Carey Building Construction Update, 2/2015

9 02 2015

I was originally going to schedule this for later in the week, but I figure I’ll run it now, since the recent twitter chatter is observant but mistaken. The Canopy Hotel is not under construction. At least, not yet. The hotel is expected to start in early Spring. But the work on the Carey Building addition is just beginning.

According to Jason Henderson at Ithaca Builds, building contractor LeChase Construction is currently conducting underpinning work on the Carey Building. Underpinning is the name of the process by which a foundation is strengthened – certainly necessary when one is about to add five floors onto a 2-story building. The second to last photo here shows some of the underpinning work on the eastern foundation wall, and the tarp is on the roof indicates prep-work for the upcoming expansion. LeChase will also be handling the construction of the Canopy Hotel next door.

It’s quite unusual in a place like Ithaca to have two separate large projects right next to each other under construction at the same time. This will be logistically complicated. In a letter to the Canopy developers, LeChase’s large trucks will have their brakes inspected before entering State Street, and will be escorted down the hill to a designated area on Seneca Street, and will leave the city via Seneca Street. According to construction phase diagrams, The steel for the Carey Building will be erected first; then, using the same crane, LeChase will begin installing steel for the new hotel. Sharing the crane will result in a cost savings to both owners.

When most of the western side of the hotel has had its steel structure craned into place, LeChase will transition to a smaller crane and switch the material unloading and staging area to East State Street. This is because the hotel occupies most of the site, so the crane is reduced and East State street will be closer to the location of the new crane. Cladding and interior materials will continue to be fed in via E. State Street through the project’s completion in Spring 2016. The Carey Building will have been completed by then, finishing by the end of summer 2015.

The Carey Building addition will add a third floor and 4,200 sq ft to the Rev business incubator (nearly doubling it to 8,700 sq ft), and on floors 4-7, there will be 20 apartments. Floors 4 and 5 will have 16 studio apartment units that average only 400-500 sq ft, their small size enabling them to be rented at a lower price. The 4 units on floors 6 and 7 will be larger 2-bedroom units. The $4.1 million project is being developed by local firm Travis Hyde Companies.

20150207_153142 20150207_153223 20150207_153246 20150207_153412 20150207_153422

carey_rev4_2

canopy_carey_logistics_1 canopy_carey_logistics_2 canopy_carey_logistics_3 canopy_carey_logistics_4





Cornell Construction Updates, 12/2014

6 01 2015

Funny How the November photos are snow-covered, and the December photos were taken when the temperature was in the low 50s F. Work continues on the future Klarman Hall, pushing onward to its intended opening in December 2015. Construction firm Welliver is plodding making slow if steady progress, with steel work and metal decking underway above ground, and utility installation and door framing in the basement. Some interior and exterior wall framing has begun on the basement, ground and first floors. The 33,250 sq ft building was designed by Koetter | Kim & Associates.

20141227_130627 20141227_130711 20141227_130745 20141227_130808 20141227_130913 20141227_130937 20141227_130955 20141227_131041

On the other side of campus, renovation work continues on Stocking Hall, the home of the food science department. The porous concrete in front of the new wing didn’t fare as well as hoped, and is being replaced. In the old building, installation of new, energy-efficient windows is underway, and should be completed in the near-term. Interior work continues as labs and academic spaces are fitted out, and the old building and new building connectors have been sealed from the element, making them water-tight. The work will wrap up this summer, weather and schedule permitting; the two-phase renovation was launched in September 2010, and the new wing (phase one) opened in July 2013. The 136,000 sq ft rebuild and renovation is nearly a year behind schedule. Contracting is being taken care of by the Syracuse office of The Pike Company, and the design of the new building is a product of a SUNY Construction Fund favorite, Mitchell Giurgola Architects of New York City.

20141227_124325 20141227_124331 20141227_124336 20141227_124419 20141227_124449 20141227_124510 20141227_124610





EcoVillage Construction Update, 12/2014

29 12 2014

Heading over to West Hill, construction continues slowly but steadily on EcoVillage’s 4-story Common House/apartment building as part of its third neighborhood, TREE (Third Residential Ecovillage Experience, following its first two, FROG and SONG).  I can’t seem to find any specific values for the number of bedrooms in the apartment building, but there are 15 units ranging from studios to 3-bedrooms. However, using a little math and deduction, a rough estimate can be established. EcoVillage claims 160 residents in its first two neighborhoods, which have 30 units each (total 60), and they expect 240 residents when the 40-unit TREE neighborhood is complete. That gives 80 residents in 40 units, of which 25 of those units are houses. Houses tend to have more occupants than apartments (2.1/house vs. 1.7/apartment from the 2010 county census), so I think 25-30 residents is a fair estimate for the apartment building.

Interior work is underway and all the windows and doors are fitted into place. Exterior finishes and balconies have yet to be installed. The houses are all complete and occupied. Construction is being handled by a local firm, AquaZephyr, which received an award from the U.S. Dept. of Energy for a “zero energy ready” home constructed as part of TREE. The apartment building is scheduled to be finished this spring. Setbacks stemming from building code requirements pushed it away from its original fall 2014 completion date.

20141227_150247 20141227_150051 20141227_150040 20141227_150002 20141227_145916 20141227_145843

treenh1





Stone Quarry Construction Update, 12/2014

28 12 2014

Like it or not, construction is well underway at the site of the future Stone Quarry Apartments on South Hill’s Spencer Road. Foundation walls and pilings are visible at the site of the townhomes, and the cinder block wall for the elevator shaft and stairwell of the apartment building is clearly visible from the street. A closer inspection of the apartment building shows that a concrete slab foundation has been poured. I’m not sure if the white slabs in the last photo are some type of insulated concrete form like the Fox Blocks used at the Thurston Avenue Apartments earlier this year, or something else (Ithaca Builds’ Jason Henderson is far more knowledgeable about these types of things than I am).

The Stone Quarry project consists of 16 two-story townhouses (2 rows, 8 each), and a 19-unit, 3-story apartment building on the northern third of the property. Specifically, the breakdown of unit sizes is follows:

16 three-bedroom Townhouses
2 three-bedroom Apartments
11 two-bedroom Apartments
6 one-bedroom Apartments

As with all projects by INHS, the units are targeted towards individuals with modest incomes, with rents of $375-$1250/month depending on unit size and resident income. While affordable housing is generally welcome and sorely needed, Stone Quarry had a number of complaints due to size, location and lingering environmental concerns.

With a theoretical capacity of 82 residents (assuming one per bedroom), the project is the largest non-student oriented project currently under construction in the city (Lofts @ Six Mile has more units with 45, but with 3 studios, 21 1-bedroom, and 21 2-bedrooms, for a theoretical max of 66 residents). The apartments are expected to be completed in October 2015. The buildout is being handled by LeCesse Construction, a nationwide contractor with an office in suburban Rochester.

20141227_143254

20141227_143318 20141227_143352 20141227_143407

inhs_stone_quarry_rev_3 inhs_stone_quarry_rev_4

400-Spencer-Road-INHS-Revised-Site-Plan-Drawings-06-16-14_Page_05-1280x828

 





Lofts @ Six Mile Creek (Cayuga Place) Update, 11/2014

5 12 2014

As much as I hate to entertain the currently-fashionable use of prepositions in project names, and the “@” symbol to make it modern and hip, that is the official name for what was the condo portion of Cayuga Green. More notably, the project website describes these as apartments rather than condos as initially planned. Apartment projects are easier to get financing for since it’s generally easier to find renters vs. buyers, but given some of the discussion about the need for owner-occupied units that has come up lately (the Old Library redevelopment comes to mind), this is a mild disappointment.

The 7-story, 45-unit, 49,244 GSF apartment building topped out on October 2nd. The concrete floors were poured and the balcony pads were craned into place and secured throughout the fall. Peering into the building from the parking garage, some steel wall frames have been erected on the upper floors, while rough interior work seems to be underway on the lower floors. The plastic sheathing is to break the winter winds and keep the space above freezing.

Developer Bloomfield/Schon + Partners planned to release leasing/pricing details last month, but I haven’t heard anything yet. Completion for the project is set for late Spring 2015, which according to their facebook, is a little later than intended due to material supply delays created by the rough November weather (curse you, polar jet stream). If the last photo is any indicator, the upper-floor units are going to have some fantastic northeast views.

As noted before, this project makes the completion of 15 years of planning and construction. At 45 apartment units, It’s also one of the largest non-student-related projects slated for a 2015 completion – the 35-unit Stone Quarry Apartments and the 21-unit 323 Taughannock are also pegged for 2015 completions.

20141129_135747 20141129_135859 20141129_135828 20141129_135807 20141129_140005 20141129_140241 20141129_140308





Belle Sherman Cottages Construction Update, 11/2014

4 12 2014

Over in Belle Sherman, work continues on its namesake housing development, the 29-unit Belle Sherman Cottages. From a glance, some site clearing might be taking place for the first set of five townhouses (lots 25-29), which are aiming for an April 2015 completion. Several homes are in various stages of construction, with some still wrapped in breathable plastic, and others undergoing final exterior and interior work. Since September, lot 18 (Craftsman Bungalow), lot 15 (Craftsman Farmhouse), lot 10 (Craftsman Farmhouse) and lot 3 (Craftsman Farmhouse) were completed or are nearly completed, while lot 17 (Victorian Farmhouse) and lot 5 (Classic Bungalow) are underway. That’s six houses in less than three months. Carina Construction and Agora Home and Development more than outdid my September estimate of 1-2 more homes before the end of the year.

For comparison’s sake, in December 2013, there were five complete houses and two more underway, and the model house was built all the way back in May 2012. Now the total number of homes built or being built is 14. The project had a great sales year and it shows. Speaking of sales, all houses except lot 9, a new design yet to be published, have been sold. All 5 units that comprise the first set of townhouses have sold as well. Marketing has not begun for the 5 units in the second set of townhouses, lots 20-24.

One of the unique features of this project is that unlike traditional on-site frame construction, these houses are assembled from modular units. The modular pieces are sourced from Simplex Homes in Scranton and trucked up to Ithaca for installation. Once the concrete block foundation has been assembled, the four modular pieces for each home are craned into place, and once the pieces are leveled with the rest of the structure, the adjoining walls and ceiling are secured with steel plates. Interior work goes on while siding, porches and other features are built onto the assembled house. This allows for a faster construction process and cuts down on finishing costs.

20141129_133942 20141129_134007 20141129_134018 20141129_134037 20141129_134046 20141129_134058 20141129_134109 20141129_134145 20141129_134220 20141129_134231

belle_sherman_cottages_102714 belle_sherman_cottages_071814_2

 





Collegetown Construction Updates, 11/2014

3 12 2014

Next stop, Collegetown.

20141129_132947

20141129_133109 20141129_133122

140College_2

Over at 140 College Avenue, framing is underway on a 3,800 sq ft, 12-bedroom addition to the historic John Snaith House. The project is designed by local architect Jason Demarest and developed by Po Family Realty, a smaller Collegetown landlord.

20141129_132913 20141129_133016 20141129_133029

This house at 205 College Avenue seems confused. Before the extremely vivid paint job and mix-and-match additions, it looked like this, and a photo from January 2014, with the paint but without the additions, is included below. I really don’t know what to make of it. I dunno how long the Lowers have been sitting on permits for this one, but I didn’t see anything go through the city boards.

1-2-2014 331





Cornell Construction Updates, 11/2014

2 12 2014

The best part about holiday photo tours is that students are few and parking is ample.

20141129_131741 20141129_131757 20141129_131809 20141129_131813 20141129_131833

20141129_131838

I know this project has been done for a couple of months now, but I was unable to take photos until now. The $650,000, 1,700 sq ft project is essentially Cornell’s history engraved in stone benches and pavers (unfortunately covered by snow and ice here). I imagine it must be a nice spot to sit when not covered in snow.

20141129_132052 20141129_132105 20141129_132151 20141129_132208

AH.Night.view

Far bigger is the continued construction for the future Klarman Hall, pushing onward to its December 2015 completion. Construction firm Welliver is plodding through the cold weather to undertake steel work, metal decking, and mechanical and electrical rough-in in the basement. The 33,250 sq ft building was designed by Koetter | Kim & Associates.





Lansing/Dryden Construction Updates, 11/2014

1 12 2014

Normally, I use a full-fledged DSLR camera for these construction tours, I accidentally forgot my camera and had to use my phone instead. The resolution isn’t as great, but they still came out better than I expected. These photos were taken on the 28th.

20141129_120035

Here we have what looks like a pair of townhomes going up in the Maple Ridge development just east of Dryden village. Maple Ridge was dreamed up as a multi-phase 50-unit housing development when it began in 2008/09, but the recession deflated those plans. Only four homes have been completed so far; the blue house with the very large garage was built earlier this year.

20141129_121915 20141129_121956 20141129_121939

Going over to Lansing, two more oddly Florida-like homes are underway at the Heights of Lansing development off of Bomax Drive. One is virtually complete with only exterior detailing left on the to-do list, the other home is but a shell, still in the rough framing stage. No new townhomes, but a third home lot was sold a few weeks ago, so another single-family home will likely start construction sometime in the near-future. The development is slated for about 80 units when complete, and since inception in 2006, has completed two homes and 17 townhouses (another project that was hit by the recession; not that there’s too much demand for high-end townhomes in Lansing anyway).

20141129_122833 20141129_122808

20141129_122722

This building underway at 720 Warren Road is for the “Northeast Dairy and Food Testing Center” I wrote about back in August. Work on the exterior shell continues for the 17,000 sq ft structure by Syracuse-based Dalpos Architects, moving towards a Spring 2015 completion.

20141129_125221 20141129_125556 20141129_125613 20141129_125616 20141129_125458 20141129_125439

This was arguably the biggest surprise. These four apartment buildings are part of the Village Circle Apartments in Lansing, the later three are likely part of the Village Solars project. The first one has been mostly complete for a year or so, and looks to be readying itself for occupancy. The last three comprise what I would guess to be 36 units; two are topped out and have house wrap on them, the middle one is still undergoing initial framing. This one went under the radar since it was approved in Spring 2013; the Village Solars project seeks to over 300 units off of Warren Road over the next 10 years.

20141129_124516
Before heading into town, I drove around to check out a couple of other projects in Ithaca’s suburbia. The Woodland Park development sold one of its pricey single-family homes and work was finishing up on a second; I chose not to stop due to a large number of construction workers at work on the site. I spied three complete sets of townhomes in the gated section as I drove past. No new homes underway in Whispering Pines, but I did see this home under construction near the intersection of Triphammer and Horvath Drive.





Belle Sherman Cottages Update, 9/2014

9 09 2014

Agora Development‘s Belle Sherman Cottages project continues to build out. Some observant readers might have caught the piece from Buffalo development blog Buffalo Rising, which featured the project as an example of smart infill development (Buffalo Rising is rather fond of Ithaca). Since the early August update from Jason at Ithaca Builds, lots 4 and 6 have been completed and lot 18, a craftsman bungalow, is substantially complete. Meanwhile, work has begun at lot 3, a craftsman farmhouse. Given the previous rate of progress, I expect 18 will be complete by the end of the month, and lot 3 by early November. I don’t think it would be remiss to think another home will start before winter sets in. Of the 19 lots for single-family homes, only two lots are left, lot 12 (another craftsman bungalow) and lot 9, a new design that has yet to be published.

belle_sherman_cottages_071814

belle_sherman_cottages_071814_2

101_4882 101_4885 101_4887 101_4889 101_4890 101_4891 101_4893 101_4894 101_4897