News Tidbits 4/15/17: Good and Bad Decisions

15 04 2017

1. It looks like the Lansing Meadows issue is being resolved. Village mayor Don Hartill has issued a sort of mea culpa for not sending the project to the Planning Board before inviting it to the Village board of Trustees, saying the Planning Board was caught off guard and it was his and the village attorney’s fault. So the project will visit the Planning Board with Hartill and developer Eric Gortzmann on hand to answer any questions the planning board might have. A workable solution is possible – the planning board isn’t necessarily opposed, they would prefer more housing but could be willing to hear out a commercial component so long as it’s set back from the road and screened from the homes by foliage. Optimistically, the cafe/diner and twenty senior housing units might be good to go within a month.

2. The Biggs Parcel is up in the air. There have been no offers since going on sale last July, and the contract with realtor CJ DelVecchio has expired. The county has decided not to renew while they weigh options. Options being weighed for the three-month hold include a smaller housing development on eight of the acres on the corner of Indian Creek and Harris B Dates Drive, and/or a solar farm, which may split neighbors between a low-intensity, eco-friendly project, and losing a portion of the woods so that the solar panels could operate. There is no plan for another Cayuga Trails-type project like what NRP proposed before the discovery of more extensive wetlands convinced them to cancell the project in September 2014.

3. The town of Ithaca has selected its firm of choice to conduct the economic development study and strategic plan for its Inlet Valey corridor southwest of the cityConsultEcon, Inc. of Cambridge, in partnership with Behan Planning and Design of Saratoga, was selected from six applications. Behan has previous experience in the area; in fact, they won an award for their work on the 2012 Varna Master Plan over in Dryden. The town will pay $30,000, and the state will pay $30,000 through its Empire State Development division. Although not state in the town agenda, I believe the time frame to perform and submit the study is six months.

According to Ithaca town’s 2014 Comprehensive Plan, the goal is to turn Inlet Valley from an auto-centric hodge-podge with no overarching character, to a semi-rural neighborhood with an agribusiness, “artisanal industrial”, and tourism focus, capitalizing on Ithaca Beer and the existing and proposed lodging. The Sleep Inn proposal submitted a potential rustic streetscape that gives an idea of the aesthetic the town seems to be going for.

4. From the PEDC, the Southside housing plan is ongoing, and the IURA has hired their new planner after Lynn Truame left for INHS. There was considerable discussion over the Waterfront rezoning, with general conceptual support, although the First Ward councilors are not fans of mixing housing with light industrial areas, or forcing businesses to compete with housing developers for waterfront sites. Councilwoman Brock (D-1st) was opposed to housing in the Cherry Street Corridor. The proposal was granted by vote the permission to circulate for review and comment, so there’s still time for thoughts and opinions to be contemplated and discussed.

5. On another note, many of the speakers at the PEDC meeting were there to speak out against the City Centre project at 301 East State Street, not because they didn’t like the building (well, most of them), but because it didn’t have affordable units, which they felt should be a requirement for abatements.

I support that to a degree, but I’m also aware that, all other things equal, the revenue loss from the affordable units has to be made up for somewhere, usually by passing the costs on to the other tenants. In that case, the city ends up with a lack of units for those with middle incomes. I like the idea of modestly more generous zoning as a tradeoff to the inclusionary housing component, but as a proposal, that didn’t go over so well – developers didn’t like it (because to build more they need bigger loans, so it hurts smaller developers), anti-development folks didn’t like it (because affordable or not, it’s more of what they don’t like), and there was significant uncertainty on whether it’d be effective.

The county IDA had its vote for the sales/mortgage/property tax abatements the following day, and they decided to grant the abatements 5-1, with legislator Will Burbank opposed. The 192-unit mixed-use project is expected to begin construction with the next couple of months, for an early 2019 completion.

6. Once in a while, you get a project so despised by neighbors, they decide to run for office as single-issue candidates – namely, to stop the project. That’s what happening in Lansing village. Mayor Donald Hartill and two incumbent trustees, Ronny Hardaway and Patricia O’Rourke, are being challenged in the May election by mayoral candidate Lisa Bonniwell and two trustee candidates, Gregory Eells and John LaVine. Their goal is to overturn the rezoning of the Park Grove property on Bomax Drive, which rezoned commercial/tech office space to multi-family, enabling a 140-unit apartment project to move forward with planning board review.

This is not the first time something like this has happened in Lansing. When the Lansing Reserve affordable housing project was proposed in 2011, two residents opposed to the project, Yasamin Miller and Brian Goodell, ran against incumbent trustees on a single-issue platform of stopping the project. They lost by 2:1 margins, but Lansing Reserve never moved forward, and since then the land has been bought by the village for park space.

Although in a Voice capacity I can’t formally take sides, I have big issues with the challenger’s platform. I’m not a big fan of the Park Grove as a project, but the rezoning makes sense. As the county’s airport business park study demonstrated, the demand for new commercial and industrial space is very limited, while from the Denter study, it is clear the demand for housing is quite strong (5,000 units in the next decade). It amazes me that the challengers are saying the project will lower property values in a village with substantial price appreciation and major affordability issues (but as noted by the Star, Bonniwell’s family developed the expensive and still incomplete Heights of Lansing project nearby, so she has a vested interest in limiting housing).

Not only that, in the interview with the Lansing Star, challenger LaVine suggests the village should look at eventually merging with the town of Lansing, which is completely contrary to the village’s formation in 1974 as a reaction to the mall, when residents demanded for stricter zoning that the town didn’t want to accommodate. The town has much looser zoning than the village. If voters think for one moment that the town wouldn’t seek to change zoning in the village to build up the tax base and cope with the likely loss of the power plant, they’re in for a rude surprise.

7. On the agendas, nothing too exciting this week. The town has a couple of telecom towers and a 600,000 gallon water tank for Hungerford Hill Road. Over in the city, it’s project review week, but zoning variances suggest another nicely-detailed garage from STREAM Collaborative (STREAM does really nice garages), a couple of home additions, and a new 1,695 SF house at 412 Worth Street in Belle Sherman designed by Jason Demarest. The property is a flag lot that straddles the city-town line, so it would be neigh impossible to do anything without a variance. Ulysses will just be discussing zoning, and the other towns and village will be doing their regular meetings later in the month.

 





News Tidbits 4/8/17: Please Don’t Document-Dump on Fridays

8 04 2017

1. Let’s start off with some bad news. The town of Dryden planning board did not take too kindly to the Evergreen Townhouses proposal at 1061 Dryden Road outside Varna. The board denied recommendation for approval unless some stipulations are met first; some might be easier, like a vegetative buffer with the neighbors and a shared driveway. Others will be trickier – the board recommended removing all the solar panels and replacing them with electric heat pumps, and board members strongly encouraged reducing the number of units.

Not to downplay the value of heat pumps since they’ve become the preferred sustainable feature for projects going before local boards these days, but there is a substantial initial cost involved for their installation, and it takes a few decades for the energy savings to pay off. Some of the cost for the pumps can be balanced out through density of units, because some flat development costs (for example, the cost of land acquisition) can be distributed out; but fewer units with a more expensive feature is the classic “do more with less money” conundrum.

Let’s take a look at some numbers. Disclaimer, these are ballpark figures and every project has its nuances or other factors to consider, like tax rates, contractor bids and logistical costs.

The Village Solars heat pumps are a $50,000-$60,000 cost, $4,000-$5,000 per unit. Phase 1 didn’t have the heat pumps, but the later phases do, and those later phases are about $2 million-$3 million per 15,000-20,000 square-foot building, with 12-22 units depending on configuration. In the case of 1061 Dryden, each 6-unit string is about 10,800 SF (1800 SF per unit, no common areas), and given the $4.5 million total cost, we’re talking a ballpark estimate of around $750,000 per townhome string. If one assumes proportional costs for the heat pumps based off square footage, that’s $30,000-$40,000 per 6-unit string. So it is a higher incremental cost per string, and more of a burden per tenant. The Village Solars rent for $1600-$1650 for a three-bedroom, and the going rate for new units in Varna is about $1950 for a 3-bedroom, if the new townhomes at 902 Dryden is any indicator. The rent increase for the Village Solars was about $50/unit, but those units are smaller, so you’re probably looking at a larger amount, conservatively $75/unit, for the Evergreen units.

Going off those numbers, it looks like heat pumps are possible, although the units will likely be somewhat less affordable as a result. It isn’t clear if that disables the proposal, because it depends on imputed vacancy rates at different income levels, and whatever the required income is to make the necessary Return on Investment. However, the project would become less feasible if there are substantially fewer units and the construction cost per unit shoots up – because of the combination of flat vs. incremental expenses, taking away six units won’t drop the cost $750,000, it’ll be less. The cost of the solar panels is also an unknown, as are the costs of doing these revisions to please the board. The development team was not at the meeting, which is unfortunate; we’ll have to wait and see how this moves forward.

2. Speaking of the Village Solars, according to the latest minutes from the Lansing Town Board, Lifestyle Properties is exploring taking down some of the old Village Circle Apartments, and replacing them with new buildings. These older, 8,000-12,000 SF structures date from the early 1970s through the early 1980s, and have 8-10 units per building. Since the newer buildings are about 15,000-20,000 SF and tend to have 18-22 units, that could explain where the 423 units statistic came from last month – some of it comes from buildings on new sites, some are replacement buildings for existing structures.

3. The city Common Council held their monthly meeting, and signed off on the IURA sale of 402 South Cayuga to Habitat for Humanity with little debate, and while the TM-PUD for 323 Taughannock was a bit problematic due to some confusion with the minutes from the public hearing, the approval was carried unanimously. The project is now free to go before the Planning Board for State/City Envrionmental Quality Review, and the Design Review is considered complete.

Side note, the city’s four fire stations were renumbered. The old numbers hailed from the days before the stations consolidated in the 1960s and 1980s, and were confusing for many. Fire Station No. 9 (309 College Avenue in Collegetown) is now No. 2, insert joke here. Central Station (310 West Green Street) becomes Station 1- Central, Station 5 (965 Danby Road) becomes Station 3- South Hill, and Station 6 (1240 Trumansburg Road) becomes Station 4- West Hill.

4. Bucket list objective achieved – an interview with Jagat Sharma. Some will be in the Voice, maybe Friday afternoon of Monday morning; but rather than leave the excess on the proverbial cutting room floor, here were some portions left out of the piece for the sake of brevity, or because they’re too technical for the general audience:

Q: So, what’s your thought process when designing a building? Apart from necessities like zoning and client requirements, do you take cue from surrounding buildings, the environment…what are you thinking about as you sketch the first concepts of a new building?

JS: For infill projects, the sites are very narrow. My project at 409 Eddy, if I recall correctly, is a very narrow site. My clients had never hired an architect before, and it was a challenge to convince them. Most of them, they think how many rooms they can rent, so you give them a number, and you work it out, and you figure out the design from the surrounding context, how the buildings line up, how the window patterns line up, symmetry, scale. You lay out a plan for how the windows would fall, how would it match with the existing window lines on surrounding buildings. Frankly, back then (409 Eddy was built in the mid-1980s) there was not much context, many buildings were in poor condition, you had some brick buildings, but otherwise not much. You try to relate it to what you’ve done before, the streetscape, you try to change up things with color, bay windows, you play with that, organize everything in a symmetrical way. Later on, my later buildings in the past 10-12 years, I’ve begun to take more liberty, play with them [the designs] more, 3-D effects, projections, penthouses, balconies, corner windows and more glass. And at the street level, they’re more urban, they have colonnades, like 309 Eddy, it looks very nice. But all of them…if you’re the only actor on the stage, you’re playing your own thing. If you look at Collegetown, Eddy Street and up, 309, 303, 301, some are angled, they’re different materials – if you’re in the middle of those, you feel like you’re in a hill town, it’s a good feeling.

Q: And how would you describe your experience with working with the city and its various interests?

JS: You earn respect from them by being honest and sincere. I deliver what I say I do, we don’t change things at the last minute. The city is happy with that. I have a good relationship with the Planning Board, what they are looking for, they want good materials, detailing. The building department wants to make sure you meet the codes; we sit down and meet if we have different interpretations on how the code reads – but you have to work on it from day one. It takes time, building inspectors, commissioners come and go and you have to earn their respect each time by doing the right thing, don’t hide anything.

5. According to Matt Butler over at the Times, Lakeview Ithaca might be a little larger than initially anticipated. In a report on homelessness, he mentions a meeting attended by Lakeview’s CEO, who said the new building would have 56 affordable units (vs. the 50 previously reported in the IURA application), with 28 reserved for those with mental disability. A time frame of fall 2018 – fall 2019 is given for construction, somewhat slower than the April 2018 start reported in the IURA application.

6. A couple of interesting things to note from the ILPC Agenda for next Tuesday, apart from the usual stairs, porches and windows. One, 123 Eddy got a revamp in accordance with the commission’s design guidance – gone is the porch, and more detail was strongly encouraged. I still prefer the previously-approved design, but this is an improvement from the Craigslist ad.

Meanwhile, downstate businessman Fei Qi is finally heading back to the board with a plan for the historically significant but structurally deficient 310 West State/MLK Street. Previously, he wanted to do 3,800 SF of office space in a renovation partially financed by state tax credits, but it wasn’t funded and the office market is a bit lackluster in Ithaca anyway. At the time, residential was ruled out due to fire safety issues.

However, this new plan is a residential project. It’s a proposed 12-bedroom “co-op” living arrangement (Co-op? SRO [Single Room Occupancy]? Neither one is a terrible idea, although SROs have negative connotations). JSC Architects of suburban NYC (Fresh Meadows) would remove a rear chimney, put in new shingles, add a wheelchair ramp and skylights, along with the to-the-studs internal renovation. It’s an interesting plan, though the ILPC might be iffy on some of the details. We’ll see how it goes over.

7. If you all could pardon me on this, the city document-dumped Friday morning, and I don’t have the time at the moment for a full write-up. But the projects memo is one of the busiest I’ve ever seen. Here’s the brief summary:

A. McDonald’s would replace their existing 4,800 SF restaurant at 372 Elmira Road with a new 4,400 SF building.

B. Benderson Development wishes to renew approvals for a 14,744 SF addition to their shopping plaza at 744 South Meadow Street (this would be on the south end next to Hobby Lobby, where KMart’s garden center was years ago), and build a new 7,313 SF addition at the north end of the strip. Apparently, Ithaca’s a safe harbor in the ongoing “retail apocalypse”.

C. 323 Taughannock as noted above

D. DeWitt House is moving forward. With ILPC Design Approval (Certificate of Appropriateness) in hand, envrionmental review still needs to be conducted. Site plan review docs note it’s a $17 million project with a December 2017 – March 2019 construction timeframe.

E. Novarr/Proujansky’s 24-unit 238 Linden apartment project

F. 118 College Avenue, carried over from the previous month, and

G. Finger Lakes Re-Use, carried over from the previous month.

 

 





News Tidbits 4/1/17: High Energy Debates

1 04 2017

1. There might be yet another potential hang-up with the Lansing Meadows project. Previously, developer Eric Goetzmann presented planned to the Lansing village Board of Trustees to densify the initial 12-unit plan and add a small retail component, such as a coffee shop, diner or similar gathering venue. The idea was well received, and so Goetzmann approached the planning board with 20 senior housing units and a small commercial lot TBD, where it was A) news to them, and B) not-so-well received.

According to the Lansing Star, the objection is not to the housing; in fact, the planning board said they’d prefer another four housing units rather than commercial. But they’re not comfortable with the sudden change, and Goetzmann’s looking at the additional costs of revised plans because the Board of Trustees and the Planning Board were not on the same page. It is kind of a weird situation, although not unprecedented (it bears some similarity to the 201 College debate in Ithaca city last year, where the Planning Department and Planning Board were not on the same page). The boards are supposed to meet in early April to retify their differences so Goetzmann knows what he can move forward with, hopefully by this summer.

Looking at the screenshot above, Salem R. LaHood of suburban Syracuse is the architect; apart from being a design partner for some high-end outlet malls, I can’t find much else on his resume.

2. The solar arrays planned in Dryden are getting are less-than-welcome reception, per Cassandra Negley at the Ithaca Times. The argument is pretty similar to the one often used on affordable housing – “we know it’s needed and we like it in concept, but we don’t want it anywhere near us”. But then far from one person is close to another; and it results in lackluster solutions, like affordable housing so far out that it’s isolated from needed goods and services.

One of the biggest sources of opposition is from family and friends of those interred at the Willow Glen Cemetery, which is the landscaped area south of the panels in the image above. Although many of the opposed do not even live in New York, let alone Dryden, it’s argued that the project is “sneaky back-room industrial solar” and will “destroy the atmosphere” (coincidentally, the land across the road from Willow Glen is zoned for and being marketed to roadside commercial tenants). It’s fine to be concerned, but looking at this particular site, the anger is a little overblown – there is sufficient room for a green screen of hedges and trees between the panels and the cemetery, which could easily be included as a stipulation as part of the approvals. Sustainable Tompkins is attempting to push back against some of the criticism, but on the balance, the public comment on the Dryden solar arrays is negative.

Let me approach this with an overarching view. Dryden is strongly opposed to an increase in natural gas (much to Lansing’s chagrin). Wind energy has been vociferously opposed just over the valley in Enfield, and Newfield essentially outlawed wind turbines. Solar panels are also being fought in Ulysses and Newfield. In Ithaca, there have been onerous battles over allowing panels on rooftops in historic districts. The energy to power homes and businesses has to come from somewhere; the preference seems to be for a sustainable option, rather than oil or gas piped in from Pennsylvania or beyond. Every choice is going to have its pros and cons – gas is cheap but environmentally unsound; wind turbines are tall and highly visible; solar panels need space for their cells. Frankly, a lightly-populated area on untaxed land owned by Cornell, which would then pay a PILOT fee for the solar panels, seems like a reasonable option. Someone has to step up and lead by example. Why not the town that fought fracking and won?

Anyway, the town pushed their meeting on the project back by one week to digest the onslaught of criticism. The meeting will be held at the town hall on Thursday April 6th at 7 PM.

UPDATE: The April 6th meeting has been cancelled and cannot be rescheduled until additional paperwork about the project has been received.

3. On the topic of energy, it looks like Cornell wants to move ahead with a trial run of its experimental geothermal project. Per the Times, the initial test phases of the “Earth Source Heating” project could take up to six years and $12-$15 million, which is a lot of money given that no one is certain if it will ultimately be a viable source of renewable energy. Some concern is being expressed that the project is too similar to fracking, but unlike the fracking process, where water is used to shatter shale beneath the surface to extract natural gas, the water used here is much lower pressure and kept in a closed loop, in comparison to fracking’s constant expansion of extraction sites. For the time being, the naysayers are assuaged, so now comes years of designing the project and permitting; an extensive Envrionmental Impact Statement (EIS) seems almost certain. ESH would be groundbreaking in more ways than one, if successful.

4. It looks like the major hurdles to the Travis Hyde Properties Old Library redevelopment have been cleared. With the historic district Certificiate of Appropriateness granted from the city’s ILPC, it’s now a matter of going through site plan review – the developer is hoping for an expedited process that’s settled by May, which given the joint meetings between the Planning Board and ILPC, may be possible. The design review is already complete as is most of the documentation, so at this point, it’s just a matter of making sure there are adequate environmental mitigations in place. After that, it’s time for the county to draft up their docs for the $925,000 sale of the property, and hopefully THP can get the mixed-use project underway later this year. The 73,600 SF project will host 58 market-rate units for the 55+ crowd, community space administered by senior services nonprofit Lifelong, and 1,250 SF of street-front commercial.

5. The Tompkins County IDA held its public hearing for the City Centre tax abatements. As expected, the reactions were mixed. A couple of developers not associated with the project (Frost Travis and Todd Fox) came out and spoke in support, which is really great. For one, these guys are invested in the city and knowledgeable about the market, so they should have an idea on whether City Centre would be a welcome economic addition or detraction. For two, it’s nice to see members of the same real estate community standing up for each other. There are cases now and in the not-so-distant past where developers went out of their way to fight other projects, with the parochial scope that as few units as possible would mean as high rents (revenue) as possible. I’m not necessarily saying every project is great and they need to stick up for it, but it’s heartening to see some are taking a broader scope and speaking on behalf of the ones they recognize as beneficial to the community.

The detractors seem less upset about the project itself than the abatements, and there is the fundamental misunderstanding that taxpayers are “paying” for this project. There is no paying; it just phases in the new property taxes on top of the existing value and taxes for the parcel, rather than one big lump increase from the moment of completion. For the sake of example, if they’re paying $100,000 in taxes now, and a given project will bring it up to $1,000,000 in taxes, an abatement means they’ll still pay $100,000 until the site’s developed, then $200,000 right after completion, then $300,000 the following year, and so on until $1,000,000 (plus inflation) is attained. I’ve tried to explain this in the Voice, the Times has tried to explain this, but it’s still a problem.

6. Two Collegetown projects were brought to light at last week’s planning board meeting. 232-236 Dryden, a Visum Development project, would replace a large surface parking lot and rundown 30-unit apartment building with a 191-bed, 2-building complex. 238 Linden, a Novarr-Mackesey infill project, replaces a 10-bed, non-historic apartment house with 24 studio units in a townhouse-format structure designed by his favorite firm, ikon.5 Architects of Princeton. The target market is Johnson students, particularly Executive MBAs who may want to be closer to the university. One of the neat features is that the rear will have a treated “chameleon-like” surface that will change color depending on viewing angle, not unlike the pearl metallics used on some custom cars.

The plan is to have both 232-236 Dryden and 238 Linden underway late this year. Both are likely to have August 2018 openings, although 232-236 Dryden might be a two-phase project, with the second structure coming online in August 2019.

Keen readers will note that the Times has the sole coverage of 238 Linden right now, and this was not in the Voice; Nick Reynolds was at the meeting, I was not, and while I’ve been trying to get renders, I have yet to come through with one. I’d rather play catch-up than sacrifice integrity. I’ll follow up in the Voice eventually, but in the meanwhile, the blog is fair game because I make no money from it.

7. The town of Ithaca planning board looks to have a fairly quiet agenda for next week. Renewing some temporary modular structures at Cornell, construction signage for Maplewood, and An 11-lot subdivision on South Hill, “Ithaca Estates III” featuring Lilium Lane, Monarda Way and Rock Cress Road.

Unfortunately, it’s the Monkemeyer property, where the town has been entertaining ideas of a new urban neighborhood since its new Comprehensive Plan was passed in 2014. Evan Monkemeyer chose to revive a plan from 2010 for two cul-de-sacs off of a new arterial road that would cut through the property; and given the long-term build-out schematic shown above, there would be more cul-de-sacs to come, for a fairly conventional 1990s era suburban layout. Even though he’s apparently mowed the future roads in place on satellite, this doesn’t match up with the town’s Form Ithaca-inspired visions at all. The issue isn’t the housing, it’s the layout. The town’s planning push has been moving away from cul-de-sacs and towards connected streets.

Monkemeyer’s gone down this road before. It didn’t work out very well. Reviving a seven year-old plan that doesn’t fit with the town’s more recent Comprehensive Plan is not, and shouldn’t be, something that is going to sail through the planning board. Token future park space isn’t going to change that. Of course, then he’ll just whine to Rep. Tom Reed again. To Monkemeyer’s credit, the town has been taken uncomfortably long with formulating their new zoning code, it looks like some of the multi-year delay was the town’s fault over who was responsible for a water easement – but given the 6+ years since the issue was raised, it doesn’t appear he was pushing the matter much.





Upson Hall Construction Update, 3/2017

29 03 2017

The new aluminum and terracotta facade is working its way down the lower floors. New window inserts and panels have been installed since the January update, although many sections are still bare, the turquoise water-resistive barrier the top layer for the time being. Slowly but surely, metal fasteners are being attached to the WRB, mineral wool insulation is attached, and the clips are completed with cross-sectional bars so that the terracotta can be put into place.

According to the last Upson construction update from Cornell Engineering, interior framing and drywall is underway on the lower floors, as well as new utilities rough-ins and mechanical piping. One can see a section of drywall through the new windows in the photos below.

The goal is to have the building completed by August, with temporary landscaping until the third phase has been funded. One has to applaud the Upson staff and students who have had to put up with the construction for what’s been almost two years at this point. The upper three floors were finished last summer, and the basement, first and second floors are being completed this year.





Cornell Law School Renovation Update, 3/2017

28 03 2017

Finally starting to see a little bit of progressing on the renovations to Hughes Hall. The rest of the old masonry wall on the lower floors has been stripped out, and is covered with plastic and plywood for the time being. Eventually, the space will be opened as the new glass enclosure is built for the new west staircase. For the record. the stairwell is completely new; it replaces one that was slightly further to the east, on the inside corner of the building. This gut renovation is down to the studs, and then some. No work on enclosing the loggia just yet.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver is the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete, meaning November 2017 if all goes to plan.

 





Gannett Health Center Construction Update, 3/2017

27 03 2017

The new northeast wing of the Gannett Health Center has been framed, sheathed, and windows have been fitted. From the outside, work is also complete on the new concrete skin for the late 1970s northwest wing, which unlike the original building, it was finished out with concrete instead of stone. Meanwhile, the remaining portion of the original 1950s structure is still undergoing interior work and the new canopy has yet to be erected, so it’ll be a couple of months before the new curtain walls are fully installed. A new roof membrane is also on the to-do list.

Looking closely at the sheathing on the new building, you can see the clips that will be used to attach the new limestone veneer (Cornell has the time and the money for the real deal; most developers opt for less expensive but similar-looking precast concrete). Based off the roofline, it looks like fireproof fiberglass mat gypsum sheathing (in this case, GP DensGlass), followed by a silver moisture protection barrier, and then metal panels or limestone depending on the location.

October 2017 is the given completion date on the Cornell Facilities webpage, but the new building should be open by August; the new landscaping is what will extend into the fall. The Pike Company of Syracuse is the general contractor (they’re also doing Upson Hall nearby), and Downtown Ithaca’s Chiang O’Brien are the designers-of-record.

I did not get as close to the site as I would have liked, because the snow was still quite deep in some spots, and some of my usual vantage points were blocked off.





Cornell Veterinary School Expansion Construction Update, 3/2017

26 03 2017

There’s been quite a bit of progress over at the Vet School. It looks like the exterior glass and aluminum are going on the new library and administrative wing. Windows and sheathing have been installed on the north face as well, with a water-resistive barrier applied over the sheathing. The new atrium is being framed out.

According to the Vet School’s construction update page, interior framing and utilities installations are underway in the new wing, and the new cafeteria is under construction – both are aiming for August completions. The new atrium and lecture hall will be closed off shortly, with interior work to launch in earnest once that occurs.

Thanks to Maria Livingston over at HOLT Architects, readers now know what the new Community Practice Service building will look like. Syracuse’s G. M. Crisalli and Associates Inc. has been selected as general contractor, and construction for the $7 million, 12,000 SF wood-frame structure is expected from March 2017- March 2018.





The Cherry Artspace Construction Update, 3/2017

26 03 2017

The corrugated metal exterior has been attached, the roof is complete, and the doors and windows are being fitted. Once the steel framing was completed, the exterior work was expected to move quickly, as all the components had already been assembled and were just waiting in storage. McPherson Builders is making quick work of the 1,900 SF project.

The Cherry Artspace crew do a great job providing updates on their website, on a much quicker timeframe than this blog. They also have some interior shots, which show the mezzanine area, and the insulation that has yet to be installed. The first show inside the new venue is scheduled for April 20th (for those interested, tickets here).

I did an in-depth interview for the Voice about the Cherry Arts and the Artspace with Director Samuel Buggeln and Associate Director Jennifer Herzog, which I very much enjoyed. A copy of that can be found here.





Tompkins Financial Corporation HQ Construction Update, 3/2017

25 03 2017

Apparently I forgot to to an update on the Tompkins Financial project last month? It must have slipped off the radar after the Voice received its spark notes version. Funny how it was about 60 F when the February photos were taken, and about 30 F when the March photos were snapped.

Anyway, structural steel framing is underway, giving an idea of the bulk of Tompkins Financial Corporation’s new 110,000 headquarters at 118 East Seneca Street. Framing has started for the first five floors of the seven story building, and mor beams will be built upward and outward – note the indents in the elevator core on the side facing Seneca Place, intended for future steel beams. The lowest floors have also received corrugated steel decking. There are still a couple of floors to go, as evidenced by the wood forms on the elevator shaft. The concrete will extend another two floors before it’s topped out. The building’s ground to rooftop height will be exactly 100 feet.

A May or early June topping out seems plausible. Occupancy is intended by March 2018. JPW Erectors, a division of the JPW Companies of Syracuse, is in charge of the framing, while LeChase Construction is the general contractor.

February 2017





News Tidbits 3/25/17: Out in the Wild

25 03 2017

1. Let’s start by touching real quick on this past week’s Ithaca town meeting. The Bundy subdivision and the renovation of the former Wings Over Ithaca space at East Hill Plaza were approved, per Matt Butler at the Times. The Greentree project was reviewed and the board granted itself lead agency to conduct environmental review. Greentree owner John Gaunt is still unsure whether he’ll keep the Elmira Road building, which is where Ithaca Beer got its start in the late 1990s. Although primarily a warehouse/ag industry project, there will be some potentially public-friendly features, namely a garden park and picnic area. The board expressed a desire to see Greentree work with neighbor Ithaca Beer for landscaping between the two buildings.

2. I followed up with Lansing town planning consultant Michael Long regarding English Village. As readers might remember from last week, that’s the 58 single-family home lots and 59 townhouses proposed somewhere in Lansing – didn’t know where because that was the first anything has been published about it. Here’s Long’s response:

“The English Village is a concept developed by Jack Young to build a network of single family homes and apts. /condos that surround the existing soccer fields along Water Wagon [sic] Road. It is still very early in the conceptual phase so there has not been an formal application made as yet, but a project that has been talked about for many, many years. We don’t have anything specific yet but is a project “In-progress”.”

Jack Young is a Cayuga Heights businessman (and chair of their zoning board of appeals), who owns a sizable amount of undeveloped land in Lansing; most of it is used for farming. The soccer fields on Waterwagon Road are just east of The Rink, which is putting in a new climbing tower. There’s been plenty of conventional suburban development up this way since the 2000s, although in recent years the new starts have slowed as conventional suburban layout have lost some of their allure to walkable urban or truly rural properties. We’ll have to keep an eye out and see what happens.

3. Now turning attention over to Dryden. Apparently the town of Dryden thinks I’m with the Ithaca Times. Anyway, two new projects have popped up on the radar this week.
The first is a 6,016 SF, 8-unit apartment on the 500 Block of Etna Road just east of the airport. All units will be 1-bedrooms. The developer is Ithacan Salim Kasimov; with partner Yelena Kurbanova, they’ve picked up some properties in and around the area for home construction over the past few years, although this might be their first multi-family building. Simple, maybe a little bland – a floor-separating exterior lap band and two different colors of siding would do wonders.

The project exceeds zoning, where 2 units/acre is allowed, and this is pursuing 8 units on 1.78 subdivided acres (the other lot holds a two-family home). SEAF here, floor plans hereThe argument was that these are all one-bedroom units, and a typical house is 3+ bedrooms, so it’s not a substantial variance. The project was in planning before the rural zoning code was updated, which complicates matters.

According to Dryden town planning director Ray Burger, the ZBA asked for more information, but the application has been withdrawn. This project is in limbo for the time being.

The second is called the “Pineridge Cottages”, and went to the Dryden Planning Board for a sketch plan review this week. This one came up on this blog a long time ago – it’s a proposal for about 20 single-family rental homes on about nine acres on the corner of Dryden Road/Route 13 and Mineah Road. At the time, the logic was that the density requirements would let it slip under the radar, since the project is under 4 units/acre and could have avoided triggering most site plan review regulations. But maybe with the revised zoning laws, that’s no longer the case.

4. It’s a Tiny Timber out in the wild! Not something that was expected while covering the Maple Festival, but there it was on the property. This would be the very first one, according to the Tiny Timbers blog. The TT blog says it’s in Hector (which is correct, it’s 500 feet from the Tompkins/Schuyler County line), but the Wellspring Farm advertises itself with a Trumansburg address, so this was really just fortuitous circumstance. The model is a Model L Lofted with optional green corrugated metal roofing.

It’s looks like sales are off to a good start – the 14 Farm Pond Circle lot is pending, as is the Ellis Hollow Road lot. A Tiny Timber Big Cube is also expected to replace a dilapidated home at 104 Grandview Place on Ithaca’s South Hill. Prospects are so good, Buzz Dolph plans to rent a warehouse on Dryden’s Hall Road to serve as an assembly facility for the modular components, and is looking for construction partners in neighboring markets. Modest, affordable owner-occupied housing is an under-served but big potential market, and to its profit, Tiny Timbers looks to be part of the solution.

5. According to documents filed with the county this week, the construction loan for 607 South Aurora is $1,920,000. Tioga State Bank is the lender on record, with Charlie O’Connor of Modern Living Rentals as developer. The documents give a March-August build-out for the 4-building project; each building will host 2 three-bedroom units, and utilize modular components. These will look pretty similar to the pair that just opened on Old Elmira Road.

The two-family directly on South Aurora is designed with a full-length porch and sculpted brackets, with Hardie Plank fiber cement boards to look more aesthetically pleasing. The trio tucked away from road will use vinyl siding. Advertisements targeting Ithaca College students are already posted on MLR’s website, saying that the 3-bedroom units will rent for $2,250/month, or $750/bedroom.

6. One of those rare interesting things from the slimmed down Ithaca Journal – it appears CFCU has been doing pretty well this decade. Not only were they recently approved for an expansion into Cayuga County and Seneca County (that’s where Geneva is, guys), the Lansing-based credit union and financial services firm has added 40% to its financial holdings and 42 jobs since the start of the decade. Not too shabby at all, keep up the good work.

7. Interesting planning board meeting shaping up. Here’s the March agenda:

1. Agenda Review 6:00

2. Privilege of the Floor 6:01

3. Subdivision Review
A. Project:
Minor Subdivision 6:10
Location: 109 Dearborn Place Tax Parcel 9.-3-11

4. Site Plan Review

A. Project:
Apartments (11 Units) 6:20
Location: 107 S Albany Street
Applicant Stavros Stavropoulos
Actions: Consideration of Preliminary and Final Site Plan Approval

B. Project:
Schwartz Performing Arts Center Plaza Improvements 6:40
Location: 430 College Ave
Applicant: Ram Venkat for Cornell University
Actions: Declaration of Lead Agency .Public Hearing . Determination of Environmental Significance, Consideration of Preliminary & Final Site Plan Approval

C. Project:
Apartments ( 5 Units) 7:00
Location: 118 College Ave
Applicant: Visum Development Group
Actions: Declaration of Lead Agency

D. Project:
Finger Lakes ReUse Commercial Expansion and Supportive Apartments 7:20
Location: 214 Elmira Road
Applicant: Finger Lakes ReUse
Actions: Declaration of Lead Agency

E. Townhomes- 238 Linden Ave – Sketch Plan 7:30

This proposal was removed right before the February meeting. Same details as before: 238 Linden is a non-historic student rental house, and a John Novarr property in a CR-4 zone – 4 floors, no parking required. Further to that, 240 Linden to its north was taken down for staging space for the Breazzano Center, but as that will be finishing up this Spring, it leaves an MU-2 (six floors, no parking) parcel open for development. A townhomes plan suggest one or both of these parcels will host something not unlike the ikon.5-designed townhouses plan Novarr plans to build at 119-125 College Avenue.

F. Apartments 232- 236 Dryden Road – Sketch Plan 7:50

Another CR-4 proposal is slated for what is currently a parking lot at 232-236 Dryden Road. Given that the parking lot address is 232-238 Dryden, it seems plausible a small, remnant component is being kept. The owner is James Rider, the 57-year owner of the Hillside Inn budget hotel in Collegetown. Going out on a limb, it’s likely he is not the developer, but someone else who happens to have a purchasing option. Four floors, no parking required, on a parking lot – seems like a good opportunity for an infill project without much risk to the city’s historic fabric.

5. Zoning Appeals 8:10
#3059, Appeal of Determination, 742 Cascadilla At (Carpenter Bus. Park) – Yes, Maguire has filed the lawsuit and this is related. Carpenter is the Plan B at this point, but they want to make sure that Plan B is legal if that’s what it boils down to.
#3060, Area Variance, 322 Park Place – small addition to an existing house.
#3062, Area Variance, 104 Grandview Place – the Tiny Timber mentioned above.
#3063, Sign Variance, 505 3rd Street (Aldi) – Aldi is renovating and expanding stores across the country, a massive 1,300+ store project that’s liable to cost more than $1.5 billion over the next few years (prototype shown above). Ithaca will be one of the first to get the new layout, adding 2,700 SF to its Aldi outpost. The move is to allow expanded fresh food offerings (meat, dairy and produce), and install new energy-efficient refrigeration units. Note that the expansion is to allow a slightly larger combined store signage area than what’s legally allowed (total 272.9 SF vs 250 SF). Victor-based APD Engineering and Architecture is in charge.

6. Old/New Business 8:30

7. Reports