201 College Avenue Construction Update, 8/2017

16 08 2017

201 College is a work in progress on the outside, but the inside is nearly complete. According to Visum Development’s Todd Fox, who happened to be at the site when the photos were taken yesterday, there are cleaning crews inside, and a certificate of occupancy is being obtained. Renters will be able to move in on Friday.

On the outside however, work is still coming along. From the looks of it, it appears all the woven bamboo siding has been attached. However, the overhead canopy has yet to be installed over the front entrance, and some of the decorative “iron ore” black metal rails and fiber cement panels (“Allura Snow White” and “Gauntlet Gray“) have yet to be clipped on over the structural metal rails. So while tenants will be able to move in for the fall semester later this week, construction on the exterior and landscaping finishes will extend into September. Similarly, the basement area, which will host the fitness room and bike storage, will need a few more weeks before it’s ready for use.

For what it’s worth, 201 College looks just like the renderings provided by its architect STREAM Collaborative, which one would think isn’t a big deal, but it is – there have been cases of developers building something that lacked details of features shown but not explicitly required in approval, which had led to consternation among the planning board and staff.

On another good note, I asked Fox how things were with neighbor Neil Golder, who led efforts to halt the project last year. Since the lawsuit failed, the two sides have been fairly amenable to each other – Fox still offered Golder solar panels on 201 to compensate for shadows, and Golder has let construction workers access his property when trying to maneuver equipment on and off site. Fox said that, in exchange for paying Golder’s water bill, he let construction crews hook up hoses from his spigots to spray down the dust and add water to the concrete.

As 201 wraps up, Fox has his eye on his other approved projects – 210 Linden Avenue, a 4-story, 36-bedroom building, has been excavated and padded (last two photos here), and is waiting on municipal permits to begin construction of the foundation. As with 201 College, William H. Lane Inc. of Binghamton will be the general contractor, and STREAM is the architect. 232-236 Dryden Road, a pair of 4-story buildings with 191 bedrooms, is due to start site prep in September. Two smaller Visum projects, for 118 College Avenue and 126 College Avenue, have no firm construction dates at this time.


Actions

Information

3 responses

16 08 2017
CornellPhD

This is a pretty handsome building from the sides – better than the usual Collegetown product. The front facade windows down toward the street look a little smaller than the renders advertised, though, which unfortunately presents a bit of a fortresslike appearance.

17 08 2017
Steve

It does look better than I feared from the renderings. The wood is a really nice touch. Now, if they could only bury more of those utility lines…

8 09 2017
Nancy T Mihevc

As of 9/8/2017 – this apartment complex is NOT FINISHED on the inside. Windows cannot be opened because handles were back-ordered, there are significant amounts of construction dust everywhere, hallways are not finished – rough walls and no carpeting, promised gym, media and study rooms are not complete.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s




%d bloggers like this: