Lofts @ Six Mile Creek Construction Update, 7/2015

30 07 2015

This will probably be the last update written for the Lofts @ Six Mile Creek apartment project; it’s very nearly complete. The lower floors already have their first occupants, while on the upper levels, the Pella windows still have labels on them, indicating that interior finishing is still taking place on the most lofty of the loft units. Outside, workers were busy cleaning off newly-laid sidewalk; exterior landscaping is up next, which will consist of weed-whacking, laying down soil, grass seed and new plantings that will hopefully enhance the Creekwalk.

It’s been nice watching this building go up, through here and on Ithaca Builds. It’s been a long, long time coming, and well-designed additions to the increasingly under-served housing market are welcome.

The Lofts at Six Mile Creek project consists of a a 7-story, 49,244 square foot structure that will contain 45 rental apartment units: 3 studios, 21 1-bedroom and 21 2-bedroom units. The building is being developed by Bloomfield/Schon + Partners out of Cincinnati, and construction is being handled by Turnbull-Wahlert Construction, also based in Cincinnati.

Leasing is being handled by CSP Management, and interested readers can apply for an apartment here or call 607-277-6961 if they feel so inclined. Prices range from $1,220 to $2,655 per month, depending on size and location of the unit.

20150727_113548 20150727_143308 20150727_143405 20150727_143453 20150727_143516

20150727_113404

20150727_145241

cayugaplace_v5





Lofts at Six Mile Creek Construction Update, 6/2015

12 06 2015

It won’t be long now, this project is in the home stretch. The protective plastic wrap is off and the product is almost ready to hit the market. The work at the “Lofts@Six MileCreek” site is mostly interior finishing at this point. A few of the exterior panels/window glazing had yet to be finished in these photos from last Friday, but a glance at the project’s facebook page shows that the windows have been installed, but the panelling has yet to be hung. Some other exterior finishes, such as balcony railings, are only partially completed as of now. A formal opening by late summer seems likely, thus completing the last phase of a 15-year project.

Looking at the rental agreement, tenants are allowed to have pets (for a $500 refundable fee and a $50 monthly rent surcharge), no more than two tenants may share a bedroom, and income is expect to be three times rent. 12 month leases only, 1 month’s rent as a security deposit.

With rents ranging from $1,220/month and up, that means that the minimum a tenant can make and live in the building is $43,920/year. A top end 2-bedroom unit, at $2,655/month, requires $95,580/year. The three studios range from $1,220-$1,460/month, one-bedrooms from $2,160-$2,355/month, and two bedrooms from $2,095-$2,655/month. There’s no doubt these are premium prices, and as discussed in the last update on this project, that’s not necessarily a bad thing for everyone else.

The Lofts at Six Mile Creek project consists of a a 7-story, 49,244 square foot structure that will contain 45 rental apartment units: 3 studios, 21 1-bedroom and 21 2-bedroom units. The building is being developed by Bloomfield/Schon + Partners out of Cincinnati, and construction is being handled by Turnbull-Wahlert Construction, also based in Cincinnati.

Leasing is being handled by CSP Management, and interested readers can apply for an apartment here or call 607-277-6961 if they feel so inclined. Questions can be directed to info@IthacaLofts.com.

20150605_114748 20150605_114809 20150605_114830 20150605_114902 20150605_114923 20150605_115108

cayugaplace_v5

 

 





Lofts at Six Mile Creek Construction Update 4/2015

22 04 2015

Heading back to downtown again, the “Lofts@SixMileCreek” (no spaces? no spaces…) apartment project is plodding away towards its anticipated late summer completion. From the outside, there’s been progress under all that protective plastic wrap – the first five floors have had their exterior walls framed and glazed (glass wall installation). The top couple of floors should be sealed up in short order.

According to an update from Jason at Ithaca Builds from the start of the month, walls and utility rough-in was underway inside the top floors, and drywall hanging and finish-work was beginning on the lowest floors of the apartment building. The Downtown Ithaca Alliance recently scheduled visits to the unfinished units as part of its Downtown Living Tour last Saturday.

Perhaps the most controversial thing about this project was when the rents were released at the start of the month – prices range from $1,220/month for a studio to $2,655/month for the largest two-bedroom on the upper floors. That got a lot of attention on the Ithaca Voice’s Facebook page, and much of it wasn’t good.

Jeff Stein, the Voice’s editor, followed up with an editorial saying that the criticism misses the point, the best way to alleviate the affordable housing crisis is to bring new units to the market at all income levels, which increases competition among landlords. Although I didn’t have a hand in the editorial, I support every word of it. Rents are high for this project, without a doubt. But the city not only needs units specifically for affordable housing, but units that will create competition for Ithaca’s burgeoning renter population.

With more units to better satisfy demand, landlords won’t be as able to charge premium prices on subpar units – inferior products will more likely be vacant. There would be a market push for owners to either upgrade their units to maintain a certain price point, or downgrade their prices to more affordable segments. Whether or not Ithaca will ever be able to get to that ideal balance between supply and demand is another story.

The Lofts at Six Mile Creek project consists of a a 7-story, 49,244 square foot structure that will contain 45 rental apartment units: 3 studios, 21 1-bedroom and 21 2-bedroom units. The building is being developed by Bloomfield/Schon + Partners out of Cincinnati, and construction is being handled by Turnbull-Wahlert Construction, also based in Cincinnati.

20150405_133449 20150405_133946 20150405_134010 20150405_134051 20150405_134118

cayugaplace_v5

10917333_314783998711665_7443965770647794346_n 10378252_313975992125799_95913780193412415_n





News Tidbits 4/4/15: And They Called It “PlanIthaca”

4 04 2015

cayugaplace_v5

1. According to Ithaca Builds and those on a VIP list-serve, the Lofts @ Six Mile Creek have released tentative rental prices. $1,220/month for a studio to $2,655/month for a top-notch 2 bedroom. Using the affordability rule (30% of monthly income), one gets $48,800-$106,200 year – given the median income in Tompkins County of just over $53,000/yr, these prices could be described as upper-middle tier. I can already hear the grumbling from commenters on the Ithaca Voice if a construction update gets posted.

The 45 units are set to be completed this summer, but those looking to take a sneak peek can sign up for an April 18th tour of the building, courtesy of the Downtown Ithaca Alliance.

inhs_pride_design_v2_1

2. Here’s an updated aerial site rendering of INHS’s 210 Hancock redevelopment. The changes to the affordable housing proposal are largely in site landscaping and layout, the biggest changes being the closure Lake Avenue and moving the playground (which is not rendered in the aerial). Traffic studies, stormwater management plans, and parking studies can be found here (it turns out that compared to the old supermarket, there will be slightly more AM traffic, and a lot less PM traffic), revised site layout here, and about 18 other documents in the April site plan review planning board directory on the city’s website. 210 Hancock will be undergoing review by the city Planning and Development Board at their April meeting.

gways_rev_3

greenways3

greenways1_final

3. Turning to another INHS project, the Greenways development is going for final approval with the town of Ithaca’s Planning Board next Tuesday. The full suite of documents can be found here. The designs above, for buildings A, B, C, D, and E in Phase I, are very nearly final, though Building C looks like it was accidentally uploaded in grey-scale. B-E will have three units each, 2 2-bedroom (1,100 sq ft) and 1 3-bedroom (1,300 sq ft). Building A will have 2 2-bedroom and 2 3-bedroom units. In sum, Phase I has 16 units and 38 bedrooms. Assuming the other units are the same configuration, the final product will have 46 units and 110 bedrooms. Build-out could take 6-8 years according to the docs, and Building K in Phase II interferes with 0.09 acres of wetland, which the Army Corps of engineers requires to be filled in before development (wetlands under 0.1 acres and not contiguous with any other wetland can be filled in without need of replacement).

The designs are by local architect Claudia Brenner. The floorplans are designed with nearly identical layouts to save money, but the varied use of exterior architectural details and colors does a nice job of giving each building a unique appearance.

Readers might recall that these for-sale owner-occupied units are being developed for the affordable housing segment (individuals/families with incomes of $38k-$57k), and that Cornell is giving INHS the property for below market price on the condition that Cornell employees that fall into the income restraints have first dibs on the units as they hit the market. The property also makes use of “woonerfs“, so-called living streets that are shared by bikers, pedestrians and vehicles, and typically have a speed limit of no more than 10-12 MPH.

ith_big_plan_map_v2

4. The city of Ithaca’s draft Comprehensive Plan is now online. The 66-page draft, called “PlanIthaca”, can be looked at here, and the proposed land use map here. Over the past year, the Comprehensive Plan Committee has been busy fleshing out the original 16-page draft document to the full-fledged PlanIthaca document above. The city will be hosting a series of open houses throughout the city during April for interested parties to look through the plan and comment, with the first open house on Monday April 13th from 3:30-5 PM at St. Luke’s in Collegetown. Comments can also be submitted by email to city planner Megan Wilson at mwilson@cityofithaca.org.

I’ll probably expand on the plan in a future post, but readers of the blog won’t be surprised by anything it says. The map appears to be lacking the neighborhood mixed-use zoning, which from reading the plan appears to be an accident. Otherwise it’s the exact same map from last spring’s write-up.  There’s a couple of interesting concepts that will be explored as things move forward beyond the plan – ideas such as city-wide form-based zoning and a transfer of development rights between properties would make for a large departure from current policies.

tfc_1

5. If you’re looking for a little more light weekend reading, feel free to check out the double feature article on the Tompkins Financial HQ plans running the weekend on the Ithaca Voice. Summing up a few salient details here, the total project will cost $26.5 million, add 77 new jobs downtown over the next decade, and run from about June 2015 to January or February 2017. The new headquarters will be about 110,000 square feet in size, 7 stories and 100 feet tall, the maximum allowed by zoning. The first floor will have a 6,600 square foot (66 feet x 100 feet) bank branch, with parking for 20-25 cars behind the first floor and under the overhanging upper floors. A basement floor will also add 6,600 sq ft of space, and floors 2-7 will have 16,300 square feet each. Across the street at 119 East Seneca Street, a new drive-thru will be built underneath the existing building, consisting of revised drive-thru lanes, surface parking, an ATM and a 985 square foot teller building.





Lofts @ Six Mile Creek Construction Update, 2/2015

13 02 2015

Even during these chilly days, work continues inside the Lofts @ Six Mile Creek apartment building in downtown Ithaca. Walking up to the building, the first thing that sticks out is that the building looks like it’s trapped in a bubble. The plastic sheeting is there for the simple reason of it’s winter in Ithaca, and its effing cold. The plastic keeps some of the sting of the wind away, and also seems to be convenient as a drawing surface. The plywood covers holes where doors will lead out to exterior balconies. Lower floors will have Juliet balconies, while upper floors and some lower-level side units will have full balconies.

A closer look shows that the first two floors do in fact have bands of Pella windows installed, separated with bands of sheathing that will eventually be covered by the exterior finishing material. According to the project’s facebook page, interior wall construction for the apartment units is currently underway. Plumbing, most electrical rough-in and fireproofing are complete, the metal frames of the apartment walls already erected; now comes hanging sheet-rock, flooring and ceiling finishes. Apartments will consist of studios, 1-bedroom units and 2-bedroom units, with some of the studios and 1 bedroom units having bonus rooms. Square footage per unit will range from 555 to 1202 sq ft. The facebook page notes that tentative rents will be posted in the next couple of weeks.

The 7-story, 49,244 square foot building will contain 45 rental apartment units. The building is being developed by Cincinnati-based Bloomfield/Schon + Partners, with construction by Turnbull-Wahlert Construction. Completion of the apartments is expected during the second quarter (April-June) of this year, wrapping up the last phase of a 15-year project.

20150207_151831 20150207_151911 20150207_151950 20150207_151954 20150207_152026 20150207_152252

cayugaplace_v5





News Tidbits 1/17/15: Capturing “The Essence of Local Surroundings”

17 01 2015

inhs_pride_conceptsketch

1. Token PSA: The third meeting for INHS’s Hancock Street/Neighborhood Pride redevelopment is next Wednesday, the 21st, 4:40-7:30. Attendees are not required to be there for the entire time. The goal of meeting three is to discuss design concepts for the proposed buildings that comprise the two remaining/competing site plans. I look forward to writing a follow-up after the meeting.

cayugafarms_2

cayuga_farms_1

 

2. Finally, some drawings for the 102-unit Cayuga Farms townhouse project in Lansing, courtesy of the Lansing Star. They look like stereotypical “McMansions” that happen to have shared walls, and the rental price for the 2 and 3-bedroom units has the mansion part covered – $1800-$2200/month. If you use the 30% rule of affordable housing, that means the a household in the cheapest unit is expected to pull in $72,000/year. To quote the project engineer, Timothy Buhl:

“The idea is to capture the transient market of people coming from urban areas to work at the colleges,” Buhl said.  “They would ultimately buy a house, but don’t know where to locate.  We’re looking for young, two-worker families.  It’s an in-between type of rental of higher-end people that we’re looking for.”

In other words, “affordability” is not a word you’ll see in this conversation. The Cayuga Farms project was initially proposed several years ago as 144 townhouse condos (I miscounted and said 138 at the time), but the market for suburban high-end townhouse condos is pretty limited – there is Ivar Jonson’s Heights of Lansing which since 2006 has sold ~17 of the 70+ proposed townhouse units, and Woodland Park, which in three years has built ~6 of 48 planned. The market is virtually non-existent, hence rentals.

On the town’s website, there’s all sorts of other data uploaded: trail recommendations, on-site sewage system details, traffic generation estimates, erosion and sediment control plans, environmental review forms and so forth. Cayuga Farms is multi-phased, with 3-4 phases from 2015-2021; phase 1 will have 44 units. Since Lansing is at capacity on its natural gas pipeline, residents will be using propane appliances until the new natural gas pipeline from NYSEG is routed in. This project already gets dinged in my book for having 354 parking spaces when zoning requires only 153 (1.5 spaces per unit). Every unit gets 3.5 parking spaces. That seems like overkill. Anyway, the planning board reviewed the SEQR on the 12th, which is a big step towards approval of the townhouse development. My gut feeling is, while there’s no doubt Ithaca needs housing in most market segments, a high-end rental unit where you have to drive to everywhere bundles just about every criticism about local development into one convenient package.

Let’s be honest, I’m generally pro-development. But I do have a short list of projects I don’t support. This is one of them. With the sprawl, gobs of parking, and mediocre design, I question its value to the Lansing community.

 

10378252_313975992125799_95913780193412415_n 10917333_314783998711665_7443965770647794346_n

20141129_135859

3. The Lofts @ Six Mile Creek project has posted preliminary unit sizes and floor plans on their facebook page. The “Studio +” and “1 Bed +” indicate bonus rooms inside the unit (suitable for another bedroom, home office, etc.). No word on rents just yet, but being new and downtown, expect an upmarket price for the 45 apartments due to enter the market late this spring. Their webpage notes they’ll be accepting reservations sometime prior to that.

canopy_v7_1

4. I think we’re up to version 7 now, but the differences in the proposed “canopy Hotel” are now so subtle that you’d have to be looking hard to spot the changes. The entrance facade is virtually the same, but the mechanical penthouse has been updated to better blend in the rest of the structure, and a couple of stylized wall inserts have been planted into the northwest wall to give the 7-story, 123-room hotel a little visual interest. More renders here, a geotechnical report here, a new cover letter here, and traffic study materials here and here. Thank goodness a lot of this work has gone paperless.

According to the documents, the new “canopy Hotel” brand by Hilton

“…is marketed towards the millennial generation (those born between 1980 and the mid-2000s), however, is relevant for the older generation of hotel guests. Each canopy Hotel is designed to incorporate the essence of its local surroundings and neighborhood feel; such as offering a local welcome gift and evening tastings of local food, beers, wines, and spirits to providing local fitness and recreation options in terms of jogging and bicycle routes (bicycles will be available for rent).”
Yes, ‘canopy’ is meant to be lower-case and ‘Hotel’ is capitalized. I’m sure the brand creators thought that was hip and edgy. Yet another reason why I would never be a good marketer. The 74,500 sq ft hotel includes a small restaurant space of 2,000 sq ft on the first floor, as well as standard hotel amenities like a small meeting room and a gym. The $19 million project hopes to start construction this spring.
upson_4
5. Looking ahead, here’s what the city Planning and Development Board seeks to do at its meeting later this month. For the canopy Hotel mentioned above, declaration of environmental significance and possible preliminary approval. INHS’s 402 S. Cayuga Street townhomes and the 6-unit 707 E. Seneca apartment project will be up for environmental review and recommendation to the zoning board for variances. The Planning Board will also declare itself lead agency for reviewing Cornell’s Upson Hall renovations, the 3 duplexes at 804 E. State Street (112 Blair). Board members will also consider approving a telecommuncations (cellphone) tower on top of a gas station at 214 N. Meadow Street, and weigh in on parking-related variances for 128 West Falls Street and 108-110 Eddy Street. It’s an interesting mix this month.




Ithaca’s Sanborn Maps

16 12 2014

This post was inspired by two events – a reader messaging me and asking about historic maps, and another reader telling me about the history of the Cayuga Place/Lofts @ Six Mile Creek site. In both these cases, I ended up looking at Sanborn Maps.

Sanborn Maps were created in the late 19th and early 20th centuries as a way to gauge the amount of fire insurance a site needed. A bunch of things come into play when gauging fire insurance – other structures nearby and their uses, geographic features, width of adjacent streets, fire walls, railroads, building materials, and so on. These maps, as exhaustive of a task as they must have been for surveyors, were crucial in determining the right price for insurance coverage. According to the wikipedia article, agents “relied upon them with almost blind faith”. The company was very successful and produced maps into the 2000s, and Sanborn was an early investment of Warren Buffett in the 1960s. Today, the maps are owned by their successor, Environmental Data Resources Inc.

sanborn_1893

With all that noted, Sanborn Maps are a veritable treasure trove of information. Ithaca and Tompkins County were included in the first Sanborn volume published in 1867, and every few years henceforth. While the 1867 map doesn’t appear online, 1866 maps from a rival publisher can be downloaded from the Tompkins County Public Library here. The 1866 Ithaca map was the same one I used in my “A Walk Down Varick Street” post from last Spring. The other Sanborn volumes listed on TCPL’s website date from 1893, 1904, 1910 and 1919. Between published volumes, updates would be sent out on “slips”, sheets with the updated lot details that one could paste into place on top of the old map. There are also 1888 and 1898 copies, which are proprietary and therefore can’t be linked. The same holds true for any map not published by the government after 1922, which takes out the Sanford Maps from 1929, 1957, 1961 and 1971. These newer maps can still be accessed for academic use at Cornell’s Olin Library.

So for the sake of example, I’m going to use the Lots @ Six Mile Creek site and its surrounding block, since I’m already acquainted with it.

map_1866

I’ll lead off with the 1866 map. #13 Cayuga is a small hotel, #16 a doctor’s office, #18 a “Select School” and #19 a livery (horse stables). All the others (excluding the one labelled “Tannery”) are homes.

map_1893

Fast forward 27 years to 1893. On the corner of S. Cayuga and E. Clinton are 3-story rowhouses. A carpet maker sits to their north, and the hotel next door has expanded in the past couple decades. The corner Livery is still there, as are most of the homes. A machine shop sits where the doctor’s office used to be, while Reynolds & Lang (a maker of farm equipment) and George Small’s Planing Mill fill out the east end of the block.

map_1904

Now for another jump, 11 years forward to 1904. The hotel is now a “Farmer’s Hitching Shed” with an earth floor, and the small 2-story building next door is the Forest City Hotel. Many liveries filling in what was once open space, and the planing mill and farm equipment factory have updated names as a result of new business partners.

map_1910

Only a few years later in 1910, the planing mill has moved and the Star Theatre and a bowling alley have taken its place. A concrete garage now sits next to the creek, a bicycle shop and a clothing store sit next to the livery on the corner of Green and Cayuga, and the Forest City Hotel has become Mobb’s Hotel.

map_1919

By 1919, it all starts to get a little jumbled. The change in orientation doesn’t help either. The Star Theatre is now a furniture warehouse and the corner livery is a garage.

Without linking to the images of the later maps, I can at least describe what happens. By 1929, Cayuga Street is automobile row, with Hudson-Essex, Nash and Buick dealerships. A large parking garage is built on the east end of the block. Some houses on Green come down for the Cayuga Press printing plant. The 1961 map shows nothing but Cayuga Press and autocentric development, parking garages and car dealerships and gas stations; the corner townhouses are gone, as are most of the other houses. The whole block is levelled for parking lots and a department store by 1971. The vacated store became the library in 2000, the parking garage went up in 2005, and the apartments have followed. But you can read about the recent work here.

For a budding history buff, the Sanborn maps are a great way to kill a few hours. It also makes one realize just how much downtown Ithaca has evolved over the decades.





Lofts @ Six Mile Creek (Cayuga Place) Update, 11/2014

5 12 2014

As much as I hate to entertain the currently-fashionable use of prepositions in project names, and the “@” symbol to make it modern and hip, that is the official name for what was the condo portion of Cayuga Green. More notably, the project website describes these as apartments rather than condos as initially planned. Apartment projects are easier to get financing for since it’s generally easier to find renters vs. buyers, but given some of the discussion about the need for owner-occupied units that has come up lately (the Old Library redevelopment comes to mind), this is a mild disappointment.

The 7-story, 45-unit, 49,244 GSF apartment building topped out on October 2nd. The concrete floors were poured and the balcony pads were craned into place and secured throughout the fall. Peering into the building from the parking garage, some steel wall frames have been erected on the upper floors, while rough interior work seems to be underway on the lower floors. The plastic sheathing is to break the winter winds and keep the space above freezing.

Developer Bloomfield/Schon + Partners planned to release leasing/pricing details last month, but I haven’t heard anything yet. Completion for the project is set for late Spring 2015, which according to their facebook, is a little later than intended due to material supply delays created by the rough November weather (curse you, polar jet stream). If the last photo is any indicator, the upper-floor units are going to have some fantastic northeast views.

As noted before, this project makes the completion of 15 years of planning and construction. At 45 apartment units, It’s also one of the largest non-student-related projects slated for a 2015 completion – the 35-unit Stone Quarry Apartments and the 21-unit 323 Taughannock are also pegged for 2015 completions.

20141129_135747 20141129_135859 20141129_135828 20141129_135807 20141129_140005 20141129_140241 20141129_140308