News Tidbits 3/11/19

12 03 2019

1. The city of Ithaca and The Vecino group have come to a tentative agreement. The two have been negotiating since entering into a 90-day Exclusive Negotiating Agreement at the end of last year. While Vecino is still looking at the financial models for the conference center space, it appears that the city is ready to move forward with a formal agreement to be voted on by the Ithaca Urban Renewal Agency (IURA) and the Common Council, and then to have the building plans reviewed by the Planning Board, and then the sale of the property to be brokered by the IURA and agreed to by the Common Council. If approval is granted in good order and state funding is obtained (Vecino is pursuing 4% low income housing tax credits, vs. the more competitive 9% variety), then construction could start on the $95 million mixed-use project by late 2020.

2. GreenStar will be asking the IURA for a $400,000 loan to assist in the construction of their new flagship location at 770 Cascadilla Avenue. It does not seem to be related to their construction woes, as the initial paperwork was filed in January, but it makes for rather awkward timing. The loan is likely to be approved without significant reservation thanks to GreenStar’s reputation and the promise of dozens of living wage jobs, though the IURA is unhappy with what is described as “weak collateral”, and it has some concerns with GreenStar’s ability to fundraise.

Important note – the paperwork mentions one of GreenStar’s funding sources will be the buyer of the current Space A Greenstar at 700 West Buffalo Street, who so happens to be “the owner of the Cascadilla Street property”. This buyer will pay $2 million for the building when GreenStar moves out in early 2020.

At first glance, one might think that’s Guthrie. But Guthrie transferred ownership of the parcel to “Organic Nature LLC” last month. Organic Nature LLC is a company owned by the project team building City Harbor. In short, the City Harbor developers are buying the Space @ Greenstar, and likely have plans for the property.

3. If you’re an urban planner – and I hope this blog is interesting to you if you are – the IURA is issuing a request for qualifications for a parking study. The project will include three major tasks: analysis of the current parking system; determination of possible scenarios of programs and actions for the future direction of the parking system that are financially sustainable; and preparation of a strategy and an implementation plan, with estimated costs and a schedule. TLDR; look at existing operations, describe future directions (ten year period), make parking-related recommendations and implementation recommendations. Knowledge of transportation demand management and experience with designing strategic initiatives to handle parking needs will be a big plus. Submission packets due April 12th to Director of Parking Pete Messmer, more info at the end of the agenda packet here.

4. Quick note – the North Campus housing proposed by Cornell was modified slightly at the request of city boards. The new design adds “break points” in the facade to activate the central wings of the buildings and make the building masses seem less imposing. The general massing and material choices remain unchanged.

5. Mid-sized Collegetown landlords Greg and Mataoula Halkiopoulos (of Matoula’s Houses) have decided to renovate a decrepit 19th century carriage house at the rear of their property at 214 Eddy Street, and turn it into a three-bedroom, 839 SF rental. 214 Eddy is in the East Hill Historic District, so the design, by local architect John Barradas, will need to be approved by the Ithaca Landmarks Preservation Commission. It looks like a practical renovation, respectful of the carriage house’s form but also with a modern touch. Early Design Guidance will be offered at the March ILPC meeting, and any decisions on a Certificate of Appropriateness are still a few months out.

6. There have been some major changes to the Perdita Flats plan at 402 Wood Street. Previous version here. For one, it now has frontage on Fair Street and will have a Fair Street address. The building and garden have been re-positioned, the footprint reduced slightly (38’x36′ to 36’x36′), larger porch, modified exterior cladding materials, and the driveway has been removed at the Planning Board’s suggestion. The building remains 4 units and 7 bedrooms, and STREAM Collaborative penned the redesign.

The wood shiplap siding and standing-seam black metal siding are a bit of an acquired taste, especially with the wood oiled or left to grey naturally. But the house is still planning to be a net-zero energy showcase of what can be done with environmentally sustainable multifamily housing, and that’s the real statement to developers (Courtney Royal and Umit Sirt) are trying to make. The owners will be applying for incentives from the NYSERDA Low-Rise Residential New Construction Program and are hoping to attain the Zero Carbon Petal of the Living Building Challenge.





802 Dryden Road Construction Update, 2/2019

28 02 2019

The townhouses at 802 Dryden Road are in varying states of construction, with no apparent pattern to the choices. Buildings “E” and “F” at the western end of the site have been framed, sheathed in Tyvek housewrap, roofed, shingled, and have doors and windows fitted. “E” has the navy blue panels, and “F” the olive green panels. Building “C”, at the eastern end of the site, is in the process of having its roof framed; a crew was on-site last weekend bolting together the trusses. Building “D” has partial framing and sheathing, Building “B” at the eastern front of the site has its slab concrete foundation finished but not framing as of yet, and forms for pouring the foundation walls are still on-site for Building “A”. So generally speaking, counterclockwise from lower left, buildings are progressively less far along.

For the record, each building, seven units apiece, will a unique address when finished – 802, 804, 806, 808, 810, and 812 Dryden Road.

It was previously noted that the purchaser was operating under an LLC tied to a Pittsburgh-area business executive, Matt Durbin. A new project website says the firm is “Maifly Development”, a small but seemingly deep-pocketed Pittsburgh company that appears to be pursuing a mixture of student-oriented and market-rate properties across the country. Along with the LEED Certified “(b)outique two-story townhome community abutting the Cornell University campus, nestled in a picturesque natural setting,” Maifly has developments in Pittsburgh and Eugene, Oregon (to be one of the city’s tallest buildings, the 230-unit/443-bed  “Hub Apartments”). In other words, this is the real estate development company Durbin owns and operates, and he has plenty on hand.

The new Ivy Ridge website shows four apartment plans, consisting of two two-bedroom formats, a three-bedroom unit, and a four-bedroom unit. The site also includes some new renders, including some interior perspectives included here at the end of the post. The number on the website is the number of C.S.P. Management, so it appears local real estate manager Jerry Dietz will be handling landlord duties on behalf of the developer.

Looking at the website Q&A, it’s clearly geared to Cornell students, and although rents haven’t been posted on most websites, it looks like C.S.P. discreetly listed them before anyone else. A two-bedroom will be $1,800/month, a three-bedroom $2,500/month, and a four-bedroom $3,200/month. Cable and most utilities (all except electric) are included in the rent, the units come partially furnished, and pets, include large dogs, are allowed. Stainless steel appliances, in-unit washer and dryer, and marble tile are also planned. Exterior features include 70 parking spaces, bike racks, stormwater ponds, bioretention areas, a childrens’ playground, and a dog park. Although the project isn’t expected to be complete until August, C.S.P. has some units listed for a June 1st occupancy, which given the site photos, it seems plausible that’s they’d open in two phases.

There’s a modest discrepancy in the construction sot, which is partially my fault. An early estimate for the 42-unit/108-bed, 50,000 SF project was $7.5 million, and that’s what I’ve used in some articles and posts. The final development cost with loan from M&T Bank is about $8.6 million.





News Tidbits 12/17/18

18 12 2018

Here’s a look at the agenda for the city of Ithaca Planning and Development Board meeting this month. It’s a week earlier than usual due to the Christmas holiday. Notes and comments in italics below.

1. Agenda Review 6:00
2. Special Order of Business – Presentation of the Greater Southside Plan 6:05
3. Privilege of the Floor 6:20
4. Approval of Minutes: November 27, 2018 6:35

5 Special Permits 6:40

A. Project: Bed & Breakfast Special Permit
Location: 130 Coddington Road
Applicant: Noah Demarest
Actions: Declaration of Lead Agency, Public Hearing, Determination of Environmental Significance, Potential Consideration of Special Permit Approval

Project Description: The applicant is seeking a Special Permit for use of the property as a homeowner occupied Bed and Breakfast. The property was originally issued a Special Permit in 1998 for operation of the five bedroom home as a homeowner occupied Bed and Breakfast; the Special Permit was not renewed in 2003, as required by §325-9c(4)(g)[3], and has therefore expired. During a recent home inspection, it was discovered the property had continued to operate absent a Special Permit, necessitating a new Special Permit application. No physical alterations to the building or the site are proposed. Issuance of a Special Permit is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act “(“SEQRA”)

This is a simple case of where the previous owner never renewed the five-year permit and didn’t tell the new buyer, who planned to continue using the home as a live-in Bed & Breakfast. No letters of opposition are on file. Approval, with the proper completion of all necessary forms, is likely to be straightforward.

B. Project: Bed & Breakfast Home Special Permit 6:50
Location: 2 Fountain Place
Applicant: Jason K Demarest
Actions: Declaration of Lead Agency, Public Hearing, Determination of Environmental Significance, Potential Consideration of Special Permit Approval
Project Description: The applicant is seeking a Special Permit to operate the existing 4,492 SF nine (9) bedroom residence located at 2 Fountain Place as a Bed and Breakfast Home. The owner is proposing to utilize four (4) of the nine (9) bedrooms as guest bedrooms for a period not to exceed 21 consecutive days, with a fifth bedroom utilized for home-owner occupancy. Guest occupancy will be limited to two persons or one family per guestroom. No exterior modifications are proposed to the existing home to establish the B&B use, and the existing house is compatible with the character of the neighborhood. Existing parking for seven (7) vehicles exists in the turnaround off Willets Place. The applicant does not propose cooking facilities in the guestrooms, and food service is to be limited to guests of the B&B. No other B&B Homes exist within 500 feet of the property. One sign that is five (5) SF maximum in area and not self-illuminated will be installed in compliance with Chapter 272 of the City Code, “Signs.”

Under city zoning code, B&Bs, which are to be owner-occupied, are allowed to four bedrooms to be used for the guests. A zoning code variance to use eight bedrooms as guest occupancy seemed unlikely, but the new owners believe the B&B may still be viable. Local architect Jason K. Demarest (brother of STREAM’s principal architect, Noah Demarest) is known for his historic restorations and historically-inspired design work, so his involvement is auspicious for those who hope that the century-old mansion and former Ithaca College president’s house retains its character.

6 Site Plan Review

A. Project: Chain Works District Redevelopment Plan (FGEIS) 7:00
Location: 620 S. Aurora St.
Applicant: Jamie Gensel for David Lubin of Unchained Properties
Actions: Review FGEIS & Town Comments – No Action
Project Description: The proposed Chain Works District seeks to redevelop and rehabilitate the +/-800,000 sf former Morse Chain/Emerson Power Transmission facility, located on a 95-acre parcel traversing the City and Town of Ithaca’s municipal boundary. The applicant has applied for a Planned Unit Development (PUD) for development of a mixed-use district, which includes residential, commercial, office, and manufacturing. The site’s redevelopment would bridge South Hill and Downtown Ithaca, the Town and the City of Ithaca, by providing multiple intermodal access routes including a highly-desired trail connection. The project will be completed in multiple phases over a period of several years with the initial phases involving the redevelopment of the existing structures. Current redevelopment of this property will focus on retrofitting existing buildings and infrastructure for new uses. Using the existing structures, residential, commercial, studio workspaces, and office development are proposed to be predominantly within the City of Ithaca, while manufacturing will be within both the Town and City of Ithaca. Project materials are available for download from the City website: http://www.cityofithaca.org/DocumentCenter/Index/119

Hey, they’re starting to include documentation links in the agenda descriptions now! Most of the town’s comments are minor modifications and a possible correction on one of the traffic lane analyses. There’s a boatload of paperwork to dig through, so this meeting is just a chance for the planning board to look at the town’s comments, digest some of the supplemental files, and make sure there are no red flags or major concerns within that subset of information.

B. Project: North Campus Residential Expansion (NCRE) 7:20
Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Determination of Environmental Significance
Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). Project materials are available for download from the City website: http://www.cityofithaca.org/DocumentCenter/Index/811

This is likely to be the most contentious part of the meeting. The planning staff have conducted their analysis. Some traffic mitigation measures are sought, including circulation and mass transit / multi-modal transit improvements. The city will make sewer system upgrades a stipulation of project approval, and being next to the Cornell Heights Historic District, the board as Lead Agency wants a more sensitive use of materials and material colors, and extensive vegetative screening to be reviewed further before approval. But the most debated component, the energy use impacts, the city feels is effectively mitigated through the proposed measures by the applicant team.

I’m going to raise one point of correction though – the number of beds is going up to 2,079, but the planning staff should note that a campus-owned fraternity house, the former Sigma Alpha Mu building at 10 Sisson Place (the chapter moved to 122 McGraw Place), is coming down to make way for the project, so the gross number of beds is at least 30 less that that figure.

C. Project: Falls Park Apartments (74 Units) 7:50
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Review of FEAF Part 3 – No Action
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11). Project materials are available for download from the City website: http://www.cityofithaca.org/DocumentCenter/Index/852

Part III of FEAF is the city planner-written review of impacts, proposed mitigations, and whether the lead agency feels the mitigations are appropriate and effective. Some stormwater, remediation plan and other supplemental materials are still needed before a declaration of significance can be made. 

D. Project: New Two-Family Dwellings 8:10
Location: 815-817 N Aurora
Applicant: Stavros Stavropoulos
Actions: Public Hearing
Project Description: The applicant proposes to demolish an existing two-family residential structure and construct two new 1,290 SF two-family dwellings on a 9,590 SF lot. The existing residential building is a legally non-conforming building with a side setback deficiency (2.9 feet instead of the required 5 feet). The proposed redevelopment will include four parking spaces for four three-bedroom apartments. The applicant is requesting the Board’s approval to use the landscaping compliance method for parking arrangement. The project site is located in the R-2b Zoning District and meets all applicable zoning lot and setback requirements. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”). Project materials are available for download from the City website: http://www.cityofithaca.org/DocumentCenter/Index/859

City staff were really unhappy about this plan last month, and it was implied that this was one of the examples of “bad” infill that may lead to the new single primary structure overlay. However, barring extreme circumstances (think Maguire at Carpenter Park), review will continue under the current regulations. No new materials appear to have been submitted since the last meeting. 

E. Project: Maguire Ford Lincoln Additions and Improvements 8:30
Location: 370 Elmira Road
Applicant: John Snyder Architects PLLC
Actions: Public Hearing, Potential Determination of Environmental Significance

Project Description: The applicant proposes to demolish a portion of the existing building and construct two additions with updated exterior materials. The existing building is 18,500 GSF, with 2,265 GSF proposed for demolition. The new building will be 24,110 GSF. Site improvements include incorporation of a new pedestrian walking path, and site connections to Wegmans. Approximately 311 parking spaces are proposed to accommodate customer, service parking, employee, and display parking. The project site is located in the SW-2 Zone, is subject to the 2000 Southwest Design Guidelines, and will require a zoning variance for a front yard that exceeds the maximum permissible in the SW-2 district (34 feet maximum permitted, 69-feet 3-inch setback proposed). This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”); however, it will be treated as a Type I Action for the purpose of environmental review. Project materials are available for download from the City website: http://www.cityofithaca.org/DocumentCenter/Index/860

The revised plans include modified architectural features (more windows, a green wall), and a greater amount of vegetated landscaping to comply with zoning. On-site solar panels are being considered per board recommendation, but the old building was not designed to hold the weight of solar panels. The new wings will be designed to host panels. Heat pumps are being evaluated for some functions, but some of the heavy-duty components like the service bay will likely rely on modified conventional fuel systems. The building will meet or exceed NYS Energy Code requirements.

F. West Hill- Tiny Timbers – Sketch Plan 8:50

This one has been a long time coming. Tiny Timbers bought a 5.45 acre parcel on the south end of Campbell Avenue’s 400 block back in September 2016, and has long planned one of its cluster home developments on the vacant lot. As noted at the time on the blog:

“Dolph et al. are looking to do a similar development to the one in Varna on a 5.45 acre parcel at the south end of the 400 Block of Campbell Avenue, which was noted in a weekly news roundup when it hit the market back for $195k in August 2015. The Journal’s Nick Reynolds touched on it in a through write-up he did earlier this week. The comprehensive plan calls this portion of West Hill low-density residential, less than 10 units per acre. Current zoning is R-1a, 10000 SF minimum lot size with mandatory off-street parking, although maybe a cluster subdivision would come into play here. The Varna property is a little over 6 units per acre. If one assumes a similar density to the Varna project, the ballpark is about 35 units, if sticking to the 10000 SF lot size, then 23 units.

On the one hand, expect some grumbling from neighbors who won’t be thrilled with development at the end of their dead-end street. On the other hand, these small houses are modestly-sized and priced, they’ll be owner-occupied, and if the Varna site is any indication, the landscaping and building design will be aesthetically pleasing.”

G. 112-114 Summit Ave – Sketch Plan 9:10

This one required some fact-checking, because 114 Summit Avenue was the former Cascadilla school dorm that came down last year to make way for the Lux apartment project at 232-236 Dryden Road. A better address for this project might be “238 Dryden”, and the rumor mill says it’s by Visum Development Group, who developed the Lux. Although the exact positioning seems uncertain, the parcel north of the Lux is CR-3 (three floors, 40% lot coverage, parking and houselike features such as gables and porches required), and the remaining adjoining parcels are CR-4 (four floors, 50% lot coverage, no parking required). With student housing experiencing a little more slack in the market lately, it’s not clear if this is student housing, or another use.

7. Old/New Business PRC Meeting Time/ Date 9:30

8. Reports
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development 9:40

9. Adjournment 9:50





238 Linden Avenue Construction Update, 12/2018

14 12 2018

John Novarr and Phil Proujansky’s project at 238 Linden Avenue is moving right along. For an all-residential construction, this is a heavy-duty building. It uses a steel frame with steel stud walls and gypsum sheathing – unlike wood-framed structures that could go up in smoke, this building is designed to be durable and withstand and potential fire-related calamities. It may be related to the fire code issues that delayed the project?

It looks like the design is similar, but not exact to the renders below. While some of the rough window openings are still being carved out of the gypsum panels, it’s not the same fenestration pattern. The sunken rear courtyard remains – it will be nice during the summer, but every leaf in Collegetown will seem to find its way in there by November.

The 13,715 square-foot building, which will house 24 studios, is topped out but not yet fully framed. Corrugated steel decking is in place and some interior framing has occurred as well. Based off the demolition plan submitted for 325 College Avenue around the corner, the targeted completion date for this structure is sometime next summer – given it’s designed to serve Executive MBA students at the Breazzano next door, that makes good sense.

Briefly, to touch on that 325 College Avenue site – the rumor mill does not know what’s planned, but the only consistent detail is that it will not be student housing. The market is too weak, and many Collegetown landlords are holding off on projects until the impacts of Maplewood, and potentially Cornell’s North Campus, have been fully absorbed. It’s not a situation where anyone seems to be going bankrupt, but the big Collegetown players have taken a more conservative approach as a result of Cornell’s new housing. As to what they could plan other than student housing, we’ll see. Faculty/staff housing, a hotel, another Cornell-related institutional use…plenty of options.

A history and overall description of the 238 Linden Avenue project can be found here.





118 College Avenue Construction Update, 12/2018

14 12 2018

This is another case of where the exterior of the building isn’t finished, but the interior is complete enough such that a certificate of occupancy may be issued. Visum Development has been advertising the units online, and they’re not cheap, $1200-$1300/bedroom. 118 College has 5 units, four six-bedroom and one four-bedroom unit. For that high-end price, they come fully furnished, and with washer/dryer, stainless steel appliances, microwaves, dishwashers, quartz countertops and private balconies. Wi-fi is including in the rent, and tenants can use the fitness center and media lounge at Visum’s property at 201 College at no extra cost. The units are all smoke-free, which might seem quirky to older readers, but it was already pretty common by my Cornell stint in the late 2000s. Interior photos can be found here. This one moves into the “complete” column on the Ithaca/Tompkins County project map.

The yellow fiber cement siding really makes this building pop. The basement-level is finished with stucco mixed with Sherwin-Williams (S-W) “Sawdust” paint, the first level is a combination of Belden face brick (Belcrest) and S-W “Truepenny” fiber cement clapboards, more fiber cement clapboard on the mid-section in S-W “Overjoy“, trimboards, balcony trim and window casing colored S-W “Svelte Sage”, black window frames, stucco (in S-W “Favorite Tan”) with more fiber cement trim and frieze boards on the top level, and the pyramidal roof caps will be standing seam metal, Pac-Clad “Aged Copper”.

As a related, humble opinion, the bamboo siding on 201 College is not ageing gracefully. The rain shadows just don’t reflect well for a luxury building. Also note the Lambo Huracan. 99% of the Lamborghinis I’ve seen in my life have been in architectural renders with no hope of matching such opulence in the final product. At $200k, that car is worth as much as a well appointed, local starter home.

210 Linden Avenue is, like 118 College, still finishing up on the exterior work, but further along. The landscaping won’t go in until the spring, which given the winter weather, is probably when the building will be truly complete.

All the building designs and eventual landscaping designs are courtesy of STREAM Collaborative, and the construction itself is the work of Romig General Contractors.

 





News Tidbits 12/9/18

9 12 2018

1. Let’s start out in Lansing. Milton Meadows if officially underway. The 72-unit apartment complex, the first development to get off the ground at the Lansing Town Center site off Route 34B, will be targeted at the 50% – 80% area median income range (~31k-~48k for a single person household) and give priority to income-qualified veterans.

The plan is to roll out the $17.1 million project in stages as the buildings are completed next year. Nine of the structures will be apartment buildings ranging from 6,600-10,200 square feet (SF), with 8 apartment units apiece. The buildings are designed so that all the units in a structure are the same size range, so all one-bedroom buildings (4), all two-bedroom buildings (3), and all three-bedroom buildings (2). The last building would be a 3,100 SF community center. Also included are 139 parking spaces, a community garden, sidewalks, playground, and stormwater management facilities. The project will be built to LEED Silver energy standards.

Funding comes from a variety of state and local sources, the largest single grant being $5.1 million courtesy of New York State. The first units should be ready by late spring, and the last units will come online next fall.

2. In the next round of county/city/Cornell affordable Housing Development Fund recommendations, breakdown above. Habitat gets some funds towards one of its home builds and to buy two other sites, INHS gets additional funds towards their citywide renovation project, and Visum’s 327 West Seneca Street gets $200,000 (this project was carried over from the last round, because they wanted to make sure Visum knew what it was doing). Perhaps the most interesting component here is the NRP Ithaca Townhomes project on West Hill near Cayuga Medical Center, which has received approval, but with a lack of high-value state funds, it has languished in post-approval funding hell. The original breakdown was 66 units in phase one and 39 in phase two, so the 69 here suggests something was modified a little bit.

Unit sizes will range from $850/month, 745 square-foot 1-bedroom units to $1500/month, 1,344 square-foot 3-bedroom units, with most units being two or three bedrooms. The infrastructure improvements (streets, lighting) will be privately built and maintained by the developer. Seven units (2 1-BR, 3 2-BR, 2 3-BR) will be set aside for the mobility impaired, three units for those with hearing or vision impairment (1 1-BR, 1 2-BR, 1 3-BR), and three units for those with special needs (1 1-BR, 1 2-BR, 1 3-BR), defined in this case as recovering victims of domestic violence situations.

The original plan was to start construction last spring, and frankly, the project probably still needs a sizable state grant before funding can go ahead. But with this funding, it’s another piece of the puzzle. If it has some dedicated funds already, and the state doesn’t have to fork over as much, then the state is more inclined to support the project because on its end, it gets more bang for the buck. So keep your fingers crossed.

3. The rumor mill says that Vecino is falling for Ithaca like a teenage girl for a boy band crush. The multi-state firm specializes in two types of housing – affordable housing (under names like Asteri, Mosaic, Libertad and Intrada) and student housing (Muse), which makes Ithaca a good fit. Rather conveniently, Vecino projects identify segments of their target market in the building name. Asteris, like the one proposed for the Green Street Garage in Ithaca, provide not just affordable housing, but several specialized units for those with developmental disabilities. Intradas, like the 157-unit Intrada going up in Saratoga Springs, provide affordable housing with a handful of units set aside for youth aging out of foster care. So, kinda just a neat little quirk there.

Arthaus, as one might guess, is the artist-focused affordable housing – the only other one I’m aware is in a converted warehouse in Troy (which all my Albany colleagues call ‘hipster central’ or ‘Williamsburg North’, the downtown far removed from its days as ‘Troilet’). The sort of tough part to make clear is that this is not limited to artists. It just has amenities geared towards creative types, like a woodshop and storage space and gallery space run by an outside non-profit. Of course, the Voice commenters hated this with a passion because artists = leftists liberal dirty hippie types = evil incarnate. I’ve learned that the softer reactions tend to be with affordable senior and affordable veterans housing, which I cynically suspect is because the most vocal complainers tend to be more politically conservative in their views, and seniors and vets tend to be more politically conservative than the general population – so rather than engaging in circular fire, some, but definitely not all, will hold their tongue.

But, while the commenters didn’t like it, the city planning board did. It’s 120 units (40 studio, 60 1-bedroom, 20 2-bedroom) of affordable housing (50-80% are median income, just like Milton Meadows in item 1), which is a hefty amount and critically needed. A number of units will be set aside for specialized needs and administered by Tompkins Community Action, which will be offered office space in the building. The project is also seeking to get arts groups involved in the design. The city was looking to start off on the right foot with the upzoned waterfront, and this is exactly the kind of creative, affordable project they were hoping for.

4. My only regret is that because the working title of 116 Catherine was 114 Catherine, readers will be confused for years to come. Jagat Sharma designed a tasteful three-story infill building in Collegetown to the rear of 116 Catherine and the Mission Apartments – these would join the rest of the Lambrou properties that comprise Eddygate Park. Also like 116 Catherine, it’s three units – two six-bedroom units, one five-bedroom unit, about as student-oriented as a project can be. Still, infill is much more preferable to a parking lot in Collegetown. Every bit of housing helps, and it’s a couple million dollars of assessed property to help fill local coffers. If the Lambrous choose to pursue this one, which is smaller than what the CR-4 zoning allows and is tucked away from the street, the planning board is unlikely to give them much trouble.

As for the Sharma-designed building that would potentially built in the foreground of this project, 301B Eddy, the last I heard was that it was not an active pursuit, if not totally off the table.

5. Here we have a do and a don’t. Do: hire a seasoned architect like Jagat Sharma, who knows his way around city staff and boards. Don’t: design anything without checking to see if the rules and regulations changed. In this case, they did, quite a bit.

The problem here with 312 East Seneca Street isn’t the development plan, which calls for ground-floor retail and studios and 2-bedroom apartments on the floors above. That’s all fine and dandy. But the city has really been focused on increasing the quality of building designs submitted for review in Ithaca, and that was codified into the Downtown Ithaca Design Guidelines, which were enacted as law earlier this year. If this were 2013, Sharma and developer Stavros Stavropoulos would probably be okay. As of now, they are not. The only part of this design that’s acceptable is the first three feet facing East Seneca Street. The exposed CMU walls on the sides? Not allowed. And according to the Times’ Matt Butler, the planning director seemed a bit insulted by the design.

Potential design options that would be compatible include additional interior facade visual elements, facade articulation and alternative side materials (brick, stone, metal panel, fiber cement, and for the sides only, synthetic stucco/EIFS) and possibly a step down in height at the rear, since the site is on the edge of its zoning.

Consider for comparison, the new Tompkins Financial building. It’s an interior block site, and while it builds very close to the boundary line and they have (and could have) bigger neighbors, the sides and rear have windows, facade variation and articulation, brick and metal panels, and design elements like sunshades and a small top floor setback. That’s very much in the mindset of what the city is looking for in the design of a downtown project. In any case, if the Stavropoli want to do something here, the sketch plan design will need to be substantially modified before there’s any hope of approval, and some meetings with city staff couldn’t hurt.

6. There have been some potential issues that have sprung up with the Emmy’s Organics project at the end of Cherry Street. The soils may be in such poor shape on the site that they’re unable to reasonably support the concrete slab for a single-story industrial building. If that’s the case, the project may not move forward, which may also result in Emmy’s moving itself and its jobs out of the city. The IURA will vote on Thursday to authorize $5,000 to hire an engineering firm to do an analysis of the geotechnical reports to see what special requirements a foundation would need, and if those requirements make the project infeasible.

7. Quick little note here – Lansing Meadows was delayed this past summer because developer Eric Goetzmann “was not able to secure contractors – too much other construction going on”, according to an email from TCAD’s Heather McDaniel. With TCAD and the village blessing, the construction start has been pushed back to Spring 2019.

8. It’s been a while since 46 South Street (formerly Hamilton Square) has updated their website, but to wrap up this post, here’s some good news for affordable housing advocates – the 73-unit, mixed-income, mixed rental and for-sale proposal by Claudia Brenner and Ithaca Neighborhood Housing Services (INHS) has passed the Trumansburg planning board’s SEQR (State Environmental Quality Review). That means that the environmental impacts are effectively mitigated by the project team. Site plan approval has yet to be issued, and is likely to be hotly debated with neighbors who have been opposed to the project since the proposal was introduced in May 2017. Review began about a year ago, and likely has a few months more yet ahead of it – certainly one of the longer review processes as of late.

On a happier note, color renderings! Nice variation in materials and style. For those so inclined, the 2 hour audio from the planning board can be found on the village website here.





News Tidbits 11/26/18

27 11 2018

Just to get this out in time, he’s a look at what will be a rather long but very interesting city of Ithaca Planning Board meeting tomorrow evening.

1 Agenda Review 6:00

2 Special Order of Business – Planning Report on ILPC recommendation to designate the former Delaware, Lackawanna, & Western Railroad Station at 701 West Seneca Street. 6:05

3 Privilege of the Floor 6:20

4 Approval of Minutes: October 23, 2018 6:35

5 Site Plan Review

A. Project: Chain Works District Redevelopment Plan (FGEIS) 6:40
Location: 620 S. Aurora St.
Applicant: Jamie Gensel for David Lubin of Unchained Properties
Actions: Distribution of FGEIS & Review of Schedule – No Action
Project Description: The proposed Chain Works District seeks to redevelop and rehabilitate the +/-800,000 sf former Morse Chain/Emerson Power Transmission facility, located on a 95-acre parcel traversing the City and Town of Ithaca’s municipal boundary. The applicant has applied for a Planned Unit Development (PUD) for development of a mixed-use district, which includes residential, commercial, office, and manufacturing. The site’s redevelopment would bridge South Hill and Downtown Ithaca, the Town and the City of Ithaca, by providing multiple intermodal access routes including a highly-desired trail connection. The project will be completed in multiple phases over a period of several years with the initial phases involving the redevelopment of the existing structures. Current redevelopment of this property will focus on retrofitting existing buildings and infrastructure for new uses. Using the existing structures, residential, commercial, studio workspaces, and office development are proposed to be predominantly within the City of Ithaca, while manufacturing will be within both the Town and City of Ithaca.

No decisions expected tonight, but the distribution of the FGEIS (Final Generic Environmental Impact Statement) is a major step forward. From here, the Planning Board will review and critique the document, and when satisfied, it will vote for a resolution of completion. A recommendation to adopt the Chainworks PUD zoning and the FGEIS findings will follow, and if successful, the Common Council will also vote to adopt the PUD zoning. That would complete generic review for the site – new builds would still come to the board as necessary, but renovations could potentially begin not long afterward. Timing-wise, the final approvals are still a few months out, but this massive 910+ unit project is slowly closing in on approvals, and potentially, construction.

B. Project: North Campus Residential Expansion (NCRE) 6:55
Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Review of FEAF Part 3
Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). All NCRE materials are available for download at: http://www.cityofithaca.org/DocumentCenter/Index/811

Materials provided indicate that city planning staff are reasonably satisfied that the energy impacts of the massive North Campus housing plan have been mitigated. The only new letter on record this month is a letter of concern from the City Historic Preservation Planner about the project’s visual and aesthetic impacts on the Cornell Heights Historic District to the west.

C. Project: Apartments (12 Units) 7:25
Location: 327 W. Seneca Street
Applicant: Noah Demarest for Visum Development
Actions: Consideration of Preliminary & Final Site Plan Approval
Project Description: The applicant is proposing to construct a three-story apartment building with 12 units. Project development requires the removal of the exiting building and parking area. The project will include exterior bike storage, a trash enclosure, walkways, landscaping, signage, and lighting. The project is in the B2-d Zoning District and has received the required variances for front-, side-, and rear-yard setbacks. A small portion at the rear of the property is in the CDB-60 District. The project has received Design Review. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”), for which the Lead Agency made a Negative Determination of Environmental Significance on September 25, 2018.

Not much to add regarding Visum’s workforce housing (80% area median income) proposal for the State Street Corridor. The project is expected to receive $200,000 from the latest round of the Community Housing Development Fund, the affordable housing fund jointly paid into by the city, county and Cornell. In this case, Cornell will cover $170,000 and the city $30,000. Cornell doesn’t have any hand in this project, but having one entity pay most of the grant for a given project makes it less complex to administer. 

D. Project: Falls Park Apartments (74 Units) 7:35
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Public Hearing, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11).

Note that IFR is a Travis Hyde Properties business entity. The attempt to gain approval for an environmentally compromised project site is likely going to be more heavily scrutinized given the recent controversy regarding proposed demolition procedures for the Old Library site.

E. Project: New Two-Family Dwellings 7:55
Location: 815-817 N Aurora
Applicant: Stavros Stavropoulos
Actions: Declaration of Lead Agency, Review of SEAF Parts 2 & 3
Project Description: The applicant proposes to demolish an existing two-family residential structure and construct two new 1,290 SF two-family dwellings on a 9,590 SF lot. The existing residential building is a legally nonconforming building with a side setback deficiency (2.9 feet instead of the required 5 feet). The proposed redevelopment will include four parking spaces for four three-bedroom apartments. The applicant is requesting the Board’s approval to use the landscaping compliance method for parking arrangement. The project site is located in the R-2b Zoning District and meets all applicable zoning lot and setback requirements. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”).

F. Project: Maguire Lincoln 8:15
Location: 370 Elmira Road
Applicant: John Snyder Architects PLLC
Actions: Declaration of Lead Agency, Review of FEAF Parts 2 & 3
Project Description: The applicant proposes to demolish a portion of the existing building and construct two additions with updated exterior materials. The existing building is 18,500 GSF, with 2,265 GSF proposed for demolition. The new building will be 24,110 GSF. Site improvements include incorporation of a new pedestrian walking path, and site connections to Wegmans. Approximately 311 parking spaces are proposed to accommodate customer, service parking, employee, and display parking. Landscape design will improve vegetative cover; however, it will not meet the City of Ithaca’s impervious/pervious requirements (12%). The project site is located in the SW-2 Zone, is subject to the 2000 Southwest Design Guidelines, and will require a zoning variance for a front yard that exceeds the maximum permissible in the SW-2 district (34 feet maximum permitted, 69-feet 3-inch setback proposed). This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”); however, it will be treated as a Type I Action for the purpose of environmental review.

G. Sketch Plan – 312 E Seneca Street, Jagat Sharma 8:35

312 East Seneca is a 4,482 SF three-story mixed-use building on the edge of Downtown Ithaca. The building was long-owned by Ithaca architect Jagat Sharma, who ran his practice from the building (1416 SF), the Alley Cat Cafe (1926 SF), and a four-bedroom apartment (1140 SF) on the upper floors.

A few years ago, the site was floated as part of the potential footprint for Visum Development’s Seneca Flats mixed-use project, though at the time it was made clear that it was not an essential property to the development, and simply a possibility if Sharma chose to sell to Visum. Sharma didn’t – in September, he sold the building to an LLC associated with the Stavropoulos family for $800,000, double the assessed value. That lofty price relative to assessed value was a big clue something was planned here, and it looks like the first glimpse of that will come tomorrow night. The Stavropoli of West Hill have been growing their assets through acquisition or development for the past several years, including the 4-unit North Aurora project in item E. above.

Normally, the Stavropoulos family is low-key about development, preferring lower-profile infill builds in established neighborhoods – the largest project of theirs to date is the 11-unit 107 South Albany project. They often turn to local architect Daniel Hirtler, but this time, Collegetown favorite Jagat Sharma will have a hand in redeveloping the building that housed his office for so many years. This would be Sharma’s first building downtown since the Greenstate Building (127 West State Street) in 1991. For the record, this would be their second Sharma commission, with a duplex planned for 209 Hudson Street being the other (granted, that’s also a modular structure).

Zoning-wise, this is CBD-60. Within that zone, Sharma can design a five-story building up to 60 feet tall, no parking required, with any variety of commercial or residential uses. Any design will have to conform with the recently-adopted Downtown Design Guidelines. The Stavropoli are likely to do all-residential or residential with ground-floor retail. The current building is quite narrow, but it also only occupied the east half of the lot – a new structure could practically touch the neighboring building at 308 East Seneca.

H. Sketch Plan – 114 Catherine Street, Jagat Sharma 8:55

Things are about to get a bit confusing. A few years ago, the Lambrou family, mid-sized Collegetown landlords and developers of Collegetown Park, presented and built an infill project at 114 Catherine Street – while all the working docs used 114 Catherine Street, the address of the existing building set back into the lot, the new 3-unit, 17-bedroom building was christened 116 Catherine Street.

This new building is expected to be a replacement for the existing 114 Catherine Street, the Mission Apartments, and is expected to complement 116 Catherine in appearance (Jagat Sharma designed that as well). Zoning here is CR-4, up to four floors, with a maximum of 50% lot coverage (but not parking required). Expect this to be student housing – probably not too big, a few dozen beds at most, but something to take note of nevertheless.

I. Sketch Plan – 130 Cherry Street, Residential, Vecino Group 9:15

130 Cherry Street is a 4,600 SF auto body shop that’s been for sale for quite a while now. The rumor mill says Vecino CEO Rick Manzardo was walking around the area a couple of weeks ago, and it looks like there was a reason for that. The plan being floated is affordable “artist housing”. This wouldn’t be a new concept to Vecino, who renovated a vacant warehouse in Troy into the 80-unit Hudson Arthaus. What makes the Arthaus unique among affordable housing is that it offers on-site amenities geared to artists, as well as income-based rents for those who make only a modest living while engaged in their creative pursuits.  Those amenities include a wood shop, on-site storage units, gallery spaces managed by a local non-profit, and a computer/digital work suite.

Zoning here is “Cherry Street District” Waterfront Zoning. Since it’s north of Cecil Malone Drive, housing is allowed – but not on the first floor. The first floor is for light industrial and many commercial uses, including restaurants, stores and offices. No ground-level storage permitted, however. In this “artist housing” format, the first floor would likely be the exhibition/gallery.workshop space. The building may be up to five floors with 100% lot coverage once setback requirements are met. Bonus for this site, the Cherry Artspace is a few hundred feet away. With about 179,000 SF in building capacity offered by the site and zoning before setbacks are considered, a potential project could be fairly sizable.

6. Old/New Business 9:35

7. Reports 9:40
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development

8. Adjournment 10:00





802 Dryden Road Construction Update, 11/2018

21 11 2018

802 Dryden Road, also called “Ivy Ridge”, was originally the product of local developer Charlie O’Connor, CEO of Modern Living Rentals. However, just as site preparation and underground utility installations were getting underway late last summer, the project changed hands. On September 12th, the site and construction plans were sold for $2.075 million. Filed on the same day was a construction loan from M&T Bank to pay for construction of the project – a rather substantial $8.6 million for the 42-unit, 108-bedroom townhouse complex. The buyer’s LLC was linked to a suburban Pittsburgh address for Matthew Durbin, and a little online searching indicates Durbin is a Cornell Johnson School (MBA) Alumnus, a former investment banker turned business executive. In short, an outside investor but with a demonstrated familiarity with the Ithaca area, business acumen and the money to make things happen. The sale does not appear to have altered the plans (any revisions would need to be approved by the town of Dryden) or the timeline.

Framing has started on one of the townhouse strings (each string is seven units apiece) and foundation work has started on a second. The plan is to have the units ready for occupancy in time for the Fall 2019 academic semester – being right next to the Cornell Arboretum, it’s a literal stone’s throw from the edge of Cornell campus, and is intended to appeal to graduate or professional students (especially students of the veterinary school, whose location on the eastern edge of Cornell campus has left them with few walkable options). STREAM Collaborative designed the units, Taitem Engineering is on board as a structural engineer, and Granger Construction of East Syracuse is the general contractor.

A full description of the project and its history can be found here.





News Tidbits 10/20/18

20 10 2018


1. So here’s an intriguing update to the stalled redevelopment at 413-415 West Seneca Street. Ithaca Neighborhood Housing Services was preparing to buy the former Ithaca Glass property and its development plans, which had hit a major snag due to structural issues with the existing building, and continued financial issues with pursuing of a completely new build (bottom). INHS was planning on purchasing the site and going with the original plan, which would have added four units to the existing two apartments and vacant commercial space. But someone outbid them for the site. The buyer, who has not finalized the purchase, may elect to use either of the plans designed by STREAM Collaborative, or pursue a different project at the site.

While that plan may have fallen through, it looks like the INHS Scattered Site 2 rehab/redevelopment plan will be moving forward following approval of amendments to the funding plan by the IURA and Common Council. The revised plan will dedicate funds toward the replacement of fourteen units (four vacant due to structural issues) in three buildings to be replaced with a new thirteen-unit apartment building at 203-208 Elm Street on West Hill, and major rehabiliation of four other structures (sixteen units) in Southside and the State Street Corridor.

2. Speaking of sales, here’s something to keep an eye on – the Lower family, longtime Collegetown landlords, sold a pair of prime parcels on October 4th. 216-224 Dryden Road was sold for $2.8 million, and 301 Bryant Avenue was sold for $1.4 million. Both properties were sold to LLCs whose registration address was a P.O. Box. A couple of local development firms like to use P.O. Boxes, but with nothing concrete, it’s uncertain who’s behind the purchases.

301 Bryant Avenue has some historic significance as the formal home of the Cornell Cosmopolitan Club. Founded in 1904 as a men’s organization to provide camaraderie and support for international students attending the university, the 13,204 SF, 35-bedroom structure was built in 1911 and served as the equivalent of a fraternity’s chapter house, providing a shared roof, shared meals, social events, lectures by students and faculty about other lands and cultures, and professional networking for students arriving from abroad. A women’s club was organized in 1921. As Cornell grew and different international groups founded their own organizations, the club’s purpose was superseded, and shut down in 1958. The building was purchased by the parishioners of St Catherine’s a parish center before the new one was built in the 1960s, and served as a dorm for the Cascadilla School before Bill Lower bought the building in 1973. Lower converted the structure into a six-unit apartment building, with the largest nit being eight bedrooms. With an estimated property assessment of $1.27 million, the sale appears to be for fair value – no issues, and no indications of redevelopment.

216-224 Dryden Road is much more interesting from a development perspective. 11,600 SF in three buildings (county data suggests either 14 units, or 9 units and 20 single occupancy rooms), the earliest buildings in the assemblage date from the early 1900s, but with heavy modifications and additions to accommodate student renter growth. Bill Lower bought the property way back in 1968. The properties are only assessed at $1.87 million, well below the sale price. That suggests that a buyer may be looking at redevelopment of the site. The site is in highly desirable inner Collegetown, and the zoning is certainly amenable; CR-4 zoning allows 50% lot coverage and four floors with no parking required. CR-4 offers a lot of flexibility – 119-125 College Avenue and the Lux are recent CR-4 projects.

3. The other recent set of big purchases also occurred on October 4th. “325 WEST SENECA ASSOCIATES LLC” bought 111 North Plain Street, 325 West Seneca Street, 325.5 West Seneca St (rear building of 325) and 329-31 West Seneca Street for $1.375 million. 325 West Seneca is a three-unit apartment house assessed at $200k, 325.5 West Seneca is a modest bungalow carriage house assessed at $100k, 329-331 West Seneca is a two-family home assessed at $360k, and 111 North Plain Street in a neight-unit apartment building assessed at $475k. Added up, one gets $1.135 million, which suggests the purchase price was reasonable.

Given that 327 West Seneca is currently the subject of a moderate-income redevelopment proposal from Visum, one would expect Visum to likely be behind these purchases, right? But the LLC traces back to the headquarters of a rival real estate development firm, Travis Hyde Properties. The whole thing strikes me as a little odd, but who knows, maybe Frost Travis bought the properties as stable assets rather than development sites.

4. Let’s stick with Travis Hyde Properties for a moment – here are the submissions related to his Falls Park Apartments proposal. Readers might recall this is the plan for 74 high-end senior apartments on the former Ithaca Gun site. Drawings here, 138-page submission package courtesy of TWMLA’s Kim Michaels here. Trowbridge Wolf Michaels Landscape Architecture will handle the landscape design, and newcomers WDG Architecture of Washington D.C. are designing the building.

No cost estimate has been released for the project, but buildout is expected to take 20 months. 150 construction jobs will be created during buildout, and the finished building will create four permanent jobs. The project will utilize New York State Brownfield Cleanup Program (NYS BCP) tax credits. In the case of this project, the credits would be a smaller credit to help cover the costs of site remediation insurance, and a larger credit awarded by the state that would cover 10-20% of the project’s property value, depending on whether it meets certain thresholds. It is still not clear at this point if a CIITAP tax abatement will be pursued.

The 74 units break down as follows: 33 two-bedroom units (1245 SF), 9 one-bedroom units with dens (1090 SF), and 32 one-bedroom units (908 SF). All units include full-size kitchens, wood and/or natural stone finishes, and about half will have balconies. Also included in the 133,000 SF building is 7,440 of amenity space, and there will be 85 parking spaces, 20 surface and 65 in the ground-level garage.

A number of green features are included in the project, such as LED lighting, low-water plumbing fixtures, and a sophisticated Daikin AURORA VRV high-efficency HVAC system, which uses air-source heat pumps. It look like there is some natural gas involved, however, for heating the rooftop ventilation units, and in the amenity space’s fireplace.

Due to soil contamination issues, the plan is essentially to dig up the soil and cart it off to the landfill in Seneca County. The soil runs up to 11.5 feet deep, and the building foundation will be 15 feet below current surface level (about 85% of the foundation will be a shallow slab, with deeper piles near the northeast corner). As a result, some of the bedrock will be removed and disposed of as well. What soil does remain on-site will be sealed in a NYSDEC-approved cap. Concerns about VOCs in the groundwater are somewhat mitigated by the geology of the site (horizontal fractures carry the VOCs downhill), but the ground level is a ventilated garage in part to prevent sustained exposure to vapor intrusion. The project will be presented at this month’s Planning Board meeting, where the board is expected to declare itself lead agency for environmental and site plan review of the proposal.

https://platform.twitter.com/widgets.js

5. So, one of the reasons why the Voice writeup on the Carpenter Park site didn’t include building renders was because in a follow-up phone call for hashing out the emailing of PDF images, Scott Whitham of Whitham Planning was adamant they not be used, describing them as highly conceptual. He didn’t even want to pass them along out of fear they’d mislead the general public. For the merely curious, here are images taken by Second Ward Councilman Ducson Nguyen.

The architecture firm that’s involved with the project is a newcomer to the Ithaca area – Barton Partners, which has a lot of rather high-end, traditional-looking design work scattered throughout the Northeast, as well as a new more modern designs similar to the placeholders. Can’t make any hard conclusions at this point, but a look through their portfolio gives an idea of what one might expect to see with the Carpenter Park redevelopment.

6. The former Wharton movie studio at Stewart Park is slated to become a gallery and visitor’s center, thanks to a $450,000 state grant. The building, which was the studio’s main office from 1914 to 1920, and is currently used by the city Board of Public Works, will be renovated into the Wharton Museum, with exhibit space, a public meeting room, and a terrace / seating area overlooking the lake. The project will be a joint effort by the Wharton Studio Museum and Friends of Stewart Park, with assistance from the City of Ithaca. Todd Zwigard Architects of Skaneateles (Skinny-atlas) will be in charge of designing the new museum space. It will be fairly modest in size, about 1,000 square feet, with the rest remaining for BPW use; the public works division will compensate the loss of space with an addition onto its annex nearby.

The project should dovetail nicely with a couple of other local nonprofit projects underway – the revitalization and expansion of the Stewart Park playground will give younger visitors something to do while their parents or grandparents check out the museum, and there’s potential to work with The Tompkins Center for History and Culture on joint projects that encourage visitors to pay a visit to both Downtown and the lakefront.

7. The Old Library redevelopment is once again the subject of controversy. Due to structural issues with the roof and concerns about it collapsing onto workers during asbestos abatement, the city condemned the building, which changed Travis Hyde Properties plans from sealing the building in a bubble and removing the asbestos before demolition, to tearing it down without removing asbestos from the interior first. Much of the asbestos from its late 1960s construction was removed as part of renovations in 1984, with more in the 1990s, but in areas that weren’t easily accessible, it was left in place.

The new removal plan has led to significant pushback, led by local environmental activist Walter Hang. A petition floating around demands that the city un-condemn the building and then forces Travis Hyde to renovate the building enough to stabilize the roof to remove the asbestos.

While the concern about the asbestos is merited, there are a couple of problems with this plan. It boils down to the fact that New York State code, rather than the city, defines what a developer can and can’t do with asbestos abatement. The two options here are stabilization and removal before demolition of the above-ground structure, or tearing it down piece by piece and using procedures like misting to keep the asbestos from getting airborne, with monitors in place to ensure no fibers are entering the air. The city can’t force a developer to choose one approach over another, if a building is condemned, and the city can’t force Travis Hyde to renovate the building to a state where it wouldn’t be condemned. That would be the NYS Department of Labor’s role. But if the city rescinded its condemnation, a roof renovation would involve removing the existing roof – a procedure that involves misting the on-site asbestos to keep it from getting airborne. With workers going in an out of the building to stabilize the structure and being put at risk by the unstable roof as well as the asbestos, the Department of Labor isn’t going to sign off on anything putting crewmen at risk of a roof collapse.

There is some consternation with this, and that’s fair. The development project did take several months longer to move forward than first anticipated, though had it started on time it’s not clear if the city and THP wouldn’t have been in this position anyway if work had started sooner. Demolition is expected to start within thirty days of the permit being issued (and it has, so in effect, any day now), and take six to eight weeks to complete.

8. Unfortunately, I had to miss this year’s architects’ gallery night, which is a shame because the local firms like to sneak in yet-unannounced plans. Case in point, this photo from Whitham Planning and Design’s facebook page clearly shows something is planned at the site of the Grayhaven Motel at 657 Elmira Road. The Grayhaven has four on-site structures, and the two westernmost buildings look as they do now…but the footprints of the two eastern buildings, where one first pulls in, do not match their current configuration. Intriguing, but also frustrating. The boards on the floor are related to the Visum Green Street proposal, and the other wall board is a North Campus proposal that didn’t make the cut, previously discussed on the blog here.

9. Out in the towns, there’s not a whole lot being reviewed as of late. The town of Lansing will have a look next week at marina renovations, a one lot subdivision, and a 4,250 SF (50’x85′) expansion of a manufacturer, MPL Inc., a circuit board assembler at 41 Dutch Mill Road. The expansion of their 14,250 SF building will create five jobs or less, per site plan review documents.

In Dryden town, the town board continued to review the proposed veterinary office in the former Phoneix Books barn at 1610 Dryden Road, and they’ll had a look at a cell phone tower planned near TC3. Danby’s Planning Board looked at an accessory dwelling application and a two-lot subdivision last week. Ulysses had a look at a proposal for a 6,400 SF pre-school and nursery building planned for 1966 Trumansburg Road, a bit north of Jacksonville hamlet.

The village of Cayuga Heights Planning Board has a single-family home proposal to look at 1012 Triphammer Road, and in the village of Lansing, the Planning Board and Board of Trustees will review and weigh consideration of a PDA that would allow the Beer family’s proposal for multiple pocket neighborhoods of senior cottages to move forward on 40 acres between Millcroft Way and Craft Road. Trumansburg is still looking at the 46 South Street proposal from INHS and Claudia Brenner.

10. Last but not least, the city of Ithaca Planning Board’s agenda for next week. Apart from the long-brewing Carpenter project, there’s nothing else that’s new, continuing the relative lull in new projects. Cornell’s North Campus Expansion continues its public hearing, and the new warehouse and HQ for Emmy’s Organics looks ready to obtain final site plan approval.

1 Agenda Review 6:00
2 Privilege of the Floor 6:05
3 Approval of Minutes: September 25, 2018 6:15
4 Subdivision Review

A. Project: Minor Subdivision 6:20
Location: 111 Clinton St Tax Parcel # 80.-11-11
Applicant: Lynn Truame for Ithaca Neighborhood Housing Services
Actions: Consideration of Preliminary & Final Subdivision Approval

Project Description: The applicant is proposing to subdivide the 1.71 acre property onto two parcels: Parcel A measuring 1.6 acres (69,848 SF) with 299 feet of frontage on S Geneva St and 173 feet on W Clinton St and containing two existing buildings, parking and other site features; and Parcel B measuring .1 acres (4,480 SF) with and 75 feet of frontage on W Clinton St and containing one multi-family building. The property is in the P-1 Zoning District which has the following minimum requirements: 3,000 SF lot size, 30 feet of street frontage, 25-foor front yard, and 10-foot side yards. The project requires an area variance of the existing deficient front yard on the proposed Parcel B. The project is in the Henry St John Historic District. This is an Unlisted Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) and the State Environmental Quality Review Act (“SEQRA”), and is subject to environmental review.

The story behind this is that for legal purposes, INHS needs to split an existing house from its multi-building lot before it can proceed with renovating it as part of the Scatter Site Housing renovation project. No new construction is planned.

B. Project: Major Subdivision (4 Lots) 6:30
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Nels Bohn for the Ithaca Urban Renewal Agency (IURA)
Actions: Consideration of Preliminary Subdivision Approval

Project Description: The IURA is proposing to subdivide the 6-acre parcel into four lots. Lot 1 will measure 1.012 acres, Lot 2 will measure 1.023 acres, Lot 3 will measure 2.601 acres, and Lot 4 will measure .619 acres. Lot 3 will be sold to Emmy’s Organics (see below), Lot 4 will be left undeveloped for future trail use, and Lots 1 & 2 will be marketed and sold for future development. This subdivision is part of a larger development project that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

The Emmy’s Organics project is really two components – one, the new building in the city-owned Cherry Industrial Park, and two, the city’s (IURA’s) construction of a street extension that would service Emmy’s and two smaller lots which could then be sold to a buyer committed to economic growth for presently low and moderate-income households.

5 Site Plan Review
A. Project: Construction of a Public Road 6:45
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Nels Bohn for the Ithaca Urban Renewal Agency (IURA)
Actions: Consideration of Preliminary & Final Approval

Project Description: The IURA is proposing to extend Cherry Street by 400 feet. The road will be built to City standards with a 65-foot ROW, 5-foot sidewalks and tree lawn, and will be turned over to the City upon completion. The road extension is part of a larger development project that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

B. Project: Construction of a 14-24,000 SF Production Facility (Emmy’s Organics) 7:00
Location: Cherry Street, Tax Parcel # 100.-2-21
Applicant: Ian Gaffney for Emmy’s Organics
Actions: Consideration of Preliminary &Final Approval

Project Description: Emmy’s Organics is proposing to construct a production facility of up to 24,000 SF, with a loading dock, parking for 22 cars, landscaping, lighting, and signage. The project will be in two phases: Phase one, which will include a 14,000 SF building and all site improvements; and Phase two, (expected in the next 5 years) which will include an addition of between 14,000 and 20,000 SF. As the project site is undeveloped, site development will include the removal of 2 acres of vegetation including 55 trees of various sizes. The facility is part of a larger project that includes subdivision of land a 40-foot road extension by the Ithaca IURA extension that is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (c) and (j) and B(4) the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11), for which the Planning Board made a Negative Declaration of Environmental Significance on September 25, 2018.

C. Project: North Campus Residential Expansion (NCRE) 7:20 Location: Cornell University Campus
Applicant: Trowbridge Wolf Michaels for Cornell University
Actions: Public Hearing (continued)

Project Description: The applicant proposes to construct two residential complexes (one for sophomores and the other for freshmen) on two sites on North Campus. The sophomore site will have four residential buildings with 800 new beds and associated program space totaling 299,900 SF and a 59,700 SF, 1,200-seat, dining facility. The sophomore site is mainly in the City of Ithaca with a small portion in the Village of Cayuga Heights; however, all buildings are in the City. The freshman site will have three new residential buildings (each spanning the City and Town line) with a total of 401,200 SF and 1,200 new beds and associated program space – 223,400 of which is in the City, and 177,800 of which is in the Town. The buildings will be between two and six stories using a modern aesthetic. The project is in three zoning districts: the U-I zoning district in the City in which the proposed five stories and 55 feet are allowed; the Low Density Residential District (LDR) in the Town which allows for the proposed two-story residence halls (with a special permit); and the Multiple Housing District within Cayuga Heights in which no buildings are proposed. This has been determined to be a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B.(1)(b), (h) 4, (i) and (n) and the State Environmental Quality Review Act (“SEQRA”) § 617.4 (b)(5)(iii). All NCRE materials are available for download at: http://www.cityofithaca.org/DocumentCenter/Index/811

D. Project: Falls Park Apartments (74 Units) 7:50 (Notes above)
Location: 121-125 Lake Street
Applicant: IFR Development LLC
Actions: Project Overview Presentation, Declaration of Lead Agency
Project Description: The applicant proposes to build a 133,000 GSF, four-story apartment building and associated site improvements on the former Gun Hill Factory site. The 74-unit, age-restricted apartment building will be a mix of one- and two-bedroom units and will include 7,440 SF of amenity space and 85 parking spaces (20 surface spaces and 65 covered spaces under the building). Site improvements include an eight-foot wide public walkway located within the dedicated open space on adjacent City Property (as required per agreements established between the City and the property owner in 2007) and is to be constructed by the project sponsor. The project site is currently in the New York State Brownfield Cleanup Program (BCP). Before site development can occur, the applicant is required to remediate the site based on soil cleanup objectives for restricted residential use. A remedial investigation (RI) was recently completed at the site and was submitted to NYSDEC in August 2018. The project is in the R-3a Zoning District and requires multiple variances. This is a Type I Action under the City of Ithaca Environmental Quality Review Ordinance (“CEQRO”) §176-4 B(1) (h)[2], (k) and (n) and the State Environmental Quality Review Act (“SEQRA”) §617-4 (b) (11).

E. Sketch Plan – Mixed-Use Proposal – Carpenter Business Park 8:10

6 Zoning Appeals 8:30
# 3108, Area Variance, 327 W Seneca Street
# 3109, Area Variance, 210 Park Place (construction of a carport)
# 3110, Area Variance, 121 W Buffalo Street (installing a deck and wheelchair lift)
# 3111, Use Variance, 2 Fountain Place (the proposed B&B in the old Ithaca College President’s Mansion)
# 3112, use Variance, 2 Willets Place

7 Old/New Business 8:40
Special Meeting October 30, 2018: City Sexual Harassment Policy, Special Permits (Some of the BZA’s Special Permits Review duties are set to be transferred to the Planning Board).

8 Reports 9:00
A. Planning Board Chair
B. BPW Liaison
C. Director of Planning & Development

9 Adjournment 9:25





118 College Avenue Construction Update, 9/2018

10 10 2018

The last of Visum‘s projects from the September photos batch is the 5-unit, 28-bedroom 118 College Avenue in Collegetown. The student-focused apartment building is topped out, fully framed, and sheathed. The mechanical penthouse, which STREAM Collaborative designed to emulate an Italianate cupola, appears to be framed but not closed in. The windows and doors have been fitted, and the balconies are partially complete. Some of the face brick can be seen on the first floor, and like the other Visum projects, the wood rails nailed over the ZIP panels will be used for attachment of the fiber cement siding. The original plans has a small top floor setback on the north face, and the projecting bays at the front (east face) were originally bumped out slightly from the side walls, but both of those features were value engineered out. At a glance, not much has changed on the outside since final approval was granted, a good sign that the project has stayed within budget – bravo to STREAM, Romig Construction and Taitem Engineering for helping Visum bring this project to fruition.

As with other inner Collegetown projects, rent will be fairly steep – $1,200 – $1,300 per bedroom per month. Visum’s property management page, Live More Ithaca, has an August 2019 availability, but I suspect this building will be finished in time for the spring semester, given how far along it is. Maybe there are renters already secured for a shorter lease period – it’s hard to imagine the building would be left newly finished but vacant for that long.