Structural steel is rising at 209-215 Dryden Road, the site of the new Breazzano Family Center for Executive Education. In the past month, the steel frame has been built out to street-level and decking is being attached to what will be the ground floor. A 90-seat tiered classroom will be in the basement below the decking, and a second 90-seat tiered classroom will be built on top of the decking. In the third-to-last photo, you can see a large open space between the steel columns, which is where the building’s four-story atrium will be. Those steel columns next to Dryden South (205 Dryden) really are as close as they look – the finished walls of the buildings will be separated by just two inches.
Like much of Collegetown, the project hasn’t been without its problems. A construction worker was injured last month when his leg was pinned against a concrete form. Thankfully, it doesn’t sound like the injury was too serious.
The six-story, 76,200 SF building is expected to open in summer 2017. Given the issues surrounding and delaying 201 College Avenue, this might be the only major building opening in inner Collegetown next year. About 200 Cornell staff will occupy the fourth through sixth floors at opening, and 350-400 Executive MBA students will attend week-long instruction sessions in the building during off-season academic periods (summer intercession and winter break).
Leave a Reply