Cornell Veterinary School Expansion Construction Update, 11/2016

23 11 2016

Definitely seeing a lot of progress on the Vet School Expansion. The new glass curtain wall on the Vet Research Tower is nearly complete, and the final finishes are due to wrap up by the end of the month. The new library/dean’s wing by the front entrance is undergoing interior framing and utilities installation. The new atrium and lecture hall are now visible from the street, now that some of the structural steel has been erected. Floor slabs and roof decking are also being laid.

The new atrium and lecture hall are expected to be closed up by January, and the whole $74 million project is aiming for an August 2017 opening. The Community Practice Service Building, a separate $7 million project on the Vet School campus, is expected to start construction in early next year with a completion in late fall 2017.

20161119_111157 20161119_111208 20161119_111225 20161119_111243 20161119_111252 20161119_111334 20161119_111358 20161119_111436 20161119_111503 20161119_111514 20161119_111632

cad048742a281097e5667382eced42333f5656954f5a3ef1021519c03b4abe9f


Actions

Information

One response

27 11 2016
Cornell PhD

Would that Bradfield Hall got some kind of recladding like this; it reeks of bad SUNY aesthetics and it’s even more conspicuous than this one.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s




%d bloggers like this: