Stocking and Klarman Hall Progress Photos, 12/2013

7 01 2014

12-17-2013 086

This photo is probably timed similarly to Jason’s over at Ithaca Builds. Consistent with his analysis, a little bit of scaffolding visible in this image gives indication of the roof work being done to Goldwin Smith, and underground work over east Avenue is closed up, if temporarily. The $61 million dollar token glassy box adds 33,250 sq ft of new usable space.

Note for Cornell visitors – from this Wednesday (Jan 8th) to April 19th, 2015, the southbound lane of East Avenue will be closed to facilitate construction of Klarman Hall. I’d get around to feeling sympathetic, but I had the Thurston Ave. bridge detour my freshman year, and then years of Milstein, so…eh. Deal with it.

12-17-2013 052

12-17-2013 072

1-2-2014 335

The time difference between photos 1/2 and 3 is about 15 days. I just happened to pass through Ithaca twice in December, for two separate events (the first one though, I was only able to take photos on Cornell campus). I doubt I’ll be as lucky in the next few months.

Stocking Hall phase 2 is underway. Luckily for me, I have a friend that is a food science alum, who sends me all of the email updates. Quoting the one sent this past Thursday:

Phase 2 of the renovation project started several months ago with a focus on getting as much of the slate roof replaced as possible before winter. I think they were able to get about 70% of Stocking re-roofed. Asbestos abatement was the first part of the inside work. Once a floor was abated, Pike [construction company] worked on demolishing all interior walls.  Last Thursday (1/2/14) an independent testing agency certified the air test was safe after the abatement was completed on all floors. We took our first look on Friday.

The basement has been gutted, the first floor has undergone asbestos abatement and will begin demo shortly, the second and fourth floors have been gutted, and the third floor isn’t far along, still in the initial teardown/salvage stage. The renovation of old Stocking is due to be complete in August 2014.





Collegetown Terrace Progress Photos, 12/2013

6 01 2014

I always carry a second set of charged batteries on me when I do these little photo tours, because the last thing I want is to have my day cut prematurely short, or pay out the nose for a new pack of AAs (I rotate through two sets of rechargeables, for the record). It doesn’t help me much when I leave the extra set on the passenger’s seat of my car, which is parked way up on Pearl Street. I was cold and soaked to the bone by the time I finally finished getting all the shots I wanted. Here, there are not only construction photos, but also shots from some less familiar angles of the project.

It still astounds me when I think of the numbers associated with this project. Seven buildings over 12 acres. The net increase in bedrooms is 589 (1,226 total, in at least 610 units). The construction cost exceeds $70 million. Using the Danter study (which assumes a 98-99% occupancy rate), that would mean 580 more residents in this area (although given the intended market, it’s mostly re-appropriation of tenants from other parts of the county). That’s more than the population of nearby Freeville. Certainly, the project has been fraught with contentious debate since it was first proposed. As development goes, it’s the proverbial 800-pound gorilla.

Buildings 5 and 6 are well-underway, heading towards a completion/occupancy date of August 2014; building 7, which is very similar to building 5 but further south (i.e. deeper into) on the property, will be constructed in the 2014-2015 timeframe.

1-2-2014 318

1-2-2014 319

1-2-2014 320

Building 5 and the elevated walkway.

1-2-2014 321

1-2-2014 322

1-2-2014 323

1-2-2014 324

1-2-2014 325

1-2-2014 326

Building 6, complete with winter-friendly plastic wrap.

1-2-2014 327

The rear addition of the George C. Williams House.

1-2-2014 330

The “Mithcell Plaza“, which incorporates elements from the locally-relevant Delano House that was demolished to make way for the project.

1-2-2014 329

Vinyl-tastic. I thought these were supposed to be metal panels…?

 

1-2-2014 328

No one mind me, I just needed a place to briefly dry off.





Gates Hall Progress Photos, 12/2013

5 01 2014

 

With an anticipated opening date early in 2014 (slightly behind schedule), the $60 million, 101,000 sq ft Gates Hall project is nearly complete. The work left at this point appears to be completion of the primary entrance structures (the “feet”, to use Jason’s term), a little landscaping, and interior work. Kinda odd to think the discussion of Gates Hall on this blog goes back to nearly the very beginning (and technically, since Bill Gates donated the money in 2006, this project has been in queue for even longer).

1-2-2014 349

1-2-2014 339

1-2-2014 341

1-2-2014 342

1-2-2014 343

1-2-2014 344

1-2-2014 345

1-2-2014 346

1-2-2014 347

1-2-2014 348





Breckinridge Place and Seneca Way Progress Photos, December 2013

4 01 2014

1-2-2014 362

1-2-2014 360

1-2-2014 361

Breckinridge Place and its 50 units move closer to completion. In his last update, Jason over at Ithaca Builds noted the removal of bricks for what he surmised to be the architectural shades, although in the renderings they were located only two-thirds up the windows, rather than at the top. These photos seem to support that. The building is slated to open in early 2014, and at least from the outside, it looks like only minor work remains.

1-2-2014 355

1-2-2014 352

1-2-2014 353

1-2-2014 354

Across downtown, Seneca Way is putting the finishing touches on its eastern facade as it inches toward its opening date this month (haven’t heard specifics, so I’m assuming a soft opening). Apart from a few details like installation of garage doors on the ground level, signage and some ground work, this building is nearly complete as well. Seneca Way brings 38 apartments and 8,600 sq ft of office space to downtown Ithaca.





Belle Sherman Cottages and Boiceville Cottages Progress, 12/2013

3 01 2014

Over my New Year’s holiday, I passed from Albany to Binghamton to Ithaca, to meet with someone and carpool west to Buffalo. This gave me a few hours to kill waiting for that person to arrive, so…carpe diem.

1-2-2014 300

1-2-2014 299

I really don’t care for the finish on the new cottages. It makes them look prematurely aged and gives them a less inviting appearance vs. their older cohorts.

1-2-2014 302

1-2-2014 301

Compared to the last photos, the cluster in the left of the second photo from top is now complete, with slab foundations in place for the next dozen cottages. I suspect these will mostly be built during the spring.

1-2-2014 304

Notably, when this day started, it was raining and in the low 40s.

1-2-2014 307

Next up were the Belle Sherman Cottages (a.k.a. Vine Street Cottages) on the east edge of the city.

1-2-2014 306

The “craftsman bungalow” on lot 19 is nearing completion, from the looks of it.

1-2-2014 308

Meanwhile, another house will be starting construction in the near future. This one looks to be lot 14, another “Victorian Farmhouse”, like the beige home in the lead-in photo. I wonder how many homes will have to be sold before marketing starts for the townhouses?

1-2-2014 305

As a quick side note, I noticed the grassy lot next to where I usually to park my car is now occupied by a two-story home. It’s not the same as the spec home proposed in the initial ad (the lot sold last August), but this house doesn’t look half bad (the entryway seems a little spartan).





A Random Mix of Project Updates 7/2013

1 08 2013

7-26-2013 058

7-26-2013 052

7-26-2013 053

Over at Breckenridge Place, the installation of the brick facade is nearing completion, and some of the windows have been installed in the six-story building. Originally slated for occupancy this fall, it looks like this has been pushed back a few months to very early 2014, according to the INHS website. This seems reasonable, as the vast majority of interior work still needs to be completed, not to mention the rest of the facade, window installation, and finishes/landscaping. An application lottery is underway for qualifying individuals.

7-26-2013 031

Looks like I can mark Collegetown’s 107 Cook Street as complete. Developer Dan Ligouri’s four units (12 bedrooms) will welcome their first tenants this summer (June/August thereabouts).  Replacing it in the queue of small residential projects, local nonprofit INHS will be launching construction on a 4-unit townhome project at the sharp corner of South Cayuga and South Titus Streets, just south of downtown. This is in addition to the aforementioned Breckenridge, a few rebuilds/renovations they have underway and the second phase of the Holly Creek townhomes, which will add another 11 units to be completed in late 2014.

7-26-2013 066 7-26-2013 049 7-26-2013 063

Ithaca makes this almost too easy. Ithaca Builds has been keeping tabs on the Planned Parenthood development, where foundation work is underway. The other two won’t start for a few more months.

7-26-2013 062 7-26-2013 067

It sure is odd to see a treeless Ithaca Commons.  Excavation and utilities replacement will be underway through December, with reconstruction and new surfacing planned for next spring and summer.

 





Seneca Way Updates, 07/2013

30 07 2013

7-26-2013 068

My compliments to the DIA for deciding to use renderings as wall posters on the construction barriers of Ithaca Commons.

7-26-2013 048 7-26-2013 044 7-26-2013 045

Seneca Way still has two floors to go before topping out, although the stairwells appear to be fully built out.  Wall panels are in place up to the fourth floor, and the wood reinforcements on the fifth floor suggest installation will begin shortly. Seneca Way will add 38 apartments and 8,600 sq ft of office space to downtown when it is completed in Spring 2014.  The office space will be fully occupied by Warren Real Estate and the non-profit Park Foundation, which had also been looking at space in the Cayuga Green Condos before that project went all-residential.

7-26-2013 047

I assume that the Argos Inn is open for guests at this time. The landscaping is tidy and the new 13-room boutique hotel breathes life into the ca. 1831 Cowdry House, which once served as the headquarters for Duncan Hines. The last owners, non-profit Unity House  (a treatment/rehab facility), moved up to Lansing right by the mall.





Collegetown Terrace Update 7/2013

27 07 2013

Taking a page out of Ithaca Builds’ format – breaking these up to reduce wordpress photo drag. I had exactly 90 minutes to try and hit as much of Ithaca as possible before getting back on the road; I didn’t see everything I wanted, but I hit a lot, and I’ll be sharing those photos over the next few days.

Phase 2 for Collegetown Terrace is nearing completion (units will have their first tenants next month), and phase 3 is underway with a targeted completion date of August 2014. Phase 2 consists of buildings 3.1, 3.2, 3.3, and 3.4. Phase 3 will have buildings 5, 6 and 7, and these buildings will be similar in appearance to phase 2.

7-26-2013 013

7-26-2013 014

The large glassy entry pavilion (where the fitness center will be, if I remember right) is largely complete, Any work left at this stage would likely be cosmetic details such as finishes.

7-26-2013 025 7-26-2013 024

Since I’m not the biggest fan of modern architecture, I was a little nervous about the facade treatment when it was first proposed. The metal tiles don’t look half bad, as the landscaping grows in they’ll blend into the environment more nicely.

7-26-2013 016 7-26-2013 015

The George C. Williams house has been sympathetically renovated, although the addition to the back is rather incongruous.

7-26-2013 018 7-26-2013 019 7-26-2013 020

Building 3.4 is quite massive, although the north facade attempts to make the structure seem a little less mammoth. The south side, deeper into the gorge, makes less of an effort. Building 5 can be under construction in the above image.

7-26-2013 021

This guy totally struggled to turn into the street. On that note, I struggled just trying to cross the street. I will be quite relieved when the reworked intersection of State and Mitchell is in place.

7-26-2013 023 7-26-2013 030

The buildings from Phase 1 are growing out their landscaping and appear to be faring all this construction rather well.

7-26-2013 026 7-26-2013 029

Not quite sure what the red-and-white checkered flag means, it could be a warning symbol or a company symbol, like the topping pine tree seen with some construction projects.

 

 

 





Ithaca Construction Photos, Spring 2013 (Non-Downtown Pt. 2, Downtown Pt. 1)

12 04 2013

4-8-2013 257

Facade work is just beginning on the new 106-room Fairfield Inn down in big box land. The project experienced a bit of a hiccup back in January when two construction workers were injured at the site, falling four stories through collapsing scaffolding above an elevator shaft. Occupancy is slated for mid-fall 2013.

4-8-2013 248 4-8-2013 249

Site prep is under way for the new 18,000 sq ft Planned Parenthood building on the 600 block of West Seneca Street. It would be unfair to label this a demolition. If anything, it looks like a careful deconstruction is underway for the run-down homes currently on the property, salvaging what can be reused before the rest of the structure is torn down. A maneuver like that deserves a big thumbs up. The project will begin construction during the summer, with completion around late summer 2014.

4-8-2013 256

Why? Because it’s Ithaca.

4-8-2013 327 4-8-2013 326 4-8-2013 324

5 of the 6 floors have been built for Breckinridge Place; rather curiously, only a couple bits of masonry and steel are up to where the sixth floor will be poured. The 50-unit project should be completed and ready for rentals by this fall.

4-8-2013 330

This photo will very quickly become outdated. Firstly because of the Commons reconstruction, which I’ll cover at another time. Secondly, the Harold’s Square project. The 10-story, 140-building will refurbish the Sage Block and the Miller Buildings (the orange brick structure left of center), while the three buildings at center will be demolished. The mixed-use project will have retail on the bottom, office space on the first few floors, and apartments on the upper six floors (estimates range from 36 to 70). Although the project still needs some zoning variances, if all goes well, construction could start by the end of the year, with completion around mid-2015.

EDIT: Oh look, new renderings. Now the building has gone from “meh” to embracing the prison motif, with slit windows in the tower and a dour face towards the Commons. This is not going to age well…

4-8-2013 343

Another soon to be outdated image. The “Lofts at Cayuga Green” will add 39 units on four 15′ floors. In a recent interview, the director of planning and development expressed concern whether the project would start this year, but given that funding is in place and the developer’s tax credits will expire otherwise, my guess is now or never.

4-8-2013 338 4-8-2013 339

Now, another project that is underway. Seneca Way will add 38 apartments and ground-floor office space. The five-story building is expected to be opened in Spring 2014. Meanwhile, the Argos Inn next door should finally be open for this business.

4-8-2013 335 4-8-2013 347 4-8-2013 349

Hotel work, approved and set to begin. At top, the site for the new Marriott. With tax abatement approved, construction will start by summer, with an 18-month buildout for the 10-story, 159-room hotel. The Holiday Inn will also begin its reconstruction this year, tearing down the low-rise portions for a 9-story tower and a convention center (and a net increase of 13 rooms). The low-rise portions are slated to close in November, and while renovation of the older tower will be done by May 2014, the new tower and convention facility will probably require another year before they are completed.

All other photos will be uploaded in the final entry.





Collegetown Construction Photos, Spring 2013

9 04 2013

4-8-2013 198 4-8-2013 199

The last time I rolled through around Thanksgiving, the Vine Street Cottages projects had two homes complete and a third underway. 4.5 months later, and the third home is complete, but the project has shown no further development. 3 homes of 29 is not a particularly auspicious sign, especially when all of the for sale signs nearby had no “sold” stickers slapped on. They’re nice homes, but it’s not easy justifying paying $300k+ when older homes of similar design are going for 100k less five minutes away.

4-8-2013 173 4-8-2013 171 4-8-2013 170 4-8-2013 168 4-8-2013 166

I still cannot get over how massive the Collegetown Terrace project is. It just dominates the terminating views along the State Street corridor. The work underway at the moment is for Phase II, set to be complete this summer. Phase III will not be as visible, as those buildings will be built closer to the gorge. One thing I did realize in taking photos was that it was extremely difficult to cross East State Street, a sentiment shared by a couple of residents who were cursing loudly while trying to cross the busy road. Thankfully, improvements to the road will be made to make it more pedestrian-friendly, including reworking the traffic lanes/island and adding crosswalks. The entire project will be complete in Summer 2014.

4-8-2013 190

Which by that time, I would not be surprised to see Novarr-Mackesey initiate plans for the former Palms property and its neighbors, all of which are owned by the development company.

4-8-2013 183

107 Cook looks to be complete.

4-8-2013 184

Maybe someday? Hopefully.

4-8-2013 177

604 East Buffalo Street. Not long ago, it was home to the Crossroads Life Center, a Christian Fellowship organization. Crossroads sold the property in December 2012, anticipating a move to a newly-constructed property that appears to be in substantial need of donations in order to actually happen. Meanwhile, WVBR bought the building for its new studio, moving out of its current digs near East Hill Plaza. In the same vein, the station is in the middle of a capital campaign to renovate the structure for their needs, to the tune of $935,000. The naming rights have been bought in full by left-wing gadfly Keith Olbermann’ 79, whose donation was partly in honor of deceased classmate Glenn Corneliess.  Hence, Olbermann-Corneliess Studios. the station expects to move in by the end of fall 2013.

4-8-2013 196

Apparently, Pontiac 1000s still exist in the Northeast. Growing up in a family with multiple mechanics, I knew as a child that owning this car, or more commonly its Chevette sibling, pretty much meant you gave up on life. Bravo to the person who’s kept one going this long, well after repairs would be worth more than the car itself.