Work on the Gannett Health Center is at the transition point between the first and second phases. With the new wing largely finished, occupants have been migrating into the new digs, while the interiors of the original 1957 wing and later 1979 addition are being prepped for a gut renovation. There’s still some bluestone and limestone cladding yet to go on the new wing’s stairwells, but the interior’s complete enough that a certificate of occupancy could be issued. I’ve received a couple messages from folks who are less than happy that the temporary main entrance in next to the ambulance bay, and that the interior’s lack of finish at moving was less than comforting to clients, but both of those problems will (hopefully) be rectified as the second phase moves towards an August 2017 completion. The whole facility will be known collectively as “Cornell Health“.
Gannett Health Center Construction Update, 7/2016
30 07 2016Comments : Leave a Comment »
Tags: construction, construction (planned), Cornell, gannett, gannett health center, photos
Categories : construction, construction (planned), Cornell, photos
210 Hancock Construction Update, 7/2016
28 07 2016At the 210 Hancock property in Ithaca’s Northside neighborhood, site prep is taking place. The site is being graded and excavation is now underway for subsurface utilities installation (water and sewer pipes, the teal tubes stacked in the photos). INHS is conducting vibration monitoring while all this goes on, although the pile installation won’t start for another couple weeks, running foe about three weeks, mid-late August to mid September. Contractor Lecesse Construction will be installing 10-15 piles per day with a hydraulic hammer, between the hours of 8 AM and 4 PM. If the Voice’s Facebook inbox during the demolition phase this past spring was any indication, some very zealous neighbors will be providing breathless live coverage.
All in all, the contractor issue set INHS back about three months, but the grant funding is accommodating and rental agreements won’t be signed until the project is much closer to completion, late spring or summer 2017. For those who meet the affordable income brackets (breakdowns here), the rental interest form is here. The 54 apartments and the 5 rental townhomes should be ready to go by this time next year.
Comments : Leave a Comment »
Tags: 210 hancock, affordable housing, construction, construction (planned), inhs, ithaca, northside, photos
Categories : affordable housing, construction, construction (planned), ithaca, photos
Collegetown Terrace Construction Update, 7/2016
19 07 2016Things are moving along steadily at the Collegetown Terrace site off East State Street. Building 7 snakes it way through the site, with work progressing from west to east. Furthest east, the concrete for the parking area is still being poured and cured.
A little further west towards the middle, the enclosed and finished parking area gives way to steel interior stud walls and unsheathed plywood, with only the lower floors in the middle section, but the steel stud walls and plywood have been built to the full height of the building (fully framed up) in the westernmost part.
The frame of a new skybridge has been installed between buildings 5 and 7, connecting near the elevator shaft/stairwell. Some Paradigm windows have already been fitted into the exterior. Eventually, the exterior will be sheathed, and then the exterior facade materials can be applied. It would honestly not be a surprise if the whole building is fully framed before the first snow flies.
Welliver‘s the general contractor for Novarr-Mackesey’s 247-unit project.

Comments : Leave a Comment »
Tags: collegetown, collegetown terrace, construction, construction (planned), ithaca, photos, student housing
Categories : collegetown, construction, construction (planned), ithaca, photos, student housing
Cayuga Meadows Construction Update, 7/2016
18 07 2016Safe to say this is under construction. Work has commenced on Conifer LLC’s Cayuga Meadows affordable senior housing project on West Hill.
Cayuga Meadows is a 3-story, 58,500 SF apartment building with 68 units, 59 1-bedroom and 9 2-bedroom. The units will be available to individuals aged 55 and older, with incomes 60% or less or the Area Median Income (AMI). AMI in Tompkins County is about $53,000 per household, so a qualifying senior household would have an annual income of $31,800 or less. 7 units will be accessible to mobility-impaired individuals, and 3 units will be designed to accommodate hearing or visually-impaired occupants. Included in the plans are two covered patios, a community garden, and stormwater, lighting and landscaping improvements. 67 parking spaces will be paved behind the building.
The history of Cayuga Meadows goes back a few years, and has its share of twists. Originally, the project had been conceived as “Conifer West Hill” in 2009 as a component to a Cornell-led mixed-use development on about 36 acres of land across from Cayuga Medical Center. Rochester-based Conifer’s part in the plan has always been the same – affordable housing for seniors. But Cornell had other plans for the rest of the acreage.
In Spring 2010, there were three different site plans being floated – the consistent components were Conifer’s project, a 68-bed assisted living facility called “Terrace at Ithaca”, medical office space, small-scale retail, 106 park-and-ride spaces, and 4,000 SF for a farmer’s market. Depending on the plan, there were townhomes, a hotel school conference center, or other institutional space for Cornell. Mixed-use, definitely, but the plans weren’t that walkable, traditional neighborhood feel that the town is looking for these days – in fact, they were fairly conventional suburban sprawl. Cornell’s approach to planning was different in the late 2000s. By good fortune, Ithaca Builds locally hosted a copy of those site plans here.
For a combination of reasons (financial feasibility, changing priorities), Cornell ended up shelving its plans. However, it would be incorrect to say the university isn’t still interested in the site – they recently bought the house at 1250 Trumansburg Road, whose property had been awkwardly carved out of the rest of the site in a subdivision long ago. In the 2010 plans, Cornell had to plan around the house, not to mention worry about the occupants complaining about Cornell’s plans. So when it came on the market and sat for a couple months, the Big Red decided to pick it up in June for $157,000, probably on the belief that it could pay off through easier site planning and development down the line.
While Cornell filed away their plans, Conifer continued with theirs since the university was still willing to give them land as long as they built affordable housing. Originally, it was conceived as 72 units when it first received preliminary approval in April 2012, but was trimmed to 68 when final approval was granted in November 2013, in order to make the project a little less expensive, and provide a little more space to the community garden. Between preliminary and final approval, Conifer also had to apply for rezoning (Medium-Density Residential to Multiple Residence in May 2012), zoning variances (June 2012, for height and building setbacks), and public works approval for utilities services to be installed.
Then came another few years’ wait while financing was being secured. As covered on the Voice, affordable housing grants are very competitive, so it often takes multiple rounds of applications before a project is finally given grant money. In Conifer’s case, the last piece of the puzzle, tax-exempt bonds, didn’t come through until late January 2016. Cayuga Meadows is a $14.9 million project – about $8.3 million comes from NYS Housing Finance Agency bonds, and another $6.3 million from Community Development Block Grant (CDBG) funds. First Niagara Bank provided the Letter of Credit for the bonds. The project will pay taxes.
With the funding in hand, Cornell and Conifer formally agreed to a subdivision of Cornell’s land – 4.9 acres for the senior housing, and another acre for the Right-Of-Way for the new road. Cornell and Conifer had to agree on a few choices for new road names, which they submitted to Ithaca’s Codes Enforcement Director (Bruce Bates), who checks with the county to make sure there are no issues with the choices, and then the three parties agree on a final selection. Cayuga Meadows’ address will be “108 Aster Lane”.
There’s yet to be a color render hosted online, but the exterior will use fiber cement siding – Certainteed “Savannah Wicker” Dutch Lap Siding and “Cypress Spruce” cedar-like shingle siding. For the sake of examples, the Belle Sherman Cottages and Stone Quarry Apartments have also used Savannah Wicker fiber cement. The roof will be Timberline “Weathered Wood” shingles.
At the project site right now, work is underway on the foundation. The building’s footprint has been cleared, the foundation is excavated, and footers are poured for where the concrete will transfer the weight into the ground. Wooden forms are built along the perimeter for the stem walls, rebar is laid for reinforcement of the concrete, and the concrete is poured and left to harden (cured). Once the concrete has had a chance to harden, the forms are lifted off and work moves onto the next section. The building will be a slab-on-grade foundation, so no worries about excavating a basement here.
As a side note, it seems fitting that the residents with east-facing windows will have some pretty fantastic views of Cornell.
Through a joint venture with Conifer, LeChase Construction of Rochester will be serving as general contractor. The excavating has been subcontracted out to Neally-DeJong Excavating of Corning, and concrete work to Architectural Concrete Plus of Dundee (Yates County, northwest of Watkins Glen). Thanks to “Drill Deep” for the clarification.
Comments : 6 Comments »
Tags: affordable housing, cayuga meadows, conifer llc, construction, construction (planned), Cornell, ithaca, photos, senior housing, west hill
Categories : affordable housing, construction, construction (planned), Cornell, ithaca, news, photos, senior housing
St. Catherine of Siena Parish Center Construction Update, 7/2016
6 07 2016This one’s a little tough to swing since it’s a jaunt from most of the other construction projects underway, but the drive over was worth the effort. St. Catherine of Siena Church in Northeast Ithaca is progressing with work on its new Parish Center.
The 8,878 SF, one-story building, vaguely in the shape of a cross, is being built to replace the existing one-story, 10,273 SF parish center, which was built in 1963 and designed by local architect Victor Bagnardi. Bagnardi also did Trinity Lutheran on Honness Lane, and the old county library a couple of years later. At over fifty years of age, with alterations, outdated interior layouts and with many of its mechanical and utility systems worn out and in need of replacement, the church opted to build a new structure rather than renovate the existing building. The centerpiece of the site, the 1961 church, was renovated in the late 2000s.
Plans originally approved in summer 2015 called for a 10,811 SF building with roughly the same overall shape and appearance as the building underway. However, that plan was trimmed down as a result of rising construction costs. An earlier plan by Ithaca architect Pamela Kingsbury was also shelved for similar reasons.
The project is expected to cost in the range of $3-$3.5 million, all of which must come from church funds and philanthropy. The Diocese of Rochester does allow bridge loans, but it does not allow any parish in its jurisdiction to carry long-term debt. A similar debt-free approach is also in place for the Al-Huda mosque planned on Graham Road in Lansing. Along with donations, St. Catherine of Siena used funds from a late pastor’s bequest, sale of land near its entrance, and leftover funds from previous budgets and campaigns to bring the construction project to fruition.
At this point, the foundation has been formed, poured and back-filled. Subsurface (under-slab) utilities, such as plumbing and electrical, have been laid for the new building. Framing should commence shortly.
Plans call for a late 2016 opening. Once the new parish center is occupied, the old parish center will be taken down and its footprint converted into new parking spaces to replace those lost to the construction of the new facility. The new center will be physically connected to the church, directly to the church’s west by about 40 feet.
Richard McElhiney Architects of New York City is the project architect. Local firms T.G. Miller PC (surveying/engineering work), Trowbridge Wolf Michaels Landscape Architects (landscaping), and TAITEM Engineering PC (rooftop solar panels) are also playing a role in the buildout.
Comments : 5 Comments »
Tags: construction, construction (planned), ithaca, photos, religious structures, st catherine of siena
Categories : construction, construction (planned), ithaca, photos
Village Solars Construction Update, 6/2016
22 06 2016For being such a large project, the Village Solars apartments in the town of Lansing tend to slip by unnoticed. Work on Phase 2 is wrapping up, and work has already begun on Phase 3, with what looks like excavation work for the foundation of Building “I”. A rolling stone gathers no moss, I guess. “I” will be an 18-unit apartment building similar in design to Building “G/H”, the building in the fourth photo, and currently the largest individual apartment building in the complex.
Building “D” is essentially complete and has been available for occupancy since May. Building “G/H”, which is just finishing up any remaining interior finishes and exterior trim, will be ready for occupancy this month. Building “E”, which is still attaching exterior trim and finishes, as well as interior work, will be ready for its tenants by about July 15th. If past work is any indicator, “I” will be ready for occupancy sometime next spring. No word on Phase 2A and Building “F”, but it’s a good bet 18-unit Building “J”, the other half of Phase 3, will commence excavation once “G/H” and/or “E” are complete.
With the completion of Phase 2 this summer, The Village Solars additions will have resulted in 77 new housing units since they began construction in 2014. Rents on the units are ranging from $850+/month for a one-bedroom, $1235+/month for a 2-bedroom and $1600-$1650/month for a 3-bedroom unit.
Comments : 5 Comments »
Tags: construction, construction (planned), general housing, lansing, tompkins county, village solars
Categories : construction, construction (planned), general housing, photos, Tompkins County
307 College Avenue (Collegetown Crossing) Construction Update, 6/2016
20 06 2016307 College isn’t too far from completion at this point. The angles where with CMU dominates the exterior look nearly finished from the outside. Some of the windows are in on the front side – the projecting section, currently covered in Tyvek housewrap, will be mostly faced with dark brick, similar to the brick used on the rear CR-4 portion. The bare expanses will be a glass curtain wall, and a lighter brick will be used on the sides and for the cornice. Traditional scaffolding needs a certain amount of space and time to be set up and taken down, so given the dense environment and summer deadline of the Collegetown Crossing project, mast climbing work platforms are used being for the bricklaying and other exterior facade work.
Greenstar’s new grocery location on the first floor should be opening August 17th, right around when the first tenants start moving into the apartments. It sounds like it will be a soft opening, with an actual Grand Opening celebration planned for some date in September. A render of the interior of the new Greenstar location, designed by architect Pam Wooster, is included below. Greenstar plans to employ 14 at the new location, and include a cafe/to-go space to complement its full-service grocery (some of the items, like those in the deli, won’t be prepared on site due to space constraints; they will be prepared at their central kitchen and brought in daily). There hasn’t been any news on tenants for the smaller two commercial spaces facing the pocket park.


Comments : Leave a Comment »
Tags: collegetown, collegetown crossing, construction (planned), ithaca, photos, student housing
Categories : collegetown, construction, ithaca, photos, student housing
209-215 Dryden Road Construction Update, 06/2016
15 06 2016At the site of the new Breazzano Family Center for Business Education, work continues on the foundation. It looks like excavation is mostly complete at this point and they’re putting in concrete footings, with digging for a new footing taking place at left in the first photo. The rebar doweled into the concrete will be tied into the walls as they’re built up. The footings closest to 205 Dryden (westernmost section) will hold the elevator shaft, stairwell and restrooms for each floor.
For those wanting a glimpse of the future, Cornell has put up a video render on Youtube showing the new building (exterior and interior) and advertising some of its features. There is an embedded copy of the video clip below.
Comments : 6 Comments »
Tags: 209-215 Dryden Road, academic buildings, collegetown, construction, construction (planned), Cornell, photos
Categories : academic buildings, collegetown, construction, construction (planned), Cornell, ithaca
Hotel Ithaca Construction Update, 6/2016
14 06 2016The Hotel Ithaca’s new wing seems to be moving right along. Most of the foundation has been completed. Some wooden forms used for foundation pours can be seen in the third photo, right next to the reinforced concrete footing. CMU walls create interior partitions within the building’s footprint – likely space for some of the 90 future hotel rooms, although none of the published materials online have shown an interior layout of the new wing. It’s suggested in the project site plan review documents that the new fitness center, breakout rooms and meeting rooms will be near where the new wing will connect to the existing hotel. Given the lack of windows or an entrance on the the first floor of the new wing facing South Cayuga, some of those function spaces are probably down at this east end of the wing, nearest to the street. Early plans did have an entrance on the South Cayuga side, but it was removed during project revisions.
The $9.5 million project is expected to open to guests in May 2017. More info about the project can be found here.
Comments : Leave a Comment »
Tags: construction, construction (planned), downtown ithaca, hotel ithaca, hotels, photos
Categories : construction, construction (planned), hotels, ithaca, photos
Collegetown Terrace Construction Update, 5/2016
31 05 2016Just like in March, there are really two sets of photos here. The first set contains photos that I’ve taken from outside the fence. The second set of photos are from inside the fence, and come courtesy of Nick Robertson and Jocelyn Garrison at Welliver, the general contractor in charge of the project, and a big thanks goes out to them for taking and sharing photos from inside the fence.
The erection of the steel frame has started on the westernmost portion of the building, and corrugated decking is being attached to each level. Work on the building is generally progressing from west to east, and the sheer length of the building allows the western sections to be quite a bit further along than the eastern sections, where foundation walls are still being formed. The reinforced concrete sections visible in the last of the Welliver photos is where the parking garage will go; readers might remember that Novarr sought and received a zoning variance to remove a floor of parking space and turn it into less expensive dorm-style housing, citing the lack of utilization of existing parking, and a desire to appeal to a larger segment of the rental market.
Set two:

Comments : Leave a Comment »
Tags: collegetown, collegetown terrace, construction, construction (planned), ithaca, photos, student housing
Categories : collegetown, construction, construction (planned), ithaca, student housing