Exploring Milstein Hall

16 08 2011

So, fortunately for me, I’m not the only person out there who has an interest in Cornell construction projects. By good fortune, I happened to receive a series of emails from a newly minted Cornell graduate, “BB”, who took the time and opportunity to explore the nearly complete Milstein Hall and pass along some photos to this blog. For that I am thankful, as my trips to Ithaca have become fewer and further between. While I am glad for the photos, I’m still going to push the token disclaimers that I do not encourage or condone the exploration of unfinished buildings, due to a safety risk and legal concerns with trespassing. Also, while he is kind enough to share the photos here, they are his property, with all associated rights and privileges. I would encourage those that want to use his photos to contact him directly.

For those who wish they could answer nature’s call while on a spaceship…

They’re not even stalls. They’re more like bathroom pods.

I’m looking at this photo, and immediately, “The Imperial March” pops into my head.





An Exercise in Mapping, Part II

15 05 2011

Under Construction: The once-vacant Plantations Building on Ithaca Commons is being renovated into 8 apartments, a small amount of office space, and a large restaurant on the first floor of the 5-story building. The project is funded partially by community grant money and will be complete in about a month.

Approved: The 6-story, 52-unit apartment building proposed by INHS (1), the 7-story, 45-unit Cayuga Place condos (2), and the 10-story, 140-room Hotel Ithaca (3) are attempting to find financing in what is still a tight market for construction loans. The INHS building is dependent on state grant money that was not granted last year, and they are hoping to obtain financing in the next round of grants. The Cayuga Place condos has been looking for more unit sales and securing bank financing for almost four years at this point, and it might be time to move that to a stale proposal.

Proposed: The 6-story Challenge Industries redevelopment proposal, which has some office space and 32 units of housing. The project is currently trying to win over the neighbors and councils for zoning variances and approval down the line.

Stale/Dead: McGraw House, a senior living facility, was looking into a 25-50 unit expansion, and held several meetings to discuss proposals on the table, but this has all been tabled until a future time.

Examining the Ithaca College Area:

Note that I don’t use Bing Maps because I like them more, but because they are more up-to-date. For example, IC’s virtually complete Athletics Center is clearly visible on this aerial image.

Under Construction are Ithaca’s College’s Circle Apartments expansion (in the site prep stage; four current buildings (132 units) will be demo’d and nine more (280 units) will be added to the complex) and a 22-unit addition of senior housing (patio homes) to Longview.

Approved are the College Crossings retail center and INHS’s Holly Creek townhomes (11 units in first phase, I think 22 total). Off the map to the south and southwest are a couple of housing developments, Southwoods and Cleveland Estates, which are being developed lot-by-lot.

The proposed facility is the long-term expansion plans for the South Hill Business Campus, which would add 197,000 sq ft in three new buildings 3-4 stories in height. The campus currently has about 288,000 sq ft, of which about 84% is leased.

The stale proposal is an apartment building off of Bella Vista Drive that has been trying to market its units for the better part of five years. I am doubtful it will ever launch construction at this point.





An Exercise in Mapping

24 04 2011

So, I figured that since I write about Cornell, IC and Ithaca-area construction projects as much as I do, it might be nice to include some form of a map. Depending on time and motivation, I might get around to putting ones together for South Hill and Downtown.

So, Cornell Campus, used here primarily as a test bed (click the image to expand its size).

Under Construction:

1 – Milstein Hall 2- Johnson Art Museum addition 3- Human Ecology Building 4- Stocking Hall Addition

Approved:

1- Wilson Lab / Synchotron Expansion (CU ERL Project)

Proposed:

1- Gates Hall

Stale Proposals (i.e. been around a while, little notable progress in the past several months-plus)

1- Goldwin Smith Hall Addition 2- Gannett Health Center Addition 3- Holley Center (Soil Lab) Expansion (most likely dead, given federal budget cuts).

Heading south into Collegetown –

Under Construction

1- Coal Yard Apartments Phase II – A 4-story, 25-unit building off of Maple Avenue.

Approved:

1 – 309 Eddy Street (5 stories, 41 units) 2- Vine Street Cottages (19 house, 10 townhomes) 3- Collegetown Terrace (several buildings, 2-6 stories, 589 units)

Proposed:

1- 307 College Avenue (5 stories, 60 units), Snaith House addition (12 bedrooms)

Mall, Airport and Vicinity –

Under Construction:

1- BJ’s wholesale Club (82,000 sq ft) and 12 senior living units 2- Heights of Lansing (~17/80 units complete).

Approved:

1- Millcroft Housing Development (~19 lots in phase II).

Proposed:

1- Lansing Reserve Project (65 units) 2-  NRP Group Project (80 units)

Stale Proposal

1- Behind the mall, a mix of additional shops and 40 apartments, in a lifestyle-center setup, were proposed about three years ago. The recession may have killed the project; at the very least, it’s been shelved.

***

This isn’t to say there aren’t plenty of other projects in the area, I just wanted to experiment with presenting local projects in a different, more visual format.





Springtime Construction Update

12 04 2011

Long story short, for the first time since about New Year’s, I was able to visit Ithaca this past weekend. Went for a national initiation for the fraternal alma mater and stayed for the day.

Milstein Hall continues towards its late 2011 completion date.

The new Human Ecology Building nears completion.

The Brian Nevin Welcome Center for the Cornell Plantations is open and ready to receive visitors.

Demolition work continues on Stocking Hall’s “new wing”, to make way for the new Food Sciences building.

Concrete pouring is well underway for the Johnson Museum addition.

The site of Gates Hall, looking southeast.

Oh Cornell. Even if you drove me nuts while I was in Ithaca, I do miss you a little bit. Partly because I have to look at this everyday:

Good thing my office is windowless.





The (All Too Late) Ithaca Projects Update

24 11 2010

Since I have no life as a grad student, following progress in the Ithaca has been a little difficult. But, I figured it was time to do an updated brief list. Ithaca has made it through the recession largely unscathed (thankfully), thanks to the stable college-based economy, and various projects are in various planning and development stages throughout the area. For the purposes of this entry, I’m ignoring the projects going on at Cornell and IC.

First off, most of the larger projects are delayed. The Hotel Ithaca is waiting for a bank loan, but given the market that could take a good year or two before a loan is secured for the 10-story hotel.  In a similar boat, the 7-story Cayuga Green condos are delayed until sales pick up and financing is secured.  The six-story, 52-unit apartment building planned for the site of the Women’s Community Building is also delayed, having failed to get a grant from the state. It will be at least one year before financing is secured and construction can begin for that project.About the only going on in the heart of the city right now are the redevelopment of the Petrune Building and the starting phases of a renovation of the Ithaca Commons.

Land remediation and site prep is still underway for the Ithaca Gun condos, which are slowly (barely) progressing towards construction of what may now be either 33 units, or increased to 45 units of “market-rate” housing. On the 600 block of West Seneca Street, a 24-unit, 3-story apartment building has been approved and site prep is to begin in the near future.The Kitchen Theatre finished construction and moved into their new digs on West State Street.

Over in Collegetown, works continues on the 589-unit Collegetown Terrace proposal, which is still making its rounds after agreeing to preserve the Williams House on State Street in exchange for getting permission to demolish the old nurse’s dormitory (Delano House). Even if the project starts this summer, full build-out will take 22 months, so expect no earlier than a mid-2013 completion.  Over on Eddy Street, plans have been approved for a24-unit, 41-bedroom 5-story apartment building next to the Souvlaki House, and construction will begin next summer. A 5-story building on the 300 block of College Avenue remains in the proposal stages. Closer to East Hill, the 4-story Coal Yard Apartments expansion is in site prep, and the now-approved Vine Street Cottages project removed three homes from its plan, leaving 19 houses and 10 townhouse units for the parcel near Mitchell Street.

Down in big-box land, Walmart has finished their expansion into a Supercenter, and Tim Horton’s is seeking approval for a store on what is now a parking lot near Buttermilk Falls.The parcel where Olive Garden was proposed is once again up for grabs. Local rumor mill had it that the land was still contaminated (it was once the site of an auto repair shop, and gas and oil and other hazardous compounds might’ve seeped into the soil deeper than first thought).

Out in the West Hill area and the town, Ecovillage is in the home stretch for approval for their third 30-unit village (TREE), and 106 townhome units (Holochuck Homes site) are approved for Route 96 near the medical center. A couple of suburban subdivisions (the Goldenrod 30-unit division, and a 22-unit INHS project called Holly Creek) are planned/approved. 22 units of senior housing are to be built near Ithaca College, and it was confirmed that the 82-unit, rather terrifying and Soviet-looking Maple Hill Apartments on Maple Avenue will be demolished when the property is returned to Cornell in 2013. Cornell has long-term goals to redevelop the site into mixed use, according to its master plan.

Over in suburban Lansing, there’s some small housing developments and a new locally-owned supermarket planned, but the big thing out there is the proposal for an 82,000 sq ft BJ’s Wholesale Club next to the mall, with 12 units of senior housing and a bird sanctuary on adjacent property (basically because the project is seeking tax-exempt status and need to offer a community benefit to get the break). The 69-unit Woodland Park project doesn’t look like it will be approved anytime in the near future.

Hopefully I’ll have more and more substantial news to write about in the tidbits entries in the upcoming months. I need a distraction from my life. Especially when I grade exams and a student thinks it’s cute to bubble “C” 40 times (he received a 15%).

 





A Look Inside the Physical Sciences Building

11 11 2010

I’ll write more substantial posts in the near future. In the meanwhile, here’s some photos I took recently on a trip back to Cornell’s campus (the joy of living only a few hours away is that weekend trips are feasible – for the record, if you asked me last year where I was going, it was to a school out in the Mountain West…but that was before their funding was cut. The next best solution just happened to be in the Northeast).

So, anyways, the work is virtually complete, with part of the building opened for light use, but the whole building is still not yet fully accessible.  As if that’s ever stopped me before.

.

This mock-up, some empty carrels and a couple of bare desks are all that is left of the Physical Sciences Library in Clark Hall. I noticed one of the pillars an eulogy tot he library that Munier Salem had written in the Sun on March 26, 2009, yellowed but encased in a simple black picture frame. I thought it was a nice gesture to the library that once was. Although I opted to not take a photo of the column, here’s a link to its online version.

Insert your name here…for about $35 million. Could be you…

Leaving the oxidized copper lampposts was a nice touch.





A Preview of Future Construction Projects

14 05 2010

A look at Cornell’s Capital Plan is a good source for the vague beginnings of any large-scale construction projects to occur down the Cornell pipeline in the next four to five years. Looking at the projects approves or under way, most have already been covered by this blog in previous entries (the ones that aren’t just renovations anyway — Warren Hall’s going to be virtually gutted over the next few years, but there will be no extensive changes to its exterior appearance). I know that Weill Cornell (WCMC) is about to start on a new 14-story, $650 million biomedical building down in the city, but I’ve always preferred to focus on the Ithaca area (because honestly, most Ithaca-based Cornellians could care less about the facilities in Geneva or New York City).

Projects seeking approval for FY (Fiscal Year) 2010 are clearly underway. The initial steel frame just went up for Milstein and the Statler’s rooms are being renovated. The Johnson Museum expansion is well underway (still in the giant hole in the ground stage, which makes sense since it’s mostly an underground expansion) and the Plantations Welcome Center is currently starting to undergo external facade work now that the frame and much of the insulation have been applied. Under the projects for future consideration section, the Olin Library improvements are in the pipeline as are the feasibility studies for the Cornell Rowing Center Renovation and Expansion and the Central Avenue Parking Garage (renders included below).

Central Ave. Parking Garage Proposal

Perhaps the most intriguing projects are the deferred major projects. Granted, they’re deferred, but they’ll likely come back online once budget conditions improve. One of these major projects is a $183 million engineering building. This could quite possibly be the one shown on the Cornell Master Plan that replaces Hollister and Carpenter Halls, especially since the master plan indicates the project is underway in some form.

However, the only probably with that theory is that there’s three buildings, all in the planning stages, in the vicinity of the engineering quad. Based off of old press releases, Site 2 as numbered in the image (the smallest circle) is almost certainly Gates Hall, which is described as a $65 million dollar project in the capital plan (makes sense; smaller building = lower cost). So, the question is, is the approved project number 1 or number 3? I doubt it’s both because then they would have to be filed separately since they are separate structures.

Another project of question is the East Hill Data Center, a $100 million project. Unfortunately, there are no rendering anywhere, and it’s impossible to use the master plan to figure out which building this might be, as the master plan totally redevelops this area, so this one is anyone’s guess.

The University Health Building and the Helen Newman expansion have been bandied about for some time. The new health building will have roughly the same footprint as the current structure, but maybe a floor taller. Helen Newman has been awaiting an expansion that will add a second pool and additional exercise space, but the original price tag was $15 million, instead of the $30 million listed in the capital plan. One wonders whether this is due to rising costs or more ambitious plans.

Hughes Hall and Myron Taylor Hall (the Law School) are due for $28 million in expansion and upgrades. If it’s anything like what is suggested in the master plan, it’s a modern-looking (i.e. clashes with everything around it) building with alot of below-grade parking. However, I have yet to see any true renderings for this project.

Last on the deferred list is an addition to the 4th floor of Phillips Hall, worth almost $6 million. Don’t expect this to be more than a few thousand square feet at most.

Well, my time at Cornell may be almost complete, but it seems like the construction will never be. It’s okay, I could always use another excuse to come back when I’m an alumnus.





Construction Photos of the New MVR North

1 11 2009

I do not condone sneaking into private property to take construction photos. That being said, if I receive them I’m more than happy to post them as the ones seen below. Most of the photos would appear to be of the parking structure in the lower floors of the building. Too bad some of the exterior photos are a little blurry.100_1848100_1849100_1865100_1850100_1854100_1862

 100_1853100_1855





News Tidbits 8/5: Ithaca Gun Redevelopment in Financial Hell

6 08 2009

This is really funny, because I passed by the site when I arrived back into Ithaca last week, and thought it was curious that no work appeared to be underway even though it was weekday afternoon. However, I didn’t have the camera with me, so I didn’t bother taking photos of the site before I left for places further north.

On the bright side, the blight that was the main building has been torn down; all that remains on the site currently are the debris/soil piles that need to be moved off-site, and of course the Ithaca Gun smokestack that is to be incorporated into a small pocket park when the property is fully redeveloped. So it could be worse.

One thing should be made clear; although there are cost overrruns with the cleanups of the site, the project to rebuild on the site isn’t cancelled. However, results may be late in coming, and may end up different from the initial plans.

http://www.theithacajournal.com/article/20090805/NEWS01/908050328&referrer=FRONTPAGECAROUSEL

The removal of demolition debris at Ithaca Gun has stopped because the development team apparently doesn’t have the money to pay its contractors.

A series of surprises, increased state oversight and community involvement has resulted in cost overruns totaling almost $1 million, according to a letter from property owner Wally Diehl, project engineer Pete Grevelding and developer Frost Travis sent to Mayor Carolyn Peterson on June 30.

The development team initially estimated demolition and cleanup would cost $1.46 million. They now estimate it will cost $2.3 million, according to the letter, which Peterson provided to the Journal on Tuesday.

The cash-flow situation apparently is so tight, the development team can’t afford to dispose of the remaining debris.

“I think there’s basically an issue of having the money in hand to pay people to do the work,” Peterson said. “My focus right now is not to have those piles sitting there.”

She submitted a resolution, which Common Council will consider tonight, asking that the $840,000 in state money intended for redevelopment go instead toward cleanup.

The city earned a $2.3 million state Restore NY grant to subsidize the developers’ project to clean up the site and redevelop it into 33 high-end condos and a public walkway to the Ithaca Falls overlook.

Appointment of a Community Advisory Group, a lengthy asbestos-removal process and “unanticipated environmental procedures, review and approvals” all led to cost overruns, according to the developers’ letter.

Peterson said it cost more than expected to preserve the smokestack and its foundation, deal with some potentially contaminated bricks, and more strictly monitor of the air at and near the site.

Before Travis’ 2007 proposal, Diehl twice proposed condo projects that would have covered cleanup costs without state help, but they were rejected by neighbors as too large. With no subsidy on the redevelopment side, the project “will require some creativity on the part of Travis & Travis and their architects,” the letter stated.

Peterson said she hadn’t heard any discussion about a bigger project or more condo units.

“Certainly, with working with the neighborhood, the preference was the proposed project. So I don’t know if there’s a proposal in mind, but I wouldn’t be entirely surprised if there needs to be some re-thinking,” she said.





Dear Ithaca, How I Missed You…

28 07 2009

I suppose that most people, on their first arrival back to the place they call home, would call their friends and make their presence known. I on the other hand decided to avoid my overcrowded sub-subletted apartment by taking photo of the campus construction projects.

100_1105

100_1050

I have to come back to 107 weeks of this? I just lost one of my main walking paths to class. This is almost like coming back to my girlfriend in bed with someone else.  I s’pose I should be glad I’ll only be affected by this for a year before I head elsewhere.

100_1051

Well, I guess if they were going to close off the street, they might as well take advantage to do soil testing for the Johnson addition. Speaking of which, am Ithaca Journal article mentioned that mercury was found at the site [1]. Considering that the building was a chemistry building, and its first incarnation burnt down back in the days before WWI, this shouldn’t be too much of a shock.

100_1104

The physical sciences building continues on its merry way towards completion.

100_1098

MVR North is also well into its construction. I’m personally hoping the concrete and mortar parking base receives an attractive stone veneer to reduce some of the brutalist qualities of the north facade.

100_1099

The Vet School’s Diagnostic Center has received part of its brick facade, on track for its opening within the next year.

100_1102

Meanwhile, Barton Hall and anabel Taylor (not pictured) are being renovated, mostly with replacement stone for the facade, and roof repairs. Barton has been particularly needy for a reno because the stone on the tower was getting to a point where it was liable to crumble away, and it reasonably couldn’t be put off any longer.

100_1103

The Hotel School addition is on target for its winter completion date. For a 12,000 sq ft addition, it really sticks out, especially when approaching from the north on East Avenue. Where the Beck Center used to clash with the south facade, now the new addition clashes with the older southwest wing of the hotel school. I don’t think it’ll do much for Statler Hall, aesthetically speaking.

 

[1]http://www.theithacajournal.com/article/20090720/NEWS01/907200328/Mercury+buried+on+CU+campus