Cornell Veterinary School Expansion Construction Update, 5/2017

24 05 2017

So many projects in the final stretch up on East Hill. The Vet School expansion’s multipurpose atrium is in the process of being closed up with its curtain wall glazing. An interior shot from the start of May shows interior stud walls are up and utilities rough-ins taking place, but drywall, interior trim and fixtures had not been undertaken.The concrete for the “grand staircase” had just been poured.

The atrium will be called “Takoda’s Run“, in honor of a greyhound adopted by alumna Janet Swanson (for whom Cornell’s wildlife rehabilitation center is named). The Swanson family are major university benefactors – Janet, Class of 1963, has given millions of dollars to the Vet School since the mid-2000s. Husband John (BS 1961, B.M.E. 1962, M.M.E. 1963), an engineer and tech executive, has given tens of millions to the university. The atrium in Duffield Hall and a lab suite in Weill are named for him, as well as several endowed professorships, fellowships and scholarships. Not just leaving it to Cornell, the couple has buildings named after them at Washington and Jefferson College in Pennsylvania, and a $41 million donation to the University of Pittsburgh led to the Swanson School of Engineering. My former editor at the Voice is definitely not a fan of this practice, but for those with a lot of money to burn, naming opportunities can be found or scoffed at here.

From the outside, the new administrative and library wing haven’t changed much since March, but at this point all Welliver has left is some window installs, exterior panels and finishes. Since I’m on a kick at the moment, the Flower-Sprecher library is named for former governor Roswell Flower (1892-94) for allocating funding, and in the early 1990s, Dr. Isidor Sprecker ’39 (Americanized from Sprecher) donated a substantial sum for renovation. It looks like some underground utilities work is going on out by the curb, possibly in preparation for the new landscaping and lighting fixtures.

The new Community Practice Service Building is underway, although I don’t have photos – the Poultry Virus Building has been demolished and the site was being cleared and readied for new construction. The timeline for the new 12,000 SF HOLT Architects-designed building is May 2017-May 2018, a couple months later than originally programmed.

The project seems to be a little bit behind schedule. The project team was initially aiming for a June completion, which was a little optimistic. The new schedule calls for an August opening.

 





Upson Hall Construction Update, 5/2017

22 05 2017

Home stretch for Upson Hall’s $74 million makeover. Nearly all of the turquoise water-resistive barrier (WRB) has been covered up with terracotta panels and aluminum inserts at this point. The utilities shaft and mechanical penthouse have been faced with a water resistant base layer and aluminum clips, and will be faced with grey metal panels. Note that those thin yellow aluminum plates on the exterior are a finished design featurethey’re intended to be a nod to the original canary yellow aluminum curtain bands that once lined Upson Hall’s facade. At this point, the upper three floors are occupied, the lower two floors and basement are being finished out, the exterior is nearly complete and interim landscaping features will be installed by The Pike Company before the building opens for full occupancy in August.

Over the next ten years, Cornell would like to utilize LTL Architects and Perkins + Will to redo the rest of the Engineering Quad with designs similar to Upson Hall. The $300 million plan also calls for the demolition of Carpenter Hall and a new multi-story building on the corner of Campus Road and College Avenue. Whether or not those things happen remains to be seen. The earliest renders of the Upson Hall plan are included at the end of this entry, and while the general design has remained the same, some of the design features, such as the shape of the bump-outs, the fenestration, and the emphasis on the south terrace were revised before the final plan was drafted.





209-215 Dryden Road Construction Update, 4/2017

17 04 2017

Work on the new Breazzano Center continues in Collegetown, with the exterior plastic sheets slowly being replaced by the metal and glass facade. On this particular windy day, the tarp was flapping enough to reveal a bit of the exterior metal stud walls underneath. On the rear of the building, the salmon-orange and dark grey panels now cover most of the exterior wall. The recently proposed 238 Linden townhouses will come up to about the top of the third floor, where the salmon panels change over to grey. 238 Linden will be roughly the same color as the lower-level panels, probably with the same metal finish. Note the clips on the exterior wall, which are for aluminum sunshades.

I’ve had contractors tell me that one of the ways you can tell the quality of the curtain wall glass is by how much distortion one sees in the reflection (optical distortion). Based off that criterion, the glass used on the entry level appears to be a fairly high grade. The opaque glass panels are called spandrel glass, and are used to conceal the floor slabs.  It looks like the thin vertical steel panels will be installed over the curtain wall, though not in all places – The northeast corner and ground floor will not have the steel panels, nor will the atrium at the front of the building.

One can barely see the interior work in these photos, but the interior stud walls were up and drywall has been hung on the lower floors, which means that most of the utilities rough-ins have been completed.

The last photo, which comes courtesy of Tom Schryver, gives an idea of the scale of the building in context – at six floors and 80 feet, it is the tallest that the Collegetown form zoning allows without a variance. At 76,200 SF, it’s the fifth-largest by square footage, after Cascadilla Hall (77,913 SF), The Schwartz Center (80,989 SF), Eddygate (95,000 SF) and 312 College Avenue (112,392 SF).





Upson Hall Construction Update, 3/2017

29 03 2017

The new aluminum and terracotta facade is working its way down the lower floors. New window inserts and panels have been installed since the January update, although many sections are still bare, the turquoise water-resistive barrier the top layer for the time being. Slowly but surely, metal fasteners are being attached to the WRB, mineral wool insulation is attached, and the clips are completed with cross-sectional bars so that the terracotta can be put into place.

According to the last Upson construction update from Cornell Engineering, interior framing and drywall is underway on the lower floors, as well as new utilities rough-ins and mechanical piping. One can see a section of drywall through the new windows in the photos below.

The goal is to have the building completed by August, with temporary landscaping until the third phase has been funded. One has to applaud the Upson staff and students who have had to put up with the construction for what’s been almost two years at this point. The upper three floors were finished last summer, and the basement, first and second floors are being completed this year.





Cornell Law School Renovation Update, 3/2017

28 03 2017

Finally starting to see a little bit of progressing on the renovations to Hughes Hall. The rest of the old masonry wall on the lower floors has been stripped out, and is covered with plastic and plywood for the time being. Eventually, the space will be opened as the new glass enclosure is built for the new west staircase. For the record. the stairwell is completely new; it replaces one that was slightly further to the east, on the inside corner of the building. This gut renovation is down to the studs, and then some. No work on enclosing the loggia just yet.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver is the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete, meaning November 2017 if all goes to plan.

 





Gannett Health Center Construction Update, 3/2017

27 03 2017

The new northeast wing of the Gannett Health Center has been framed, sheathed, and windows have been fitted. From the outside, work is also complete on the new concrete skin for the late 1970s northwest wing, which unlike the original building, it was finished out with concrete instead of stone. Meanwhile, the remaining portion of the original 1950s structure is still undergoing interior work and the new canopy has yet to be erected, so it’ll be a couple of months before the new curtain walls are fully installed. A new roof membrane is also on the to-do list.

Looking closely at the sheathing on the new building, you can see the clips that will be used to attach the new limestone veneer (Cornell has the time and the money for the real deal; most developers opt for less expensive but similar-looking precast concrete). Based off the roofline, it looks like fireproof fiberglass mat gypsum sheathing (in this case, GP DensGlass), followed by a silver moisture protection barrier, and then metal panels or limestone depending on the location.

October 2017 is the given completion date on the Cornell Facilities webpage, but the new building should be open by August; the new landscaping is what will extend into the fall. The Pike Company of Syracuse is the general contractor (they’re also doing Upson Hall nearby), and Downtown Ithaca’s Chiang O’Brien are the designers-of-record.

I did not get as close to the site as I would have liked, because the snow was still quite deep in some spots, and some of my usual vantage points were blocked off.





209-215 Dryden Road Construction Update, 2/2017

1 03 2017

Admittedly, when the entire building is sealed up in opaque plastic covers, it makes for a less-than-interesting construction update. The plywood doors are for the loading and unloading of materials via lifts, and apart from those, there isn’t much to break up the monotony of white plastic sheets. Note that the access doors are not the same as the elevator shaft, which is located about midway along the west wall next to 205 Dryden/Dryden South.

However, it does look like some exterior facade work is starting to get underway. Brown and grey metal panels are beginning to be installed on the building’s rear face – this is the side that will have the least amount of glass, as occupants won’t have much to see if developer John Novarr moves forward with his plans for townhomes on the double-lot of a house that came down to allow a construction staging area for the Breazzano Center. With the new home to the Executive MBA expected to open up this Spring, Novarr can proceed with options for that double-lot. 238 Linden is zoned CR-4, four floors with no required parking. The proposed townhouses could provide a visual transition between the 80-foot Breazzano and the 2.5 story houses that comprise most of the housing stock on this block of Linden Avenue, some of which are for pending sale.

In further detail, the rear facade windows are 1″ insulated glass with aluminum frames, and translucent insulated spandrel glass below the panes. The metal panels are insulated aluminum and are installed using a framing system – you can see the grey insulated panels with clips along the top edge of the panels. The plastic covers on the panels are to protect against scratches and scuffs prior to installation. ikon.5 sought to provide differentiation with mahogany brown panels on the south (Linden Avenue) side, with lighter salmon-peach panels planned for the north (Dryden Road). The west and east sides will be a little bit of of both. The first floor the street facing sides, and the atrium will be glass curtain walls. The dark panels are intended “to differentiate upper from lower and facilitate a relationship with the smaller scale of adjacent buildings,” per the application. Some of the later documents show a lighter shade of gray for the south side of the top floors, but to be frank, I am uncertain what is accurate.

Note that the fourth floor’s back side will have few windows because that is where the 1,990 SF video production studio will be located, and this requires a controlled-light environment. Presumably, with the green room and studio rooms, the intent is to have a comfortable and efficient interview space for live videos recorded for or streamed to students at remote campuses. The large flank of plywood panels at ground level is the service exit, with future loading dock and trash/recyclables enclosure.

20170218_120030 20170218_120120 20170218_120144 20170218_120149 20170218_120207 20170218_120254 20170218_120309 20170218_120351 20170218_120401 20170218_120408 20170218_120535

209_215_2

209_215_3





Cornell Law School Renovation Update, 1/2017

17 01 2017

From the outside, it doesn’t look like much is happening. But, given all the steel beams on site, the safe bet is that the former dorms inside are still being gutted to nothing but the load-bearing walls, and those beams will become a part of the new interior partitions, new stud walls for the enhanced faculty office and professional space. This is by and large an interior renovation, but perhaps after the deepest cold of the season passes, we’ll see more progress towards enclosing the loggia and the new stairwell on the west face. The wire mesh over the exposed west wall is for safety reasons.

20170107_105312 20170107_105321 20170107_105342 20170107_105408 20170107_105424 20170107_105432 20170107_105542 20170107_105624

hughes_cornell_4 hughes_cornell_3





Cornell Veterinary School Expansion Construction Update, 1/2017

17 01 2017

Starting to see more progress on the structural frame of the $74.1 million Vet School additions. The reinforced concrete frame of the new library and administrative offices now extends all the way back to the rest of the Vet School complex; the new section is draped over with plastic sheets. Also, as the new wing gets fleshed out, the rough openings of the windows are taking shape. It doesn’t look like there’s been too much exterior progress on the new atrium.

According to the project webpage (last updated two weeks ago), interior framing (metal stud walls probably) is underway, rough-ins are underway, and the new cafeteria is under construction. Welliver will have the new atrium and lecture hall fully closed up by the end of January. Most of the Vet Research Tower work has been completed, but new office layouts are still in the works for the sixth and seventh floors, and that work won’t get underway until this Spring.

The new $7 million ($4.9 million hard cost) Community Practice Service Building is out for bid, with a march demo planned for the Poultry Virus Building currently on site, and a March 2018 opening, about seven months after the bulk of the new Vet School structures. It is a wood-frame 12,000 SF building designed by HOLT Architects, and I still have yet to find an image of the design.

20170107_102456 20170107_102508 20170107_102521 20170107_102540 20170107_102615 20170107_102640 20170107_102646 20170107_102708 20170107_102740 20170107_102838 20170107_102846

cad048742a281097e5667382eced42333f5656954f5a3ef1021519c03b4abe9f

20160522_131445 20160522_131417 20160522_131344

20160522_131403





209-215 Dryden Road Construction Update, 12/2016

14 12 2016

Cornell’s Breazzano Family Center at 209-215 Dryden Road is closed up for the winter. Literally, with white plastic sheeting, as a protective measure against the elements while interior work moves along. The plywood holes on the front and back sides are removable so that a lift can deliver materials to different floors of the 6-story building. One can make out the dramatic entry foyer above the steel stretching out the sheeting above the ground floor. Note that the height of the building, 80 feet, is the maximum permitted under Collegetown’s form zoning (MU-2, up to 6 floors or up to 80 feet).

The plan is to have the new 76,300 SF building open by Summer 2017. Hayner Hoyt Corporation of Syracuse is the general contractor.

After the last Breazzano update a couple months ago, I had contacted Cornell to do a piece about the expanding Executive MBA program, what’s driving the growth, why Collegetown, and so on…but after being led around or misled by several emails over a few weeks, I gave up on the piece. For what it’s worth, Poets and Quants did a thoughtful article and interview here with the Johnson School Dean, Soumitra Dutta, talking about the future of the MBA program and the business school merger with the Dyson/AEM program and the Hotel School. Maybe I’d have had better luck if I just sidestepped Cornell’s PR unit.

20161209_155004 20161209_155019 20161209_155104 20161209_155204 20161209_155215 20161209_155234 20161209_155258

209-215_2