Not completely done, but substantially complete enough that this will be the last visit. Only landscaping, paving, and exterior and interior finish work (trim pieces, carpeting) Three of the nine eight-unit apartment buildings have been opened for occupancy. The others will open over the next month or so. The units are by and large spoken for already, having been awarded through a housing lottery to screened but otherwise randomly selected income-qualified tenants (making 50-80% area median income).
This $17.3 million, 72-unit project is wrapping up, and with the confusion over Tiny Timbers it may be the only residential component of the Lansing Town Center for some time yet. A further 56 units may be built as a “Phase II” 2-3 years from now when the sewer is in. There will be at least one commercial neighbor moving in next year – the Salt Point Brewing Company has started site prep for their new 4,000 SF restaurant and tap room next door.
Project background and history can be found here. SWBR Architects of Rochester is the architect. Cornerstone Development Group is the developer, and the Taylor the Builders of Rochester served as the general contractor. Passero Associates served as project engineer.
The history and details of the project can be found here.
Leave a Reply