Martin Y. Tang Welcome Center Update, 8/2018

6 08 2018

I don’t typically follow renovations, but figured I’d play the role of curious alumnus and drop in to the newly renovated Martin Y. Tang Welcome Center at Noyes Lodge on the north shores of Cornell’s Beebe Lake.

The 7,646 SF Noyes Lodge originally opened in 1958 as a womens’ dining hall, and over the years was re-purposed to become the Language Resource Center, with audio carrels and other equipment for those with linguistic coursework. Cornell decided to shift facilities, moving the LRC to Stimson Hall and renovating the lodge into a campus welcome center, which opened in June. This is now where student tour guides gather their broods, vs. the old days when they would congregate at Day Hall. The lower level hosts conference space, utility rooms and offices.

The Tang family have long been trustees and major donors to the university. The $3 million gift in October 2016 was in response to a challenge grant created by mega-donor Atlantic Philanthropies (funded by Charles Feeney ’56), which offered up to $3 million in matching funds to donations towards the new welcome center – so with $6 million secured, the renovation’s financing was secured and will be able to move forward. Cornell has long considered a reception and exhibition space by the gorges, having mulled over but ultimately backing away from a plan penned by architect Richard Meier in the late 1980s. Tang, Class of 1970 and now retired, was a venture capitalist based in Hong Kong, and the regional chairman of a recruitment firm for business executives.

JMZ Architects of Glens Falls, a favorite of the SUNY System, was the design firm in charge of the renovation and re-purposing. The exhibition space is the work of Poulin and Morris Inc. of New York City.

With that all said, here’s a story.

When I first visited Cornell, it was for Cornell Days: cold, windy and kinda desolate. My mother and my uncle made the trip with me, since I had just been accepted to the university – my family did not have the money or time to visit schools unless I was already given an offer. Out first stop was RPCC on North Campus. On a Powerpoint on a TV screen were two sailors kissing; it was part of a promotion for a campus LGBTQ organization.

Having come from a blue-collar and fairly conservative town north of Syracuse, my mother was shocked into silence, and my uncle proceeded to have a crisis of moral conscience on whether his nephew should attend such a school. You have to keep in mind, it was still controversial for many of our town’s older generation that the high school A.P. Government teacher was openly gay. The kids didn’t care, and I couldn’t have cared less that day either.

Anyway, what warmed my mom up to Cornell were “the castles”. Sage Hall. The Arts Quad. Uris Library. But as for me, I didn’t feel like I fit in. My tour group was a bunch of wealthy kids, one of whom loudly grumbled his disappointment that he didn’t get into Yale and his mother didn’t like Dartmouth. Why would a 17 year-old want the constant reminder that he’s not cut from that cloth or a part of that world?

So I wrote out a deposit check with my money from waiting tables to SUNY Geneseo. And Geneseo was the check that had been put out in the mail. Until my mom took the envelope out of the mailbox and tore it up, putting one out to Cornell in its place. We had some fights after that. She wanted me to give “that big money Ivy League school” a chance, I was not as keen.

When I first arrived at Cornell, I was pretty sure I’d transfer to Geneseo after the first semester. I didn’t feel comfortable there. But then I started to meet other people who didn’t feel comfortable there or fit that upper-crust Cornell image, and we became friends. Suddenly, the urge to leave was much weaker. Mom had resigned herself to the idea of me transferring by Thanksgiving, but when she found out I hadn’t completed the paperwork, she was pretty happy.

As for me, well, I was required to attend a fancy dinner a few weeks earlier where an older gentleman who had funded one of my scholarships urged me to visit his old Cornell fraternity, and I went to their Thanksgiving dinner as a polite gesture. I found it to be a down-to-earth place filled with people with backgrounds like mine, that’s how I ended up coming back for rush week and in Greek life – something I managed to hide from my mom until graduation day. I steadily came to know more people, get involved in different activities on campus, and things went from there. And a growing fascination with “the castles” and their history led to Ithacating. I guess in some sense it all worked out eventually.

 





South Meadow Square Construction Update, 8/2018

6 08 2018

It looks like the new south retail endcap is using a standard EIFS (Exterior Insulation Finishing System) for the exteriors. EIFS, also known as synthetic stucco or by the brand name Dryvit, is a pretty common choice for commercial builds. Readers might remember when it was used with the Holiday Inn Express built a couple of years ago on Elmira Road. Over the plywood there’s a dark grey moisture barrier. This is being overlaid with an adhesive and insulation board, which will then get a reinforcing mesh, base/scratch coat, and a finish coat. Drainage cavities are then built over the barrier to allow water that has penetrated the surface to exit the wall without wrecking it (a big problem with early EIFS systems).  The north endcap looks like it already has insulation boards in place, as well as a base coat for the primary moisture barrier, and a white coat that might be a primer for the finish coat. New curbing, lighting and a fire hydrant have been installed.

Although the south endcap is 14,744 SF, the listing on commercial real estate website Loopnet says there are two spaces, one about 15,000 SF, and a second 3,400 SF. The property doesn’t show a 3,500 SF space, and the north endcap is 7,315 SF, so it’s not clear what that refers to. It could be the 3,200 SF space that is planned for a the pad parcel next to Firehouse Subs, but that hasn’t started yet. If that is the case, however, that implies Benderson Development may have a tenant under contract for the north endcap that they just haven’t yet announced.

 

 





East Pointe Apartments Construction Update, 8/2018

6 08 2018

No one can say DGA Builders is wasting time. A visit on Friday showed three sets of CMU foundation walls have been assembled and mortared, each for a ten-unit townhouse string. A few crewmen kept an eye on a material placement truck, also known as a stone slinger, as it launched rocks into the footprint encased by the foundation walls. This may be a crushed stone base (hardfill) for a concrete slab pour, given the stacks of rebar with surface rust sitting nearby. A shallow foundation would work fine here because two-story buildings aren’t especially heavy as structures go, and it would be less expensive and time consuming than a deep foundation. Elsewhere around the site one sees PVC sanitation pipes (sea green), water pipes (blue), and pieces for utility junctions.

Meanwhile just a stone’s sling away on Nor Way, Forest City realty continues work on the six-unit string (hexplex?) of townhouses. Two are fully framed and roofed, two have had their first floor framed though not fully sheathed, and the other two are only partially framed on the first floor. As with all the townhouse strings, these will incorporated some unique design features while keeping the general unit layout the same. I know they’re not happy about the East Pointe townhomes, but it could be a good synergy – the price points ($1,400-$2,000/month fr East Pointe, $350k for the Heights of Lansing townhouses) are such that renters who may wish to stay in that neighborhood may look at the Heights townhomes as an option.

A website is now up and running for East Pointe. It’s mostly stock images and bland corporate-speak, but they do have floor plans and some new renders. Here’s the advertising pitch:

“This apartment community is located on 20 acres in Lansing, NY, which is part of the Ithaca, NY, market. This is new construction of 140 state-of-the-art apartments. There will be 36 one-bedroom units, 90 two-bedroom units, and 14 three-bedroom units. The project will include fourteen apartment buildings with 10 units in each building that will be walk-up garden style with private entrances and a community building. All units will have high end finishes and amenities, including stainless finish appliances, microwave, dishwasher, washer and dryer, ice maker, granite counter tops, wood cabinets, vinyl plank flooring and wall-to-wall carpeting, tile showers, high end plumbing fixtures and lighting fixtures. All apartments will include a patio or deck. The community building will include the leasing and maintenance office, Great Room and warming kitchen for gatherings, and a fitness center. The project also includes an outdoor pool with changing rooms and shower.”

I have no idea what a warming kitchen is, but my very Sicilian mother is pretty good at turning kitchens into warming spaces around the holidays. A photo of the community center is included below.

UPDATE: I’m just going to add this here since the timing was ever so slightly off- on Monday the 6th, the construction loan was filed with the county. M&T Bank is lending Park Grove (represented by an LLC) $22.6 million for construction of the East Pointe project.





802 Dryden Road Construction Update, 8/2018

5 08 2018

Not a high-profile project here, but sizable. 802 Dryden Road, also called “Ivy Ridge”, is the latest project to come out of Modern Living Rentals (MLR). MLR is led by local developer Charlie O’Connor, and as I noted previously, “[h]e is arguably one of the most reticent developers in Ithaca, preferring unobtrusive projects that he hopes will create as little debate as possible. It’s kinda funny in a way, because although he’s a business partner with Todd Fox (Visum’s property management is handled by MLR), the two of them are near-opposites in that regard.”

True to form, while 802 Dryden is a sizable 50,000 SF, $7.5 million project, it was the subject of relatively little public debate during its approvals process. It’s located next to arboretum, replaces four rental houses and a motorcycle repair shop, and the number of residences within 500 feet could be counted on two hands. The project consists of 42 two-story townhouse rental units on three acres, six strings of seven units in a right trapezoid layout. Each string contains four two-bedroom units, two three-bedroom units and a four-bedroom unit (108 beds total). It’s a two-minute drive from the east end of Cornell’s campus (B Lot), and an easy sell to students and staff looking to live in a quieter location near campus.

Zoning on the site is fairly dense, all things considered. Although rather far from Varna’s core, the project does fall under Varna Hamlet Mixed Use District zoning, which allows ten units per acre. A redevelopment bonus of dilapidated properties gave another two units per acre, and a green bonus of two units an acre was also permitted. The green features part required some debate and confirmation. The project seeks LEED Certification and will apply LEED standards for neighborhood design.

The project was first proposed in June 2017. At the time, its design was a virtual clone of another MLR project, 902 Dryden Road, albeit with different colors. The designs were revised at least three times. The design work was passed from STREAM Collaborative to John Snyder Architects, who did substantial alterations, and then again, and then STREAM once again did some work on it. The final set of renders are here, with the site plan docs here. Originally there were three townhouse string designs, but it looks like it was reduced to two in the final round. The six buildings are generally but not exactly the same – the gables are mirrored, some additional trim pieces are used on the gables for the Dryden Road pair, and they alternate between a dark blue vertical fiber cement panel (probably HardieBoard), and a dark green panel. Original approvals may have been issued in November 2017, but the last revisions were approved this past May.

Exterior features include 70 parking spaces, bike racks, trash/recycling enclosure, stormwater ponds, bioretention areas, signage, a childrens’ playground, pavilion and a dog park split up for large and small breeds. Planned interior features include granite counter tops, stainless steel appliances, a washer and dryer in each unit, contemporary lighting, and marble tile. Expect these to be in the same price range as the other recent MLR units, which have been in the $650-$750/bedroom range. The units are expected to be ready for occupancy by June 2019.

There’s a little bit of pre-building infrastructure work that had to take place before construction, because this is a sort of no man’s land between the settled parts of the town of Ithaca and the town of Dryden where no municipal water service was available. The public water main had to be extended to service the project, and the main will be deeded over to the town. At this time, the existing buildings have been removed, but the land has yet to be cleared; we’re really just at the initial phases of the project.

Along with MLR, STREAM and John Snyder Architects, GMB Consulting Services did the LEED score analysis, T.G. Miller P.C. handled land surveying and Marathon Engineering tackled the civil engineering work – Marathon’s Adam Fishel shepherded the project through the town boards. I don’t have a contractor listed, but will share it when I do.

Pre-construction (Google Maps, Nov. 2015)

Renders:

August 3rd:





105 Dearborn Place Construction Update, 8/2018

4 08 2018

It’s no secret that people are living longer. In 2014, residents of Tompkins County could expect to live to 81.21 years, an increase of about 7% from 75.92 years in 1980. It’s also no secret that the population in general is getting older – the Cornell Population and Demographics unit estimates that Tompkins County’s population over the age of 65 has gone from 9,301 in 2000, to 14,454 in 2017, an increase of 55.4%.

From a business perspective, this creates opportunities for various forms of senior housing, housing designed to allow matured individuals to age in place. However, there are cases where specialized, skilled care may become a necessity. This can include specialty facilities like Brookdale (memory care), nursing homes like Beechtree and Cayuga Ridge, and premium personalized care options like Kendal and Bridges Cornell Heights.

Founded in 2001, Bridges Cornell Heights occupies three expansive homes in the historic Cornell Heights neighborhood north of Cornell campus – one was built new in 2005, and the other two are renovations, the last being just a few years ago on Kelvin Place. Each house has sixteen residents or less, and to be frank they could be described as a luxury retirement homes – a high degree of personalized care and a commensurate price tag.

With full occupancy and a waiting list in hand, Bridges has decided to move forward with plans for a fourth house in Cornell Heights, and the second all-new home. The property will be located on the southeast corner of Wyckoff Avenue and Dearborn Place, a small vacant field recently sub-divided from the former Palentological Research Institute next door (which is separately being renovated into a two-family home by Classen Ambrose’s husband). According to the 1928 Cornell Map, the property was once home to the neighborhood school, but the school and its building ceased to be many years ago.

Given that Cornell Heights’ century-old architecture is defined by high-end, visually unique homes, the new property is seeking the same qualifications. Rochester-based Bero Architecture, which specializes in historic design, has been retained and early drawings show an imposing 10,930 SF two-story cultured stone and cedar-shingle Craftsman-style home with 12 bedrooms (four of the bedrooms will be designed for double occupancy for couples). The landscaping will be similarly fitting and designed by Cornell landscape architecture professor Paula Horrigan. Exterior features include a porte cochere, porous driveway and courtyard parking for nine vehicles (all residents, staff are given pre-paid parking off-site at a nearby fraternity and walk over), as well as three patios, walkways and lush plantings (500+ perennials, 127-140 shrubs, and 35 trees).

Since Cornell Heights is a historic district, the Ithaca Landmarks Preservation Commission was required to sign off on any new construction visible from the outside. The design of the house changed very little from start to finish in the approvals process – Bero is good at what they do, and the ILPC was amenable to the design, though some requested tweaks were made to landscaping and parking along the way. They also requested a dated plaque to ensure no one mistakes the new build for an older structure. The project was proposed in May 2017, and approved in October, generally smooth sailing. I can remember when I did the Bridges article for the Voice, Classen Ambrose was very worried about the neighbors reacting negatively. To that credit, some of the full-time neighbors opposed the project, and it’s not often one sees a “senior living operators are converting and destroying the neighborhood” argument. But overall, the opposition was minor. The house is contextual, and the environmental impacts are fairly modest once the mitigation measures (parking off-site, new trees) are considered.

Classen Ambrose has said that the house will programmatically be a little different from the existing trio of homes in that it will be independent living instead of the enhanced assisted living employed at the other homes. That means a lower level of care – residents may receive assistance in housekeeping and cooking, but they are otherwise capable of managing their day-to-day activities. The new facility will also add at least four more staff to Bridges’ payroll, which is in the low/mid 40s and has been seeking living wage certification.

Side note, although it’s been replaced with newer videos, Mack Travis, the founder of Ithaca Rentals and renovations (now Travis Hyde Properties under his son and son-in-law) once did a testimonial in a short video extolling Bridges’ service for his family members. Now years later, Bridges will be providing services to residents of THP’s DeWitt House senior living project.

This is a high-end development where no expense is being spared. Tompkins Trust Company extended a $4.2 million loan, filed with the county on July 20th. Construction is expected to take about a year, with local firm Schickel Construction in charge of the buildout. Alongside with Bero and Horrigan, T. G. Miller P.C. did the civil engineering work for the project.

The project does include a finished basement, and it appears the site has been cleared, excavated, and concrete masonry (cinder block) walls are being assembled at present. Construction will be a traditional wood-frame approach. Note the ZIP panels on the neighbor at 109 Dearborn, as it goes from a dull 1930s office/storage space and becomes a two-family home, also designed by Bero Architects.

Pre-construction (Sep 2017 Google Street View)

August 2018

   

Drawings:

 





Tompkins Center for History and Culture Construction Update, 7/2018

2 08 2018

I don’t usually spend much time covering renovations, but here’s a major project that deserves a good summary.

Let’s start this off with a little self-promotion by linking to the summary and project team interviews I did for the Voice pack in February. The History Center (THC) is a non-profit that celebrates Tompkins County’s past, with an eye towards improving its future. It’s a source for genealogists, historians, teachers, archivists, and many of the old-timey photos that the Voice, Times and other news outlets share with intrigued readers. The History Center has been renting space at 401 East State Street (Gateway Center) on a 25-year lease, due to expire this year.

When weighing their options, there were a couple of reasons why a move was looking better than a renewal of the lease. For one, it would give them a chance to find a more visible place to call home – a higher-profile location would give them more opportunity to be seen, and hopefully be heard. For two, the rent on their existing space was set to go up quite a bit, nearly doubling to $90,000/year.

It happened that Tompkins Trust was in the midst of building its new headquarters, so there was potentially some space opening up in the downtown area. A prime site availed itself in a pair of buildings along the pedestrian-only block of 100 North Tioga Street, better known as “Bank Alley” since nearly all the buildings along it were occupied by banks. 106 North Tioga Street, the shorter brick building, was the county clerk’s office when it was built back in 1863. Its neighbor at 112 is relatively young, built for the predecessors of Tompkins Financial in 1895. 106 was acquired by the bank in 1949, and various renovations from the 1950s through 1980s brought the buildings together as a bank complex with a modern connector space between them. After initial discussions in 2015, Tompkins Financial said it was open to a sale of the 18,826 square-foot space, and the county, who helps covers The History Center’s expenses, paid for a $15,000 feasibility study.

The first public discussion of the plan, then dubbed “The Tompkins County Heritage Education Center”, was in October 2016. The feasibility study checked out, so in January 2017, The History Center, in conjunction with other non-profits, requested $35,500 from the County Tourism Program for early stage development costs – a capital campaign, branding and marketing materials, and architectural drawings.

The project could be described as part “heritage tourism”, part visitor’s bureau and information center, and part non-profit office space. The Tompkins Center for History and Culture will house the CVB’s Downtown Visitors Center (part of the Tompkins County Chamber of Commerce) and The History Center on the first floor. The Wharton Studio Museum, the Dorothy Cotton Institute, and the Community Arts Partnership will also be major components of the project. Historic Ithaca and the Discovery Trail will also be affiliated with the Center, and a newly rebuilt “Tommy” bi-plane will be on permanent loan in the exhibit area. Most project partners will have office space on the second and third floors. The History Center is promoting the TCHC as a co-working space that would allow non-profit partner organizations to work together more efficiently, enabling them to share the costs of administrative functions, and tackle and divvy up larger grants and projects.

The Tompkins Center for History and Culture was a bit of an effort to name. It was initially turned down by the county legislature last summer because they wanted The History Center to do community outreach and make sure people were okay with the moniker. And two legislators still opposed the new name, one for not having the exact phrase of “Tompkins County” in it. To be honest, it’s a mouthful even now.

The project’s costs are estimated at about $3.75 million, but the enumerated amount is $3,345,100. Originally, the cost was $2.9 million. The county paid $2 million for the property, about $400,000 below assessment. The other $900,000 was for hard and soft costs related to the renovation itself. As for recuperating some those costs, $1.365 million is being paid for by a pair of NYS grants, a $1.06 million arts and culture grant, and a $305,000 economic development grant, which were awarded as part of the state’s economic development competition in December 2017. An earlier state grant gave $28,500 towards planning costs of the project. Another portion ($100,000) will be covered through some of the hotel room tax. Another $450,000 or so will come out of the $1.75 million being raised in the a capital campaign supported by individual and institutional private donors.

The county initially expected to be on the hook for $350,000. But in May, The TCHC requested and received an extra $445,100 in appropriations, which the county would have to cover in the short-term. The extra cost, raising the renovation’s price tag to $1,345,100, was attributed to bids coming in over projections and additional design costs. The legislature is hoping the expense is justified through the boost in tourism (30,000 visitors, a mix of local and non-local, will walk through its doors annually after it opens) as well as the modest rent it will charge the non-profits for the office space.

STREAM Collaborative is doing the design work, Tetra Tech did the structural engineering, New York’s Tessellate Studio is designing the new exhibit area and Iron Design developed the logo, website and marketing material. On the construction side, Marchuska Brothers Construction, LLC, of Endicott, has the the General Work Contract ($561,000); Johnson Controls, Inc., of Rochester, won the Mechanical Contract ($502,638); and Richardson Brothers Electrical Contractors, Inc., of Ithaca, earned the Electrical Contract ($135,550). Marchuska is a fairly recent addition to the Ithaca area, and just finished a gut renovation of a manufacturing facility into medical offices in Lansing village.

With Tompkins Financial now in its new HQ and out of Bank Alley, construction could proceed and the formal “groundbreaking” for renovation was last month, Tompkins Center for History and Culture is expected to open in early 2019. The website for TCHC can be found here.

At this point, asbestos removal by LCP Group has been finished, and some of the windows have been removed in 112 North Tioga while non-load bearing interior walls are removed and the interior space is reconfigured for its new tenants. Exterior work will generally be limited to murals, lighting and signage.

Render:

July 7th:

July 27th:





238 Linden Avenue Construction Update, 7/2018

22 07 2018

Might be jumping the gun a bit on this, but the fence encroachment into the street, pile driving equipment and steel/caisson tube liners on site are leading me to believe this one is in site prep.

Consider this project thr second half of a 2-for-1 package deal from developer John Novarr. Novarr and his business partner, Phil Proujansky, own a fairly large and widespread set of local properties, with the massive Collegetown Terrace project being the best known ($190 million investment, 1,250+ beds, 16 acres). Most of the rentals operate under Novarr-Mackesey Property Management. Their latest development was on behalf of Cornell, the 76,000 SF Breazzano Family Center for Business Education, which was dedicated last fall, an imposing six-story building at 209-215 College Avenue in Collegetown.

When Novarr first bought the properties that would be demolished to make way for the Breazzano, he bought a ramshackle six-bedroom house at 238 Linden Avenue for $1.35 million – this was in December 2010, before he had assembled his final, full group of properties (and realized Pat Kraft was flatly not interested in selling to him, later doing his own redevelopment at 205-07 Dryden), so the purchase of 238 Linden could be seen as a secondary purchase to give room for flexibility, and a place for construction staging in the notoriously tight spaces of inner Collegetown. In its last few years, Novarr did not rent out the house, which was in poor shape and torn down in June 2015. A redevelopment was always intended at some point, through it was only as the Breazzano plans were drafted did Novarr and Proujansky settle on a concept.

Inner Collegetown is a captive rental market – regardless of economic recessions, there will always be students willing to pay a premium to live near Cornell’s campus. The Breazzano project presented a unique opportunity – the project will serve up to 420 Executive Education students, who tend to be older, deep-pocketed, and infrequent visitors to campus, coming up for a few weeks of the year.

The new 238 Linden is designed to tap those Executive Education students who might come up more frequently, or prefer to have a second place to call home during their matriculation with the Johnson School. The project is a 13,715 square-foot building with 24 efficiency units (studios). It will be 4 stories with a habitable basement, just under 50% lot coverage, and is fully compatible with the site’s CR-4 zoning.  Each fully above-ground floor will host 5 efficiency units, with four in the partially-exposed basement. While intended for Johnson Executive Education students, it does not appear it would have provisions limiting the units to E-MBAs.

The design intent was to create a townhouse-like appearance, in form if not in function. The exterior includes fiber cement panels to complement the colors of the Breazzano, aluminum windows and a glass curtain wall with energy-efficient glazing. A number of green features are included in the project, such as LED lighting, low-water plumbing fixtures, and a sophisticated VRF high-efficency HVAC system, which uses air-source heat pumps.

Plantings, walkways, steps and retaining walls are planned, with decorative entry stair bridges and little landscaped courtyards to provide a pleasing aesthetic for the basement units. As with all inner Collegetown projects, no parking is required so long as a transportation demand management plan (TDMP) is filed and approved by city planning staff. During Site Plan Review, the project cost was estimated to be about $2 million.

The project had a pretty quick trip through the planning board – it was proposed in March, there were very few suggested aesthetic changes, and since everything conforms with the size and intent of zoning, the board was pretty comfortable with the proposal. However, while it was approved in July 2017, the project was unable to move forward because of a change in state fire codes that essentially made construction along Linden Avenue illegal for any building taller than 30 feet (and 238 Linden is 45 feet tall), because Linden is too narrow. The way around this was to petition the city Board of Public Works to treat the parking space on the street in front as a loading zone, creating a “wider” street since a fire crew would no longer have to worry about parked cars along the street frontage. This made it easier for the project to obtain a fire code variance from the state. Normally, BPW would reject this, but 238 Linden and Visum Development’s 210 Linden had already been approved when the code was changed, so they got a special, rare accommodation. Suffice it to say, any other Linden project would be difficult if not impossible under the revised state fire code.

As with all of his other projects, the architect is ikon.5 of Princeton, with local firm Trowbridge Wolf Michaels Landscape Architecture serving as the project team representatives, and T.G. Miller P.C. providing the civil engineering work. The modern design may not be to everyone’s taste, but Novarr likes the architecture firm’s work so much, he asked them to design an addition to his property in Cayuga Heights. Beauty is in the eye of the wallet-holder. No word on who the general contractor will be, but Novarr has often turned to Welliver for his construction work. The original buildout period was estimated at ten months, so a plausible occupancy for 238 Linden would be complete by Summer 2019.





107 South Albany Street Construction Update, 7/2018

18 07 2018

107 South Albany is a curious mix of sheathing. The front and part of the sides consists of standard Huber ZIP System plywood panels, while the sides use GP DensElement fiberglass mat sheets with maroon liquid flashing. Atop that, wood furring is being attached, and trimboards and fiber cement lap siding (or panels, for the wall next to the central staircase) are added to finish out the exterior. The front entry will have a brick veneer, but only on the first floor, so that doesn’t explain the difference in sheathing. The windows are fitted, but the front entry is not.

These apartments should be open for occupancy in time for the new academic semester. Advertisements say August 1st, but that might be a stretch. Still, these are coming in at a more modest cost than other new market additions ($1,100/month), and adds some density to the State Street Corridor.

Background information on the project and its specifications can be found here. Renting Ithaca (Nick Stavropoulos) is the developer, and Flatfield Designs (Daniel Hirtler) is the architect.





Harold’s Square Construction Update, 7/2018

17 07 2018

Harold’s Square is starting to take shape. The white sheets on top of the basement level are Sika Corporation UltraCure NCF curing blankets. When the steel was laid, corrugated decking was laid on top to create the base of the floor. A rebar wire mesh was then laid and tied into place, and the concrete was poured into the floor cavity, with wood forms to keep the pour in place. The rebar strengthens the concrete and ensures structural integrity. In this mid-June Facebook photo from the Harold’s Square page, you can see the decking going over the structural steel. A week and a half later, you can see the rebar grid over the completed decking. The concrete was poured in early July, the slab was covered in the cellulose fiber blankets to promote an even and structurally sound cure, and after seven days they tested the concrete and the results came back all-clear, meaning they can start to put weight on the concrete and work their way up.

Meanwhile, structural steel erection will be taking a short break as masonry work begins on the Commons-facing side of the project, followed by masonry work on the Sage Building. The steelwork will resume in late July. Subcontractor Paolangeli will be doing backfilling (earthwork to cover up the foundation) on the Green Street (south) side of the project now that the shell of the basement has been built.

The WordPress for the project can be found here, and the Ithacating project description here.





118 College Avenue Construction Update, 7/2018

16 07 2018

The last of Visum’s trio of Collegetown projects underway is the 5-unit, 28-bedroom building at 118 College Avenue. Officially, one other Visum project has city approvals and is permitted to start construction, a close fraternal twin to 118 College just a few houses up at 126 College Avenue. However, the existing house is rented out for the academic year, so any build-out there (and Visum seems to have deep enough pockets to eventually do it, all things considered) will not begin until June 2019 at the earliest.

As with 210 Linden, Romig General Contractors is in charge of the buildout, and Taitem Engineering is doing the structural engineering – as with Visum’s other projects designed by STREAM Collaborative, the building is built to be net-zero energy capable. Using electric heating and appliances, energy efficient fixtures, low-E windows, double-stud exterior walls and high grade insulation creates a very high degree of energy efficiency that they hope to tie into an off-site solar array, offsetting the carbon footprint of the building and its use.

118 College still has another floor to go before it’s topped out, and the mechanicals will be hidden inside the historically-inspired “Italianate cupola” penthouse. Water and sewer service was installed this past week. I’m uncertain this one will be ready in time for returning Cornell students late next month, though it’s not impossible given that it’s a relatively small wood-frame structure. So far, with the rough window openings I’m seeing one substantial difference from the renders – the windows on the wings of the front facade are smaller than originally planned.