Stewart Park Inclusive Playground Construction Update, 12/2018

15 12 2018

Here’s a look at the Stewart Park Inclusive Playground project. Overseen by the non-profit Friends of Stewart Park (FSP), the two-phase plan was approved by the city earlier this year, and started construction in September for a May 2019 completion. Plans for the project date back to at least 2015, with formal planning board review moving forward in late 2017. Among the features planned are (from the website):

  • A new, accessible splash pad that will conserve water.
  • Specially designed school-age and pre-school play structures.
  • An accessible berm  that provides children a starting point for exciting play experiences for all children.
  • The use of native plants and sustainable building materials and site design strategies to make the playground a model for green playground design.
  • Educational opportunities to interpret the natural environment of the park – the vegetation, birds, fish and wildlife that make this site so special.
  • Natural play areas including a music garden and sand play area.
  • Numerous swings and climbing structures, shaded seating areas and many benches for relaxing.
  • New accessible bathrooms and changing stalls adjacent to the playground and carousel.
  • A restored and accessible Carousel (completed).
  • Accessible walkways and paths linking to the Cayuga Waterfront Trail and other areas of the park and Ithaca’s waterfront.

When FSP refers to an inclusive playground, it means that it offers something for kids of all abilities – it offers a full sensory experience with lots to touch, to see and to hear. Disabled children will be able to access and enjoy much of the equipment, as well as the gardens and play areas.

Complementary additions will include a parking lot addition, benches, and bathrooms. The cost of the new and improved facilities is $1.7 million ($1,517,500 in hard construction costs like materials and labor, $182,100 for soft costs like design fees, legal and permitting, and a $50,000 annual maintenance fund). The project will take about nine months to construct, and be built through a combination of traditional paid construction crews, and volunteer community builds.

As previously reported, the location of the new structures is between the splash pad on the west end of the park and the carousel to the east, south of the transmission lines, with a total area of about 1.65 acres. The area north of the power lines is envisioned as an open play and picnicking area. With the exception of the large swings, the existing equipment will eventually be removed to near the DPW maintenance building and the ‘Whirly Bug’. The older play structure near the carousel will be moved, to another park if possible.

Three playground design and landscaping firms are involved with FSP’s plans – Parkitects, Play by Design and EarthPlay are coordinated designs and features to maximize the play value and amenities, while giving a nod to local features like rock formations and the steamboats that used to come down the lake. T.G. Miller is handling the more technical details like grading and stormwater management, and STREAM Collaborative designed the 900 square-foot storage and bathroom building.

The first phase, which includes the pre-school play area, is open, much of it thanks to the work of over a thousand of volunteers back in September, and participating organizations who sponsored volunteers and support services during the intense six-day build. Phase II will start next year, once the worst of winter has passed.

On the funding side, $1 million was received in a state grant spearheaded by Ithaca’s state Assemblywoman, Barbara Lifton (D-125th). The remaining $700,000 is being raised through a capital campaign. At last update, $658,082 had been committed by private sources. The big donors are listed here, and if you want to help close the gap in the home stretch, the donation link is here. A specialized fundraiser for the new accessible surfacing materials (a safe, durable material on which wheelchairs can move) for the playground is here.

 


Actions

Information

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s




%d bloggers like this: