210 Hancock Construction Update, 7/2016

28 07 2016

At the 210 Hancock property in Ithaca’s Northside neighborhood, site prep is taking place. The site is being graded and excavation is now underway for subsurface utilities installation (water and sewer pipes, the teal tubes stacked in the photos). INHS is conducting vibration monitoring while all this goes on, although the pile installation won’t start for another couple weeks, running foe about three weeks, mid-late August to mid September. Contractor Lecesse Construction will be installing 10-15 piles per day with a hydraulic hammer, between the hours of 8 AM and 4 PM. If the Voice’s Facebook inbox during the demolition phase this past spring was any indication, some very zealous neighbors will be providing breathless live coverage.

All in all, the contractor issue set INHS back about three months, but the grant funding is accommodating and rental agreements won’t be signed until the project is much closer to completion, late spring or summer 2017. For those who meet the affordable income brackets (breakdowns here), the rental interest form is here. The 54 apartments and the 5 rental townhomes should be ready to go by this time next year.

20160717_143140 20160717_143212 20160717_143239 20160717_143304 20160717_143318

20160717_143202

inhs_pride_design_v5_3 inhs_pride_design_v5_2 inhs_pride_v3_elevations_1

inhs_pride_design_v5_1


Actions

Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s




%d bloggers like this: