Cornell Veterinary School Expansion Construction Update, 11/2016

23 11 2016

Definitely seeing a lot of progress on the Vet School Expansion. The new glass curtain wall on the Vet Research Tower is nearly complete, and the final finishes are due to wrap up by the end of the month. The new library/dean’s wing by the front entrance is undergoing interior framing and utilities installation. The new atrium and lecture hall are now visible from the street, now that some of the structural steel has been erected. Floor slabs and roof decking are also being laid.

The new atrium and lecture hall are expected to be closed up by January, and the whole $74 million project is aiming for an August 2017 opening. The Community Practice Service Building, a separate $7 million project on the Vet School campus, is expected to start construction in early next year with a completion in late fall 2017.

20161119_111157 20161119_111208 20161119_111225 20161119_111243 20161119_111252 20161119_111334 20161119_111358 20161119_111436 20161119_111503 20161119_111514 20161119_111632

cad048742a281097e5667382eced42333f5656954f5a3ef1021519c03b4abe9f





Upson Hall Construction Update, 11/2016

22 11 2016

Because of the multi-phased, tiered buildout of Upson Hall’s renovation, it’s easy to miss the changes. For example, in the first photo, there really haven’t been any exterior changes to the fourth or fifth floor, but on the third floor, there’s been significant progress – the old stone has been removed, the new stud walls have been erected, gypsum-based glass mat sheathing has been laid and waterproofed, and new windows have been fitted. You can see the latest batch of exterior wall progress on the third floor of the west face, third photo below. The first and second floors have had their old exteriors stripped as well, but at the moment the frame is exposed. The interior has been gutted and new utilities rough-ins are being routed.

On the side facing the Engineering Quad, the progress has been similar – the third floor has seen the most work recently as the renovations work their way from top to bottom. Turning to the east face, sheathing extends to the bottom floor, and it looks like an aluminum roof cap has been installed on the new bump-out. The general contractor for Upson is The Pike Company, which is touting the project with computer-generated images of construction staging on its front webpage.
20161119_115304 20161119_115324 20161119_115359 20161119_115406 20161119_115453 20161119_115518 20161119_115541 20161119_115630 20161119_115651 20161119_115713 20161119_115733 upson-header-1920x700





Cornell Law School Renovation Update, 11/2016

22 11 2016

Introducing a new project to work into the rotation – work has begun on Cornell Law’s renovations of Hughes Hall. Coincidentally, I broke this story for the Voice almost a year ago to this date.

In Summer 2012, the Cornell Law program embarked on a three-phase renovation and expansion program to their facilities. The first phase was a 17,500 SF, mostly-subterranean addition of an auditorium space, two large-group classrooms. foyer space, and a renovated courtyard. Designed by Boston-based Ann Beha Architects and constructed by Welliver, that $23.8 million phase, certified LEED Platinum, was completed in late summer 2014. Plans for phase II came forth in November 2015, and were approved by the city this past March. Phase III, which calls for renovations to the law school library, has yet to be presented.

Hughes Hall was built by the university in 1963 and named for former professor Charles Evans Hughes. Hughes only spent two years at Cornell, partially because of the need to make better money from private practice, and partially because of familial pressures to leave behind a “one-horse town like Ithaca”. He would later serve as governor and a Chief Justice of the U.S. Supreme Court. Hughes was a source of inspiration for mid-20th century megadonor Myron Taylor, and so the new law school dorms were named in his honor. The building served as the dorm and dining facility for the law school until 2005, when the first and second floors were renovated for administrative and faculty office space.

The Hughes Hall remodeling will have three basic components: enclosing the open-air loggia that currently connects Hughes Hall with Myron Taylor Hall, adding a staircase to the west side of Hughes Hall, and repaving the dining terrace by the Fork and Gavel Café. Administrative offices and event spaces will be on the lower floors, and faculty offices on the upper floors. The renovations will be seeking LEED Silver certification – this is two levels lower than the LEED Platinum of phase one, but it’s a lot easier and cheaper to achieve energy savings when a project is underground.

As a result of the remodeling, the last law school dorm units, totaling 47 student beds, were removed. At the time this was announced, Maplewood had yet to come forth, and I did a rare editorial for the Voice calling Cornell out on a lack of planning and poor stewardship. Minor site plan and landscaping improvements are planned.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver will serve as the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete. The project was initially slated to begin in June 2016 and wrap up in July 2017, but it appears the construction launch ended up being a few months later than anticipated.

In the photos below, some of the exterior stone veneer has been stripped from the wall, and on the lower levels the windows and some of the concrete masonry wall has been removed. This will be where the new glass-enclosed staircase will go. Work on closing up the loggia has yet to start.

20161119_114538 20161119_114624 20161119_114638 20161119_114820 20161119_114831 20161119_114847 20161119_114920 20161119_114925

hughes_cornell_4 hughes_cornell_3 hughes_cornell_2

 





Cornell Ag Quad Rehabilitation Construction Update, 11/2016

21 11 2016

It’s that time of the month – construction updates will be forthcoming over the next several days.

On Cornell’s campus, work on the Ag Quad renovation continues. The eastern half of the quad, closer to Mann Library, is mostly complete – phase one of two. There weren’t as many underground utilities to lay in the eastern half, so it was able to progress more quickly, limiting the risk of running into winter. The new pavers are being set into place, and hay has been thrown down to keep the fresh soil and seed from blowing away, and to provide a warmer, moister environment for it to germinate in when the time comes. Those big holes behind the new seating area are for new trees that have yet to be planted – best practices state that trees are most likely to survive if planted in early spring.

Meanwhile, on the western half of the property, most of the new utilities (electrical, steam, sewer and water) have been laid, and new lamppost mounts are in place. According to a worker on-site, that metal structure in the third-to-last photo is a protective barrier to keep soil from falling back in onto workers as they assemble and lay the new utility lines. The precast concrete blocks in the second-to-last photo are protective covers for the new steam pipes. The pipes are laid, the protective barriers are put into place over them, and the channel is backfilled with soil to bring it to ground level. Cosmetic surface work on the western half of the Ag Quad will have to wait until next spring, when the threat of winter storms has passed.

The $9.6 million project began during the summer, and is scheduled for a completion before the 2017-18 academic year. MKW & Associates LLC of New Jersey is the lead landscape architect, Over & Under Piping Contractors Inc. of Auburn is the GC, and Albany-based CHA Consulting Inc. is providing civil engineering expertise. Background information on the project can be found here.

20161119_112653 20161119_112722 20161119_112732 20161119_112807 20161119_112835 20161119_112911 20161119_112936 20161119_113029 20161119_113341





209-215 Dryden Road Construction Update, 10/2016

14 10 2016

With the rise of the structural steel, 209-215 Dryden Road (aka the Breazzano Family Center for Business Education) is starting to make a significant dent in the Collegetown skyline.

The floorplates are up to the fourth level, and the vertical steel columns indicate just how tall the building will be when the steel skeleton is built out. The concrete floor has been poured on the ground level, and corrugated steel decking has been laid on the upper floors – note that only the first and second floors have reached their full dimensions, the upper floors are waiting for the delivery of additional steel columns and cross beams for the crane to hoist into place. The sheets of wire grid seen outside the fence are for future concrete floor pours, providing strength and rigidity for the concrete, just as rebar does for foundations.

The large gap in the front of the building is the multi-story atrium space – the lower three floors are academic class space, while the upper three floors are academic office functions for the Cornell Executive MBA program. The smaller gap towards the north (right) side is for a stairwell.

Nice touch with the subtle commemoration of 9-11 emergency responders. It’s not uncommon to see these tributes when steel work is underway during the fall.

20161007_154941 20161007_155001 20161007_155014 20161007_155017 20161007_155050 20161007_155054 20161007_155100 20161007_155116 20161007_155139 20161007_155206 20161007_155234 20161007_155255

209-215_2 209-215_basement





Upson Hall Construction Update, 9/2016

2 10 2016

Work on the upper levels is progressing. Slowly but steadily, mineral wool is being laid and aluminum clips are being installed for the terra cotta panels. It looks like the most progress has been made on the east facade. The windows in the bump-outs have received aluminum trim. Although the project update page hasn’t had a fresh post since early August, the upper floors (3-5) should be occupied by this point and many of the utilities systems have been overhauled. Most of the interior work is now focused on the lower levels (Basement, and Floors 1 and 2). The Pike Company of Rochester will continue the interior renovations during the academic year, but as long as all goes to plan, the building should be wrapped up by August (landscaping is another matter).

20160918_135255 20160918_135339 20160918_135401 20160918_135507 20160918_135535 20160918_135628 20160918_135742 20160918_135846





Cornell Veterinary School Expansion Construction Update, 9/2016

1 10 2016

Check out that glass curtain wall going up on the Vet Research Tower. The lighter hues vs. the original dark glass gives the building a airier, less ominous presence. We’re starting to see some HVAC rough-ins going in the new library/administration building. The deconstruction of existing wings appears to be wrapped up and it looks like works has started on the frame of the new academic building to go between Schurman Hall and the VRT. Although not visible from these photos (because it is a pain to maneuver around the vet school), Cornell and its contractor Welliver have been working on the foundation and underground utilities, and construction of a new second-floor cafeteria space.

A separate project, the Community Practice Service Building, is in the design phase. CPS is what you think it is – fourth-year students, as part of their final year of education, provide low-cost veterinary services to the greater Ithaca area. It will replace the Poultry Virus Lab, which will come down in December. The CPS Building will take just under a year to build.

For those with some serious dough lying around, the new academic building’s naming rights are available for $20 million, and the administration building’s naming rights are being offered for $7 million. For the rest of the 1%, a lecture hall goes for about $1.5 million, and regular classrooms for $250,000. The most inexpensive options appear to be tutorial rooms for $75,000.

20160918_130307 20160918_130105 20160918_130035 20160918_130024 20160918_130005 20160918_125934 20160918_125838 20160918_125829 20160918_125806 20160918_125726

20160522_131445 20160522_131417

3f5656954f5a3ef1021519c03b4abe9f

cad048742a281097e5667382eced4233 eea787361994de9625f74b19aa50d91e





Cornell Ag Quad Rehabilitation Construction Update, 9/2016

28 09 2016

Kinda outside the normal coverage, but an important project nevertheless. Cornell is currently undertaking a major rehabilitation of the CALS Quadrangle, better known as the “Ag Quad”. The $9.6 million “Ag Quad Utility Infrastructure Upgrades and Landscape Revitalization Project” (originally $7.8 million) began during the summer, and is scheduled for a completion before the 2017-18 academic year. Most of the construction is planned during the summer months of 2016 and 2017, when the ground is easier to work with and impact on campus activities is at a minimum.

According to university landscape architect David Cutter, the work has planned for at least a decade, but was a lower priority vs. other projects such as the Mann Library and Warren Hall renovations, which used the quad as a staging area. With the bulk of building renovations complete (a new academic building on the south side of the quad, but it’s just a hazy concept at this time), and with infrastructure approaching 100 years old, the university decided now was as good a time as any to get the rehab underway. Plans were approved by the Ithaca city Planning Board in February.

The first phase is what’s underway now. That involves the replacement of underground utilities infrastructure. In that catch-all are water pipes, sewer pipes, steam pipes, and a new ductbank (electrical conduit grouping) for telecommunications from the CIT Building. Several walkways have been excavated to make way for new or improved underground utilities corridors. The second phase is refreshed landscaping. Along with new permeable pavement walkways and entrance plazas in front of Roberts Hall and Mann Library come 54 new tree plantings, a rain garden, and upgraded lighting (from two poles to twenty). The plazas will come with movable tables and chairs, traditional benches and concrete slab benches (rough-hewn sides, cut/thermally-finished tops). For additional safety, the rehabbed quad will host collapsible bollards, an increased number of blue light security phones, and a new emergency vehicle path. Primary walkways will be 12′ wide, and secondary walkways 8′ wide. Some of the new garden spaces and landscaping will be done by students in various CALS programs.

The project has been the subject of relatively little controversy compared to most. Some consternation was expressed that four Cornellian cherry trees next to the west side of the Plant Science Building would be cut down for “infrastructure changes”, but other than that, there wasn’t much else in the way of concern or opposition. Eleven other trees are also or are being removed, so the net gain is 39.

The $9.6 million is coming mostly out of the university’s budget (CALS and Utilities), with some private funds. MKW & Associates LLC of New Jersey is the lead landscape architect, Over & Under Piping Contractors Inc. of Auburn is the GC, and Albany-based CHA Consulting Inc. is providing civil engineering expertise.

In the photos below, the new sanitary and steam pipes are being fed through a protective concrete threader, and new cobbled pavers being paid out in front of Mann. The rebar sticking out of the curved concrete in front of Mann is part of a bi-level concrete stairwall that will be capped with cut stone – my guess is the rebar is there to strengthen the concrete, and will be trimmed down once the concrete is fully cured and the project team is ready to move on to the next step. The metal tool on the left side of the last photo is a portable trench shield used for pipe installation.

20160918_131244 20160918_131314 20160918_131411 20160918_131430 20160918_131806 20160918_131810 20160918_133025 20160918_133246 20160918_133322 20160918_133644 20160918_133712 20160918_133753 20160918_133926

ag_quad_2

Pg-3-Rendering





209-215 Dryden Road Construction Update, 08/2016

23 08 2016

Structural steel is rising at 209-215 Dryden Road, the site of the new Breazzano Family Center for Executive Education. In the past month, the steel frame has been built out to street-level and decking is being attached to what will be the ground floor. A 90-seat tiered classroom will be in the basement below the decking, and a second 90-seat tiered classroom will be built on top of the decking. In the third-to-last photo, you can see a large open space between the steel columns, which is where the building’s four-story atrium will be. Those steel columns next to Dryden South (205 Dryden) really are as close as they look – the finished walls of the buildings will be separated by just two inches.

Like much of Collegetown, the project hasn’t been without its problems. A construction worker was injured last month when his leg was pinned against a concrete form. Thankfully, it doesn’t sound like the injury was too serious.

The six-story, 76,200 SF building is expected to open in summer 2017. Given the issues surrounding and delaying 201 College Avenue, this might be the only major building opening in inner Collegetown next year. About 200 Cornell staff will occupy the fourth through sixth floors at opening, and 350-400 Executive MBA students will attend week-long instruction sessions in the building during off-season academic periods (summer intercession and winter break).

20160821_101952 20160821_102029 20160821_103440 20160821_103525 20160821_103604 20160821_103623 20160821_103652 20160821_103721 20160821_103726

209-215_2

209-215_basement

 





209-215 Dryden Road Construction Update, 06/2016

15 06 2016

At the site of the new Breazzano Family Center for Business Education, work continues on the foundation. It looks like excavation is mostly complete at this point and they’re putting in concrete footings, with digging for a new footing taking place at left in the first photo. The rebar doweled into the concrete will be tied into the walls as they’re built up. The footings closest to 205 Dryden (westernmost section) will hold the elevator shaft, stairwell and restrooms for each floor.

For those wanting a glimpse of the future, Cornell has put up a video render on Youtube showing the new building (exterior and interior) and advertising some of its features. There is an embedded copy of the video clip below.

20160608_162032 20160608_162035 20160608_162040 20160608_162217 20160608_162257 20160608_162323

209-215_2 209-215_basement