209-215 Dryden Road Construction Update, 2/2017

1 03 2017

Admittedly, when the entire building is sealed up in opaque plastic covers, it makes for a less-than-interesting construction update. The plywood doors are for the loading and unloading of materials via lifts, and apart from those, there isn’t much to break up the monotony of white plastic sheets. Note that the access doors are not the same as the elevator shaft, which is located about midway along the west wall next to 205 Dryden/Dryden South.

However, it does look like some exterior facade work is starting to get underway. Brown and grey metal panels are beginning to be installed on the building’s rear face – this is the side that will have the least amount of glass, as occupants won’t have much to see if developer John Novarr moves forward with his plans for townhomes on the double-lot of a house that came down to allow a construction staging area for the Breazzano Center. With the new home to the Executive MBA expected to open up this Spring, Novarr can proceed with options for that double-lot. 238 Linden is zoned CR-4, four floors with no required parking. The proposed townhouses could provide a visual transition between the 80-foot Breazzano and the 2.5 story houses that comprise most of the housing stock on this block of Linden Avenue, some of which are for pending sale.

In further detail, the rear facade windows are 1″ insulated glass with aluminum frames, and translucent insulated spandrel glass below the panes. The metal panels are insulated aluminum and are installed using a framing system – you can see the grey insulated panels with clips along the top edge of the panels. The plastic covers on the panels are to protect against scratches and scuffs prior to installation. ikon.5 sought to provide differentiation with mahogany brown panels on the south (Linden Avenue) side, with lighter salmon-peach panels planned for the north (Dryden Road). The west and east sides will be a little bit of of both. The first floor the street facing sides, and the atrium will be glass curtain walls. The dark panels are intended “to differentiate upper from lower and facilitate a relationship with the smaller scale of adjacent buildings,” per the application. Some of the later documents show a lighter shade of gray for the south side of the top floors, but to be frank, I am uncertain what is accurate.

Note that the fourth floor’s back side will have few windows because that is where the 1,990 SF video production studio will be located, and this requires a controlled-light environment. Presumably, with the green room and studio rooms, the intent is to have a comfortable and efficient interview space for live videos recorded for or streamed to students at remote campuses. The large flank of plywood panels at ground level is the service exit, with future loading dock and trash/recyclables enclosure.

20170218_120030 20170218_120120 20170218_120144 20170218_120149 20170218_120207 20170218_120254 20170218_120309 20170218_120351 20170218_120401 20170218_120408 20170218_120535

209_215_2

209_215_3





Village Solars Construction Update, 2/2017

27 02 2017

The Village Solars have made progress on their latest pair of apartment buildings. Building “I” has made more progress on its exterior finishes, while “J” is fully framed, roofed and shingled. Both of these will likely open this spring.

It’s starting to get that point where the second stage of the Village Solars may be getting ready for review by the Lansing municipal boards. The last big phase, Phase 4 with Building “K”, “L” and “M”,is likely to get underway this year for a completion in 2018, and phase 2A, the mixed-use Building “F”, has been something of a question mark for exact timing. That will finish out the initial 206 market-rate units, which range from studios to three bedrooms.

village_solars_4

There’s an early site plan floating around showing a potential buildout second stage expansion, and although it’s outdated, it gives an idea of the general layout of later phases. Most of the later buildings would be built to the east of the initial phases, as infill between existing apartments. The total number of units in the second expansion was initially about 136 units, but given the recent trend of breaking up larger units into smaller studio units to satisfy market demand, the number is likely to be higher when formal plans are submitted.

Right now, they seem to be about the only large-scale solution to Lansing’s development quandry – the first phase uses natural gas, but with the assistance of green advocacy group Sustainable Tompkins, the later phases have been built to utilize all-electric services with air-sourced heat pumps. This led to new utilities layouts, and the merging of “G” and “H” into one building.

According to an Ithaca Times article from last March, for a 12-unit building at the site (construction cost $2 million), the upfront cost increase was $50,000-$60,000, an increase of 2.5-3%. This is balanced out by the 30-year savings on energy costs for the building ($40,000-$80,000), and a premium on the monthly rents of about $50. Units go for $1050-$1650/month, depending on size and location. Six of the Daikin heat pump units can be seen in the third photo from top.

 

20170218_110328 20170218_110346 20170218_110431 20170218_110437 20170218_110503 20170218_110515 20170218_110552 20170218_110623 20170218_110647 20170218_110745 20170218_110819 20170218_110839 20170218_110940 20170218_111007 20170218_111034 20170218_111056

village_solars_2





St. Catherine of Siena Parish Center Construction Update, 2/2017

25 02 2017

For practical purposes, this project is basically complete. The exterior work is nearly finished for the new building, and deconstruction work has started on the old 1960s parish center (notice how the stone veneer has been stripped). It looks like the contractor (Edger Enterprises of Elmira was the GC, but the trailer on-site is for large-scale contractor Rycon) doing the exterior panels is using form boards to prop up the metal panels, which is odd since they were using metal rails underneath. The decorative windows within the stonework of the west facade are a nice touch. Enjoy your new parish center, folks.

20170218_104314 20170218_104336 20170218_104341 20170218_104408 20170218_104421 20170218_104431 20170218_104443 20170218_104512 20170218_104650 20170218_104655





Poet’s Landing Phase II Construction Update, 2/2017

23 02 2017

Poet’s Landing is moving along. Framing for the first eight-unit building is underway; the slab foundation has been poured for two more. The other four buildings in the 48-unit project will come along as the weather warms up – it’s possible that LeChase may have the sites cleared forms ready for the rest of the foundation pours, but they may be buried under the snow (this was the first place I visited last Saturday morning, so the unseasonable heat had yet to do its melting magic).

According to an article published just yesterday, Boston Capital has bought the Low Income Housing Tax Credits (LIHTCs) awarded to Conifer Realty to help finance the project. The Boston-based real estate investment firm paid $7.6 million. Boston Capital can apply those credits to the taxes on its holdings, and Conifer gets the money it needs to pay for hard and soft development costs (which total $10.8 million, the rest coming from federal/state grants and equity). Boston Capital is a frequent partner of Conifer, having bought their LIHTCs many times in the past, including those awarded to the 72-unit first phase of Poet’s Landing that opened a few years ago.

poets-landing-ii

Quoting Housingfinance.com, which also had the first actual render of the project shown above:

“Located on 10 acres, Poets Landing II will feature 16 one-bedroom, 24 two-bedroom, and eight three-bedroom units in six two-story buildings. Units will include central heating and air conditioning, dishwashers, patios/balconies, and storage. Residents at Poets Landing II will have access to the community amenities at Poets Landing I, which feature a leasing office, a great room, a computer workstation, a laundry center, and a playground. The apartments will be available to families earning 60% or less of the area median income.”

20170218_095951 20170218_100015 20170218_100102 20170218_100157 20170218_100221 20170218_100254 20170218_100323 20170218_100326 20170218_100330 20170218_100346

 





902 Dryden Road Construction Update, 2/2017

22 02 2017

Visum Development’s townhouse project at 902 Dryden Road in Varna is coming along. The 8 new townhouses are divided up into three building sections – 3-unit section “A”, closest to Fall Creek; 3-unit section “B”, closer to Dryden Road, and 2-unit section “C”, which has a shared wall with the existing two-unit house.

“B” appears to be the furthest along – fully framed (wood frame), roofed, sheathed with ZIP panels, and windows have been fitted. “A” is undergoing framing of its second floor, and “C” is waiting for its foundation to be poured, with forms in place and underground utilities routed and capped.

Visum’s Facebook page says 32 new beds, which is half-right; the eight new townhouse units will have 26 bedrooms. The other six bedrooms come from the existing two-family, which will be renovated. So it depends on one’s definition of “new”. The final product has eight 3-bedroom, 2 bath units and two 4-bedroom, 2 bath units.

While Visum and Modern Living Rentals are different entities with partial ownership lap, MLR handles all of the renting and property management for Visum. The four-bedrooms are renting for $2400/month, and the 3-bedrooms for $1,500-$1,950/month. Quoting the ad:

“Brand new construction in late 2016, has all the amenities needed! Brand new EVERYTHING, stainless steel appliances, granite counter tops, kitchen complete with a dishwasher! Great sized rooms with ample closet space, all custom tiles bathroom as well! Washer and dryer IN unit!”

Varna has lower premiums on land, taxes and somewhat lower development costs, and those are all savings to the developer. But because it’s not a captive market like Collegetown, or as desirable as Fall Creek, the rents are lower. In short, Varna has lower development costs and also lower revenue. In this case the project team feels those two overarching factors balance out, and the townhouses are able to provide a comfortable return on investment.

All units have August 1st as the move-in date. STREAM Collaborative is the architect, Bella Faccia Construction is the general contractor, and Emery Construction of McGraw is doing the framing. More information on the project can be found here.
20170218_103016 20170218_103052 20170218_103106 20170218_103127 20170218_103131 20170218_103152 20170218_103224 20170218_103229 20170218_103253

902_dryden_final 902_dryden_v4_1





Hotel Ithaca Construction Update, 2/2017

21 02 2017

The to-do list for the $13.8 million Hotel Ithaca “modernization” is drawing short as it nears its May completion date. All the DensGlass fireproof fiberglass mat gypsum sheathing is in place and the edges of the panels are closed up with liquid flashing. On top of the sheathing are metal clips to which the exterior panels are mounted. The stone veneer on the first floor is mostly finished. Many, but not all of the balcony doors, windows and AC units have been fitted. Details like balcony railings will be installed towards the end of exterior work. On the inside of the building, it’s a good bet that the rough-ins are complete, insulation and drywall is probably in place and close to being completed, with crews moving onto things like subfloors/underlayment, painting, and installation of room fixtures such as sinks and bathtubs. The rest of the AC units will likely go in after the subfloors are installed.

Some Hotel Ithaca job postings are advertising 94 new rooms, but unless there were some last minute changes, the number on file is 90. Also worth noting, the contractor, Buffalo-based Krog Corp., and its team of subcontractors have done a fairly good job of staying on Hart Hotels’ schedule – the SPR doc from two years ago called for an April 2017 opening.

More background info on the Hotel Ithaca project can be found here, and by using the “Hotel Ithaca” tag one can backtrack through the bimonthly progress reports.

20170218_124910 20170218_125001 20170218_125022 20170218_125054 20170218_125120 20170218_125323 20170218_125334 20170218_125340

hotel_ithaca_final_1





1001 North Aurora Street Construction Update, 2/2017

20 02 2017

Another project making rapid progress in a short time. The two two-family homes at 1001 N. Aurora Street are being framed out. Going over the wood studs are Huber ZIP sheathing plywood panels, like all the cool kids are using in residential wood-frame construction.

There are pros and cons to each approach. DuPont, in sales literature for its Tyvek Housewrap, touts easier installation, more durability during installation, and claims superior waterproofing. The ZIP system, however, has made significant inroads into the construction market because it does an excellent job at allowing moisture to escape while keeping external water from getting in, and although it requires a little more care to work with (taping), it’s still fairly easy to work with. ZIP panels also tend to be more expensive. Liquid water-resistant barrier (WRB) sprays like the ones you see used on commercial buildings and at Cornell tend to provide the best waterproofing, but they are the most expensive option. So if one drew a scale weighing cost and performance, they could have housewraps at the low end of cost and relative performance, ZIP panels in the middle, and WRB sprays at the top.

Anyway, these duplexes will be known as 202 Queen Street and 206 Queen Street. In the signage on the site, the bottom design is what was approved (quick tip – do not use old renders on signage). They replace a single-family home. Stavros Stavropoulos is the developer, and Daniel Hirtler the architect – the two are also behind the plans for the new 11-unit apartment building at 107 South Albany Street.

20170218_133909 20170218_133914 20170218_133932 20170218_133947 20170218_134030 20170218_134045 20170218_134115





210 Hancock Construction Update, 2/2017

20 02 2017

Normally construction sites get updates every two months. But at the INHS Hancock project site, things are getting really interesting in a short time.

First, the main apartment building. In just the past month, section “A”, the southernmost wing, has been wrapped in Blueskin, roofed, and the windows have been fitted. Answering a question from a few months back, it looks like the Blueskin’s purpose is to be the water/vapor membrane under the brick. The section of “A” under the weatherproof plastic tenting is being bricked – a few loose bricks can be seen in the last photos through holes in the plastic. Not only do the workers appreciate some protection from the elements, brickwork requires temperatures to be kept above freezing so that the water in the mortar doesn’t freeze out, so not only is there plastic wrap, Lecesse has also deployed portable heaters. Section “B” will follow with the Blueskin sheathing, roofing and window-fitting, and then “C” and “D”, which host the indoor garage (hence the CMUs) and are still being framed out.

The five rental townhouses have a typical wood-frame build-out – first comes wood framing and roofing, then tar papered and shingling, housewrapping and window fitting. Interestingly, the seven for-sale townhouses (collectively referred to as “202 Hancock”) are using Huber ZIP sheathing panels, which the rentals did not. The Hancock street trio of homes have been framed but not roofed, while the Lake Avenue quartet are still being framed out, awaiting the rest of their roof trusses. The insides of the for-sale homes are still just bare stud walls at this point, while the rentals are probably far enough along that most utility rough ins have been completed, and sheetrock is being hung in the units. All in all, Lecesse Construction and their subcontractors have been moving at a very good clip over the past month or so.

A construction loan filing on January 23rd states Tompkins Trust lent INHS $1,581,796 to finance the 202 Hancock units. The total cost (hard and soft) of the seven for-sale units is estimated at $2.36 million. The five two bedroom units (1,147 SF) will be sold for about $114,000, and two three-bedroom units (1,364 SF) for $136,000, to qualified applicants making 60-80% of local AMI, or $37,000-$49,000/year.

For the sake of comparison, the apartment building and for-sale units are partially financed with a $7,790,511 loan from a Citibank fund – through an LLC, Citibank bought the low-income housing tax credits (LIHTCs) awarded to the project by New York State. The apartment building’s total cost comes to $13.8 million, with the rest financed through INHS’s money, federal tax credits, housing grants and a low-interest loan from the state’s housing division (NYSHCR).

Renters or homeowners interested in obtaining a unit can fill out an inquiry form here. The rentals will be ready for occupancy by August 1st, 2017, and the for-sale units are looking at a November 2017 completion.

20170218_132608 20170218_132630 20170218_132650 20170218_132705 20170218_132720 20170218_132737 20170218_132806 20170218_132824 20170218_132828 20170218_132850 20170218_132905 20170218_132928 20170218_133033 20170218_133051 20170218_133132 20170218_133217 20170218_133245 20170218_133259 20170218_133312 20170218_133355 20170218_133420

inhs_pride_design_v5_3

blueskin-vp100-brick inhs_pride_design_v6_1202_hancock_2 202_hancock_1 202_hancock_3

inhs_pride_design_v6_1





The Cherry Artspace Construction Update, 1/2017

20 01 2017

The Cherry Artspace was saved for last because originally, these photos were going to be used in an Ithaca Voice article. But, with the State Theatre piece running this week, it didn’t seem like a good idea to run two pieces about performing arts spaces in a short span, so the Cherry Arts will be profiled in a piece next month. That would make these photos too old by then, so here they are.

The Styrofoam block “floaters” are mostly in place and a steel rebar mesh has been laid on top in anticipation of pouring the concrete slab – the mesh will provide increased strength to the concrete as it cures. Water, sewer and utility hookups are piped beneath and up through the foundation. Looking at the sawhorses, it looks like McPherson of Ithaca is the general contractor. The 1,900 SF building should be ready for its first performances sometime this Spring.

20170107_115618 20170107_115631 20170107_115645 20170107_115703 20170107_115707 20170107_115729

cherry_2





Upson Hall Construction Update, 1/2017

18 01 2017

It’s become a little more difficult to shoot photos from certain angles, now that one of the previously-open sidewalks has been closed off. But, it’s not a surprise, they’ve been working on Upson’s new face. The exterior stud framing has been underway on the lowest floors of the west face. Sheathing is being attached, and the rough openings indicate future windows. The lowest floors of the east side, a little further along, have already been coated in turquoise waterproofing material, and are being fitted with windows. On the upper floors, there’s been considerable progress with the terra-cotta and the aluminum surrounds. It doesn’t look like there’s been much progress with attaching new mineral wool and clips, the current work is either finishing up what was well-underway (the upper floors), or getting started with the new exterior (the lower floors), not a whole lot of work going for the in-between stages at the moment.

Inside, you can see the new interior framing being built inside the fully-gutted and renovated interior. According to Cornell’s last update in December, interior demolitions are complete, mechanical rough-ins are ongoing in the basement, and electrical and plumbing are underway on the first and second floors.

Like Gannett, The Pike Company is the general contractor in charge. LTL Architects and Perkins+Will are in charge of design.

20170107_103946 20170107_104030 20170107_104052 20170107_104055 20170107_104104 20170107_104120 20170107_104139 20170107_104430 20170107_104456 20170107_104540 20170107_104555 20170107_104906 20170107_104910 20170107_104921 20170107_104955