Cornell Veterinary School Expansion Construction Update, 6/2018

14 06 2018

Looks like we can move this project into the “completed” column. The 12,000 SF, $7 million building is open and occupied – in fact, there appeared to be a couple of folks transferring crates of paperwork into the building as these photos were being taken.

HOLT Architects designed a modest LEED Silver structure with clean, modern lines, and G. M. Crisalli and Associates Inc. did a bring job bringing that design into reality. At this point, the four years of construction at the Cornell University Veterinary School appears to finally be complete. The school will gradually build up to its expanded size (102 to 120 students per class), expand its lab and research capabilities, and through the Community Practice Service building, serve the community in which it resides. The state released its press announcement calling the Vet School Expansion complete last week – and noted that the final price tag for all the phases was $91.5 million.

Before:

Render:

After:





Cornell Veterinary School Expansion Construction Update, 3/2018

21 03 2018

The Cornell College of Veterinary Medicine’s new Community Practice Service is set to open in May, and it certainly appears to be in the home stretch. Exterior finishes are underway. Atop the dark blue water-resistive barrier are rigid foam insulating panels, and what appears to be a combination of corrugated steel panels (probably Morin or a similar brand), Alucobond aluminum composite trim panels and simulated wood fiber cement boards. These materials have made or are making appearances on other recent builds as well – HOLT Architects, the designers of the new CPS Building, also incorporated corrugated metal and flat aluminum panels into 210 Hancock’s multi-story apartment block. Meanwhile, wood-like fiber cement shingles will be used as one of the finishes on The Lux apartments at 232-236 Dryden Road.

It seems a little strange that the “clips” on which the wall panels will be fastened are wood instead of steel. Perhaps since the exterior finishes are light, waterproof and will be sealed tight, it’s an acceptable choice. The frame for the rooftop mechanical screen is in place, and the flag strings suggest that the roof membrane is being laid. If you look closely enough through the windows, you can see steel interior stud walls and HVAC ducts. Compared to the renders, there only seem to be a few minor differences in materials and appearance (the corrugated metal panels, and maybe the fenestration over by the entrance).

According to HOLT’s project webpage, the $7 million project is aiming for LEED Silver Certification. Here’s the building description from their webpage (which, kudos to the HOLT website manager, because not many architects include their buildings currently underway):

“The new 11,000sf Community Practice Service Building, is a stand-alone veterinary clinic and teaching facility that will provide a real-world veterinary practice to the surrounding community.

The new building design includes a welcoming waiting area, as well as veterinary surgery, imaging, and exam rooms; procedure induction/recovery, and animal holding areas; lab and pharmacy spaces; staff and faculty offices, conference rooms, lockers, restrooms, and other support spaces.

Once complete, this building will be a beacon for pet health and wellness in the community and on campus – with the architecture exemplifying the quality of learning and client service that will happen within its walls.”





Cornell Veterinary School Expansion Construction Update, 1/2018

23 01 2018

At this point, the expansion is done, and the construction at hand is the new $7 million Community Practice Service Building at 107 Farrier Road, where the Poultry Virus Lab once stood. It looks like a waterproof spray coat was applied above the previously-applied water-resistive barrier, based on the overspray on the rough window openings. There are plastic sheets with ribbing up over some of the exterior walls and part of the front entrance – the rendering shows concrete walls with decorative finishes,  so what might be happening is that these are still curing, and the sheets are there to keep precipitation (whatever it may be this time of the year) from penetrating and changing the concrete and water mixing ratio, which can weaken the wall.

The roof equipment (HVAC commercial units) appears to be in place, but the synthetic rubber membrane has yet to be laid. A truck at the rear of the construction site suggests Michael A Ferrauilo Plumbing and Heating of Rochester is one of the subcontractors. They’ll be busy for a while yet; stacks of insulating form board and galvanized metal utility ducts suggest plenty of interior and exterior work still left to be done before the May opening.

Background info on the project can be found here.





Cornell Veterinary School Expansion Construction Update, 11/2017

19 11 2017

The new 12,000 SF Community Practice Service building is fully framed, sheathed in plywood, and appears to be coated in a dark blue water resistive barrier (WRB). Most of the structure is wood frame, with some lightweight structural steel used to frame the canopies over the front and rear entries. Windows have yet to be fitted in the rough openings, and the plastic sheet covers might be for worker protection from the elements as G. M. Crisalli and its subcontractors work on interior rough-ins. HVAC roof equipment is in place, but the sheets on the roof suggest the final material has yet to be applied (perhaps EPDM synthetic rubber or a similar membrane). The front parking lot is already paved and striped, and as shown back in September, the concrete sidewalk has been poured and is nearly complete. Variations in facade materials (flat and corrugated aluminum, wood panels/wood-like fiber cement panels) will help to break up the structure’s bulk as it heads towards completion. The new CPS Building, designed by Ithaca’s HOLT Architects, should be open by May 2018.





Cornell Veterinary School Expansion Construction Update, 9/2017

29 09 2017

After two years of updates, the vet school expansion is practically finished. The exterior finishes are complete, and the Flower-Sprecher library is stocked with bookcases and workstations. Final landscaping and interior finish work appears to be all that is left on the agenda. According to a construction update from the Vet School, the academic spaces officially opened for academic use on September 11th. The exterior landscaping will be finished by October 1st, and offices and labs will be fitted out from now through December. The interior atrium is certainly cavernous and imposing, and it’s a shame the doors were locked during this past weekend’s visit.

The veterinary complex has never been an especially attractive group of structures, and the expansion project, designed by Weiss/Manfredi of New York, manages to add a modern update without being ostentatious. The boost in class sizes will give more students (120 per class, vs the current 102) a chance at Cornell’s quality veterinary education, and the growth provides fringe economic benefits for the Ithaca area as well. The new lecture halls, tutorial and surgery areas will no doubt be put to good use educating students and serving the community at large.

If I want to mark one concerning note, and be the obnoxious discriminating alum at the same time, I could point out that it appears that what was once the #1 vet school in the country is no longer #1 – UC Davis, whose student population is nearly 25% larger, is the new gold standard. So I suppose alumni could take to arguing over where the vet school’s resources would be better used. But, I study puffy clouds and cow farts for a living, and vet school politics is a debate outside this blog’s scope.

While this is the last update for the expansion, the new $7 million, 12,000 SF Community Practice Service Building will continue to use the same tags and headings, since the projects, though separate, have always been included in the same update posts. At this time, general contractor G. M. Crisalli & Associates has completed the foundation and underground utilities, and is erecting the wood framing for the walls of the one-story building. It looks like the front entrance area uses structural steel framing as a canopy. Sections of plywood sheathing are also up, and it looks like they may be planning to use a form of housewrap. A bit surprised they didn’t spring for ZIP panels, but each barrier has its pros and cons.  Some interior stud walls have also been assembled. The front sidewalks have already been poured and the curbing extruded, which seems reasonable as heavy equipment enters and exits from the other side of the construction site. The new CPS Building, designed by local firm HOLT Architects, should be open by May 2018.

Old:

New:





Cornell Veterinary School Expansion Construction Update, 7/2017

25 07 2017

Just clearing out the photo stash – only a small sampling of the photos made it into the Voice round-up. The first set show the new administration and library wing finishing exterior aluminum panel installation, new curbing being laid, and the mostly finished entry and atrium area. The later photos are of the new Community Practice Service building, which is finishing underground utilities routing and foundation work – the new service facility will be one-story and wood-frame, which should allow the structural framing to move quickly.

The new vet school facilities will be open by late August, and the new CPS Building neat spring.





Cornell Veterinary School Expansion Construction Update, 5/2017

24 05 2017

So many projects in the final stretch up on East Hill. The Vet School expansion’s multipurpose atrium is in the process of being closed up with its curtain wall glazing. An interior shot from the start of May shows interior stud walls are up and utilities rough-ins taking place, but drywall, interior trim and fixtures had not been undertaken.The concrete for the “grand staircase” had just been poured.

The atrium will be called “Takoda’s Run“, in honor of a greyhound adopted by alumna Janet Swanson (for whom Cornell’s wildlife rehabilitation center is named). The Swanson family are major university benefactors – Janet, Class of 1963, has given millions of dollars to the Vet School since the mid-2000s. Husband John (BS 1961, B.M.E. 1962, M.M.E. 1963), an engineer and tech executive, has given tens of millions to the university. The atrium in Duffield Hall and a lab suite in Weill are named for him, as well as several endowed professorships, fellowships and scholarships. Not just leaving it to Cornell, the couple has buildings named after them at Washington and Jefferson College in Pennsylvania, and a $41 million donation to the University of Pittsburgh led to the Swanson School of Engineering. My former editor at the Voice is definitely not a fan of this practice, but for those with a lot of money to burn, naming opportunities can be found or scoffed at here.

From the outside, the new administrative and library wing haven’t changed much since March, but at this point all Welliver has left is some window installs, exterior panels and finishes. Since I’m on a kick at the moment, the Flower-Sprecher library is named for former governor Roswell Flower (1892-94) for allocating funding, and in the early 1990s, Dr. Isidor Sprecker ’39 (Americanized from Sprecher) donated a substantial sum for renovation. It looks like some underground utilities work is going on out by the curb, possibly in preparation for the new landscaping and lighting fixtures.

The new Community Practice Service Building is underway, although I don’t have photos – the Poultry Virus Building has been demolished and the site was being cleared and readied for new construction. The timeline for the new 12,000 SF HOLT Architects-designed building is May 2017-May 2018, a couple months later than originally programmed.

The project seems to be a little bit behind schedule. The project team was initially aiming for a June completion, which was a little optimistic. The new schedule calls for an August opening.

 





Cornell Veterinary School Expansion Construction Update, 3/2017

26 03 2017

There’s been quite a bit of progress over at the Vet School. It looks like the exterior glass and aluminum are going on the new library and administrative wing. Windows and sheathing have been installed on the north face as well, with a water-resistive barrier applied over the sheathing. The new atrium is being framed out.

According to the Vet School’s construction update page, interior framing and utilities installations are underway in the new wing, and the new cafeteria is under construction – both are aiming for August completions. The new atrium and lecture hall will be closed off shortly, with interior work to launch in earnest once that occurs.

Thanks to Maria Livingston over at HOLT Architects, readers now know what the new Community Practice Service building will look like. Syracuse’s G. M. Crisalli and Associates Inc. has been selected as general contractor, and construction for the $7 million, 12,000 SF wood-frame structure is expected from March 2017- March 2018.





Cornell Veterinary School Expansion Construction Update, 1/2017

17 01 2017

Starting to see more progress on the structural frame of the $74.1 million Vet School additions. The reinforced concrete frame of the new library and administrative offices now extends all the way back to the rest of the Vet School complex; the new section is draped over with plastic sheets. Also, as the new wing gets fleshed out, the rough openings of the windows are taking shape. It doesn’t look like there’s been too much exterior progress on the new atrium.

According to the project webpage (last updated two weeks ago), interior framing (metal stud walls probably) is underway, rough-ins are underway, and the new cafeteria is under construction. Welliver will have the new atrium and lecture hall fully closed up by the end of January. Most of the Vet Research Tower work has been completed, but new office layouts are still in the works for the sixth and seventh floors, and that work won’t get underway until this Spring.

The new $7 million ($4.9 million hard cost) Community Practice Service Building is out for bid, with a march demo planned for the Poultry Virus Building currently on site, and a March 2018 opening, about seven months after the bulk of the new Vet School structures. It is a wood-frame 12,000 SF building designed by HOLT Architects, and I still have yet to find an image of the design.

20170107_102456 20170107_102508 20170107_102521 20170107_102540 20170107_102615 20170107_102640 20170107_102646 20170107_102708 20170107_102740 20170107_102838 20170107_102846

cad048742a281097e5667382eced42333f5656954f5a3ef1021519c03b4abe9f

20160522_131445 20160522_131417 20160522_131344

20160522_131403





Cornell Veterinary School Expansion Construction Update, 11/2016

23 11 2016

Definitely seeing a lot of progress on the Vet School Expansion. The new glass curtain wall on the Vet Research Tower is nearly complete, and the final finishes are due to wrap up by the end of the month. The new library/dean’s wing by the front entrance is undergoing interior framing and utilities installation. The new atrium and lecture hall are now visible from the street, now that some of the structural steel has been erected. Floor slabs and roof decking are also being laid.

The new atrium and lecture hall are expected to be closed up by January, and the whole $74 million project is aiming for an August 2017 opening. The Community Practice Service Building, a separate $7 million project on the Vet School campus, is expected to start construction in early next year with a completion in late fall 2017.