The to-do list for the $13.8 million Hotel Ithaca “modernization” is drawing short as it nears its May completion date. All the DensGlass fireproof fiberglass mat gypsum sheathing is in place and the edges of the panels are closed up with liquid flashing. On top of the sheathing are metal clips to which the exterior panels are mounted. The stone veneer on the first floor is mostly finished. Many, but not all of the balcony doors, windows and AC units have been fitted. Details like balcony railings will be installed towards the end of exterior work. On the inside of the building, it’s a good bet that the rough-ins are complete, insulation and drywall is probably in place and close to being completed, with crews moving onto things like subfloors/underlayment, painting, and installation of room fixtures such as sinks and bathtubs. The rest of the AC units will likely go in after the subfloors are installed.
Some Hotel Ithaca job postings are advertising 94 new rooms, but unless there were some last minute changes, the number on file is 90. Also worth noting, the contractor, Buffalo-based Krog Corp., and its team of subcontractors have done a fairly good job of staying on Hart Hotels’ schedule – the SPR doc from two years ago called for an April 2017 opening.
More background info on the Hotel Ithaca project can be found here, and by using the “Hotel Ithaca” tag one can backtrack through the bimonthly progress reports.
Leave a Reply