Taking a look at the Ithaka Terraces site at 215-221 West Spencer Street, one question immediately comes to mind – is Building “D” still happening? The other three are far along, and yet there appears to be no sign of Building “D”, a mirror of Building “C”, starting construction. It could be cost concerns or pre-sales worries, or simply a matter of timing. The website doesn’t look like it’s been updated recently, and marketing for the condo units doesn’t seem to have started yet.

Apart from the completion of the roofing, not much additional work has occurred on the exterior of Building “A”. Its twin, Building “B”, has finished framing, sheathing, windows are being fitted and the roofing is well underway, sheathed and covered in Certainteed DiamondDeck and WinterGuard underlayments, but not yet shingled. Building “C” has had its multi-story porch erected and it looks like the R39 cellulose insulation is underway. New to this update are the Bituthene sheets on the concrete foundation walls of “C” – Grace Bituthene Membrane is a two-component system, the first is a sticky, liquid rubberized asphalt compound, the second a laminated HDPE film, and together they’re used for weather and moisture protection, handy when your walls will be exposed to moist soil uphill and several feet deep. The white walls facing the future grand staircase are water-resistive barriers to protect the plywood ZIP panels from the mositure-absorbing stucco finish.

Local eco-builder AquaZephyr LLC (run by Kendall and Mike Carpenter) is the general contractor, Taitem’s doing the structural engineering, T.G. Miller is in charge of civil engineering, STREAM’s the architect, and Ed Cope (PPM Homes) is the developer. Side note, I dropped by the Wyllie site and didn’t see work on the renovation underway, although it’s not clear if the state grant funding has been disbursed yet. It and the PPM’s Ithaca Glass Apartments are expected to get underway this spring.

Also, let’s not forget the ’80s hair metal blasting over the stereo on-site. I guess nothing gets the work done like Whitesnake and Twisted Sister.

UPDATE: From the architect, Noah Demarest, on the status of Building “D”: “It’s a logistic issue. Couldn’t get all the foundations in at the same time. Should be starting soon.”


Actions

Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s




%d bloggers like this: