Carey Building Construction Update, 2/2015

9 02 2015

I was originally going to schedule this for later in the week, but I figure I’ll run it now, since the recent twitter chatter is observant but mistaken. The Canopy Hotel is not under construction. At least, not yet. The hotel is expected to start in early Spring. But the work on the Carey Building addition is just beginning.

According to Jason Henderson at Ithaca Builds, building contractor LeChase Construction is currently conducting underpinning work on the Carey Building. Underpinning is the name of the process by which a foundation is strengthened – certainly necessary when one is about to add five floors onto a 2-story building. The second to last photo here shows some of the underpinning work on the eastern foundation wall, and the tarp is on the roof indicates prep-work for the upcoming expansion. LeChase will also be handling the construction of the Canopy Hotel next door.

It’s quite unusual in a place like Ithaca to have two separate large projects right next to each other under construction at the same time. This will be logistically complicated. In a letter to the Canopy developers, LeChase’s large trucks will have their brakes inspected before entering State Street, and will be escorted down the hill to a designated area on Seneca Street, and will leave the city via Seneca Street. According to construction phase diagrams, The steel for the Carey Building will be erected first; then, using the same crane, LeChase will begin installing steel for the new hotel. Sharing the crane will result in a cost savings to both owners.

When most of the western side of the hotel has had its steel structure craned into place, LeChase will transition to a smaller crane and switch the material unloading and staging area to East State Street. This is because the hotel occupies most of the site, so the crane is reduced and East State street will be closer to the location of the new crane. Cladding and interior materials will continue to be fed in via E. State Street through the project’s completion in Spring 2016. The Carey Building will have been completed by then, finishing by the end of summer 2015.

The Carey Building addition will add a third floor and 4,200 sq ft to the Rev business incubator (nearly doubling it to 8,700 sq ft), and on floors 4-7, there will be 20 apartments. Floors 4 and 5 will have 16 studio apartment units that average only 400-500 sq ft, their small size enabling them to be rented at a lower price. The 4 units on floors 6 and 7 will be larger 2-bedroom units. The $4.1 million project is being developed by local firm Travis Hyde Companies.

20150207_153142 20150207_153223 20150207_153246 20150207_153412 20150207_153422

carey_rev4_2

canopy_carey_logistics_1 canopy_carey_logistics_2 canopy_carey_logistics_3 canopy_carey_logistics_4





Cornell Construction Updates, 12/2014

6 01 2015

Funny How the November photos are snow-covered, and the December photos were taken when the temperature was in the low 50s F. Work continues on the future Klarman Hall, pushing onward to its intended opening in December 2015. Construction firm Welliver is plodding making slow if steady progress, with steel work and metal decking underway above ground, and utility installation and door framing in the basement. Some interior and exterior wall framing has begun on the basement, ground and first floors. The 33,250 sq ft building was designed by Koetter | Kim & Associates.

20141227_130627 20141227_130711 20141227_130745 20141227_130808 20141227_130913 20141227_130937 20141227_130955 20141227_131041

On the other side of campus, renovation work continues on Stocking Hall, the home of the food science department. The porous concrete in front of the new wing didn’t fare as well as hoped, and is being replaced. In the old building, installation of new, energy-efficient windows is underway, and should be completed in the near-term. Interior work continues as labs and academic spaces are fitted out, and the old building and new building connectors have been sealed from the element, making them water-tight. The work will wrap up this summer, weather and schedule permitting; the two-phase renovation was launched in September 2010, and the new wing (phase one) opened in July 2013. The 136,000 sq ft rebuild and renovation is nearly a year behind schedule. Contracting is being taken care of by the Syracuse office of The Pike Company, and the design of the new building is a product of a SUNY Construction Fund favorite, Mitchell Giurgola Architects of New York City.

20141227_124325 20141227_124331 20141227_124336 20141227_124419 20141227_124449 20141227_124510 20141227_124610





Holly Creek Construction Update, 12/2014

4 01 2015

Stone Quarry hasn’t been the only project INHS (Ithaca Neighborhood Housing Services) has been working on this past year. Over on South Hill, the non-profit affordable housing developer has been wrapping up Phase II of Holly Creek, a townhouse development just west of the intersection of King Road and Danby Road/Route 96B. Like the first phase, phase II totaled 11 units, bringing the total on-site to 22 units in rows of 3 or 4 units. No further phases are planned.

The 2-bedroom and 3-bedroom units are complete and the last few are for sale ($106k and up) to first-time homebuyers that meet INHS’s buyer criterion. The design is a product of local architect Claudia Brenner, and construction was handled by local firm Avalon Homes LLC. Some commenters on Voice articles have been asking about whether certain builders are local and pay living wages. I checked and yes, they do.

The project has received criticism in some circles for being in too suburban of a location. INHS stands by its choice of location for being on a bus route and because the site had infrastructure/utilities already in place.

20141227_140738 20141227_140754 20141227_140802 20141227_140830 20141227_140837 20141227_140953 20141227_140956 20141227_141002





206 Taughannock Boulevard Construction Update, 12/2014

30 12 2014

Okay, I’ll be completely honest – I don’t know what’s going in here. I don’t know what the mix of uses is, or many residential units there are. Here’s what I do know.

206 Taughannock was until earlier this year the site of the Unfinished Furniture Store (otherwise called the “Real Wood Furniture Store“) owned and operated by the Zaharis family. From the county records, the building itself is a 9,156 sq ft structure originally used for retail and warehouse space and dated to sometime in the 1970s. The store closed in April when its owners retired, and a building permit shown in a ground-floor window was issued in July to the Zaharises. I ran this past IB’s Jason on Twitter, and his guess was about as good as mine; residential units on top and maybe some of the bottom, with a reduced retail space. Photos of the store before renovation can be seen here at Ithaca Builds – the Lehigh Valley House next door is being renovated by its owner (Tim Ciaschi) into 6 condos and ground-floor commercial space. With the 323 Taughannock project approved just up the road, Inlet Island has been seeing increased interest from both current owners and prospective developers. Perhaps the biggest loss is the removal of a rather attractive mural from the front of the structure.

The work itself looks like a complete gutting of the original two-story building, with new windows punched into the walls and sedate exterior (fiber cement?) siding attached to the more complete exterior sections.

I reached out to the owners but have yet to hear a reply; if anyone has some info to share, feel free to reply to this post or send an email. These projects are the most fun for me, because they go without fanfare, but are just as important as any other project of equal size; they lie in wait for discovery and publication.

20141227_144617 20141227_144631 20141227_144707 20141227_144748 20141227_144755 20141227_144900





EcoVillage Construction Update, 12/2014

29 12 2014

Heading over to West Hill, construction continues slowly but steadily on EcoVillage’s 4-story Common House/apartment building as part of its third neighborhood, TREE (Third Residential Ecovillage Experience, following its first two, FROG and SONG).  I can’t seem to find any specific values for the number of bedrooms in the apartment building, but there are 15 units ranging from studios to 3-bedrooms. However, using a little math and deduction, a rough estimate can be established. EcoVillage claims 160 residents in its first two neighborhoods, which have 30 units each (total 60), and they expect 240 residents when the 40-unit TREE neighborhood is complete. That gives 80 residents in 40 units, of which 25 of those units are houses. Houses tend to have more occupants than apartments (2.1/house vs. 1.7/apartment from the 2010 county census), so I think 25-30 residents is a fair estimate for the apartment building.

Interior work is underway and all the windows and doors are fitted into place. Exterior finishes and balconies have yet to be installed. The houses are all complete and occupied. Construction is being handled by a local firm, AquaZephyr, which received an award from the U.S. Dept. of Energy for a “zero energy ready” home constructed as part of TREE. The apartment building is scheduled to be finished this spring. Setbacks stemming from building code requirements pushed it away from its original fall 2014 completion date.

20141227_150247 20141227_150051 20141227_150040 20141227_150002 20141227_145916 20141227_145843

treenh1





Stone Quarry Construction Update, 12/2014

28 12 2014

Like it or not, construction is well underway at the site of the future Stone Quarry Apartments on South Hill’s Spencer Road. Foundation walls and pilings are visible at the site of the townhomes, and the cinder block wall for the elevator shaft and stairwell of the apartment building is clearly visible from the street. A closer inspection of the apartment building shows that a concrete slab foundation has been poured. I’m not sure if the white slabs in the last photo are some type of insulated concrete form like the Fox Blocks used at the Thurston Avenue Apartments earlier this year, or something else (Ithaca Builds’ Jason Henderson is far more knowledgeable about these types of things than I am).

The Stone Quarry project consists of 16 two-story townhouses (2 rows, 8 each), and a 19-unit, 3-story apartment building on the northern third of the property. Specifically, the breakdown of unit sizes is follows:

16 three-bedroom Townhouses
2 three-bedroom Apartments
11 two-bedroom Apartments
6 one-bedroom Apartments

As with all projects by INHS, the units are targeted towards individuals with modest incomes, with rents of $375-$1250/month depending on unit size and resident income. While affordable housing is generally welcome and sorely needed, Stone Quarry had a number of complaints due to size, location and lingering environmental concerns.

With a theoretical capacity of 82 residents (assuming one per bedroom), the project is the largest non-student oriented project currently under construction in the city (Lofts @ Six Mile has more units with 45, but with 3 studios, 21 1-bedroom, and 21 2-bedrooms, for a theoretical max of 66 residents). The apartments are expected to be completed in October 2015. The buildout is being handled by LeCesse Construction, a nationwide contractor with an office in suburban Rochester.

20141227_143254

20141227_143318 20141227_143352 20141227_143407

inhs_stone_quarry_rev_3 inhs_stone_quarry_rev_4

400-Spencer-Road-INHS-Revised-Site-Plan-Drawings-06-16-14_Page_05-1280x828

 





Ithaca Marriott Construction Update, 11/2014

7 12 2014

Officially, the downtown Ithaca Marriott is underway with site prep. Perhaps because it only just started, there was hardly anything to speak of on its site. An orange plastic construction fence blocks off the perimeter of the property, and there appear to be some pipes and concrete blocks on site. IPD had the parking lot blocked off, presumably to keep the lot closed to downtown patrons, and to use Green Street to meet their monthly ticket quota.

Although multiple sources indicate a Spring 2017 completion, the sign attached to the front of the site displays Spring 2016 as the completion and opening period. Binghamton-based William H. Lane Inc. was selected as contractor for the project, and opened an Ithaca office to oversee the operation. The $32 million, 10-story, 160-room hotel was designed by Cooper Carry Architecture and is being developed by Urgo Hotels out of Bethesda, Maryland. Urgo’s nearest other hotels are the Whiteface Lodge in the Adirondacks, and several in the NYC area, and Ithaca is well outside their normal scope. I suppose the Marriott could be used as an example of how Ithaca is attracting the attention of out-of-town investors and developers.

hotelIthaca_2010

This project really has had quite the drawn-out process, originally proposed as the Hotel Ithaca back in 2008. At that point, it was a 9-story, 102-room hotel with a cost of $17 million, to be developed by Rimland Development and operated by boutique firm Gemstone Hotels. Well, a lot happened along the way. The project was approved, the recession hit, the project stalled due to an inability to get financing, the cost kept going up from $17 million to $25 million to $27 million, and the number of rooms went from 102 to 125 to 140. Then the Marriott version came into play in 2012 with a $19 million price tag, it was approved, it too failed to get financing, and went back to the board with a value-engineered design for the now $32 million project. With money from Ensemble Investments, the project has been able to launch. There have been three separate designs with ballooning price tags. To actually have something underway is a welcome denouement to this saga.

The Marriott is one of only several hotels planned for Ithaca, with the new 123-room Canopy a couple blocks away intending to start construction shortly, and 76-room and 37-room hotels for Elmira Road. With high room rates and low vacancy rates, the market is expected to comfortably absorb at least two of those. All of them might cause an older suburban hotel to be closed.

20141129_135427 20141129_135449 20141129_135451





Lofts @ Six Mile Creek (Cayuga Place) Update, 11/2014

5 12 2014

As much as I hate to entertain the currently-fashionable use of prepositions in project names, and the “@” symbol to make it modern and hip, that is the official name for what was the condo portion of Cayuga Green. More notably, the project website describes these as apartments rather than condos as initially planned. Apartment projects are easier to get financing for since it’s generally easier to find renters vs. buyers, but given some of the discussion about the need for owner-occupied units that has come up lately (the Old Library redevelopment comes to mind), this is a mild disappointment.

The 7-story, 45-unit, 49,244 GSF apartment building topped out on October 2nd. The concrete floors were poured and the balcony pads were craned into place and secured throughout the fall. Peering into the building from the parking garage, some steel wall frames have been erected on the upper floors, while rough interior work seems to be underway on the lower floors. The plastic sheathing is to break the winter winds and keep the space above freezing.

Developer Bloomfield/Schon + Partners planned to release leasing/pricing details last month, but I haven’t heard anything yet. Completion for the project is set for late Spring 2015, which according to their facebook, is a little later than intended due to material supply delays created by the rough November weather (curse you, polar jet stream). If the last photo is any indicator, the upper-floor units are going to have some fantastic northeast views.

As noted before, this project makes the completion of 15 years of planning and construction. At 45 apartment units, It’s also one of the largest non-student-related projects slated for a 2015 completion – the 35-unit Stone Quarry Apartments and the 21-unit 323 Taughannock are also pegged for 2015 completions.

20141129_135747 20141129_135859 20141129_135828 20141129_135807 20141129_140005 20141129_140241 20141129_140308





Belle Sherman Cottages Construction Update, 11/2014

4 12 2014

Over in Belle Sherman, work continues on its namesake housing development, the 29-unit Belle Sherman Cottages. From a glance, some site clearing might be taking place for the first set of five townhouses (lots 25-29), which are aiming for an April 2015 completion. Several homes are in various stages of construction, with some still wrapped in breathable plastic, and others undergoing final exterior and interior work. Since September, lot 18 (Craftsman Bungalow), lot 15 (Craftsman Farmhouse), lot 10 (Craftsman Farmhouse) and lot 3 (Craftsman Farmhouse) were completed or are nearly completed, while lot 17 (Victorian Farmhouse) and lot 5 (Classic Bungalow) are underway. That’s six houses in less than three months. Carina Construction and Agora Home and Development more than outdid my September estimate of 1-2 more homes before the end of the year.

For comparison’s sake, in December 2013, there were five complete houses and two more underway, and the model house was built all the way back in May 2012. Now the total number of homes built or being built is 14. The project had a great sales year and it shows. Speaking of sales, all houses except lot 9, a new design yet to be published, have been sold. All 5 units that comprise the first set of townhouses have sold as well. Marketing has not begun for the 5 units in the second set of townhouses, lots 20-24.

One of the unique features of this project is that unlike traditional on-site frame construction, these houses are assembled from modular units. The modular pieces are sourced from Simplex Homes in Scranton and trucked up to Ithaca for installation. Once the concrete block foundation has been assembled, the four modular pieces for each home are craned into place, and once the pieces are leveled with the rest of the structure, the adjoining walls and ceiling are secured with steel plates. Interior work goes on while siding, porches and other features are built onto the assembled house. This allows for a faster construction process and cuts down on finishing costs.

20141129_133942 20141129_134007 20141129_134018 20141129_134037 20141129_134046 20141129_134058 20141129_134109 20141129_134145 20141129_134220 20141129_134231

belle_sherman_cottages_102714 belle_sherman_cottages_071814_2

 





Collegetown Construction Updates, 11/2014

3 12 2014

Next stop, Collegetown.

20141129_132947

20141129_133109 20141129_133122

140College_2

Over at 140 College Avenue, framing is underway on a 3,800 sq ft, 12-bedroom addition to the historic John Snaith House. The project is designed by local architect Jason Demarest and developed by Po Family Realty, a smaller Collegetown landlord.

20141129_132913 20141129_133016 20141129_133029

This house at 205 College Avenue seems confused. Before the extremely vivid paint job and mix-and-match additions, it looked like this, and a photo from January 2014, with the paint but without the additions, is included below. I really don’t know what to make of it. I dunno how long the Lowers have been sitting on permits for this one, but I didn’t see anything go through the city boards.