News Tidbits 7/2/16: Not the (City Centre) of Attention

2 07 2016

201_college_v5_1
1. Let’s start this off with the big news of the week – the proposal for 201 College Avenue was approved by the Planning Board. The debate was spirited, to put it most politely; catty, to use the official write-up in the Voice; and in the follow-up phone call I had with my editor, who attended the meeting with a Voice summer intern, she described it by saying “both sides were pretty awful”. I am sympathetic to Neil’s predicament, although I think it’s also a fairly unique case; I hope some sort of arrangement with the solar panels is worked out.

The observations regarding age and view of the project is actually pretty similar to a conversation the Journal’s Nick Reynolds and I had on Twitter about the City Centre project – older Ithacans often have starkly different views on density and urban development than younger residents, who tend to be more pro-density and pro-urban infill/growth. The young aren’t naive and more so than the old are obsolete; but they are products of different times. Today’s older Ithacans are the same ones who were frowned upon by the old Ithacans of their youth (the Silent Generation and the Greatest Generation), who were much more politically conservative and made up the large majority of the city’s Republicans from when Ithaca was once a contested city, and the Boomers were moving in and tilting it leftward. A sociologist could probably make a good research paper studying Ithaca’s generational views of urban environments.

Anyway, construction on this project is supposed to start in short order; funding has already been secured, and Binghamton-based W. H. Lane Inc. will be the general contractor for the $6 million project.

trebloc-future
2. Meanwhile, City Centre’s sketch plan was also reviewed at the Planning Board meeting. The initial reaction seems muted, gauging from Nick Reynolds’ Twitter and the lack of comment from my Voice colleagues.

city_centre_1

city_centre_2

 

According to the sketch plan submission, the vast majority of units (240 of the 255) will be studios (120) ranging from 457-563 SF, and one-bedrooms (120) ranging from 580-754 SF. The other 15 will be two-bedroom units, eight 914 SF units and seven 1,370 SF units. All units are market-rate, with target demographics including young professionals and downsizing empty nesters. Students are allowed, though the units won’t be marketed to them. Ground floor retail will be 10,700 SF at the corner of State and Aurora. 7,220 SF fronting State Street will be “Leasing/Club Space” for building and tenant functions. The 71-space parking garage will be accessed via East Green Street, car share membership will be included in the rent, and there will be indoor bike racks.

With the mild initial reaction noted, we’ll see how the project details shape up as the summer progresses, and the board potentially launches formal project review (Declaration of Lead Agency) as soon as late July.


3. Hitting the market this week is a potential opportunity for the deep-pocketed investor/developer. The property is 2248 North Triphammer Road in the village of Lansing. The sale consists of two parcels totaling 3.42 acres – a 1.53 acre parcel with a 2,728 SF M&T Bank branch built in 1992 and holding a long-term triple-net (NNN) lease; the other, an undeveloped 1.89 acre parcel to the rear that the listing notes could be developed out into 13 housing units. The price for the pair is $2,125,000.

A triple-net lease means the tenant pays everything – insurance, maintenance and real estate taxes (formally, net insurance, net maitenance and net real estate taxes on the leased asset – the three nets).  Because of this, the rent is substantially lower than it otherwise might be. There are certain cases where a landowner might want to do triple-net – like when they’re a tax-exempt entity leasing out to a for-profit company. A quick check of the records shows the properties are owned by Cornell, and were acquired in 1953 and 1960. What the property has been to Cornell is a fairly safe investment (though with a lot of fine print to determine who pays for things like if a tornado hits or the foundation cracks), generating a modest amount of rent and functioning like an inflation-protected bond, but guaranteed by the lessee rather than the government. All the better when the tenant is stable and signed on for the long-term, as is the case here.

The county has the bank parcel assessed at $635,000, the undeveloped parcel at $140,000.  Lansing village zoning has Commercial High Traffic for the bank property, and High Density Residential for the vacant parcel. HDR zoning requires 6,000 SF of land per dwelling unit in a 35′ tall multi-unit building, and 1.89 acres = 82,215 SF, so that’s where the 13 units comes from. For comparison’s sake, single family is 12,000 SF, and duplexes 15,000 SF (or, doing the math, one could in theory carve out six home lots, or 5 duplex lots for 10 units, though with lot setbacks, the property’s triangular shape probably lowers those figures).

4. On the other end of the sales process, the former Maine’s supermarket has been sold. The six year-old, 26,146 SF building at 100 Commercial Avenue in the city of Ithaca was purchased for $4,150,000 on Thursday the 30th, by Illinois-based Agracel Inc., well above its $3.1 million assessment. Agracel is an industrial space and warehouse developer, fitting for a property once described as a “food and party warehouse”. The former Maine’s appears to be a little on the small side compared to the rest of their portfolio, but there is the possibility of expansion, or even a teardown and rebuild if they really felt the need.

Readers may recall that Maine’s closed its Ithaca store in February, which along with a closing in suburban Rochester reduced its stores from six to four.

20160701_095549

20160701_095552
5. Work on the new Storage Squad facility has begun on the 1400 Block of Dryden Road east of Varna. Right now, the focus is on site clearing; the house was used by local fire departments for training exercises, and will come down in a controlled burn later this summer. The 79,000 SF storage facility should be ready for use by February 2017. One full time and a few part-time jobs will be created.

And for the record, I think that’s my middle finger.

6. So this is curious. The city recently uploaded a couple of older documents detailing development plans off of Floral Avenue on the southern tip of Ithaca’s West Hill neighborhood.

The first dates from Febraury 1992, and is a filing to create a 27-lot cluster subdivision on 4.15 acres at 452 Floral Avenue. The paperwork indicates that the intent was affordable housing, by a company named House Craft Builders. The city’s then-Planning Director, H. Matthys Van Cort, wrote a recommendation for negative declaration of environmental significance, and the project was approved in June 1992, but it never moved forward, and 452 remains vacant land today. It appears House Craft was dissolved in 2012; the officer was an architect for Ecovillage who has since retired and moved out of state.

The second is a subdivision requested by INHS in 1987. The filing requested 236 Floral Road be split into two parcels, with the intent of renovating a decrepit 236 into a for-sale affordable single-family home, and build a new house on 224. This was approved, and eventually, 236 was renovated and transferred to its owner in 1996, and 224 was built in 1994.

Now, as interesting as this all is, the city doesn’t upload decades-old subdivision files just to amuse nerds. The $64,000 question is, why were they uploaded now?





News tidbits 6/26/16: The Odd Time Out

26 06 2016

trebloc-future2-1-620x420 trebloc-future

1. In what was ostensibly the biggest news of the week, Newman Development Group (NDG) of Vestal announced plans for the Trebloc site in downtown Ithaca. “City Centre” includes nine floors total, with roughly 250 apartments from studios to 2-bedrooms, about 10,000 SF (square feet) of retail space, 3,200 SF of amenities like a business center, and an underground garage of 70 spaces (the site is zoned CBD-120, which has no parking requirement). Readers might recall that Texas-based student housing developer Campus Advantage had proposed the State Street Triangle project, but their purchase option was not renewed by the owner of Trebloc.

Looking at their portfolio, Ithaca is NDG’s odd market out – most of their projects involve suburban retail centers and chain hotels, with shopping plazas from coast to coast. A smaller division, NDG Student Living, focuses on acquiring and building student housing, with their most recent projects in Binghamton and Oneonta. Ithaca seems to be the only metro where they’ve built general housing; earlier this decade, they worked with local businessman Bryan Warren on the Seneca Way mixed-use project on the east end of downtown.

The gut reaction to Newman as a developer is that, although they’re not very accustomed to urban mixed-use, there is one market where they do know what they’re doing, and that would be Ithaca’s.

Let’s just start right off the bat with one big difference between NDG and CA – the way the news was broken. CA was caught off-guard when the Journal’s David Hill broke the news of a 120-foot building a few days before the Planning Board meeting. NDG, working with local consultant Scott Whitham, emailed the same press release to each of the three major news organizations in Ithaca, which gave them the upper hand on the way information was delivered. The Times ran their copy first with almost no additional details, the Voice came a little later in the afternoon with more details such as unit total and retail space, and the Journal’s version came in the evening with even more details, such as the 70-space underground garage, and plans for the project to pursue CIITAP, the city’s property tax abatement program.

We’ll see what happens next week. The garage, not removing the turn lane, the general housing focus as opposed to students, and an initial design by Humphreys and Partners Architects that doesn’t repulse people are all cards that NDG holds that CA didn’t. But, there will still be sizable opposition. Playing your cards correctly is just as important to a winning hand as having them.

2. It looks like Gimme! Coffee is percolating something new out in Trumansburg. Through an LLC, the local coffee chain picked up 25-27 West Main Street for $350,000 on the 20th. The building is the former Independent Order of Odd Fellows Temple, a fraternal organization which established a chapter in Trumansburg in 1839, with ties to an older fraternal organization going further back to 1818. The 19th century temple is now about 1,700 SF of retail space, and 3 apartments totaling 3,300 SF on the upper floors; recent tenants have included Life’s So Sweet Chocolates and a barber shop.

Ithaca also had a location, first in downtown, and then on West Hill from the late 1920s. The older location was demolished to build the county library in the 1960s, while the West Hill location is a mix of uses today, one of which is the Museum of the Earth.

Gimme! has had a 1,200 SF shop at nearby 7 East Main Street since 2002, but they rent the space from Interlaken businessman Ben Guthrie. Logical guess here would be, they like Trumansburg, they wanted to buy a space and stay near where they are now, this opportunity came up down the street and they went for it. The sale price on 25-27 W Main is a substantial climb from the $288,000 it sold for in June 2010; I guess they call Trumansburg “little Ithaca” for a reason.

201_college_v5_1

3. So, documents filed with the 201 College project this week were quite intriguing. First off, no action was taken at the zoning board meeting, but the developer of 201 College modified the project so that it no longer needs the setback variance or the entryways design variance. The planters were shrunk down in order to keep the sidewalk 12′ wide as requested by the Planning Board. Some additional 3-D drawings were also sent along, and site elevations and utilities plan here.

201_college_future

One of the images sent along was a “future context” file of potential nearby projects in the next couple of years. This document likely stems from the Planning Board debate of just what is likely to get developed in the vicinity over the next 5 years or so. There are four massings, merely following what zoning allows.

302-306 College Avenue – “Avenue 302”, by the Avramis family. Two buildings, one of six floors, one four, possibly in the 2017-2019 timeframe. Nothing formal has been discussed since the 2014 sketch plan, but the houses currently there are leased through May 2017.

215 College Avenue – A Novarr project. All that is publicly known at this stage is that Novarr wants to start construction in Summer 2017. Zoning allows 5 floors.

202 College Avenue – 202, 204, 206 and 210 College Avenue are all Novarr properties (there is no 208), as is the adjacent 118 Cook Street, which is not included in the massing outline. The College Avenue parcels allow 5 floors, 118 Cook 4. There hasn’t been any news with these properties lately.

119-125 College Avenue – three houses (there is no 123) owned by an Endicott-based landlord. I had to put out some inquiries on these houses, and there may be a sale in the works, although nothing’s on file with the county yet. These are CR-4, allowing 4 floors, but they could be tough to redevelop because these houses are seen as potentially historic resources.

Anyway, a vote on the project’s approvals is set for Tuesday. Neil Golder has created a group called “Save the Soul of Collegetown” to stage a rally in front of city hall that evening and try and halt the plans, but the last I checked on Facebook, three of the five people going were reporters.

 

amici house 1 county
4. Going more into briefs now, the Amici House funding plan for building a housing facility for 23 at-risk youth, and a second structure for five head-start classrooms and 42 students, was approved by the county this week. Once the sale is finalized, expect the official plans to be presented to city officials not long thereafter. Once those are approved, additional grant applications can be filed and hopefully, construction will be completed no later than 2018. According to the county’s press release, the Amici plan will create about 25 living wage jobs.

gannett5

5. Starting on the 27th, Gannett Health Services will begin to transition over to the new addition, while work begins on renovating the older wings of Cornell’s healthcare facility. This marks the rough completion of phase one, and the halfway point for the $55 million project. The Gannett webpage says the whole facility will be known as “Cornell Health” upon completion.

6. Back in November, Ithaca’s second ward saw a competitive election between candidates Ducson Nguyen and Sean Gannon. One of the big differences between the two was on development – Nguyen advocated for urban development in downtown, and Gannon thought there was too much building going on and it needed to be slowed down. Nguyen won by a hefty margin on election night.

A building loan agreement was inked next week to build a new duplex (two-unit semi-detached house) behind an existing property at 512-514 West Green Street. $330,000, Ithaca’s Carina Construction will be the contractor (expect a Simplex modular duplex). The property is bisected by zoning, with the rear falling into the State Street development corridor, so no parking is required for the new rear duplex. At a glance, it looks like a winning plan – it will be modest-sized, it’s in a walkable area, and it supplies much-needed housing. The Ciaschi family is developing the units.

The property also happens to be next door to Mr. Gannon. I’m sure he will be all kinds of amused.

 





205 Dryden Road (Dryden South) Construction Update, 6/2016

21 06 2016

With occupancy expected by August, the trio of Collegetown midrises are moving at a pretty fast clip. 205 Dryden (Dryden South) has topped out, and construction crews are installing exterior steel stud walls and building out the structural frames for the projecting bay windows. Some light-colored brick can be seen on the pillars at the front entrance, and eventually it’ll expand to cover the front elevation, with limestone accents providing some visual interest. The interior light well seen from College and Dryden and the roof cap will be faced with colored metal panels in a shade similar to the limestone and brick. These photos are a week and a half old at this point, and since they were taken, the exterior stud walls have been sheathed with gypsum panels and Tyvek.

The building will have 10 4-bedroom suites, and according to the website, only one suite is left (5th floor, $1350/person), with rooms “for singles and small groups also available”.

A quick side note here – although the address when proposed was 205 Dryden, the address being used in the marketing materials is 207 Dryden. Either one is permitted, as the new Breazzano Center going up next door is 209-215 Dryden.

20160608_162342 20160608_162914 20160608_162951 20160608_164905 20160608_164919 20160608_164927 20160608_164946 20160608_165304

dryden_south_rev_1

205_dryden_-_rendering





307 College Avenue (Collegetown Crossing) Construction Update, 6/2016

20 06 2016

307 College isn’t too far from completion at this point. The angles where with CMU dominates the exterior look nearly finished from the outside. Some of the windows are in on the front side – the projecting section, currently covered in Tyvek housewrap, will be mostly faced with dark brick, similar to the brick used on the rear CR-4 portion. The bare expanses will be a glass curtain wall, and a lighter brick will be used on the sides and for the cornice. Traditional scaffolding needs a certain amount of space and time to be set up and taken down, so given the dense environment and summer deadline of the Collegetown Crossing project, mast climbing work platforms are used being for the bricklaying and other exterior facade work.

Greenstar’s new grocery location on the first floor should be opening August 17th, right around when the first tenants start moving into the apartments. It sounds like it will be a soft opening, with an actual Grand Opening celebration planned for some date in September. A render of the interior of the new Greenstar location, designed by architect Pam Wooster, is included below. Greenstar plans to employ 14 at the new location, and include a cafe/to-go space to complement its full-service grocery (some of the items, like those in the deli, won’t be prepared on site due to space constraints; they will be prepared at their central kitchen and brought in daily). There hasn’t been any news on tenants for the smaller two commercial spaces facing the pocket park.

20160608_162651 20160608_162721 20160608_162758 20160608_162805 20160608_162829 20160608_162923

20160608_161811 20160608_162435 20160608_162527

20160608_162035

307college_rev2_1

ctown_crossing_rev2_1

greenstar_ctown.png

greenstar_ctown_2.png





327 Eddy Street (Dryden Eddy Apts) Construction Update, 6/2016

19 06 2016

Steve Fontana’s mixed-use project at 327 Eddy Street has topped out since the April update. The exterior stud walls are up on the front facade, as is a little gypsum sheathing. The CMU Block rear portion is also topped out, although it appears that the design of the rear was also changed/value engineered such that it no longer have the larger band of windows on the top floor. The large window at top center is split between two units,  and using the wood stud walls as a guideline, one can kinda get the impression of soaring ceilings and a big, glassy open space. More interior wall faming can be seen from the rear of the building. Units range from studios to 5-bedroom apartments, with prices starting at $950/person and topping out at $1250/person for choice units.

While the apartments are able to command to premium price, Fontana has had issues finding a commercial tenant for the 1,800 SF first floor, and expressed his concerns at a city PEDC meeting where the active-use code for Collegetown was modified to match the slightly more flexible code used with the Commons.

Things should be moving right along for an August opening.

20160608_164146 20160608_164214 20160608_164236 20160608_164251 20160608_164449 20160608_164504 20160608_164509 20160608_164513

327_eddy_rev4_1

327_eddy_rev2_3





News Tidbits 6/18/16: Wit Fails Me After Eight Years

18 06 2016

201_college_v4_1 201_college_v4_2
1. Let’s start off with a brief update on 201 College Avenue. My colleague Mike Smith at the Voice did an encompassing article on the topic late last Friday, and there have been a couple more modest developments as of late. Apart from the multi-million dollar sale mentioned last week, the city’s Design Review Committee also gave their input on the project. They said they like the current form of thje building’s front (west) entrance, because it calls forth elements of Grandview House a few doors down. they also recommended darker or neutral grey colors to minimize the appearance of the fifth floor, more windows along College Avenue, warm accent colors, and tweaks to the window and cladding scheme. The resulting revisions were incorporated into the latest building design seen above, and for which additional images, material samples sheet and interior plans can be found here. The project will be discussed at the Project Review meeting next week, and the official Planning Board meeting Tuesday 6/28, at which the public hearing will be held, and consideration of preliminary approval.

107_s_albany_v2_2

107_s_albany_v2_1

2. Speaking of design review, 107 South Albany also went through the committee this week. Recommendations included projecting window sills, stucco all the way back to the rear balconies, and noting on docs that the large sign on the existing building would be removed during the renovation. Site Plan Review app here, drawings here, Full Environmental Assessment Form (FEAF) here, planting plan here.

The renovation and addition seems like a good example of re-use in a corridor that the city is targeting for new investment. It preserves the century-old structure and adds housing in such a way that, by location and design, doesn’t have a significant visual impact. By zoning, Nick Stavropoulos could have sought five floors if he wanted. This plan will be going through the whole shebang at the June meeting – Declaration of Lead Agency, Public Hearing, Determination of environmental Significance, and Prelim and Final Approval.

Among other things to be discussed at Project Review and the Planning Board meetings – Prelim/Final Approval for 602 West State Street (the Elmira Savings Bank project), signage for Collegetown Crossing, and a few minor zoning variances. New sketch plans, if any, will be announced on the PB Agenda next week.

3. This week in big sales – someone plunked down $680,000 on a house at 107 Catherine Street in Collegetown. I say somebody because they conducted the purchase through an LLC (aptly named “105-107 Catherine Street LLC”) registered by a local law firm last summer. Just like the Maguire purchase of the Carpenter Circle land, this effectively hides the buyer from public view. The same purchase bought 105 Catherine for $780,000 last November. It looks like 105 has 10 bedrooms and 107 has 7 bedrooms, based off assessment docs.

cafd1

105 and 107 Catherine make up the edge of the CR-4 Form District. By zoning, an applicant could build up to four floors, no parking required. A development plan would likely consolidate lots. Something to keep an eye on. Collegetown is getting to be a very expensive place.

4. Meanwhile, here’s something that’s just hitting the market. For the budding landlords, 306 North Cayuga is up for sale. The “C. R. Williams House” was built in 1898 (interior/exterior photos from the early 1980s here). The current owner, Jeff Kalnitz, picked it up for $300k in 1997, had it on and off the market a couple of times, and then decided to do a thorough ILPC-approved renovation. The 12,500 SF property, which holds six high-end apartments and approvals for a seventh, is being offered at $1.45 million. It’s worth looking at the listing if only for the glamorous interior shots.

amici house 1 county
5. On Tuesday, the Tompkins County Legislature will vote on whether or not to take $118,000 from the county’s general fund to indirectly help build head start classrooms and a living facility for homeless young adults.

The $118,000 would be use to purchase a house at 661 Spencer, whose land would be incorporated into plans for a 23-person facility for homeless young adults (some with children) aged 18-25, and five classrooms. The classrooms would be built as one building, while the housing looks to be an addition to the TCAction building. The one-story house at 661 Spencer, built in 1950 and formerly formerly owned by the Amici family, would be removed.

The plan is the latest incarnation of TCAction’s Amici House project, slated to share their headquarters property at 701 Spencer Road on the southern edge of the city of Ithaca. TCAction first acquired their property with the help of the county back in 2001; the cost of the purchase is paid back to the county in the form of a 20-year lease.

If the legislature approves, the lease would be extended by two years so TCAction can pay them back for the up-front cost of buying 661 Spencer. The Amici House project would be completed by 2018.

6. Poet’s Landing in Dryden will be moving forward with its 48-unit second phase. The rentals, which are targeted at individuals making 60% of county median income, are expected to begin construction in August with a late summer 2017 opening. Phase I, which consisted of 72 units, opened in early 2013. The state awarded the project $1,600,000 from its Housing Trust Fund, and $734,956 in Low-Income Housing Tax Credits to help finance the apartments’ construction.

tfc_v2_1

7. Tompkins Trust held the official groundbreaking this Friday for it’s new 7-story headquarters. Plans were slightly delayed after some issues arose with NYSEG. The current plan is to have the 123,000 SF building ready for occupancy by March 2018. Costs have risen somewhat, from $26.5 million to $31.3 million.





409 College Avenue (Student Agencies eHub) Construction Update, 6/2016

17 06 2016

The Student Agencies eHub renovation seems to be moving along, though perhaps a little slower than originally anticipated. Luckily, since Cornell’s in summer intersession, the offices aren’t be used as much as usual, which allows work to commence on the second phase of renovations. Under the scaffolding, it looks like the old facade is off and work on the new glass curtain wall is underway.

20160608_163016 20160608_163049 20160608_163117





209-215 Dryden Road Construction Update, 06/2016

15 06 2016

At the site of the new Breazzano Family Center for Business Education, work continues on the foundation. It looks like excavation is mostly complete at this point and they’re putting in concrete footings, with digging for a new footing taking place at left in the first photo. The rebar doweled into the concrete will be tied into the walls as they’re built up. The footings closest to 205 Dryden (westernmost section) will hold the elevator shaft, stairwell and restrooms for each floor.

For those wanting a glimpse of the future, Cornell has put up a video render on Youtube showing the new building (exterior and interior) and advertising some of its features. There is an embedded copy of the video clip below.

20160608_162032 20160608_162035 20160608_162040 20160608_162217 20160608_162257 20160608_162323

209-215_2 209-215_basement





News Tidbits 6/11/16: Summer’s Heated Discussion

11 06 2016

Image Property of HOLT Architects

1. We’ll start this off out in Lansing. The 153 acres of land for the Lansing town center is once again in the news. The Lansing Star is reporting that the town is once again serious about selling the land.

So begins yet another chapter in the 20-year saga of the town center land. The town bought the land from the state in 1993 for $100,000, and at the time the land was deed-restricted to recreational use. In 2012, the town paid an additional $294,800 to remove the recreational deed restriction. An article about it was published here in August 2012 (original map below; dunno where why offhand it says 156 acres vs. the 153 reported now). HOLT Architects and TWMLA were hired to draw up some overarching design themes, a Request for Proposals was issued, and three developers responded.

lyc2

Calamar Enterprises’ Buffalo office submitted a proposal for a $17.4 million, 110-unit market-rate senior apartment building on 13.5 acres, and Cleveland-based NRP Group submitted plans for 80 one-story patio homes on about 15.5 acres. Calamar later re-sited their project at the town’s wish to the northern part of the land, and increased the number of units to 124. Green Square, led by David Taub and HOLT Principal Graham Gillespie, proposed 60 units of housing and 23,000 square feet of retail in 2-3 story arrangements, and civic and recreational space. Altogether, the value of the three would have approached $50 million.

gs_phases

However, all of this was contingent on a sewer being built, which did not happen. The developers agreed to do a package plant that would service just the town center, there was discussion of an IDA-backed tax incentive zone, and the town stood to make a hefty return on investment, but…to quote the Star, “However, the deals fell through.  Actually it seemed more like they just faded away. At least one of the developers had signed paperwork saying they intended to purchase acreage from the Town.  The Town didn’t seem in any hurry to sell the land, even with clearly interested developers.  When the developers disappeared there was no reported effort by the town to pursue the deals.”

Since then, the town continues to get a steady stream of interest, but no real idea on how they want to move forward. Like Ithaca city and town, they’re looking at the possibility of Form-Based zoning for the site, and the town hopes to issue a more specific RFP than before, incorporating revised assessment values. The most intensive approach involved the Form-Based Code and a specific RFP, the least specific is just putting up a for-sale sign ans seeing what happens. Whatever the case, the lax approach the town has taken the past few years may no longer be feasible, with the ticking tax time time bomb of the possible power plant closure looming over the town and schools’ budgets.

old_library_thp_v4

2. Speaking of long processes, the Old Library project has formally filed paperwork here to begin the application process for the Certificate of Appropriateness from the Ithaca Landmarks Preservation Commission. The meeting is scheduled for city hall at 5:30 Tuesday the 14th. Although it says early design review, a lot of the legwork has already been done at this point, since the Planning Board and ILPC have been conducting joint meetings with the project team over the past several months to create a design that they’re all comfortable with. However, the ILPC is likely to refine some details moving forward.

old_library_thp_v4_2
At this point, the unit mix consists of 22 1-bedroom units with about 700 SF each, 25 2-bedrooms with about 900 SF each, and 10 2-bedrooms with 1200 SF each, the extra space intended as a den or home office. The building also includes a 1,800 SF community room to be administered by Lifelong, and 3,750 SF of first floor commercial space. The total facility size comes out to about 85,600 SF, and parking for 25 cars and at least 12 bikes, and another 34 bike spaces for the community room. Exterior materials include brick, limestone, and a couple forms of fiber cement, including wood-textured fiber cement.

Southeast+Rendering

3. The STREAM Collaborative House at 228 West Spencer is up for sale. The house has its own website here. The 1,152 SF, 2-bedroom net-zero energy house is listed at a price of $305,000. For more info on the house, Noah Demarest was kind enough to give a construction tour of the house while it was underway, and the blog post I wrote up afterwards can be found here.

evergreen_dryden_1
4. It’s pretty clear at this point that the Evergreen Townhouses project at 1061 Dryden is evolving into the next hot-button development issue out in Varna. The Times has their interview with the angry neighbor here, and more info can be found in the town of Dryden’s April planning board meeting minutes here. So far, the only image of the townhouses themselves has been a perspective that only shows massing – 2 stories, gabled roofs.

Also of note is the town of Dryden Planning Department’s recommendation to the town board (and the planning board’s approval) for an increase in density in certain areas. The change in code affects parcels zoned rural residential, with municipal water and sewer access. The density would be increased from 2 units per acre to 6 per acre. Looking at the zoning map and the sewer map, that would primarily affect the corridor from Varna to the 13/366 intersection, and a rural swath just north of Dryden village near TC3. What this would do is allow 1061 Dryden Rd to withdraw PUD application, and apply for a special use permit (SUP), which are generally easier to obtain.

On a side note, googling Tiny Timbers brings up a Times editorial, written by the Times, that argues against Tiny Timbers for not fitting in with the appearance of Varna. Actually, it kinda takes everyone to task, from developers to town government to residents. But, to make one counter-point regarding mixed-use, commercial services need a certain amount of traffic (not necessarily vehicular) to thrive. If the population base within a certain radius isn’t there, the risk is too great for someone to put their money on the line and hope that they can somehow draw in customers. If Varna wants a mixed-use center with shops and cafes, they’re going to need the population to support it. Some think that will include 1061, some (probably more) think Tiny Timbers, but if there’s no “push”, the ball won’t be rolling.

201_college_v3_1

5. A couple of minor things to note in sales. The 4,200 SF former “Imperial Buffet” property next to the Shoppes at Ithaca Mall has sold to a Syracuse-bsed LLC (Watersprite LLC, established 2004) for $590,000 on Friday the 10th. I personally will always remember this place as being the only place my mother was comfortable with eating in Ithaca because she hates eating out, and felt everything else was “snobby and expensive”.

Meanwhile, the 12-bedroom, 2,837 SF house at 201 College Avenue, the property subject to a heated debate between Neil Golder and Todd Fox, sold for $2.65 million on Friday the 10th, which seems outrageous except that it’s becoming the norm for inner Collegetown transactions – Novarr picked up 5,500 SF 215 College for $5.3 million last year. There will be no delving into that debate again this week, but the city uploaded 580 pages of documentation here, and my colleague Mike Smith is preparing a story for the Voice.

20160522_143925 20160522_143949

6. Houses of the week. This pair of duplexes are being built on Birdseye View Drive near Ithaca College. Each house has a 4-bedroom unit and a 2-bedroom unit; recent advertisements on Craigslist (since expired, so no link, sorry!) have them $750/bedroom. The developer is the owner of Mahogany Grill downtown, who also happens to be a part of the business team renovating the former Lucatelli’s into a new restaurant, a Tapas and pasta restaurant called Mix Social Dining after the chef’s wife.

These photos are a couple weeks old now, but the one on the right looks nearly complete, while the one on the left was still in the (wood) framing and sheathing stage. Based off the rough window and door openings, they are not exactly the same, but expect them to look similar.





News Tidbits 6/4/16: A Stormy Summer Start

4 06 2016

201_college_v3_1
1. We’ll start this week off with a follow-up on the 201 College Avenue debate. All discussions of planning philosophy noted, one solid request, as reported by Josh Brokaw at the Ithaca Times, was to try and reduce the bulk from the College Avenue side, if not necessarily the building footprint. The above drawing was submitted by STREAM Collaborative’s Rob Morache earlier this week, with a cover letter describing the changes here. The modification reduces the building by 2 bedrooms, to 74, which to go by Todd Fox’s comment in the Times article, puts the project at the borderline of financial feasibility. The middle still pops out a little because that’s where the fire stairs are located. Some minor details were changed with the accent panels, and recessing the windows slightly on the south and west facades. For the record, the panels are Nichiha and Allura fiber cement, with painted metalwork and fiberglass window sashes.

Although now outdated, a shadow study for the previous design has since been uploaded by the city. There are two versions, with and without neighboring building shadows, here and here respectively.

Expect further detail refinements; the building is set to go in front of the Design Review Committee Tuesday morning.

20160414_120418

2. WSKG did a segment earlier this week on micro-apartments, with an interview with Frost Travis and the Carey Building project wrapping up on East State Street. A few details worth noting from the segment – 5 of the 20 rental units (which range from $1,225/month for the microunits to $2,699/month for a high-end penthouse 2-bedroom) are already spoken for and the building’s not even finished yet. For some reason, Monica Sandreczki says there will be about 35 residents at full occupancy, which is a big stretch since there are 16 micro-units and 4 two-bedroom units – going one person per micro-unit and bedroom, a better estimate would be 24.

The news piece also notes that the 201 College project contains micro-apartments – which is true, given that the building is 44 units and 74 bedrooms, and at least the early plans had a number of split-level 410-670 SF studio units.

401_lake

3. And 401 Lake Street will bite the dust. The Common Council voted 8-1 last Wednesday night to have structure demolished and the tax-foreclosed properties be designated as parkland. Cynthia Brock (D-1st) voted against the measure and preferred a sale for tax reasons, and her ward counterpart George McGonigal (D-1st) argued that the city was destroying historic working-class housing, though he ultimately supported the measure. Brock did take a whack at new affordable housing in the city, commenting that INHS is getting $75,000 for each townhouse, and Habitat for Humanity getting $75,000 for a duplex even with its volunteer labor, when there was a potential, cost-efficient opportunity for affordable housing designation with this unit. Josephine Martell (D-5th) seemed to be the strongest proponent for demo, stating that the unique potential to enhance the Ithaca Falls Natural Area should be taken every opportunity of. The city bought the tax-foreclosed property from the county; the background on that is on the Voice here.

The funds for the demolition, estimated at $25,000, will come from the sale of IURA land to the Hilton Canopy project. That measure was approved 6-3, with Brock, McGonigal and Graham Kerslick (D-4th) opposed. With work on the Lake Street Bridge currently underway, demolition is not expected for at least a few months.

There was a thought exercise regarding the selling the falls’ parking lot to INHS for development of 3-9 units of affordable housing; it’s an interesting idea, since 401 and the adjacent are right next to the Falls, but the 0.55 acres of city property adjacent to the Lake and Lincoln Streets intersection is still over 200 feet away at its closest point.

4. The rare bit of news out of Enfield. A $612,000 building loan was issued by the Bank of Greene County to provide funds for renovating and expanding the volunteer fire station at 172 Enfield Main Road.

Give that Enfield issues no more than a handful of new construction permits each year, it’s about the only other thing going on apart from the Black Oak Wind Farm debate. One would think that arguments like “the wind does not blow as much as it used to” would be easily shot down and things would move forward, but instead it’s Marguerite Wells, the project manager for BOWF, getting raked over the coals. I don’t have a dog in this fight, but I do feel bad for her.

5. In case anyone was wondering – county planner Megan McDonald says the Denter housing study will be publicly available by late July.

arpt_pk_1

6. Here’s something intriguing from the county’s Facilities and Infrastructure Committee agenda – a proposal to “Prepare airport land for future development“, seeking $500,000. None of the money comes from the county; it appears to be dependent on grants, or an interested developer. Which, given the fact that this shows up in budget docs going back to 2014, doesn’t exactly seem to be generating many queries.

The parcels are described as the “Cherry Road and Agway parcels”, which must be owned by the county since they want to lease out the land – but checking the deed records of parcels adjacent to the airport, there’s no record of an Agway in any of the deed histories. The parcels may be related to the properties in the airport business park feasibility study, shown above and awarded to the team of Clark Patterson Lee and Camoin Associates this past winter.

7. It’s unusual to see Cornell buying property these days, but this Friday, the university purchased the house at 1250 Trumansburg Road on Ithaca’s West Hill for $157,000. The house is a 19th century fixer-upper on 1.21 acres – Cornell owns the land surrounding it, some of which is being subdivided off to build the Cayuga Meadows affordable senior housing project. The house is assessed at $215,000, but the real estate listing notes it needs some work, and it’s been off and on the market for five years.

Several years ago, Cornell expressed intent to develop the 35 acres it owns into a mixed-use complex with a hotel institute, housing, offices and medical services, but the only part of the plan that ever really moved forward was Conifer’s project. I haven’t seen the plans in years, but I remember the early plans (there were a couple versions) were very sprawly; six, eight years ago, walkability was not as valued as it is now.

By buying the house, Cornell reduces its need to work around a neighbor and can incorporate the property into potential plans. This purchase would seem to suggest that Cornell still has strong interest in developing the rest of the West Hill property at some point. In the meanwhile, Cornell might rent it out while the school figures out what it wants to do with the acreage.

20160522_151346 20160522_151417

8. House of the week. From the outside, 228 West Spencer Street is almost done, and the interior is fairly far along as well, with finishing work underway. Architect Noah Demarest says the house will be put up for sale in a few weeks, if everything goes as planned.