From the outside, the Dibella’s pad building is just about done. All that’s left is signage and accessory installations such as bike racks. The open paved space south of the building will be a patio for outdoor dining, which would be a nice spot on a day like this.
The inside is still being finished out – looks like the some interior walls are still waiting for their drywall to be hung, and in other spots, the drywall has been primed but trim and paint have yet to be applied. Allowing a few weeks for trimming and painting and equipment installation, it looks like the sub shop could open by Halloween.
Marx Realty might have switched contractors when work shifted from the building itself to the outfitting of the interior. A&E Construction handled the construction of the building (the “shell space”), but Marco Contractors Inc. of suburban Pittsburgh is handling the interior fit-out. More infp about the DiBella’s project can be found here.
Perhaps because of its high visibility, by a wide margin more emails come in asking about what’s being built here than any other project in the county.
Leave a Reply