the fish scales and aluminum panels, there might be a dark blue fiber cement siding not unlike that seen on the smaller buildings lining East State Street. The east cinder block stairwell seen in November’s photos has been wrapped in waterproofing and is now receiving its exterior finishes. Most of the windows have been fitted at this point. The AC units have yet to be installed, and from what could be seen through the windows and openings, the inside has had drywall hung in some locations, but is still down to the stud walls in other sections. There are a couple of architectural quirks that give the building a little bit of visual interest – for instance, the reverse-pitch on the roof where Valentine Place terminates, probably indicating a stairwell or landing area, breaks up the monotony of the wall. I really like the curtain-wall glass used for the amenities/common area at the southwest corner of the structure.

A pine tree on the roof is a traditional way to celebrate the “topping out” of the building.

By the way, I have been wrong – the fish scales are in fact metal, their finish coat just makes them feel like vinyl. According to a trade industry website, they are “0.032-aluminum (0.032” thickness), diamond-shaped, flat metal CastleTop Shingles from ATAS International Inc. of Allentown, Pennsylvania. ikon.5 architects selected three standard colors-Hartford Green, Patina Green and Hemlock Green-and four designer colors-Adobe Dust, Metallic Gold, Acorn Yellow and Louisburg Green.” It looks like the shingles are more commonly advertised for roofing, although their interlocking tabs allow them to be used for walls as well. The three shades of green on Building 7 are the three standard colors, logic being that designer color shingles likely cost more and were used more sparingly. The other four show up on Building 3 where it approaches East State Street.

 

20170106_163724 20170106_163805 20170106_163817 20170106_163912 20170106_163931 20170106_163951 20170106_164021 20170106_164026 20170106_164102 20170106_164206 20170106_164212 20170106_164249 20170106_164309 20170106_164636 20170106_164719 20170106_164730  20170106_164800 20170106_165233