Village Solars Construction Update, 1/2018

24 01 2018

Work continues at the Village Solars apartment project in Lansing, though it’s mostly been interior construction these past couple months. 102 Village Place has had some of its composite wood siding applied (LP SmartSide treated and engineered wood siding), and the electrical wiring and air-source heat pump units are in place, though not fully connected just yet.

102 VP was already framed, roofed and fitted by the November visit, so chances are, they’ve already done utilities rough-ins and insulation, and they’ve moved on to drywall, baseboards and interior trim boards, priming and painting, and maybe some plumbing fixture and cabinetry installs. The three-story apartment building, which replaces a ten-unit 1970s structure, will have 24 units – 12 studios, three 1-bedroom, six 2-bedroom, and three 3-bedroom. If one wants to look at this from a population perspective, each of the ten units was a 1-bedroom, so the back of the envelope says there will be a net gain of 26 residents (one per bedroom, 36 – 10). And presumably, a couple million dollars in assessed value.

116 Village Place, the younger of the pair, is not as far along but has been fully framed, wrapped and shingled since November, and some siding has been attached. It looks like not all the windows have been fitted, given the wrapped rough opening on the third floor in the first photo below. Based off the open door in that same photo, it looks like framing, insulation and utilities rough-ins (plumbing, electrical, HVAC) are ongoing. 116 is the smaller building of the two, with 18 units, 12 studios and six 2-bedrooms. Like 102, it also replaces an older apartment building, an eight-unit structure of one-bedroom units (and 14 more residents on-site, using the same math as before).

Lifestyle Properties is the developer, with their in-house contractor in charge of construction. It doesn’t look like the new units are being marketed yet, but existing 2-bedrooms are going for $1,325/month, and 3-bedrooms for $1,375-$1,720/month. Anecdotally, Lifestyle has had an easier time filling the smaller units than the larger 3-bedroom units.





Village Solars Construction Update, 11/2017

25 11 2017

Another redeveloped building is underway at the Village Solars property along the 1000 Block of Warren Road in Lansing. The original 8-unit, 8-bedroom 116 Village Circle is no longer of this world; the early 1970s structure was torn down to make way for a new three-story building with 6 2-bedroom units and 12 microunits (400-600 SF). Along with the framed and sheathed 102 Village Place, that means that Lifestyle Properties does in fact have two buildings underway at the site; perhaps the last visit in September just happened to catch the project during a brief lull.

102 Village Place has been fully framed, sheathed, roofed, windows and doors have been fitted, and the fiber cement siding is just beginning to be installed (possibly by T&J Contractors of Auburn; most construction work by Lifestyle Property/the Lucente family is handled by an in-house crew). On the inside, expect electrical, plumbing, and HVAC to be underway; with no open doors or windows, it was not clear if they’re hanging drywall yet. In comparison to the “older” new apartment buildings, these new ones have different fenestration and even have stone veneer at the bases, though the overall building designs are generally similar. It’s not completely certain what the purpose of all the eaves (eavelets?) are on the walls of 102, though given the utility lines, it may have something to do with weather/ice protection for the air source heat pumps, which are shielded by small eaves and wood lattice on the latest completed apartment buildings.

The replacement structure for 116 Village Circle is just starting the framework for the second floor. As previously noted, it’s not uncommon to just housewrap over the rough openings, and cut out the holes later. The excess will be trimmed off and the edges will be fastened back to the inside wall, allowing for a tight and complete wrapping of the rough opening. Taking a guess, 102 will probably be done by the end of March, and 116 the end of June perhaps.

Side note, I’ve never noticed the Village Solars construction crew put a flag up on topped-out structures before.





Village Solars Construction Update, 9/2017

1 10 2017

It looks like the Village Solars are moving along, albeit at the slowest pace in years. Since 102 Village Place was torn down back in June, the site was cleared, the foundation and underground utilities reconfigured, and framing has begun on its replacement. The wood frame was up to the top floor by the time of this late September site visit, and erection of the roof trusses was due to take place in just a few days. The housewrap is already in place, and as the interior receives its frames, pipes, wiring and rough-ins, work will being on window and door fittings. Probably looking at an early spring finish here.

Note that it’s not uncommon to just housewrap over the rough openings, and cut out the holes later. The excess will be trimmed off and the edges will be fastened back to the inside wall, allowing for a tight and complete wrapping of the rough opening.

Interestingly, none of the other tear-downs or new building sites have started, meaning that only one building is currently under construction. That’s rather unusual for Lifestyle Properties, whose in-house construction crew typically works on 2 or 3 buildings at a time. There was a dirt pile near one of the future building sites, but it’s been that way for a while, so it’s likely being used as a staging area. The limited construction suggests that the Lucentes may be falling behind their anticipated construction timeline, which generally calls for two or three buildings a year in order to stay on track.





Village Solars Construction Update, 6/2017

17 06 2017

It’s not often that I run into someone who’s aware of this blog, let alone while taking site photos. When I arrived at the Village Solars property off of Warren Road in Lansing, I was immediately surprised to see they were taking down one of the older 1970s 10-unit properties, 102 Village Place. A salvage job this is not; the excavator was actively tearing through the brick veneer and wood window frames, leaving them in a pile as it slowly worked its way through the building. A gentlemen with a hose was spraying the fresh debris down to keep airborne dust to a minimum. To be honest, even if the building has little historic value, there’s always a bit of a bittersweet feeling to see a place that hundreds called home fall to the march of progress.

And the march of progress it is. As readers of the Voice may be aware, the plan for the Village Solars has been changed up. The next few phases will remove the 1960s-1970s 8-unit and 10-unit (all 1-bedroom) buildings and build new Village Solars buildings on their foundations. The net gain in units will be 70, bringing the number built and to be built from 502 to 572, and a gain in bedrooms of about 124.

It’s a bit complicated of a breakdown – four of the new building planned – 24-unit “K”, 24-unit “L”, and 18-unit “M” – were originally to be the next phase. When all that was said and done, Building “F”, which will host retail components, a community center and 20 studio units, was to be built. Those are being pushed off in favor of the replacement units. For example, 102 Village Place, coming down in the photos below, will be replaced with a 24-unit building that will also be called 102 Village Place. It’s five peers closest to the Village Solars will also be coming down for the construction of 18 or 24 unit apartment buildings on their footprints. There will be five phases, and it looks like two older buildings will come down and have replacements built each year for the next three years, with the last two being the all-new K/L/M and F. The designs for the six new buildings will be similar to the existing Village Solars.

So while taking photos, I happened to see a gentleman in a wide-brimmed hat and loafers, drinking a couple beers. I intended to not make waves and to just walk past when he broke the ice by saying “I’m surprised there aren’t more neighbors out watching. You don’t see something like this everyday.” I ended up making my acquaintance with Jon Lucente, the son of Rocco Sr., brother of Steve and uncle to Rocco Jr. – so, not as directly involved as the others, but still aware and knowledgeable. Turns out he lives in the Village Solars.

One of our conversation topics swirled around the hassles of regulation – a little talk on the Briarwood mess ten years ago, a little bit about Varna, and a lot about the Village Solars. To be frank, he had nothing but great things to say about Lansing town government. But he complained some of the building code regulations created headaches for his family and their in-house contracting team. For example, the buildings had be earthquake-proof, and the expensive sprinkler systems over the balconies are only legal until 2022 but they were the only type approved for use. Interestingly, they originally wanted to do four floors but building codes say an elevator is required for 4 or more floors (this tripped up Ecovillage as well as few years back). Jon brought this all back to the cost being passed on to tenants.

On my end, it was mostly just polite acknowledgement. I understand his point, but details like the elevator rule are in the building code for safety reasons. The thing is, building codes are an imprecise science – they may be too stringent in some circumstances, but lacking in others, so as a result they’re constantly re-evaluated. Given an event like the London Grenfell Tower fire disaster, where the Reynobond aluminum panels were stuffed with polyiso insulation, which is a risk because it can produce toxic fumes if it burns, there’s always good reason to take a hard look at the codes and reassess. For the record, polyiso is a common insulation material, although in the local cases I’m aware of, it goes on over the fireproofing and under the cladding, meaning it would be very difficult to set it on fire, and the Grenfell case implies the panels may have created a tunnel effect for heat and flame. The specific cladding that was used on Grenfell Tower is banned for use on buildings taller than 40 feet in the U.S.  

Anyway, I still enjoyed an opportunity to chat with one of the Lucentes. Building “I” is occupied and Building “J” will be open for occupancy at the start of July – just a little exterior trim left to do on the outside. The photos below have a close-up of the fiber cement board used on the Village Solars, which apropos to this post, doesn’t burn because it’s basically sand and concrete mixed with wood pulp. Won’t make the same claim about those wood-grain trim boards though.





Village Solars Construction Update, 4/2016

19 04 2016

Heading into the spring, it looks like the Village Solars project off of Warren Road in Lansing has made some pretty substantial progress with its second phase.

Building “D”, which contains 12 apartments, is essentially complete inside and out, though not yet occupied.

Building “G/H”, which holds 18 units, is fairly far along from the outside – cement boards have been attached to most of the east face, and some more wood siding has been applied to the west face. Exterior details like balcony railings and trim boards have yet to be installed.

Building “E” is topped out, and the roof rafters are being sheathed with Huber ZIP panels. The stairwells are still being framed out. Windows have been fitted in most of the rough openings on the first and second floors, but have yet to reach the third floor. Housewrap covers most of the plywood walls, with the exception of the stairwells. “E” will have 11 apartments.

From observation, it looks like Lifestyle Properties (the Lucente family) could start renting out Building “D” tomorrow if they wanted, Building “G/H” towards the end of the Spring (possibly Mid-July from the Craigslist posting), and have Building “E” ready for occupancy before the semester starts. Phase two of the 174-unit apartment project is being built with a $6 million loan from Tompkins Trust. Phase one’s 36 units opened last year.

EDIT: From Rocco Lucente the younger – “We will have our first move ins for 1067 Warren Road (Building D) on May 1st. The other two buildings are currently scheduled for June 15th and July 15th completion. We did get our Certificate of Occupancy for Building D around two weeks ago, but with the various cleaning and landscaping work we set our target for May 1st.”

No loans have been secured yet for the three later phases, and plans are still in the works for an addition across Village Place that would bring the total number of new apartments to over 300.