Ithaca Tompkins Regional Airport Construction Update, 5/2019

27 05 2019

U.S. Senator Chuck Schumer dropped by earlier this month to make the formal announcement that the U.S. Department of Transportation had awarded the Ithaca-Tompkins Airport a $9,999,990 grant toward the airport renovation and expansion project. This money was not unexpected, though never a given; along with the $14.4 million New York State grant, the county’s portion of the bill is expected to only be about $260,000 (out of $24.7 million) assuming costs remain stable.

Now underway is Phase 2 of the project, which involves renovation and expansion of the passenger screening checkpoint of the departure lounge and the terminal’s gate area. Gone is the airport entrance canopy, and coming soon are a new concourse for arrivals and departures, and new jet bridges to contribute to the 6 gates that will operate at ITH. (Want more details? Click here). Streeter Associates of Elmira, who built Phase 1, will also be in charge of the buildout of Phase 2. The airport project is expected to be finished before the end of the year.

Oof. Hope you have a jack kit in the trunk.





East Pointe Apartments Construction Update, 5/2019

26 05 2019

Quote: “The first 10-unit apartment strings are ready for occupancy in the 140-unit East Pointe Apartments complex on Bomax Drive in Lansing village. In the typical overwrought, florid language of press releases, Park Grove realty, the developer, states the “East Pointe Apartments offers residents a unique living option away from the compact noisy rentals of downtown Ithaca with comparable prices ranging for $1695 a month for a spacious one-bedroom to just shy of $2,000 a month for a three-bedroom unit,” with “luscious walk-up gardens”, granite counter tops, stainless steel appliances and wall-to-wall carpeted bedrooms with USB outlets.

As the photos make clear, the “luscious walk-up gardens” aren’t a thing just yet, though there were dozens of saplings stacked next to Bomax Drive, waiting to be planted. Rather unusually, the timeline of the project was moved up, from a Spring 2020 completion to a finish by the end of 2019. Glancing around the project site is like a step-by-step walkthrough of the construction process. First comes the excavation and slab foundation pour with underground utilities poking out in various pipes and tubes. Then comes from the wood framing, the felt papering of the roof, and the plywood sheathing and Tyvek wrapping. Next are the roof shingles and insulation, the rough-ins, the vinyl siding and fixtures. Once the trim boards are up and the cabinets, flooring and finishes are in, they’re just about ready for their new renters.”

***

Red boxes overlay townhouse strings that are largely complete from the outside. Green is framed and sheathed (plywood with Tyvek housewrap), but lacks exterior siding, trimboards and architectural details. Blue are townhouse strings where framing is underway. Purple boxes are strings that are undergoing foundation pours and utilities installation. Looking at the site and comparing it to the site plan above, it seems that the community center is actually to the east (right) of the entrance, so there likely going to be two townhouse strings to its left (west), one of which is largely completed and one of which is just a foundation slab at this point.

It appears they’re sticking to just the two color palettes (tan/blue and grey/yellow) and not using the third color combination from the rendering. Although the project states the first units are open for occupancy, it did not appear anyone was living there yet when these photos were taken earlier this month.

Here’s a full copy of the typically puffed-up press release, which appears to quote one of my previous Voice articles:

“Ithaca, New York (March 25, 2019) – East Pointe Apartments, the village of Lansing’s latest property development opens for residence off Bomax Drive in Ithaca, New York. The first apartments are currently available for occupancy.

East Pointe Apartments are in the heart of Lansing, New York – a rural community just North of Ithaca on the shores of Cayuga Lake. The new real estate development will help the historic village gain momentum into the twenty-first century. Rochester, NY developers and property managers, Park Grove Realty hopes to set a standard for luxury living within the community.

With 20 acres and 140 state-of-the-art new construction apartment units the Ithaca Voice rightly reports East Pointe Apartments as, “…one of the largest projects the village of Lansing has seen in many years.”

Lansing’s multi-million dollar property development project will include 42 one-bedroom units, 84 two-bedroom units, and 14 three-bedroom units all nestled within the quaint village of Lansing, New York. East Pointe Apartments offers residents a unique living option away from the compact noisy rentals of downtown Ithaca with comparable prices ranging for $1695 a month for a spacious one-bedroom to just shy of $2000 a month for a three-bedroom unit.

When approaching East Pointe Apartments property development, residents will be greeted by the luscious walk-up gardens upon pulling into their personal attached garage. Each unit includes a private entrance with a choice of oversized patio or deck.

Inside luxuries include a private laundry room with in-unit washer and dryer, granite counter tops wood cabinets and stainless steel appliances in the kitchen, high end electric and plumbing fixtures, and wall-to-wall carpeted bedrooms with USB outlets throughout.

The high-end finishes extend beyond the residences with access to Fiber Optic WiFi throughout the complex, an exclusive dog park, and a luxury community building. The residents will enjoy an in ground pool, fitness center, great room, and kitchen. The community building will also house the leasing office and professional on-site management staff.

DGA Builders, LLC construction will continue to expand the residences throughout 2019 with all 14 buildings scheduled to be completed by the end of the year.

Park Grove Realty has over 35 years of real estate experience in property development, property management, and consulting. Their focus on long-term value and community-centric actions have earned them Western New York’s Landmark Society Award of Merit. They continue to broaden their portfolio in 2019 with upcoming developments all over the Northeast.”

 





Village Solars Construction Update 5/2019

25 05 2019

From the Voice, with light editing:

“Quietly plodding along off the 1000 Block of Warren Road, Lifestyle Properties’ Village Solars Apartments continues its steady buildout. This is one of the largest projects in Tompkins County, with 277 apartments approved, with potentially more in the works on the adjacent property to the east. So why doesn’t it get much attention? They build a couple of apartment buildings each year, they don’t have tax abatements or any high-profile review process because they were approved by the town as a Planned Development Area (flexible “D-I-Y” zoning), and they’re in a less-trafficked part of the county north of the airport. They’re low profile, physically and programmatically.

Under construction right now are Buildings “K” (113 Village Circle) and “L” (40 Village Place), which make the 11th and 12th buildings to have been built in the past five years. The 24-unit Building “K” is mostly complete from the outside, and likely to open for occupancy later this spring, adding another 3 three-bedrooms, 6 two-bedrooms, 3 one-bedrooms and 12 studios to the market. 24-unit Building “L”, just to its east, isn’t as far along. It’s framed, sheathed and has had its windows and doors fitted, but the fiber cement siding is only partially finished, and exposed interior stud walls are visible through the windows. If you’re wondering what the rat’s nest of white cables are, those are connections for the air-source electric heat pumps – the units are installed towards the bottom, and the cables are framed in by a bump-out for aesthetic purposes.

The latest two buildings are being funded courtesy of a $5.6 million construction loan extended by Elmira Savings Bank. According to the loan filing, both buildings are expected to be completed and ready for their first tenants by the end of September. But more realistically, given that the local rental market revolves around the academic cycle and that some graduate and professional students make their homes here, expect the new apartments to be ready for occupancy no later than mid-August.”

***

I must have missed the part when “Equinox Way”, the new through road was named. Still waiting a construction start on Building “F”, as seen below the site is just grass at the moment. Offhand, Lifestyle Properties can start one more building before they have to build the mixed-use community building, and regardless, the community center must be complete by the end of 2020.

The timeline and plans for each phase is out of whack because the redevelopment of the existing apartment 1970s buildings was expected before new sites were to get underway. I’d venture a guess the 2019-2020 phase would be 18-unit Building “M” and the Community Center, for an August 2020 completion.

Giving credit where credit is due – the in-house construction crew is moving fast with these. Building “L” hardly had its site cleared and wood foundation forms in back in February. Years of practice pays off, perhaps. Interior walls and insulation is in, but drywall has yet to be hung, so completion is still a couple of months away.





Milton Meadows Construction Update, 5/2019

25 05 2019

From the Voice:

At the site of the future Lansing Town Center, the Milton Meadows affordable housing apartment complex is well underway. Cornerstone Development Group of Rochester is developing the 72-unit, $17.3 million project, which consists of 10 buildings, nine eight-unit apartment buildings, and a community center. The project is being built by Taylor the Builders and was designed by SWBR Architects, both of Rochester.

Gross rents (rent plus utilities) will range from $680 to $1,400 a month, with 64 units for households with incomes 50 to 80 percent of the area median income ($29,500-$47,200/year for a single person, $33,700-$53,900 for a two-person household). The remaining seven units are expected to rent at market rate, with the final one reserved for the live-in property manager. Along with military service veterans’ preference (first dibs) on all available units, five apartments will be set aside for service veterans with physical disabilities. More specifically, expected rent ranges are $680 to $750 for one bedroom units, $835 to $850 for two bedroom apartments, and about $950 to $1,100 for three bedrooms. Market rate units will max out at about $1,400 for a three bedroom unit.

Construction on the property launched last November and is moving along at a fast pace. The community center building is framed, sheathed and has been faced with siding and white trim boards. Two of the apartment buildings are framed and sheathed with windows fitted and Tyvek wrapped, two more buildings are being framed, and foundation work was underway on at least one more building. The unfinished Louise Bement Lane is the only road close to the project site and offers just a limited line of sight, so more apartment buildings could be undergoing excavation or foundation pours.

Cornerstone and Taylor have deployed this design in other towns, so they have a familiarity with it, and that allows for a more efficient deployment of labor, a quicker construction timeline, and a higher fit and finish because they know the design’s quirks and where they’ve had issues in the past. Expect the apartments to start hitting the market this summer, and for completion of the project before the end of the year.

***

Perhaps to add a little more, the building in the foreground with the blue water-resistive barrier is all one-bedrooms, and the one to its north is all two-bedrooms. There are three separate building layouts, one with 8 one-bedroom units, one with 8 two-bedroom units, and one with 8 three-bedroom units (the first of which is being framed to the west/middle of photo four). There will be three of each design here, and you can see what the finished examples look like at the webpage for the practically-identical Frances Apartments in the town of Sweden here.

Note that Woodsedge Drive has yet to be realigned to make a proper four-way intersection with Louise Bement Lane. It’s on the to-do list for this summer. I do not know what the grid of embedded steel pipes on the roadway is used for, as the site plan doesn’t indicate anything unusual here. Maybe it’s where underground utilities diverge from Bement Lane and into the project site.

More information about the Milton Meadows project, including site plan details and project history can be found here.





105 Dearborn Place Construction Update, 5/2019

24 05 2019

We’ll change up the format a bit for this post. Below is a recent email from Ithaca resident Joan Jacobs Brumberg:

I had an opportunity to talk yesterday with Elizabeth Classen Ambrose who is the organizational power behind a growing Bridges community. I wanted to find out more about Library Place interiors but we ended up spending a fascinating hour talking about The Craftsman, a new kind of Ithaca residence for the elderly resembling the group homes in Holland and Denmark.

Four things about this project — to be completed in November 2019– strike me as important for the public to know:
1. This is a new form of independent living for 16 older folks who do not want home or apartment to care for. Each individual room is lovely with private bath and fireplace, small refrigerator. I believe you bring your own furnishings, ie.,  the things you care about most.
2. No upfront payment and no lease.
3. Residents have access to special Car Share vehicles and also Bridges shuttle service if they do not drive.
4. Many amenities for the elderly: warming pool, gym, a trainer, maybe podiatrist and physical therapy. And a special add on: garden space.

I told some people my age about this facility and everyone asked “How did you learn about it?” Even if they are candidates for Library Place, my friends have older parents, relatives, and friends who are burdened with private homes or apartments that are increasingly hard to care for.

***

It came as part of an article pitch for the Voice, but since I did an article about Bridges for the Voice two years ago, I declined. The website for the new house is online, with plenty of rather sumptuous interior renders (a few embeds are below many more are on the website). The twelve bedrooms (eight single-occupancy, four double-occupancy for couples) will feature heated floors, fireplaces in some units, large-screen televisions, optional dry bar with refrigerator and hot beverage maker, and private deck or patio areas. Other planned features include an on-site fitness center, storage room, car share, spa and salon services, on-site concierge, and lush landscaping befitting a high-end independent living facility. Residents are expected to be able to go about their daily activities with little to no assistance, but cooking, cleaning and laundry are taken care of by staff. Pending “interviews” by staff for compatibility, residents may even be allowed to have their pets join them.

Schickel Construction has the house largely finished from the outside. Painting of the cedar shingles continues, and architectural detailing/trim (balconies, porch columns) is ongoing. The stone veneer has yet to be attached to the built-out cinder block basement level, but all of the windows and most of the doors have been fitted. No photos of the back side, because there was a kitchen staffer on break who was clearly uncomfortable with this shutterbug.

More background info about the project can be found here.

 





310 West State Street Construction Update, 3/2019

28 03 2019

For lovers of old houses, the 1880 Queen Anne-style house at 310 West State Street, dubbed “The Tibbetts-Rumsey House”, is being renovated into a co-op for young professionals, with $500,000 of help from the state’s RESTORE NY grant fund. The plan is to restore the house into an eight-bedroom co-op style living space, with a new modular six-bedroom co-op unit in the rear of the property. The two co-ops are separate.

The money generated by the new carriage house/rear co-op helps to pay for the expensive renovations needed for the existing home, which was in a poor condition due to previous ownership (the Salvation Army). It’s not as architecturally unique as the carriage house that was condemned and torn down several years prior to this project, but it does reuse a couple of design elements. The previous had an irregular shape, brick finish and mansard roof; the replacement will have a rectangular footprint with Hardie Board (fiber cement) siding and a gable roof, similar to barns from the late 1800s time period it is taking its cues from. The project also comes with new landscaping, fencing and eventually, 36 solar panels on the new build’s roof.

The 3,800 SF residence was designed by local architect Alvah B. Wood and built by contractor John Snaith (of Snaith House) in 1880. Wood, a Cornell classmate of the more famous architect William Henry Miller, designed a number of prominent local structures, including the old Ithaca town hall at 126 East Seneca Street (built 1881, demo’d 2003, now the site of Tompkins Financial’s brand new HQ), the Immaculate Conception Church (1896) and the railroad/bus depot at 701 West State Street (1898). Union Army Captain J. Warren Tibbetts and his family were the first residents of the home. It was sold to the Rumsey family in 1885, and they owned it until 1966. The developers are Dr. David Halpert and his wife Teresa Halpert Deschanes. Prior to this project, failed renovation plans included a rental property and a drug addiction treatment facility (long term plans had included the potential for a “safe injection” facility, but the purchase deal fell through and the Halperts swooped in shortly thereafter).

From the Trulia Ad:

310 W. State St.

Bugbee’s Place: Why live alone for when you could come home to friendly faces for $? If you are willing to share you bathroom with one other person, you could live in a high-style 1880 gem, gut-renovated from 2017-2019. All new plumbing, electricity, insulation, storm windows, sprinklers, heating/AC. Fossil-fuel free, ductless mini-splits, refinished floors and walls; all new kitchen and bathrooms.

Alvah Bugbee Wood was a prominent architect who designed churches, railroad stations, schools, and factories. (See his photo in Ithaca City Hall, as a member of the very first Common Council.) Early in his career, before he was sought out for commercial jobs, AB designed a few large wooden houses for wealthy Ithacans. This is one of the few remaining, and is now listed on the National Register of Historic Places.

Eight bedrooms (ranging in size from medium to huge; plenty of room for queen beds, desks, dressers, bookcases, nightstands; large closets or multiple armoires. Giant Victorian windows with custom interior storms and velvet blackout curtains. Your own individually-controlled almost-silent ductless AC/heating unit. Share your bathroom with one other (individual medicine cabinets; 38″ shower; plenty of linen space. Plenty of storage in the attic.

Common areas include living room with original fireplace, communal-sized dining room, multi-room Victorian kitchen suite (walk-in pantry, butler’s pantry, separate scullery with dishwasher and two sinks; butcher-block chopping station). Gourmet appliances include induction range with 5-cu-ft self-cleaning convection oven, 50 cu ft of refrigerator space, etc. Laundry room with Electrolux front loaders. Original and vintage hardware, deco tiles, and retro color palette throughout.

Fenced-in private yard for your doggies, with patio and raised-bed planters so you can grow stuff. Share the yard with another co-op in the new cottage at the back of the lot. Limited parking.



OLD





Library Place (Old Library Redevelopment) Construction Update, 3/2019

27 03 2019

Not a whole lot to say at the moment – everything above surface level on the site has been cleared as of the end of February, and grading/leveling is taking place. Part of the existing 1960s foundation will be reused for underground parking, and part of it will be taken out. According to the project team, an examination of the existing foundation column footers vs. the blueprints found that eight of the column footers were not where indicated on the as-built drawings. That created a conflict with portions of the new structure, ans so these column footers are being removed (probably by the demolition subcontractor, Gorick Construction of Binghamton; LeChase is the general contractor overseeing the whole project).

It might seem weird, but this isn’t the first time something like this has happened. Half the footers were missing outright at Ed Cope’s Ithaca Glass site, which led to a total overhaul of the project plans (now held by Visum, although I haven’t heard anything about the plan since the transfer was announced in November).

It’s a bit unusual since the project is already underway (or at least, the site prep is), but Library Place has yet to receive approval for a tax abatement. The Tompkins County Industrial Development Authority (IDA) will be receiving the tax abatement application in early April and the board will get their first glance at it on April 10th. A public hearing on the abatement will be held sometime before the May 8th IDA meeting. Assuming the application is approved at the May 8th meeting, pile driving would start within a few days of approval.





Tompkins Center for History and Culture Renovation Update, 3/2019

25 03 2019

The Tompkins Center for History and Culture is on track to open in a few weeks. I have not seen a specific date, but it will be sometime in April.

I stopped by to take a few quick photos, when The History Center’s Executive Director (and candidate for town of Ithaca supervisor) Rod Howe opened the door and asked if I wanted a tour. Unfortunately, it was not going to work with my schedule that day. Luckily, a sneak peak of the interior can be found on the TCHC’s Facebook page.

***

Throwback time. This photo comes courtesy of Terry Harbin. This was once the 100 Block of North Tioga (across the street from the TCHC. The Blood Building, 109-113 North Tioga, was built in 1870 and also known as the Old Masonic Block.

This photo appears to come from the mid 1960s. For one, the Cornell library to the north (left) has been demolished, and that happened in 1960. For two, the car in the foreground is a 1963 Plymouth Fury, which had a unique slantback front end (growing up in a family of mechanics had to come in handy for something). The car behind it is a 1963 Chevrolet, since most Chevy models upgraded to three tail lights on each side for 1964, and that body style was ’62-’64 only. The truck, eh, not so good with, I don’t remember so many of those in my family’s shops. It’s a Chevy in the same mid 1960s time frame.

Even in Ithaca’s salty winters, the cars probably outlived the building. It would come down in 1966 and, several years later, be replaced by the new Bank Tower addition, which was built from 1974-75. The little third-floor addition on top of that came along in the early 1980s. You can still its outline on Bank Tower’s north face.

Also, note the building that once stood where the Seneca Garage is. It was a last ditch effort to revive downtown, but Urban Renewal removed a lot of tired but attractive buildings that Ithaca and many other communities are trying to recreate (in form if not necessarily style) today.





Harold’s Square Construction Update, 3/2019

24 03 2019

It seems we can move this one back into the under construction column? It’s been a weird few months.

The developers, L Enterprises (David Lubin) and Mcguire Development of Buffalo, parted way with Taylor the Builders, the construction manager, back in January. They were able to line up another construction manager in LeChase Construction of Rochester, which has done its fair share of work around Ithaca and Tompkins County. Issues with transferring control and insurance paperwork of the 300-ton crane, however, delayed the project’s construction by several weeks, but the project did finally resume in early March.

I can tell you that whole “craziness”, as project rep Vicki Taylor Brous put it, gave a lot of city staff and elected officials heartburn. Given the city’s recent policy of advocating for density and downtown development, a hulking, stalled steel skeleton was the type of thing that was going to really make any future project a difficult sell.

It was also very upsetting for neighboring business owners. The project has already created some frustration with its blockading of the Commons playground out of safety concerns. The construction, and lack thereof, created an unattractive nuisance, with people steering away from neighboring businesses and taking their money elsewhere. The abatement was shifted forward a year, but not without significant blowback from members of the general public who had taken the opportunity to air their grievances with the development team. The current plan is to have the office and retail space available for occupancy by the end of the year, with housing occupancy by spring 2020.

At the crux of the issue are claims by Taylor that the project had undergone significant changes and that Taylor wanted to be compensated for the late changes. Although downplayed at the time, it became clear in the months since that there were major programmatic and minor aesthetic changes. The programmatic change was the reduction of 30 micro units (for a new total of 78) to make way for an additional 10,000 SF of office space for an unspecified tech tenant, as mentioned in the revised IDA application. (For those curious, the rumor mill says it’s a growing local tech firm; 10,000 SF is about the right size for a 40-50 person operation). Most of its commercial spaces appear to still be on the market.

There have also been some substantial if overall minor aesthetic changes, partially as a result of transitioning some residential space back to commercial offices. Some of the metal panels are being replaced with a terra cotta exterior finish, elimination of a mechanical screen because the equipment was smaller than first anticipated, the addition of balconies on the corners, the elimination of two windows per floor on the south face in order to comply with International/NYS Building Code, and window revisions on the fifth floor for the new tenant.

The renderings at the end of this post were published in 2018. The designs are for the revisions that were reviewed by the planning board last month, with the exception of the fifth floor office tenants and changes to suit them. The only reasons I can come up for waiting to submit these changes, was that either they didn’t have to (as mentioned before, after approval, the circumstances required for re-approval are rather murky), or that they weren’t sure what was going to happen with the fifth floor and wanted to have all their revisions in one package to avoid further trips to the board. It’s not clear when they began negotiating with the tech tenant, and when Taylor started to have issues working with the developers.

Anyway, work has recommenced on the steel structure, as the eighth floor is built out. Since the upper floors have small floorplates, the building’s steel structure will likely top out before the start of summer. From there, it’s fireproofing, sprinkler systems, exterior and interior wall framing, rough-ins, sheathing, and all the fun stuff that makes a building begin to look like its final product.





City Centre Construction Update, 3/2019

24 03 2019

All of City Centre’s retail occupants have been identified – The Ale House, Collegetown Bagels and Chase Bank. Although two of three are cannibalizing other Downtown locations, the move comes with some benefits – it’s an expansion for CTB and the Ale House, and the Ale House is expecting to add 20 jobs, and CTB will likely add a few new positions as well. Chase is totally new, and if the average bank branch is 2,000 SF and 6.5 staff, it seems safe to assume that a 5,357 SF branch/regional office is probably 12-15 staff. Ithaca’s own HOLT Architects is engaged in some minor building design work and Whitham Planning and Design is doing the landscaping (including the heat lamps, string lighting and fire pits), Saxton Sign Corporation of Auburn will make the signage, Trade Design Build of Ithaca and TPG Architecture of New York will flesh out the interiors, and East Hill’s Sedgwick Business Interiors will provide furnishings. Clicking here will allow you to scroll through the interior layouts for the retail spaces.

A glance at their Instagram suggests that as of a week ago, about 100 of the 192 apartment units have been reserved. There don’t appear to be any particular trends in the unit selection, an off-the-cuff suggests a similar occupancy rate for studios, one-bedroom and two-bedrooms, and there’s no strong preference in floors, though perhaps there’s a slight preference towards interior-facing units (I wouldn’t call it statistically significant). It appears they’re filling at a good clip now that graduate and professional students are making their commitments to Cornell (professional students, for example business/MBA and law/JD students, tend to be older and wealthier, and are one of the target markets for the project). If trends continue, the project will be in good shape for its June opening, with full retail occupancy and high residential occupancy, even at City Centre’s decidedly upmarket prices.

On the exterior, some of the Overly and Larson ACM metal panels have yet to be installed (mostly on the back./interior side), trim and exterior details are partially in place, and the ground level is still being built out with commercial doors and utility fixtures (garage doors for commercial deliveries, for example). The roof membrane doesn’t appear to be in place yet either. Overall, though, the exterior is substantially complete, and it looks like the will finish out over the next several weeks on schedule, which is a pretty big deal for a 218,000 SF $53 million project. Kudos to Purcell Construction and their subcontractors on that. Signage and landscaping will also go in this spring. I’m not big on the patterning of the metal panels (which looks like design by MS Paint), but it seems to be the go-to exterior material of choice.

Background information and the history of the project can be found here.