1325 Taughannock Boulevard Construction Update, 3/2016

25 03 2016

It occurred to me, while taking photos of the “Lake House project”, a mansion underway at 1325 Taughannock last weekend, that there’s a babbling brook just north of the garage, with a small waterfall.

It’s okay to be jealous. I am.

Since January, most of the wood shingle siding has been attached, although some of the Green Guard Housewrap is still visible. Some sections of the foundation and concrete column bases have been covered with stone veneer, but the large, partially chiseled rock on-site suggests some genuine stone is also being used (when one can afford to take out a $2.25 million construction loan for a single-family home, why not splurge). The front door is still a plywood sheet, but windows have been fully fitted from what could be seen from the road. A small section of the roof remains exposed felt paper, but will be finished with what are likely to be metal sheets, based off of New Energy Works‘ render.

Quoting a press release from New Energy Works:

“Settled on a cliff above Cayuga Lake, the Lake House project is a full timber frame home which will use over 500 timbers to create 4,880 square feet of living space for a growing family. The interior frame will be crafted of kiln-dried Douglas Fir, while the exterior will use fresh sawn Douglas Fir with kiln-dried curves. Two distinct bowstring trusses with steel bottom chords are featured in the kitchen to support the second floor above.”

Photos from the timber frame raising last summer can be found here. If anything, the side that faces the lake is even more impressive. Here’s a render of the “back side”, the view from the lake:

LAKESIDE

This will probably be the last visit. The house should be completed by the end of May, and it’ll be a little unsettling to take photos when it’s occupied. I’m not sure a feature in the Voice, even if permitted by the owner, would have the allure of “The Lifestyles of the Rich and Famous“, or just piss readers off. At least two comparably grand lakeside homes are planned along Taughannock Boulevard and Maplewood Road.

20160319_150241 20160319_150308 20160319_150330 20160319_150340 20160319_150345 20160319_150424

20151108_144517

image001

ithaca_lakeside_timber_frame

great_room_ithaca_timber_frame_web





Texas Roadhouse Construction Update, 3/2016

24 03 2016

Some readers love it, others hate it, but Texas Roadhouse is well on its way to a May opening. The steakhouse chain has made pretty good progress on their 7,193 SF restaurant on Elmira Road across from Ollie’s and the Vitamin Shoppe. In fact, a small temporary space next to the Vitamin Shoppe is where Texas Roadhouse is conducting interviews for the 170 staff it plans to have at opening.

The lap cedar siding is coming along, covering up the Tyvek housewrap from most angles (brick and metal flashing will cover what’s left). USG Securock glass-mat sheathing has been applied to the exterior walls facing and near the kitchen/food prep area for fire safety – the sheets are noncombustible and serve as a form of passive fire protection. The roof has been covered with felt paper, but no shingles have been attached yet. Closer to the ground, brick veneer has been applied to the base of the eastern and northern walls. I’m not sure what’s going on next to the street-facing foundation wall; but that is where the entrance ramp will be going.

Texas Roadhouse corporate is developing the site, leasing the land from plaza owner DDR Corp. of Ohio. GreenbergFarrow of suburban Chicago is serving as an architectural consultant for the project, and Edger Enterprises of Elmira is the general contractor.

20160319_142826 20160319_142829 20160319_142905 20160319_142942 20160319_142954 20160319_143020 20160319_143205

texas_roadhouse_v3_1 texas_roadhouse__v2_1

texas_roadhouse_2





619 West State Street Construction Update, 3/2016

23 03 2016

Not much left to go here. 619 West State Street, the future home of HOLT Architects, is near the finish line. The wood siding has been attached, although it’s hard to tell if the (dormer? periscope window?) will be sided with wood or the off-white metal paneling like most of the plaza. It doesn’t look like the rooftop solar panels have been installed yet, but they’re on the to-do list. Exterior and interior work is a little further behind on the rental portions of the building, where two smaller commercial spaces will be available to tenants. Someone from HOLT feel free to comment, but I think one of the spaces is already spoken for.

I can vouch from being that that HOLT’s interior space is nearly complete, and looks great. The lime green paint in the entrance area stands out and gives it a certain liveliness. I was tempted to take photos, but there were multiple people working inside finishing up HOLT’s space last Saturday, and I felt uneasy with the idea of interrupting for an impromptu tour. So I was that guy, staring inside, awkwardly holding his camera phone, before giving in to preconceived social mores and leaving them be. I guess I’m a lot more comfortable bothering people when they’re outdoors.

Tompkins Trust Company is providing the financing, and local company McPherson Builders is in charge of general construction. The project cost for the net-zero energy structure comes in at about $482,500, based off the construction loan on file with the county. More discussion about the net-zero features can be found here, and HOLT’s move to the West End here.

20160319_144706 20160319_144734 20160319_144737 20160319_144811 20160319_144822


619_w_state_st_1

 





Holiday Inn Express Construction Update, 3/2016

22 03 2016

Work on the new Holiday Inn Express at 371 Elmira Road is progressing. the foundation work is currently underway. It looks like they’re going with a shallow, slab-on-grade foundation that spreads the weight of a building all around the concrete slab. The formwork’s been done, and rebar criss-crosses the yet-to-be-poured concrete. The rebar mesh is a reinforcement for the concrete when it gets poured, helping to prevent cracks that may form in the concrete from spreading throughout the foundation and causing major damage. The blue tubes are a part of the under-slab utilities. Elsewhere on the site, it looks like stacks of Tembec and Millar Western Canadian lumber are being used to assemble wood trusses that will be used in the hotel’s wooden frame.

The 4-story, 79-room hotel is expected to open late this summer. Rudra Management and Rosewood Hotels (Jayesh Patel) of suburban Buffalo is the developer.

20160319_141548 20160319_141636 20160319_141959 20160319_142012 20160319_142018

holiday_inn_express_v2

holiday-inn-express-original-1





Boiceville Cottages Construction Update, 3/2016

21 03 2016

Some good progress has been made with the new cottages over at the Boiceville Cottages site. the cottages with the red-orange trim appear to be fully finished and occupied, while those with the blue trim have some interior finish work left before they can be rented out to tenants.

Newly risen since the last visit in January are a set of fuchsia-trimmed cottages that have been framed, sheathed, and partially stucco’d, and a fourth set of cottages that are still at the sheathing stage. Peering inside, you can see the interior stud walls and windows yet to be fitted into their openings.

That leaves a fifth and final batch of cottages that remain foundation slabs for the time being, but will likely start construction as we head through spring. Rents for the houses range from $1,095-$1,725/month, depending on the unit.

Bruno Schickel hosted congressman Tom Reed on a visit to the construction site a couple of weeks ago (more about that here and here). The $2.2 million last phase, which consists of 17 cottages, is expected to be completed this summer, bringing the total number of units on the site to 140. The cottages have been built in phases – 36 in 1996/97, 24 in 2006/07, and about 80 in multiple sub-phases since 2012.

Once the project wraps up, Schickel Construction plans to turn their attention to finishing their newly-acquired Farm Pond Circle project in Lansing.

20160319_123813 20160319_123819 20160319_123922 20160319_123930 20160319_123949 20160319_124119 20160319_124140 20160319_124150 20160319_124200 20160319_124228 20160319_124237 20160319_124241 20160319_124319 20160319_124455 20160319_124500

boiceville_1





Affordable Housing Week 2016

8 03 2016

Expanding on last year’s theme, it’s affordable housing week. The Ithaca Urban Renewal Agency will be holding public hearings on March 24th and 28th as part of the process to determine who will receive money from the Housing and Urban Development (HUD) grants awarded to the city. The 25 applicants (up from 21 last year) range from jobs training to community services to the development of affordable housing. All summed up, there’s $1.85 million requested, and $1.56 million available, so that means an 84% chance of funding, all parameters being equal. For comparison, in 2015, $1.78 million was requested out of $1.215 million available, just a little over two-thirds of the total. The chances for funding have gone up this year.

Part of the reason for the better chances this year is unfortunate – the return of $273,869 in 2014 HOME funding meant for INHS’s 402 South Cayuga project that has not come to fruition. Although HOME funds can be awarded for rental projects, the funding was awarded by the city specifically for owner-occupied housing, so the money comes back into play. There’s also about $26,300 left over from last year that went unallocated.

Without discounting the value of the other applications, the focus here will be on the real estate development projects. For the record, writing about a project is neither an endorsement or opposition from this blog.

202_hancock_1

202_hancock_2

1. Last year, INHS applied for and received almost $458k for 210 Hancock, for which site prep is currently underway. This year, they’re applying for funding for two projects – seven owner-occupied units at 202 Hancock (new tax parcel), and the single-family home planned for 304 Hector Street.

The 202 Hancock townhouses are requesting $567,000 towards a total project cost of $2,359,013. This is a high figure, but it also seems like it would address the recent, very major issue of rapidly rising construction costs derailing multiple affordable housing projects. INHS will be putting up $550,000 of its own money, and already has received a $280,000 city/county/Cornell grant (Community Housing Development Fund) towards the project. The rest comes from bonds, the state, land equity and the buyers themselves.

202_hancock_3

Doing the math ($1,438,640 construction cost, 8,463 SF total), the construction cost budgeted is $170/SF, a little less than the $190/SF they paid for 203 Third Street, but not impossible. Perhaps a larger project of townhouses can utilize cost efficiencies to keep the price down a bit.

The two-story wood frame townhouses would be LEED Certified. Five two bedroom units (1,147 SF) would be sold for about $114,000, and the two three-bedroom units (1,364 SF) for $136,000, available to those making 60-80% of local AMI, or $37,000-$49,000/year. The townhouses would be a part of the Community Housing Trust (CHT), keeping them affordable even as they are sold to others in later years. the anticipated construction period is November 2016 – June 2017. HOLT Architects of Ithaca is designing the townhomes.

Design wise, they look halfway between the first iteration of the rental townhouses, and the approved version.

304_hector_inhs

2. Also from INHS, the 304 Hector application. The amount requested is $100,000 towards a $369,294 project. This seems remarkably high. In the application, INHS notes the construction costs of $262,000 are from actual bids received from Rick May Construction (who is also doing 203 Third Street) and subcontractors. The math comes out to about $191.50/SF. One of the reasons for the very high cost is that INHS is required to hire contractors with enough liability insurance to cover any major accidents, and a lot of smaller builders don’t have enough insurance. $40,000 has already been granted towards the project from the CHDF.

The house would sell for $142,000 to a family making $37,000-$49,000/year (60-80% AMI), the same parameters as the 202 Hancock townhouses. The house would also be a part of the CHT. An April 2017 – January 2018 construction is planned. Local company STREAM Collaborative is the house’s architect.

402_s_cayuga_st_boggsfernandez

3. Meanwhile, at the 402 South Cayuga Street site, developer/architect Zac Boggs and Isabel Fernandez are requesting $105,000 towards their 4-unit townhouse project, priced out at $1,020,000, of which $820,000 is for construction. Of the 4 units, one two-bedroom unit will be available to a family making 80% AMI or less (i.e. $49,000/year or less), selling at $150,000. The other three units, 2 2-bedroom and 1 3-bedroom, would be rented out for 2-5 years, and then sold on the “lower-end of market-rate”, which is estimated in the mid to upper $200s. The units would follow LEED standards, and the affordable unit would be put into the CHT.

Precision Builders of Ithaca would construct the project. A May 2016 – June 2017 build-out is planned, though it doesn’t appear to factor in the planning board approval process.

Aside from the grant, most of the funds for the project will come from a bank loan, with $120,000 of their own money and $40,000 in county bond funds. Assuming these are the same size as the 2 and 3-bedroom INHS townhouses, the construction cost comes out to about $170/SF.

One thing that comes to mind in the context of the inclusionary zoning debate is that this might be the only way to really go in the long-term. If INHS gets priced out of feasibility in the city, trying to cover the cost of affordable units with substantially more expensive market units might be the only option, which is a rather uncomfortable thought. One of the issues with inclusionary zoning is that it prices out the middle; developers have to make up the cost somewhere, and the market-rate units are the scapegoats. Communities end up with a small portion of affordable housing, but mostly expensive housing. With this project, part of the money is being recuperated by renting the other units for at least a few years, which some may scoff at, but costs are, what they are.

habitat_2

4. Habitat for Humanity is requesting $75,000 towards their $305,500 duplex project at 101-107 Morris Street (to be redesignated 202-204 Third Street) on the Northside. Each unit will sell to a familiar making less than 60% AMI ($36,750/year), and the families will have to put in “sweat equity”, helping to build the houses (350 hours of labor). To keep costs down, labor is volunteer-based and materials are donated – as a result, the project only has a $180,000 construction cost, a little over $60/SF.

The units will be two-story, have porches and designed to fit into the neighborhood. The state has given the project a $70,000 grant already, and the city/county/Cornell CHDF has given $80,000. the rest is covered by corporate grants (Cargill, Lowe’s, M&T Bank) and individual donations. A timeline of April 2017 – April 2018 is anticipated.

No renders, but the above site plan was included in the application.

622_w_clinton

5. Last, the only truly new project for this post. 622 West Clinton Street in the South Side neighborhood. The applicant, Jerame Hawkins, proposes deconstructing a decaying barn at the rear of the property and replacing it with an affordable owner-occupied duplex. Hawkins, who runs the county’s Youth Advocate Program, would make each unit available to a family making 60% AMI or less ($36,750/year or less), in particular Section 8. The duplex would be modular, 3-beds and 1,561 SF each, with Carina Construction and Finger Lakes ReUse working with Hawkins on the project. The construction cost of $292k works out to about $93/SF.

The house at the front of the property, which dates from the late 1800s, would be renovated and retained as affordable housing. Hawkins is requesting a grant of $135,000 towards the $364,634 project. A project timeline of October 2016 – January 2017 is given in the application.

The one potential red flag I’m seeing is a line in the app that says “retaining for a minimal [sic] of 1 year”. Either that gets clarified and extended, or the IURA won’t be interested this proposal on account of it not being affordable for long enough a period of time.





News Tidbits 3/5/16: Here Comes the Papierkrieg

5 03 2016

chapteR_house_reconst_v4_2chapter_house_v4_1
1. Let’s start off with something that led to a couple of worked up messages and emails to the Voice inbox – a potentially controversial revision to the Chapter House proposal that would replace the north eave of the building with a wall (bottom image). In the documentation, there’s no written explanation as to why the change is being requested from the approved plan (top image); but I wonder if it has to do with fire safety regulations or zoning issues between the Chapter House and the rebuild being prepared for 406 Stewart next door. Architect Jason Demarest is working on both projects for their respective owners (400-404 Stewart’s Sebastian Mascaro and 406 Stewart’s Jim Goldman), so he’ll be representing both projects at the Landmarks meeting next Tuesday the 8th at 5:30 PM. Also on the agenda are a couple of minor renovations, discussion about potential work to The Nines at 311 College Avenue, and discussion of an expansion to the East Hill Historic District.  This might just be for the Orchard Place properties that are locally historic but not nationally recognized, but we’ll find out for certain next week.

1401_dryden_1

2. Some of your might be wondering what happened with the 902 Dryden vote. Well, the vote still has yet to be taken. Moldern Living Rentals was still work on the last details of the Stormwater Pollution Prevention Plan for runoff (SWPPP), so the town of Dryden won’t be taking a vote until their March meeting, which has yet to be posted to their website (most likely it’s Thursday the 10th, or Thursday the 17th). The next-door neighbors still took time out to call the 40% downsized project a travesty and that it wasn’t shown in the 2012 Comprehensive Plan. Veering into editorial territory, my original comment from last month still stands:

“[A] master plan is not an exact thing; if it shows for three sets of five townhouses on a parcel, that’s not what may necessarily may happen. It just indicates the kind of density and scale of development the plan deems appropriate. 902 Dryden isn’t drawn on the master plan, but the plan welcomes the idea of townhouses on Forest Home Drive, which 902 abuts. So a vote in favor of the 8 new townhouses is, indirectly, a vote of support in the Varna Master Plan.”

I would give more weight to Todd Bittner’s objective concerns about stormwater than subjective comments of character, especially when they’re from someone who said they were disgusted by the thought of rentals. When Bittner checks out the revised SWPPP, if it looks acceptable, I think the project should be approved.

On another note, 1401 Dryden, the Storage Squad project (pictured above), seems to have lost a lot of its charm after getting caught in red tape last fall. The owners had to squeeze into a smaller area to satisfy the revised, expensive SWPPP. They’re hoping to hide most of it with landscaping.

dewitt_house_v3_1 dewitt_house_v3_2

3. Just a quick update on the Travis Hyde Properties Old Library proposal. The ILPC and Planning Board had their joint meeting, project team partners HOLT Architects and TWMLA landscape architects have incorporated their comments, and here is the current product. Sorry, no renderings, just site plans. Previous plan here. Overall, the site layout hasn’t changed too much, a courtyard and green space will be next to the DeWitt Park Inn, and the building is set back to maintain rhythm with its neighbors. The exterior is supposed to have more projections and recesses, the top floor set back 6 feet, and incorporation of balconies on the upper floors (not sure how this will affect the plan for the inverted roof). Unit count is 21 1-bedroom, 24 2-bedroom, and 9 3-bedroom, 54 instead of the original 60 (39 1-bedroom, 21 2-bedroom). The addition of 3-bedrooms is surprising for senior apartments; from what I’ve been told, typically the large majority of demand is with 1 and 2-bedroom units. The Planning Board and ILPC have another shared meeting at City Hall on the 8th.

chain_works_rev3_3

4. The Chain Works review process is chugging along. At its meeting on the 8th, the Planning Board’s special meeting will decide whether the Draft Generic Environmental Impact Statement is ready for public review (not expected to be controversial). Then on the 9th, Cornish et al. will be giving a report to the Common Council’s Planning Committee about the timeline and current status. Another staff progress report will be presented at the Planning Board meeting on the 22nd, and the next day on the 23rd, the city CC and town board Planning Committees will meet review proposed draft PUD zoning for the massive mixed-use project. With adequacy being agreed upon, the project can begin project review 15 or so days later; first public meeting is tentatively scheduled for March 29th.

The city just uploaded the comments of reviewers on the DGEIS – most are relevant, some are pretty good suggestions and critiques. Then there’s “Reviewer 3”, most of whom’s comments were put aside as they’re not relevant to adequacy. Those are but a preview of the potential flare-ups to expect at the public meeting.

12366349_10153784612864664_8478297861508040090_n

5. Stumbled on this by chance, but it seems to verify initial suspicions from a few months back; a project proposal goes with the sale of multiple parcels of land totaling 9.2 acres off Park Lane and Slaterville Road in the town of Ithaca. The property, for sale at $995,000, is being marketed by Carol Bushberg Real Estate, which doesn’t have the render on their listing page or their Youtube video, but they do on facebook. The conveyed plans call for a 26-lot subdivision, and given the proposed lot lines, it doesn’t look like it would be affected by the town’s moratorium on 2-unit structures, because each unit has its own lot even though some of them share a wall. It also meshes with the town’s Comprehensive Plan, which calls for 2-4 units per acre in this area (in the site plan, it’s just under 3 per acre). So to all you would-be home developers, here’s an opportunity.

20151108_154213

6. Speaking of the 2-unit moratorium in the town of Ithaca, it looks like that’s going forward to the Town Board to schedule a public hearing. The Planning Committee decided it was a good idea. The documentation says it would last at least a year, by which time the town hopes to have its new form-based, anti-student special zoning in place. Editorializing again, I still oppose this proposed law not because of the issue with low-end student housing, but because it’s too broad, affecting the whole town. The last 2-unit approved in Ithaca town wasn’t a student special – it was a 3-bedroom house with an accessory 1-bedroom apartment off Calkins Road. The husband and wife building the house will be living in the larger unit. I don’t think the whole town should be subject to a law that’s only been written to address a South Hill issue (the law’s language claims it’s a concern in East Ithaca as well, but I haven’t seen or heard of a new student-oriented rental in East Ithaca in at least the past few years). Anyway, whether for or against it, comments can be sent to Town Clerk at townclerk@town.ithaca.ny.us. The town meeting will be at the town hall on Monday the 7th at 5:30.

202_hancock_1
7. Here’s a preview of next week’s mid-week post: A look at some of the affordable housing proposals and plans that applied to the city for grant funding this year. INHS applied for their owner-occupied townhouses, the Boggs/ Fernández proposal for 402 South Cayuga is there, Habitat’s duplex, 304 Hector, and a new plan by a private citizen for an owner-occupied affordable duplex behind the house at 622 Center Street in the South Side neighborhood. Keep an eye out for that Monday night or Tuesday morning.

maguire_carpenter_2

8. From the other news outlets now; the Times is reporting that the sketch plan for the Maguire auto dealership proposal for the Carpenter Business Park actually had a warm reception from the Planning Board. In particular, board stalwart John Schroeder was impressed with the sidewalk along 13 (which would help transition the Waterfront and nearby environs to mixed-use) and public amenities. The board is cognizant of the site’s issues and the city’s hopes for the area, so those do play into the thought process – perhaps part of it is that Maguire’s jobs and features could work as a draw for mixed-use development of nearby parcels that don’t have so many issues. The board’s role stops at this point, with the just passed TM-PUD now front and center – unless Common Council okays the project, it won’t be back again. But Maguire did ask for a letter of support if the board was willing; we’ll see.

texas_roadhouse_v3_1

9. Meanwhile, the Journal is reporting that Texas Roadhouse will be opening May 23rd. No doubt the relatively dry and mild winter helped keep this project moving along (February construction update here). The 7,163 SF restaurant expects to hire 170 to 200 employees, of which 80 will be full time. That number astounds me just a bit because I worked at a steakhouse in high school, and although we were maybe half the square footage, we only had a staff of about 40. Even in Ithaca’s crowded restaurant scene, there aren’t many options for the red meat lovers that don’t cost an arm and a leg, and chances are good this will appeal to a different crowd than most, and be something of a draw from the nearby rural areas. Best of luck to them and their staff.

20160219_134003 20160219_134057

201_w_clinton_1

10. Let’s wrap this up with House of the Week. Quick update on Zac Boggs and Isabel Fernández’s 201 West Clinton Street carriage house. Fully shetathed (Huber ZIP system panels), fully roofed and shingled, and fully fitted with windows, the exterior work left will focus on exterior siding attachment and refinishing the original 1960s garage to match the historically-inspired vertical addition. The exterior calls for sawn board-and-batten wood fitting, though it’s unclear if it will be unpainted wood, or painted yellow. The 1 bedroom, 520 SF space looks like it could be ready for occupancy by late spring.





209-215 Dryden Road Construction Update, 02/2016

3 03 2016

First progress report of many. As Collegetown projects go, Novarr-Mackesey’s plan for 209-215 Dryden stands out for a number of reasons.

For one, it calls for a six-story plus basement, 76,200 SF academic/research building to be 100% occupied by Cornell University’s Executive MBA program. No residential or mixed-use to be found here, and given its primary occupancy of office workers and Executive MBA students (who tend to be older, deep-pocketed and will only be coming up from New York a few weeks of the year), not the typical Collegetown crowd either.

For two, this is one of those rare occasions where a Collegetown building under construction is not designed by local firm Jagat Sharma. ikon.5 Architects of Princeton, a John Novarr favorite, penned the steel-and-glass box with its multicolored steel mullions.

By the city’s estimate (from the Site Plan Review form), the construction itself will cost $12 million. From construction loan paperwork filed with the county in December, the total cost, including hard and soft construction costs, will be $15,912,823.33. Wells Fargo Northwest is the lender.

In September, the county approved a payment-in-lieu-of taxes (PILOT)-like tax abatement, taxing the finished building at $5.2 million plus 2% per year. The amount is still more than the ~$1 million value of the original, unimproved properties on the site, and it comes with a 50-year guarantee that Cornell won’t be able to but the property and make it tax-exempt, something that was hinted at a few times in the TCIDA application.

209-215 Dryden will host about 420 Cornell MBA students and staff when it opens in late Spring 2017, later increasing to 600 as Cornell fills out the rest of the square footage. The basement and first three floors will be dedicated classroom/academic space (including 90-person LGI classrooms), and the upper three floors will be office space. A large three-story atrium will mark the building’s primary entrance. At opening, it will be fully leased by Cornell, but only 70% occupied. Sounds like plenty of short-term flex space.

Since December, the site has been cleared of weeds and any remaining debris, and it looks like foundation prep work (excavation) might be starting on the far side of the property away from the streets. Some steel H-beams have been brought to the site, possibly for use in shoring up the site along the excavation perimeter. The H-beams are drilled or driven in at regular intervals, and hold the soil back while the foundation is excavated. A pile driver, tubular piles, an excavator, and a Dynapac compaction roller are on-site. So, the primary duties at hand appear to be excavation of the new building’s foundation, and shoring up the soil surrounding it so that the site remains stable while that work is going on.

As the signage on Novarr’s corner building suggests, Hayner Hoyt Corporation of Syracuse will be the general contractor.

20160220_111747 20160220_111809 20160220_111822 20160220_111902 20160220_111945 20160220_111948 20160220_111956 20160220_112419

cornell_novarr_1 cornell_novarr_3 cornell_novarr_5 cornell_novarr_6 cornell_novarr_2





205 Dryden Road (Dryden South) Construction Update, 2/2016

2 03 2016

The street was closed off when I stopped by the Dryden South mixed-use site to take a few updated photo. From the flatbed of a semi, loads of wood were being craned into the project site. Asking one of the construction crew walking nearby, he said they were wood form to be used in concrete pours. Forms provide stability and shape while the concrete hardens, and they provide support to the steel reinforcing rods (rebar) embedded in the concrete. Some of those rods can be seen poking out of the concrete pillars in the photos below; they’ll tie into the walls as they’re built up.

Most of the current work appears to be focused on the first level, where the new Kraftee’s bookstore will be located. The ground-level exterior walls (Concrete Masonry Units [CMU] from the looks of it) have been built out and the interior walls are being assembled.  It shouldn’t be long before Dryden South really starts to move skyward. The six-story building is expected to open for occupancy before classes start in August.

LeChase Construction is the general contractor, and local firm Jagat Sharma is the architect.

20160220_112051 20160220_112137 20160220_112154 20160220_112209 20160220_112220 20160220_115028

dryden_south_rev_1





Ithaca Marriott Construction Update, 2/2016

1 03 2016

Now that the fairly complicated foundation work has been completed, things are moving along at a good pace over at the Marriott construction site in downtown Ithaca. Concrete has now been poured up to the seventh floor of the ten-story building. USG Securock glass-mat sheathing panels are being attached to exterior metal stud walls erected over the lowest levels. The floors are covered in plastic sheets from about the fourth level down, a sign of sprinkler fitting and major utilities roughs-in underway (given the major heat wave in the medium-range forecast, they may not be needed much longer).

A story I’ve heard through the grapevine is that Marriott worked with developer Urgo Hotels to design a new room design format for this Ithaca project. The rooms will be at a premium price point, but somewhat smaller than most comparable hotel rooms, so Marriott is approaching the hotel and the rooms themselves with new styling concepts that make efficient use of the space while maintaining a high-end look and feel to each hotel room. Marriott has a history of working with Urgo for new design areas, so if done well, this will be yet another proverbial feather in their cap.

This project gets a lot of flack from certain angles for not being “Ithaca-like”, but given that the site had been a small, awkwardly-accessed parking lot since the Green Street garage was erected in the early 1970s, it’s a huge, huge improvement. The hotel’s 160 rooms are expected to average occupancy between 70 and 80% (the market average is closer to 60%, but new hotels and downtown locations tend to have higher occupancy rates). That translates to 112 to 128 travelers on any typical day who will literally be able to walk right out onto the Commons, eating at restaurants, shopping at the boutique stores and spending their dollars on the “Ithaca-like” businesses that people hold near and dear. Not only does the project create dozens of jobs downtown, it has a real stabilizing effect on other businesses by offering a steady stream of well-heeled customers that will buoy bottom lines and be an asset to shopkeepers and restaurateurs as they ride out slow periods. For nearby businesses, there’s reason to look forward to its August opening.

The $32 million hotel was designed by  Cooper Carry Architecture of Atlanta, and Binghamton-based William H. Lane Inc. is the general contractor.

20160219_134825 20160219_134922 20160219_135002 20160219_135112 20160219_135231 20160219_135431 20160219_135503 20160219_135521marriott_rev1_1