Village Solars Construction Update, 4/2016

19 04 2016

Heading into the spring, it looks like the Village Solars project off of Warren Road in Lansing has made some pretty substantial progress with its second phase.

Building “D”, which contains 12 apartments, is essentially complete inside and out, though not yet occupied.

Building “G/H”, which holds 18 units, is fairly far along from the outside – cement boards have been attached to most of the east face, and some more wood siding has been applied to the west face. Exterior details like balcony railings and trim boards have yet to be installed.

Building “E” is topped out, and the roof rafters are being sheathed with Huber ZIP panels. The stairwells are still being framed out. Windows have been fitted in most of the rough openings on the first and second floors, but have yet to reach the third floor. Housewrap covers most of the plywood walls, with the exception of the stairwells. “E” will have 11 apartments.

From observation, it looks like Lifestyle Properties (the Lucente family) could start renting out Building “D” tomorrow if they wanted, Building “G/H” towards the end of the Spring (possibly Mid-July from the Craigslist posting), and have Building “E” ready for occupancy before the semester starts. Phase two of the 174-unit apartment project is being built with a $6 million loan from Tompkins Trust. Phase one’s 36 units opened last year.

EDIT: From Rocco Lucente the younger – “We will have our first move ins for 1067 Warren Road (Building D) on May 1st. The other two buildings are currently scheduled for June 15th and July 15th completion. We did get our Certificate of Occupancy for Building D around two weeks ago, but with the various cleaning and landscaping work we set our target for May 1st.”

No loans have been secured yet for the three later phases, and plans are still in the works for an addition across Village Place that would bring the total number of new apartments to over 300.

20160414_174742 20160414_174754 20160414_174809 20160414_174852 20160414_174921 20160414_175002 20160414_175115 20160414_175233 20160414_175611 20160414_175618 20160414_175729

village_solars_2 village_solars





News Tidbits 4/16/16: The Real Estate Shopping Spree

16 04 2016

old_libe_thp_holt_v4

1. On Monday, the county’s Old Library Committee received an update from Travis Hyde Properties about the redevelopment. Perhaps the biggest development is that Lifelong is no longer moving into the building. Instead, they will sell keep their office at 119 W. Court Street, sell the historic building at 121 W. Court Street, and have free use of DeWitt House’s community room for classes and workshops. Lifelong would also be the administrator of the community room, so rental fees for use of the room by other organizations will be paid to Lifelong instead of Travis Hyde. Lifelong’s treasurer claims this arrangement will save them $50,000 vs. the original proposal.

According to the Ithaca Journal piece by Andrew Casler, law firms have expressed interest in the 121 West Court Street property, although other business and housing isn’t out of the question. 121 is just outside the DeWitt Park Historic District.

The number of units is down from 60 to 55 (though some of those are now 3-bedroom units…the Tines is reporting 57 units total), and parking spaces are down from 30 to 25, all internal to the building since Lifelong is no longer moving in. Frost Travis is quoted as saying he might be looking into expanding the age range of possible tenants (currently proposed as 55+), but that seems liable to garner significant blow-back from neighbors if pursued.

The current plan is to have approval by September, sale of the property by October, and after any final site plan approval tweaks, construction may begin next Spring.

20150727_145000

2. The Ithaca City PEDC had another crack at incentive zoning this past Wednesday. And the consensus is, everybody dislikes it for one reason for another. Some of the development community feels it doesn’t go far enough, while some local activists feels it goes way too far. Sounds like the plan is striking a good compromise if it’s ticking the stakeholders off for not being more like their way of thinking. But, proof would be in practice, and seeing if any developer would actually be interested in pursuing a plan that utilizes the incentive zoning.

On a related note, Svante Myrick deserve a laurel – when asked at the meeting why there’s a housing shortage in Ithaca, he pretty much nailed it – the growing economy, increasing student and retiree populations, and a renewed interest towards urban environments are driving demand higher than in decades past.

201_college_v2_3
3. For this week’s eye candy, here’s a perspective drawing of the multistory apartment building proposed at 201 College Avenue. One thing that stands out here that doesn’t in the elevations (the latest of which can be found here) is that the corners are stepped down, so the bulk of the building is lessened. The planning board is expected to agree to be the lead agency for environmental review at its April meeting.

4. So I’m mostly leaving this to my colleague and editor Jolene Almendarez, because she is much more familiar with the Elmira Savings Bank situation than I am. But it’s worth noting that Steven Wells, the Massachusetts man who sold ESB the properties, was on a buying spree this week. On Tuesday, Wells paid $224,000 for 508 West State Street (the old Felicia’s Atomic Lounge), $884,638 for 622 Cascadilla Street where Zaza’s is located, and $1.5 million for 402-410 Third Street, a commercial plaza home to Finger Lakes Physical Therapy.  Felicia’s was noted here on the blog when it went up for sale last August for $350k.

ith_big_plan_map_v2

They all have different owners, and they’re in varying physical conditions. The only thing that unites these three properties is all that are in areas the city as ripe for redevelopment for urban mixed-use in the Comprehensive Plan. Felicia’s was upzoned in June 2013 to CBD-60, permitting a 60-foot tall building, no parking required. 622 Cascadilla is WEDZ-1a, allowing for five floors and no off-street parking requirement. Lastly, 402-410 Third Street is B-4, 40′ max and 50% lot coverage, but allows virtually any kind of business outside of adult entertainment. Those are some of the city’s more accommodating zoning types, so we’ll see what happens moving forward. At the very least, the public relations game will be starting from behind the proverbial eight ball.

5. Out in Dryden, the William George Agency is seeking county legislature approval to issue $2.7 million in bonds to finance construction of a new 24-bed residence hall. The facility will affect about 1 acre, be about 15,000 square feet, and start construction this Spring, taking about one year to build.

As the county deems appropriate, they can approve the issuance of tax-exempt municipal bonds to finance construction projects. First the planning committee signs off on it, and then the general legislature takes it up for a vote. The non-profit residential treatment center secured a $2 million construction loan this past January to fund roof repairs and renovations to cafeteria area. The agency, established in the 1890s, employs over 340, making it one of the larger private employers in Tompkins County.





News Tidbits 4/9/16: A Slippery Situation

9 04 2016

maplewood_site_plan_concept

maplewood_site_plan_concept_v2

1. The town of Ithaca had their first substantive meeting about Cornell’s Maplewood Park Redevelopment, and later this month, the city of Ithaca will have their take on the 4.5% that sits within their boundaries (picture a line up Vine Street – that’s the city line). According to documents filed with the city, approvals from them will only be needed for one building. Application/SPR here, cover memo from Whitham Planning and Design here, Part I of the Full Environmental Assessment Form here, and narrative/drawings here.

From the SPR, the schedule as already been shifted slightly to an August 2018 completion rather than July – they also threw out a $3.67 million construction cost that doesn’t make much sense offhand. Edit: It looks like it’s just a basic estimate of 4.5% of the total project cost of $80 million.

The biggest change so far is a revision of the site plan. In response to community meetings, Cornell shifted smaller 2-3 story stacked flats and townhouses closer to the Belle Sherman Cottages, pulled back a couple of the larger apartment buildings, and added a new large apartment building to the southeast flank. Cornell has its goal of housing at least 850 in the redevelopment, so all design decisions revolve around accommodating those students with their families, while coming up with a design the community can live with.

The city will vote at its April meeting to defer Lead Agency to the Town of Ithaca, which will leave them with the ability to provide input, but the town board will be the ones voting on it.

2. It’s not often that a project gets undone by a single public commenter at a meeting. But the Journal’s Nick Reynolds got to experience such a momentous occasion at the town of Ithaca’s planning board meeting. He documents it on his Twitter account.

Someone that I didn’t cover because it wasn’t especially news-worthy is Cornell’s plan to replace the Peterson Parking Lot at the intersection of Tower and Judd Falls Roads with a cutting-edge 100% porous paved lot and a Cornell-created soil designed to promote rapid growth of trees in high traffic areas (a new island would be built in the middle of the lot). Basically, an eco-friendly, less-invasive parking lot, if there ever could be a thing.

Then Bruce Brittain, the Forest Home community historian, completely undid the plan with a contour map. Generations ago, the property was filled with debris and garbage, even old construction trucks. And while there may be a parking lot on it now, a porous lot, which would be heavier when watered, is liable to collapse right onto the Plantations below. Meaning, no porous lot, no green showcase. Back to the drawing board Cornell.

201_college_1

201_college_v2_1

3. Here’s a little more information on the 5-story, 44-unit/76-bedroom apartment proposal for 201 College Avenue. SPR Application here, FEAF here, project narrative here, BZA worksheet here, drawings here , letter of discontent from Neil Golder here. Looking at the drawings, there have been some slight revisions, mostly with the College Avenue entrance and the materials and fenestration at street level. The SPR gives us a $6 million construction cost, and a proposed construction time frame of July 2016 – August 2017. Units will be a mix of 1 to 4 bedrooms (24 1-BD, 12 2-BD, 4 3-BD, 4 4-BD). While the project falls into the Collegetown Form District, an area variance will be required for a front yard setback from College Avenue, which the board feels will help the street be more like a boulevard.

The city planning board is expected to Declare itself Lead Agency for environmental review at the April meeting. Developer Todd Fox hopes to have approval by the end of the June meeting. STREAM Collaborative is the project architect.

902_dryden_final

4. This week’s eye candy comes courtesy of Noah Demarest and Todd Fox (yes, they seem to be getting a lot of mentions this week). It had occurred to me that while an image of the revised 902 Dryden townhouses had been presented at the meeting where it was approved, the town never uploaded the copy. Noah and Todd were kind enough to send me a copy of the image presented at the meeting, and gave their permission to share it here. 8 new units, 26 new bedrooms. The duplex building in the middle already exists, but two new units will be built opposite a shared wall. Two three-unit clusters will be built on the east side of the parcel.

Cayuga-Meadows-Shot

5. It’s official as of March 28th. Construction permits have been issued for Conifer LLC’s 68-unit Cayuga Meadows project on West Hill in the town of Ithaca. Expect the first construction update, and a synopsis, when the first construction update comes around, which won’t be until mid-to-late May since West Hill projects get visits during odd-numbered months.

6. Just a couple minor city subdivisions to pass along. One, an application in outer Collegetown at 513-15 Dryden Road to separate the land into two parcels (513 and 515). The lot owner will then build himself a new house on the vacant lot. CR-1 Collegetown Form District, and it looks like no variances will be needed.

The other subdivision is on the city’s portion of West Hill. The property is a vacant lot that borders Westwood Knoll, Taylor Place and Campbell Avenue. The property owners, who live next door on Westwood, want to divide the vacant lot into two vacant lots to sell for single-family home construction. Once again, it looks like no zoning variances will be needed, just regulatory PB approval.

With the consolidation and realignment of 312-314 Spencer Road mentioned last week, this makes three subdivisions scheduled this month. That’s pretty unusual, as the city typically sees only one every 2 or 3 months on average.

7. Looks like someone made a tidy profit. Local landlord Ed Cope picked up 310 and 312 E. Buffalo Street for $885,000 on the 6th. 310 E. Buffalo is a 6-unit apartment building, 312 is a parking lot. The previous owner, a Philadelphia-based company, picked up the properties for $800,000 back in October 2014. So, $85,000 (+10.6%) for 18 months of ownership. The properties are part of the East Hill Historic District, where the Philly-based firm recently had a hell of an experience because the owners before them replaced the windows without notifying the city, and that was a big no-no as far as historic districts and the ILPC are concerned. They mandated the windows all be replaced with more historically-appropriate fittings. Hopefully that came up during the sales negotiations.

For what it’s worth, the parking lot is zoned R-3a – a 4 story building with 35% lot coverage. Since it’s in a historic district, a hypothetical proposal would likely look a lot like its neighbors.

11-24-2012 171

8. And another big sale this week, on Friday – the house at 210 Thurston sold for $2.5 million to the Alpha Chi Omega sorority. The house had been on the market since last November for $2.75 million. This actually sold relatively quick, given its large size and fairly unique nature. The seller purchased the property for $677,500 in December 2011, and renovated the property for use by the Cornell wrestling team.

Alpha Chi Omega has occupied the house at 509 Wyckoff Road for a number of years, but did not own the property – the owner, who picked up the property in 1971, is a business partner of Kimball Real Estate.

 





A Construction Tour of a Net-Zero Energy House

6 04 2016

A couple of weeks ago, Noah Demarest was kind enough to give a tour of the new net-zero energy single-family house underway at 228 West Spencer Street in the South Hill neighborhood.

Most readers of the blog will be familiar with Noah Demarest’s name – he’s the head architect of STREAM Collaborative, which has been involved in projects like 902 Dryden Road, 201 College Avenue, State Street Triangle and the Franklin proposal for condos at the Old Library site.

228_w_spencer_1

Noah’s a little more involved in this project than most – he’s in charge of the build-out, and the cost of construction is coming out of his own pocket. Local landlord Ed Cope is a silent partner in the project, having purchased the land from the previous owner for $15,000 last February. The sale came with a different set of house plans, and the unique topography and constraints of the site made it such that the BZA had to approve virtually any new construction proposed on the parcel – Noah drew up plans for a different design, and those were later accepted by the board.

20160319_130922

You can see how that unique site topography plays in here. The framing, sheathing (ZIP system), roofing and panelling of the house was done by local company Ironwood Builders. With much of the exterior work completed, activity has shifted largely to the interior spaces, which Noah is doing with his own construction team.

20160319_130936

My initial impression was that they were going for an exposed wood trim look similar to the framework of Tudor-style houses, but Noah says the trim will be painted the same color as the fiber cement siding. The shingles are a nice, Craftsman-style touch.

20160319_131043 20160319_131055

First photo is looking down, second is looking up. The house, just under 1,000 SF, has living space on three levels – the kitchen and living room will be on the second floor, and a bedroom and bathroom are on the first and third floors. This will be put up on the market for sale once it is ready – not a rental. Noah envisions this being the type of house that would be great for a young couple or even a deep-pocketed grad student.

By the way, just mentioning for the sake of acknowledgement – I’m not a fan of ladders.

20160319_131113 20160319_133609

As work moves closer to completion, a porch pergola will be built here.

20160319_133613 20160319_133748

This will be a net-zero energy house, meaning zero net energy consumption – what gets taken from the grid also gets returned to the grid. In the case of this home, an off-site set of solar panels will offset the energy that is taken from the grid. The house will also achieve a very high degree of energy efficiency. One of the ways that’s being accomplished here is the use of an air source heat pump, which transfers heat from outside to inside a building (and vice versa) via a refrigeration compressor and condenser. The system can absorb heat from the outside air and transport it into the home, and can work in reverse during the summer, absorbing heat from inside the home and transporting it outside.

According to Noah, the system tends to be somewhat less efficient in extremely cold weather (-10 F or so; at that point it becomes difficult to extract usable heat energy), but is otherwise very capable for providing heating and cooling needs. Appliances will be all-electric, no gas.

20160319_133939

The house is also very heavily insulated – 2.5 inches of foam, with the fiber cement siding on top of that.

20160319_134029 20160319_134056
These last couple shots are from the bottom level – bathroom plumbing is in the process of being installed in the basement bathroom unit. The plan is to have the house ready for sale later this year.

One of the things that I personally am looking forward to is that Noah plans on making the costs of construction available to the city, as an example of what construction costs tend to look like for infill on an inner-city parcel. Having more examples to rely on, and a clear description of cost per square foot, gives the city more information to help guide its approach to planning and development. Noah noted during the tour was that the zero net-energy aspect is a relatively minor component in the expenses of the project.

 





News Tidbits 4/2/16: The Walls Come Tumbling Down

2 04 2016

hotel_ithaca_final_1

1. Demolition and site prep work has begun for the Hotel Ithaca’s new 5-story addition. The work appears to be right on schedule, since a March construction start had been planned. The $9.5 million, 90-room project replaces a two-story wing of rooms built in the early 1970s. Hart Hotels of Buffalo hopes to have the new wing open for guests this fall. NH Architecture of Rochester is the firm designing the project, which received some “sweet burns” when it was first presented with cross-hatched panels and “LEED-certified stucco”. Eventually, the planning board and developer settled on a design after review, and the project was approved late last year.

For those who like to see walls a-tumblin’, the Journal’s Nick Reynolds has a short video of the demolition on his Twitter feed here.

2. Looks like there’s a little more information about the 16-unit “small house” subdivision planned in Varna. A Dryden town board document refers to the document as “Tiny Timbers”. Which is a name that has come up before – in STREAM Collaborative’s twitter feed.

https://twitter.com/streamcolab/status/673601010313641984

https://twitter.com/streamcolab/status/657329991827509248

Making an educated guess here, STREAM is working with landowner and businessman Nick Bellisario to develop the parcel. It would also explain the huge mounds of material that had been on the site as of late – compressing the very poor soil so that something could be build onto it, even if they’re merely “tiny timbers”. It doesn’t look like these are more than one or two rooms, with an open floor plan on the first floor and either a room or loft space above.

At first impression, these are a great idea – relatively modest sizes tend to be more environmentally sensitive, and with the subdivision, it’s likely they would be for-sale units with a comparatively modest price tag. On the other hand, tiny houses are something that a lot of local zoning laws don’t accommodate well (minimum lot size, minimum house size, septic), so that would be something to be mindful of as the project is fleshed out more and starts heading through the town’s approval processes.

201_college_1

3. Here’s some good news – the initial reception to Visum’s 201 College Avenue project was favorable. Josh Brokaw at the Times is reporting that apart from debates over a more distinctive roofline and setbacks from the street (which is more ZBA than Planning Board), the board was supportive of the project.

Meanwhile, as for something they were not in support of, the possibility of removing the aesthetic parts of site plan review as a benefit to affordable housing incentive zoning was not something that sat well with them. One thing that does get missed in the article, though, is that that benefit would only be in areas with form zoning guidelines for building appearance and siting (right now, that’s only Collegetown).

cma_2 cma_3

4. Never a fan of being scooped, but the Journal’s Nick Reynolds broke the news of a 3-story, 39,500 SF outpatient medical facility planned for Community Corners in Cayuga Heights. Owner/developer Tim Ciaschi (who also did the Lehigh Valley Condos on Inlet Island) will build-to-suit for Cayuga Medical Associates, with design work by HOLT Architects.

In most towns, this would be fairly cut and dry. But this is Cayuga Heights, which probably has the most stringent board in the county. The village routinely says no to anything that could draw students in (mostly housing, but historically it also included taverns and restaurants), and people prepare multi-page tirades against two-lot subdivisions, let alone what happens when a sorority tries to move in. In the project’s favor are its distance from homes and its modest densification of Community Corners, which the village has been slowly migrating towards in the past few years. The board’s raised concerns with not enough parking, so a traffic study was included with the March materials. We’ll see how this all plays out, a medical office building might work well with Cayuga Heights’ older population.

5. The city decided to take action on the owner of the Dennis-Newton House by fining him $5,000 for building code violations. Steven Centeno, who picked up the property from the Newtons in 1982, was initially charged with over 11,000 violations, and pleaded guilty to 35 counts. According to the city, Centeno was ordered to make repairs in 2012, and got the building permits, but never commenced with repair work. If he fails to bring the property up to compliance within six months, a further fine of $42,000 will be levied. This is not unlike the case last April where the city fined lawyer Aaron Pichel $5,000 for code violations on 102 East Court Street, the “Judd House”. Work on that property is underway.

maplewood_site_plan_concept

6. Likely to be some bureaucratic progress on the Maplewood Park redevelopment next week. The town of Ithaca will be looking at declaring itself Lead Agency for environmental review of the 500-600 unit project. designs and exact plans are still in the formative phases, so no new news on those quite yet. In order to build the new urbanist, form-based project as intended, Cornell will be seeking a Planned Unit Development (PUD), which will give them flexibility in how they can lay out the site. The portion in the city of Ithaca, the two buildings towards the northwest corner (boundary line goes down Vine Street), will be built as-of-right, and it looks like a sketch plan will be presented for the city’s portion during their April Planning Board meeting.

A FEAF is included in the meeting agenda, but since the project will have to undergo a Environmental Impact Statement (much more detailed than a FEAF), it’s not very descriptive.

341_coddington_1

341_coddington_3

7. Ugh. I give credit to the town of Ithaca’s planning board for trying to accommodate a solution where the 170-year old house could at least be moved to a different site. I’m disappointed in both the town of Ithaca’s Planning Committee (members of the town board) and the Iacovellis, neither of which seem to be devoting much thought to an amenable solution. The town’s planning committee chair is hell-bent on keeping students out, and the Iacovellis are now trying to rush the demo permit since they feel their livelihood is threatened. This is an unnecessary loss due to intransigence.





Cornell Veterinary School Expansion Construction Update, 3/2016

30 03 2016

A generalized summary can be found on the Voice here. The concrete frame for the Veterinary School expansion is up to the third and final floor of what will be the new Flower-Sprecher library. As build-out continues, the existing building behind (east) of the new construction will come down and be replaced with new program space; the second floor will sit above an entry court and pedestrian walkway that leads to an indoor gallery space and central courtyard. The open space on the right (south) side of the structure will be a two-story atrium space. The addition will have a glass curtain wall, and the academic spaces that face the gallery will be faced with wood panels.

Cornell and general contractor Welliver will be looking to bring the project to completion by June 2017. Weiss/Manfredi is the project architect.

20160319_155209 20160319_155242 20160319_155305 20160319_155319 20160319_155335 20160319_155345

EntryPlaza10-2 LibraryReadingRoom10-2

3f5656954f5a3ef1021519c03b4abe9f 8f098b7e26544f579eb7411b9a1716aa

eea787361994de9625f74b19aa50d91e





Upson Hall Construction Update, 3/2016

28 03 2016

This one’s short and sweet for the moment due to time constraints. A generalized description of the latest progress can be found on the Voice here, and Cornell’s bi-weekly progress report is here. A more thorough rundown was given in January’s update here.

20160319_160249 20160319_160337 20160319_160400 20160319_160504 20160319_160527 20160319_160559 20160319_160644 20160319_160647 20160319_160654 20160319_160713 20160319_161727





Gannett Health Center Construction Update, 3/2016

27 03 2016

Most of the curtain walls are complete, only the stud walls on the northwest face are still exposed. Sunshades have been installed on the outside of each floor. The bluestone and limestone veneers will be apply to the base columns and walls at some point later this year. From the outside looking in, it looks like good progress is being made on finishing-out the interior of the new wing. A write-up can be found as a part of last week’s Voice article here.

Chiang O’Brien of Ithaca is the architect for the two-phase, $55 million project, and the general contractor is The Pike Company of Syracuse. The new wing will open late this summer, and the second phase, which is primarily renovations of the existing wings, will run from this summer to late summer 2017.
20160319_160951 20160319_161136 20160319_161158 20160319_161227 20160319_161247 20160319_161304 20160319_161310 20160319_161400 20160319_161508





Collegetown Terrace Construction Update, 3/2016

26 03 2016

So there are really two sets of photos here. The first set contains photos that I’ve taken from outside the fence. The second set of photos are from inside the fence, and come courtesy of Nick Robertson and Jocelyn Garrison at Welliver, the general contractor in charge of the project. Their photos are much more visually telling than mine, and a big thanks goes out to them both.

Currently, work is focusing on drilling piles, and forming and pouring the foundation walls. In some sections, foundation walls are being formed. Concrete pours as liquid and dries into a hard solid; forms are a solid barrier (typically wood or durable plastic) that simply forces the concrete to dry in the shape it’s supposed to. After the concrete has been poured and dries into the desired shape, the forms are removed and moved down to the next section. Work on the foundation walls appears to be progressing from west to east along the excavated and pile-driven footprint for building 7.

If you look closely at the Welliver photos, you can see the steel wire mesh that will be embedded in the concrete and provide stability for the walls. The additional steps on the forms may have to do with stepping the foundation up along the slope of the site.

20160319_154015 20160319_154025 20160319_154036 20160319_154053 20160319_154416 20160319_154420 20160319_154432

Set two:

welliver_ctown_0316_1

welliver_ctown_0316_2

welliver_ctown_0316_3

welliver_ctown_0316_4





News Tidbits 3/26/16: Big Plans and Small Town Intrigue

26 03 2016

 

201_college_1

1. Starting with with the new project of the week. In case it was missed, the write-up for the new 5-story apartment building proposed for 201 College Avenue can be found here. 201 College is being proposed by Todd Fox under his new development entity, Visum Development Group; Modern Living Rentals will continue to exist as a rental property management company. Excluding perhaps a small question with where the average grade is to determine the 70′ max height, is looks like the proposal fits the MU-1 zoning; and apart from a couple of the usual grumblings against students and/or density, there isn’t likely to be too much of an issue with the proposal. Noah Demarest of STREAM Collaborative is responsible for the design, which will make be faced with colored metal panels.

On a related note, the Journal broke this before the Voice, and it appears they may have used to the city’s Site Plan Review pre-application as a source. That’s not online for public viewing; someone would have had to give it to them. Which seems a bit dodgy, given one of the goals of the now-mandatory pre-application is to offer initial thoughts to make sure a project is palatable, and to avoid another public controversy like State Street Triangle.

312_spencer

2. Meanwhile, the other partner in Modern Living Rentals, Charlie O’Connor, is pursuing a small project of his own on the other side of the city. O’Connor has submitted subdivision plans to merge two lots at 312 and 314 Spencer Road, and subdivide two legally-buildable lots from the merged property for a total of three, one of which will contain the existing houses. The new lots would be on vacant land behind the existing houses, which are currently owned by the Lucatellis (the same folks who ran Lucatelli’s next door). O’Connor would be purchasing the home and land pending approval of the subdivision. Each of the two new lots would then be developed into a 2-family home. Noah Demarest of STREAM Collaborative is handling the application. Drawings can be found here.

biggs_1

3. The Biggs Parcel will be put up for sale. As the county notes in its press release, the county administrator has been given permission to procure a realtor and market the property on the condition that any offers from the Indian Creek Neighborhood Association and/or the town of Ithaca be entertained (though not necessarily selected). The ICNA had offered some unknown amount for the property, which they have sought to keep undeveloped, but the offer was rejected. Previously, the site was the location of a proposed 58-unit affordable housing development, but the project was discontinued when more extensive wetlands were discovered on the property.

One of the big sticking points has been whether or not the 25.5 acres would be taxable – the county wants to sell to a private owner that will pay taxes, but proposals to preserve the land often dovetailed with plans to donate it to an organization like Finger Lakes Land Trust, which would render the property tax-exempt. The land had been valued at $340,000 before the discovery of the additional wetlands, and the reassessment value will become available on May 1st.

Realtors will apply to the county to list the parcel, and a realtor is expected to be chosen by the county by May 4th.


4. A large property in Trumansburg village noted for development potential has sold after being on the market for two and a half years. Local architect Claudia Brenner picked up the 19.27 acres in two adjacent parcels for $240,000 on the 22nd, about 25% off its original $300k asking price. 18.77 acres is registered to 46 South Street, the other 0.5 acres is a small L-shaped lot between 209 and 213 Pennsylvania Avenue. The previous owners used the property as cropland, and it had been in the same family since the 1940s.

In an email, Brenner said it’s too early to comment, but that future plans are being considered. The site has the village’s R-1 zoning, which allows home lots as small as 15,000 SF (~0.35 acres), and small scale multi-family residential and commercial services.

tfc_v2_1
5. Talk about big delays. Tompkins Financial will be pushing their $26.5 million project back a whole year, according to an interview a Cornell Sun staffer conducted with JoAnn Cornish, the city’s planning director. The project was supposed to start this quarter and be completed in Q1 2017. Now it will be completed in Q1 2018.

summit_danby_1

6. A few months ago, the Summit Enterprise Center proposal in Danby was described in one of the weekly news roundups. Docs filed by STREAM Collaborative’s Noah Demarest on behalf of owner David Hall call for modifications of a Planned Development Zone for the property at 297-303 Gunderman Road. Danby’s PDZ is not unlike the city’s PUD and town of Ithaca’s PDZ, where the form and layout is regulated rather than the use. The original PDZ for the property dates from the mid-1990s.

Well, after months of vociferous debate, the project has officially gone into bureaucratic Hell, complete with political turmoil and accusations a-flyin’. My colleague Mike Smith has the full story on the Voice. Rather than rehash Mike’s detailed explanation, let’s just leave it at this – Summit probably isn’t moving forward anytime soon.