Upson Hall Construction Update, 7/2017

28 07 2017

Cornell has several projects that are finishing up within the same short time frame. The renovation of Upson Hall will be one of them. Some of the Morin aluminum panels have yet to be clipped over the mineral wool, but the exterior is largely finished. It appears that the ribbing in the terra cotta panels becomes gradually finer from bottom to top. Interior work is still ongoing, from the windows it appears that drywall has been hung, but finishing work, such as interior railings, remains to be done.

The timeline is to have the second phase completed by August, with an eventual third phase that will upgrade the landscaping from simple sidewalks and green space to more complex plaza areas with pavers, stone and wood benches and lighting effects. Given future plans to upgrade the Engineering Quad, the presence of heavy equipment and staging areas close by if not reused means that Cornell prefers to wait until all work is done on the buildings before upgrading the grounds (consider the Ag Quad for example).





Gannett Health Center Construction Update, 7/2017

27 07 2017

Here are the rest of the photos from the Cornell Health, formerly known as Gannett Health Center. The Voice write-up is here. The project is mostly complete, with some sidewalk and landscaping yet to be completed (the official timeline has the project wrapping up in October, but given the stocked pharmacy and furnished lobby, the project is practically complete from this blog’s perspective). Look for a potential final Voice article later in the fall, as part of an official tour of the building around the time of the ceremonial ribbon-cutting.

On a personal note, I want to briefly send my apologies for the slow updates; I’ve been dealing with a personal loss, and their passing hit me harder than I anticipated. It’s also been a very slow week news-wise, so don’t expect a weekly news round-up tomorrow evening.





Cornell Veterinary School Expansion Construction Update, 7/2017

25 07 2017

Just clearing out the photo stash – only a small sampling of the photos made it into the Voice round-up. The first set show the new administration and library wing finishing exterior aluminum panel installation, new curbing being laid, and the mostly finished entry and atrium area. The later photos are of the new Community Practice Service building, which is finishing underground utilities routing and foundation work – the new service facility will be one-story and wood-frame, which should allow the structural framing to move quickly.

The new vet school facilities will be open by late August, and the new CPS Building neat spring.





Cornell Law School Renovation Update, 5/2017

24 05 2017

Externally, not much has changed since March, although it looks like work is starting on enclosing the north loggia. The Fork and Gavel Cafe is closed for renovations through September, but a carry-out offshoot will serve in its place. Most of the work on this $10.2 million project is internal, converting former dorms into academic office and support space. With any luck, the next visit will be from the inside.





Gannett Health Center Construction Update, 5/2017

23 05 2017

Another Cornell project in the final stretch is the second phase of the $44 million Gannett Health Services reconstruction, now known as “Cornell Health“. The new entrance is being fleshed out with fiberglass mat sheathing, and will be finished out with stone and brushed aluminum. The silvery material is a Carisle 705FR-A fireproof air/vapor barrier, which is made of aluminum and HDPE (plastic) sheets. The entrance canopy will be enclosed in glass, and the concrete podium will be concealed when the front entrance is backfilled to the height of Ho Plaza. The new northeast wing is being clad in limestone panels atop a continuous anchor system, because stone is dense and it needs a system able to support its weight. OCD-inducing Side note, that “Cornell Health” lettering signage is a different font than the rest of campus, Arial versus the campus’s usual Kabel font.

Like with Upson, the plan is to have the building open by August, although the landscaping could take another couple of months, wrapping up by October 2017.





Upson Hall Construction Update, 5/2017

22 05 2017

Home stretch for Upson Hall’s $74 million makeover. Nearly all of the turquoise water-resistive barrier (WRB) has been covered up with terracotta panels and aluminum inserts at this point.┬áThe utilities shaft and mechanical penthouse have been faced with a water resistant base layer and aluminum clips, and will be faced with grey metal panels. Note that those thin yellow aluminum plates on the exterior are a finished design featurethey’re intended to be a nod to the original canary yellow aluminum curtain bands that once lined Upson Hall’s facade. At this point, the upper three floors are occupied, the lower two floors and basement are being finished out, the exterior is nearly complete and interim landscaping features will be installed by The Pike Company before the building opens for full occupancy in August.

Over the next ten years, Cornell would like to utilize LTL Architects and Perkins + Will to redo the rest of the Engineering Quad with designs similar to Upson Hall. The $300 million plan also calls for the demolition of Carpenter Hall and a new multi-story building on the corner of Campus Road and College Avenue. Whether or not those things happen remains to be seen. The earliest renders of the Upson Hall plan are included at the end of this entry, and while the general design has remained the same, some of the design features, such as the shape of the bump-outs, the fenestration, and the emphasis on the south terrace were revised before the final plan was drafted.





Upson Hall Construction Update, 3/2017

29 03 2017

The new aluminum and terracotta facade is working its way down the lower floors. New window inserts and panels have been installed since the January update, although many sections are still bare, the turquoise water-resistive barrier the top layer for the time being. Slowly but surely, metal fasteners are being attached to the WRB, mineral wool insulation is attached, and the clips are completed with cross-sectional bars so that the terracotta can be put into place.

According to the last Upson construction update from Cornell Engineering, interior framing and drywall is underway on the lower floors, as well as new utilities rough-ins and mechanical piping. One can see a section of drywall through the new windows in the photos below.

The goal is to have the building completed by August, with temporary landscaping until the third phase has been funded. One has to applaud the Upson staff and students who have had to put up with the construction for what’s been almost two years at this point. The upper three floors were finished last summer, and the basement, first and second floors are being completed this year.





Cornell Law School Renovation Update, 3/2017

28 03 2017

Finally starting to see a little bit of progressing on the renovations to Hughes Hall. The rest of the old masonry wall on the lower floors has been stripped out, and is covered with plastic and plywood for the time being. Eventually, the space will be opened as the new glass enclosure is built for the new west staircase. For the record. the stairwell is completely new; it replaces one that was slightly further to the east, on the inside corner of the building. This gut renovation is down to the studs, and then some. No work on enclosing the loggia just yet.

Design work is by KSS Architects, with offices in Princeton and Philadelphia. Frequent Cornell collaborator Welliver is the general contractor. The project is expected to cost about $10.2 million and take about 13 months to complete, meaning November 2017 if all goes to plan.

 





Gannett Health Center Construction Update, 3/2017

27 03 2017

The new northeast wing of the Gannett Health Center has been framed, sheathed, and windows have been fitted. From the outside, work is also complete on the new concrete skin for the late 1970s northwest wing, which unlike the original building, it was finished out with concrete instead of stone. Meanwhile, the remaining portion of the original 1950s structure is still undergoing interior work and the new canopy has yet to be erected, so it’ll be a couple of months before the new curtain walls are fully installed. A new roof membrane is also on the to-do list.

Looking closely at the sheathing on the new building, you can see the clips that will be used to attach the new limestone veneer (Cornell has the time and the money for the real deal; most developers opt for less expensive but similar-looking precast concrete). Based off the roofline, it looks like fireproof fiberglass mat gypsum sheathing (in this case, GP DensGlass), followed by a silver moisture protection barrier, and then metal panels or limestone depending on the location.

October 2017 is the given completion date on the Cornell Facilities webpage, but the new building should be open by August; the new landscaping is what will extend into the fall. The Pike Company of Syracuse is the general contractor (they’re also doing Upson Hall nearby), and Downtown Ithaca’s Chiang O’Brien are the designers-of-record.

I did not get as close to the site as I would have liked, because the snow was still quite deep in some spots, and some of my usual vantage points were blocked off.





Cornell Veterinary School Expansion Construction Update, 3/2017

26 03 2017

There’s been quite a bit of progress over at the Vet School. It looks like the exterior glass and aluminum are going on the new library and administrative wing. Windows and sheathing have been installed on the north face as well, with a water-resistive barrier applied over the sheathing. The new atrium is being framed out.

According to the Vet School’s construction update page, interior framing and utilities installations are underway in the new wing, and the new cafeteria is under construction – both are aiming for August completions. The new atrium and lecture hall will be closed off shortly, with interior work to launch in earnest once that occurs.

Thanks to Maria Livingston over at HOLT Architects, readers now know what the new Community Practice Service building will look like. Syracuse’s G. M. Crisalli and Associates Inc. has been selected as general contractor, and construction for the $7 million, 12,000 SF wood-frame structure is expected from March 2017- March 2018.